About this file

This document package includes a DD Form 1354 template for transferring Department of Defense real property assets between agencies, along with details of the Joint Base Elmendorf-Richardson Mini-MACC solicitation.

The DD Form 1354 is used to transfer military real estate between DOD components and other government entities. It collects information on transferred facilities including identification details, physical attributes, costs, funding sources and acceptance. The template instructs users on completing each field.

Solicitation FA500021R0001 is for the JBER Mini-MACC contract supporting general construction projects up to $5 million. Work includes multiple disciplines to build on-base facilities. The government provides designs from 35-95% complete for the contractor to execute. The contract establishes a pool of contractors for small projects requiring general contractor services but not significant design work.

View the file

Other files for this federal contract opportunity

Other files attached to JBER Mini-MACC, newest first.
File Type Posted
Solicitation Amendment FA500021R00010007 SF 30.pdf PDF
Amendment 006 FA500021R00010006 SF 30.pdf PDF
Amend 5 QA 207-210.pdf PDF
Amendment 005 FA500021R00010005 SF 30.pdf PDF
Amend 004 QA 41-206 Amendment 004 20210527.pdf PDF
Attachment 3b Specs Seed Project Rev 01 20210521.pdf PDF
Attachment 3a SOW Seed Project Rev 01 20210521.pdf PDF
Attachment 3c Drawings Seed project B5327 Rev 01 20210521.pdf PDF
Amendment 004 FA500021R00010004 SF 30.pdf PDF
Q-A 1-40 Amendment 003 20210520.pdf PDF
Amendment FA500021R00010003 SF 30.pdf PDF
Amendment 002 Mini-MACC Site VIsit Sign in.pdf PDF
Amendment 002 FA500021R00010002 SF 30.pdf PDF
Solicitation - FA500021R0001 20210503 Amend 1.PDF.pdf PDF
Attachment 3 FOPR-Seed Project 20210503 Amend 1.pdf PDF
Solicitation Amendment FA500021R00010001 SF 30.pdf PDF
Attachment 1 Mini-MACC SOW 17 July 2020201221.pdf PDF
Attachment 1e Mini-MACC SOW - CAD GIS RECORD DRAWING DESIGN AND AS BUILT STANDARD 20201208.pdf PDF
Attachment 3 FOPR-Seed Project 20210430.pdf PDF
Attachment 3f DBA WD AK20210409.pdf PDF
Attachment 6 PPCL 20210430p.pdf PDF
Attachment 1d Mini-MACC SOW - ENV_PRECON Checklist 20201208.pdf PDF
Attachment 1g Mini-MACC SOW - 673ABW Form 3 Dig Permit (20 Version) 20201208.pdf PDF
Attachment 3a SOW Seed Project 20201208.pdf PDF
Attachment 5 Financial Data Form 20201208.pdf PDF
Attachment 9 Teaming consent 20201208.pdf PDF
Attachment 1g1 Mini-MACC SOW - Dig Permit Custom Map Elmo 20201208.pdf PDF
Solicitation - FA500021R0001 20210430.pdf PDF
Attachment 1b Mini-MACC SOW - JBER_Elmendorf_IFS_20201208.pdf PDF
Attachment 3b SPECs Seed project 20201208.pdf PDF
Attachment 3d AF 66 Seed Project 20201208.pdf PDF
Attachment 4 Price Schedule 20210204.pdf PDF
Attachment 1a Mini-MACC SOW - JBER Richardson IFS_20201208.pdf PDF
Attachment 1c Mini-MACC SOW - JBER Hazardous Waste Management Plan - 20201208.pdf PDF
Attachment 1f Mini-MACC SOW - Contractors Fire Safety Guide 20201208.pdf PDF
Attachment 1g2 Mini-MACC SOW - Dig Permit Custom Map Rich 20201208.pdf PDF
Attachment 1i TIA-568 Telecomm Cabling Standard.pdf PDF
Attachment 2 NAFI General Provisions-Clauses 20210322.pdf PDF
Attachment 3c Drawings Seed project 20201208.pdf PDF
Attachment 3e DD1354-fillable seed project 20201208.pdf PDF
Attachment 7 PPQ 20210419.pdf PDF
Attachment 8 Past Performance Supplement Worksheet 20210416.xlsx XLSX spreadsheet
Show all 42

