This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract CN230, Task Assignment 53, Change Order 01. The contract involves the consultant firm Weiler Engineering Corporation and pertains to the Dr. Von D. Mizell - Eula Johnson State Park Restroom Improvements project located in Florida. The change order was approved by FDEP representatives including Budget Representative Tamika Bass, Project Manager Theresa Carron, Contract Manager Ralph Perkins, and Contract Authority Bryan Bradner, along with consultant representative R. Jeff Weiler, PE of Weiler Engineering Corporation.

The change order authorizes three additional subtasks totaling $10,215.80 in fixed-price costs with no reimbursable expenses. Subtask 7 adds lead and asbestos testing and reporting services for $5,115.17, utilizing EPA Test Method 6010 and NESHAP protocols with deliverables due within 60 calendar days. Subtask 8 provides geotechnical investigation services for $2,746.88 to recommend piling depths for boardwalk replacement, also due within 60 calendar days. Subtask 9 delivers 100% boardwalk design plans and specifications for $2,353.75, due 120 calendar days from execution. The original task execution date is January 23, 2023, with the task end date remaining November 30, 2024. Payment is contingent upon FDEP approval of deliverables for each subtask. The change order increases the total task amount from $96,996.32 to $107,212.12.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC3.pdf PDF
CN-370000-CN230-T14CO1.pdf PDF
CN-370000-CN230-T14CO2.pdf PDF
CN-370000-CN230-T15.pdf PDF
CN-370000-CN230-T16.pdf PDF
CN-370000-CN230-T1CO1.pdf PDF
CN-370000-CN230-T20.pdf PDF
CN-370000-CN230-T21.pdf PDF
CN-370000-CN230-T24.pdf PDF
CN-370000-CN230-T25.pdf PDF
CN-370000-CN230-T2CO2.pdf PDF
CN-370000-CN230-T3.pdf PDF
CN-370000-CN230-T34CO2.pdf PDF
CN-370000-CN230-T35.pdf PDF
CN-370000-CN230-T36CO1.pdf PDF
CN-370000-CN230-T36CO2.pdf PDF
CN-370000-CN230-T39.pdf PDF
CN-370000-CN230-T3CO1.pdf PDF
CN-370000-CN230-T45.pdf PDF
CN-370000-CN230-T45CO2.pdf PDF
CN-370000-CN230-T49.pdf PDF
CN-370000-CN230-T51.pdf PDF
CN-370000-CN230-T53CO2.pdf PDF
CN-370000-CN230-T56.pdf PDF
CN-370000-CN230-T62.pdf PDF
CN-370000-CN230-T64CO1.pdf PDF
CN-370000-CN230-T76.pdf PDF
CN-370000-CN230-T79.pdf PDF
CN-370000-CN230-T7CO1.pdf PDF
CN-370000-CN230-T9.pdf PDF
CN-370000-CN230-T92.pdf PDF
CN-370000-CN230-TA33.pdf PDF
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T25CO3.pdf PDF
CN-370000-CN230-T26.pdf PDF
CN-370000-CN230-T2CO1.pdf PDF
CN-370000-CN230-T37CO2.pdf PDF
CN-370000-CN230-T45CO1.pdf PDF
CN-370000-CN230-T4CO1.pdf PDF
CN-370000-CN230-T52.pdf PDF
CN-370000-CN230-T53.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN230 53 01 61397C

Dr. Von D. Mizell - Eula Johnson State Park Restroom Improvements

Weiler Engineering Corporation

Robin Palmer 941-505-1700 rpalmer@weilerengineering.org

Ralph Perkins 850-245-2640 Ralph.Perkins@FloridaDEP.gov

Adding ACM and LBP survey and report, geotechnical investigation and boardwalk plans per the attached proposal dated 7/7/23.

