This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a contract with Weiler Engineering Corporation. The change order, numbered 02, modifies Task Assignment 34 under FDEP Contract CN230 for Project RBF1052. The project is located at Shell Island and is titled "Replacement Pole Barn and Kayak Cover." Key personnel include Jeff Weiler as the Consultant Representative for Weiler Engineering Corporation and Ralph Perkins as the FDEP Contract Manager. The change order was signed and approved on December 20-21, 2022, by representatives from both the FDEP and Weiler Engineering Corporation.
The change order extends the project timeline by 240 days at no additional cost to the FDEP due to Collier County variance and permitting issues. The original task end date of December 30, 2022, is extended to August 26, 2023. The total contract amount remains $59,350.68, comprising $12,755.00 in reimbursable expenses and $46,595.68 in fixed fees. No modification to the task amount was made; the extension addresses delays in Subtask 7 and 8 related to construction plans and permitting. The project funding is allocated from FDEP's budget using the 29-digit FLAIR code 37202261019375004000010208000.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN230 34 02 RBF1052
Shell Island Replacement Pole Barn and Kayak Cover
Weiler Engineering Corp.
Jeff Weiler 941-505-1700 weiler7@mac.com
Ralph Perkins or successor 850-245-2460 Ralph.Perkins@FloridaDEP.gov
This change order is for time only, Adding 240 days due to Collier county variance / permitting issues See attached proposal dated 07/12/22.
$ 3,255.00 $ 31,637.68 $ 34,892.68 $ 12,755.00 $ 46,595.68 $ 59,350.68
$ 0.00 $ 0.00 $ 0.00 $ 12,755.00 $ 46,595.68 $ 59,350.68
9/15/21
12/30/22
12/30/22
8/26/23
Lisa Yarborough Lisa Yarborough Digitally signed by Lisa Yarborough Date: 2022.12.20 09:40:58 -05'00' 12/20/2022
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2022.12.21 07:40:44 -05'00'
David Matson David Matson Digitally signed by David Matson Date: 2022.12.21 09:20:02 -05'00'
Jeff Weiler Jeff Weiler Digitally signed by Jeff Weiler Date: 2022.12.21 11:01:08 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.12.21 11:59:13 -05'00'
F1052 37538020000 102080/00 261019 U3111 131500 LH $ 59,350.68
$ 59,350.6837202261019375004000010208000
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
November 4, 2022
Garland Sandel
Design Project Manager
Bureau of Design and Construction
Florida Department of Environmental Protection
3900 Commonwealth Boulevard 260K, MS 520
Tallahassee, FL 32399
850-245-2685
Re: Rookery Bay Replacement Pole Barn and Kayak Cover FDEP Contract No: CN230 Task Assignment
No: 34, Project No: RBF1052
Mr. Sandel, We are requesting a time extension for the Rookery Bay Replacement Pole Barn and Kayak Cover project.
This extension would be at no additional cost to the FDEP. The current contract expires on 12/30/2022;
however, Subtask 7 & 8 for construction plans and permitting are still underway. We are requesting a 240-day extension to allow for enough time for the permitting process to be completed.
If you have any questions, or require additional information, please do not hesitate to contact me at (941)
505-1700 or electronically at rpalmer@weilerengineering.org.
Sincerely, Robin Palmer, P.E.
Project Manager
Weiler Engineering Corporation
| CN230 TA 34 Rookery Bay Replacement Pole Barn and Kayak Cover.pdf |
| Rookery Bay Maintenance Building Request for Contract Extension (002).pdf |
File details come from the government source that posted it. Updated .