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY Form Approved OMB No. 0704-0188

PAGE OF PAGES

1. FROM (Organization Name) 2. DATE PREPARED

(YYYYMMDD)

3. PROJECT/JOB

NUMBER

4. SERIAL NUMBER

7. CONTRACT

NUMBER(S)

5. TO (Organization - Installation Code and Name) 6. RPSUID/SITENAME/

INSTCODE/INSTNAME

8. TRANSACTION DETAILS

a. METHOD (X all that apply)

ACQUISITION BY CONSTRUCTION

TRANSFER BETWEEN SERVICES

CAPITAL IMPROVEMENT

INVENTORY ADJUSTMENT

PARTIAL ASSET

PLACED-IN-SERVICE

TOTAL ASSET

PLACED-IN-SERVICE

9.

ITEM

NO.

11.

CATEGORY

CODE

12.

CATCODE

DESCRIPTION

14.

SUST.

CODE

20.

FUND

SOURCE

15.

PRIMARY

UM

18.

SECONDARY UM

QUANTITY

17.

SECONDARY

UM

16.

PRIMARY UM

QUANTITY

19.

COST

23.

ITEM

REMARKS

24. STATEMENT OF COMPLETION. The facilities listed hereon are in accordance with maps, drawings, and specifications and change orders approved by the authorized representative of the using agency except for the deficiencies listed on the reverse side.

25a. ACCEPTED BY (Typed Name and Signature) b. DATE SIGNED

(YYYYMMDD)

a. TRANSFERRED BY (Typed Name and Signature)

c. TITLE (Area Engr./Base Engr./DPW/Construction Agent)

b. DATE SIGNED

(YYYYMMDD)

c. TITLE (DPW/RPAO) 26. PROPERTY

VOUCHER NUMBER

PREVIOUS EDITION MAY BE USED.̀̀

b. WHEN/EVENT (X one)

7a. PLACED-IN-

SERVICE DATE

(YYYYMMDD)

c. TYPE (X one)

DRAFT INTERIMFINAL

10a.

FACILITY

NO.

AREA OTHER 21.

FUND

ORG

22.

INTER-

EST

CODE

PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ORGANIZATION.

Adobe Designer 9.0

10b.

RPUID

13.

TYPE

CODE

The public reporting burden for this collection of information is estimated to average 30 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Washington Headquarters Services, Executive Services Directorate, Information Management Division, 4800 Mark Center Drive, Alexandria,VA 22350-3100 (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if itdoes not display a currently valid OMB control number.

DD FORM 1354, AUG 2013

27. CONSTRUCTION DEFICIENCIES (Attach blank sheet for continuations) 28. PROJECT REMARKS (Attach blank sheet for continuations)

INSTRUCTIONS

GENERAL. This form has been designed and issued for use in connection with the transfer of military real property between the military departments and to or from other government agencies. It supersedes ENG Forms 290 and 290B (formerly used by the Army and Air Force) and NAVDOCKS Form 2317 (formerly used by the Navy).

Existing instructions issued by the military departments relative to the preparation of DD Form 1354 are applicable to this revised form to the extent that the various items and columns on the superseded forms have been retained. The military departments may promulgate additional instructions, as appropriate.

For detailed instructions on how to fill out this form, please refer to Unified Facilities Criteria (UFC) 1-300-08, dated 16 April 2009 or later.

SPECIFIC DATA ITEMS.

1. From. Name of the transferring agency.

2. Date Prepared. Date of actual preparation. Enter all dates in YYYYMMDD format (Example: March 31, 2010 = 20100331).

3. Project/Job Number. Project number on a DD Form 1391 or Individual Job Order Number.

4. Serial Number. Sequential serial number assigned by the preparing organization (e.g., 2010-0001).

5. To. Name and address of the receiving installation, activity, and Service of the Real Property Accountable Officer (RPAO).

6. RPSUID/SITENAME/INSTCODE/INSTNAME. Site Unique Identifier and name or installation code and name where the constructed facility is located.