$ 2,823.20 $ 94,173.12 $ 96,996.32 $ 2,823.20 $ 94,173.12 $ 96,996.32

$ 10,215.80 $ 10,215.80 $ 2,823.20 $ 104,388.92 $ 107,212.12

1/23/23

11/30/24

11/30/24

11/30/24

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.08.23 11:40:03 -04'00'

Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.08.23 11:49:38 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.08.23 13:27:32 -04'00'

R. Jeff Weiler, PE Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.08.24 10:12:52 -04'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.09.11 08:08:49 -07'00'

61397C 37505000107 080039/23 423001 U3200 131500 QK $ 10,215.80

$ 10,215.80

July 7, 2023

Ms. Theresa Carron

Project Manager

Bureau of Design and Construction

Florida Department of Environmental Protection

3900 Commonwealth Boulevard 260-L, MS 520

Tallahassee, FL 32399

RE: Mizell- Johnson State Park - Restroom 4 Replacement, CN - 230, TA - 53 - Change

Order 1 - Add Lead and Asbestos

Dear Ms. Carron, The Department has decided to demolish the existing bathroom and extend the boardwalk accordingly. Lead and Asbestos testing and site specific geotech will be necessary.

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:

Please review the attached Proposal Summary and deliverables.

Sincerely, R. Jeff Weiler, P.E.

President

The Weiler Engineering Corporation

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289- 416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG http://www.weilerengineering.org/ mailto:INFO@WEILERENGINEERING.ORG

Ms. Theresa Carron Mizell - Johnson State Park Restroom 4 Replacement

CN 230/TA53 - CO 1

Mizell-Johnson State Park

Contract Number 230, Task Assignment Number 53 - Change Order 1

Subtask 7: Lead and Asbestos Testing

Description:

Consultant will coordinate with a Sub-Consultant to prepare a lead (3 samples) and asbestos (20 samples) report. Utilizing EPA Test Method 6010 and NESHAP, respectively.

Deliverable:

Report delivered via PDF/Email.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 7: Lead & Asbestos

Firm Name Position Classification Unit Unit Rate Numbe r Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 4 580

Tierra

Senior Engineer Hr 178.60 3 535.80

Sr. Project Engineer Hr 146.53 10 1465.30

Sr. Technician Hr 77.21 24 1853.04

Clerical Hr 75.67 9 681.03

Total Lead/Asbestos 5115.17

Reimbursable Cost 7 Only: (if applicable)

Description Number @ Total

Ms. Theresa Carron Mizell - Johnson State Park

Postage

Printing

Overnight Travel

(if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total Cost 7

Total Subtask 7 5115.17

Subtask 8: Geotech

Description:

Consultant will coordinate with a Sub-Consultant to prepare a geotechnical report recommending piling depths for the boardwalk replacement.

Deliverable:

Report delivered via PDF/Email.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8: Geotech

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 2 290

Geotech Universal

Universal Senior Project Engineer Hr 165.84 4 663.36

Universal Project Engineer Hr 94.50 8 756

Universal Staff Engineer Hr 68.46 12 812.52

Universal CAD Drafting Hr 54.00 4 216

Total Geotech 2,746.88

Robinson_MS Text Box 821.52

Ms. Theresa Carron Mizell - Johnson State Park

Subtask 9: 100% Boardwalk plans Description:

Boardwalk plans completed to 100%.

Deliverable: Incorporate Client review of 60% plans, Consultant shall include 100% boardwalk plans and details with the plans for the rest of the project signed and sealed plans, digital 1-PDF and 1-CAD including:

Opinion of Probable Cost;

Site Details and General Notes Foundation/Piling Plans and details;

Beam schedules;

Cross sections and details;

Specifications

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 9 - 100% Plans - Boardwalk

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 1 145

Principal in Charge 195 .25 48.75

Registered Professional Engineer 145 1 145

Registered Engineer Intern 115 8 920

Senior Engineering Designer 100 4 400

Engineering Technician 80 8 640

Clerical 55 1 55

Total 2353.75

Ms. Theresa Carron Mizell - Johnson State Park

Reimbursable Cost:

Description Number @ Total

Postage 0 35 0

Printing 0 2.30 0

Overnight Travel

(if applicable)

Reimbursable Total Cost

Total for

Subtask 9

2353.75

Project Schedule:

Activity Duration (Calendar Days) Days from Execution

Subtask 7: Lead/Asbestos 60 60

Subtask 8: Geotech 60 60

Subtask 9: Boardwalk Plans -

30 120

Ms. Theresa Carron Mizell - Johnson State Park

Summary of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 7 Lead & Asbestos $5,115.17 0

Subtask 8 Geotech $2,746.88

Subtask 9 Boardwalk Plans $2,353.75 $0.00

Total Fixed Price Cost: $10,215.80 $0.00

Overall Total Cost: $10,215.80

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)