7. Contract Number(s). Contract number(s) for this project.

7a. Placed-In-Service Date. RPA Placed In Service Date. This is the date the asset is actually placed-in-service.

8. Transaction Details.

a. Method of Transaction. Mark (X) as many boxes as apply.

b. When/Event. When or event causing preparation of DD Form 1354. X only one box.

c. Type. Draft, interim, or final DD Form 1354. X only one box.

9. Item Number. Use a separate item number for each facility, no item number for additional usages.

10a. Facility Number. Assigned in accordance with the Installation/Base Master Numbering Plan.

10b. RPUID. Identified in Real Property Inventory.

11. Category Code. The category code describes the facility usage.

12. Catcode Description. The category code name which describes the facility usage.

13. Type. Type of construction: P for Permanent; S for Semi- permanent; T for Temporary.

14. Sustainability Code. Reports whether or not an asset meets the sustainability guidelines set forth in Section 2(g) of Executive Order 13514. Valid values are: 1 (asset meets the guidelines); 2 (asset does not meet the guidelines); 3 (asset not evaluated); 4 (asset not subject to guidelines).

15. Area: UM 1. Area unit of measure; use the unit of measure associated with the category code selected in 11.

16. Total Quantity UM 1. The total area for the measure identified in Item 15. Use negative numbers for demolition.

17. Other: UM 2. Unit of Measure 2 is the capacity or other measurement unit (e.g., LF, MB, EA, etc.).

18. Total Quantity UM 2. The total capacity/other for the measure identified in Item 17.

19. Cost. Cost for each facility; for capital improvements to existing facilities, show amount of increase only. If there is no increase for the capital improvement, enter N/A.

20. Fund Source. Enter the Fund Source Code for this item.

21. Funding Organization. Enter the code for the organization responsible for acquiring this facility.

22. Interest Code. Enter the code that reflects government interest or ownership in the facility.

23. Item Remarks. Remarks pertaining only to the item number identified in Item 9; show cost sharing.

24. Statement of Completion. Typed name, signature, title, and date of signature by the responsible transferring individual or agent.

25. Accepted By. Typed name, signature, title, and date of signature by the RPAO or accepting official.

26. Property Voucher Number. Next sequential number assigned by the RPAO in voucher register.

27. Construction Deficiencies. List construction deficiencies in project during contractor turnover inspection.

28. Project Remarks. Project level remarks and continuation of blocks.

DD FORM 1354 (BACK), AUG 2013

DD Form 1354, Transfer and Acceptance of DoD Real Property, August 2013

WHS/ESD/IMD

9.0.0.2.20120627.2.874785 TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY Form Approved OMB No. 0704-0188

PAGE

OF

PAGES

1. FROM (Organization Name)

2. DATE PREPARED

(YYYYMMDD)

3. PROJECT/JOB

NUMBER

4. SERIAL NUMBER

7. CONTRACT

NUMBER(S)

5. TO (Organization - Installation Code and Name)

6. RPSUID/SITENAME/

INSTCODE/INSTNAME

8. TRANSACTION DETAILS

a. METHOD (X all that apply)

ACQUISITION BY CONSTRUCTION

TRANSFER BETWEEN SERVICES

CAPITAL IMPROVEMENT

INVENTORY ADJUSTMENT

PARTIAL ASSET

PLACED-IN-SERVICE

TOTAL ASSET

PLACED-IN-SERVICE

9.

ITEM

NO.

11.

CATEGORY

CODE

12.

CATCODE

DESCRIPTION

14.

SUST.

CODE

20.

FUND

SOURCE

15.

PRIMARY

UM

18.

SECONDARY UM

QUANTITY

17.

SECONDARY

UM

16.

PRIMARY UM

QUANTITY

19.

COST

23.

ITEM

REMARKS

24. STATEMENT OF COMPLETION. The facilities listed hereon are in accordance with maps, drawings, and specifications and change orders approved by the authorized representative of the using agency except for the deficiencies listed on the reverse side.

25a. ACCEPTED BY (Typed Name and Signature)

b. DATE SIGNED

(YYYYMMDD)

a. TRANSFERRED BY (Typed Name and Signature)

c. TITLE (Area Engr./Base Engr./DPW/Construction Agent)

b. DATE SIGNED

(YYYYMMDD)

c. TITLE (DPW/RPAO)

26. PROPERTY

VOUCHER NUMBER

PREVIOUS EDITION MAY BE USED.̀̀

b. WHEN/EVENT (X one) 7a. PLACED-IN-

SERVICE DATE

(YYYYMMDD)

c. TYPE (X one)

DRAFT

INTERIM

FINAL

10a.

FACILITY

NO.

AREA

OTHER

21.

FUND

ORG

22.

INTER-

EST

CODE

PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ORGANIZATION.

Adobe Designer 9.0 10b.

RPUID

13.

TYPE

CODE

The public reporting burden for this collection of information is estimated to average 30 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Washington Headquarters Services, Executive Services Directorate, Information Management Division, 4800 Mark Center Drive, Alexandria,VA 22350-3100 (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if itdoes not display a currently valid OMB control number.

DD FORM 1354, AUG 2013

27. CONSTRUCTION DEFICIENCIES (Attach blank sheet for continuations)

28. PROJECT REMARKS (Attach blank sheet for continuations)

INSTRUCTIONS

GENERAL. This form has been designed and issued for use in connection with the transfer of military real property between the military departments and to or from other government agencies. It supersedes ENG Forms 290 and 290B (formerly used by the Army and Air Force) and NAVDOCKS Form 2317 (formerly used by the Navy).

Existing instructions issued by the military departments relative to the preparation of DD Form 1354 are applicable to this revised form to the extent that the various items and columns on the superseded forms have been retained. The military departments may promulgate additional instructions, as appropriate.

For detailed instructions on how to fill out this form, please refer to Unified Facilities Criteria (UFC) 1-300-08, dated 16 April 2009 or later.

SPECIFIC DATA ITEMS.

1. From. Name of the transferring agency.

2. Date Prepared. Date of actual preparation. Enter all dates in YYYYMMDD format (Example: March 31, 2010 = 20100331).

3. Project/Job Number. Project number on a DD Form 1391 or Individual Job Order Number.

4. Serial Number. Sequential serial number assigned by the preparing organization (e.g., 2010-0001).

5. To. Name and address of the receiving installation, activity, and Service of the Real Property Accountable Officer (RPAO).

6. RPSUID/SITENAME/INSTCODE/INSTNAME. Site Unique Identifier and name or installation code and name where the constructed facility is located.

7. Contract Number(s). Contract number(s) for this project.

7a. Placed-In-Service Date. RPA Placed In Service Date. This is the date the asset is actually placed-in-service.

8. Transaction Details.

a. Method of Transaction. Mark (X) as many boxes as apply.

b. When/Event. When or event causing preparation of DD Form 1354. X only one box.

c. Type. Draft, interim, or final DD Form 1354. X only one box.

9. Item Number. Use a separate item number for each facility, no item number for additional usages.

10a. Facility Number. Assigned in accordance with the Installation/Base Master Numbering Plan.

10b. RPUID. Identified in Real Property Inventory.

11. Category Code. The category code describes the facility usage.

12. Catcode Description. The category code name which describes the facility usage.

13. Type. Type of construction: P for Permanent; S for Semi- permanent; T for Temporary.

14. Sustainability Code. Reports whether or not an asset meets the sustainability guidelines set forth in Section 2(g) of Executive Order 13514. Valid values are: 1 (asset meets the guidelines); 2 (asset does not meet the guidelines); 3 (asset not evaluated); 4 (asset not subject to guidelines).

15. Area: UM 1. Area unit of measure; use the unit of measure associated with the category code selected in 11.

16. Total Quantity UM 1. The total area for the measure identified in Item 15. Use negative numbers for demolition.

17. Other: UM 2. Unit of Measure 2 is the capacity or other measurement unit (e.g., LF, MB, EA, etc.).

18. Total Quantity UM 2. The total capacity/other for the measure identified in Item 17.

19. Cost. Cost for each facility; for capital improvements to existing facilities, show amount of increase only. If there is no increase for the capital improvement, enter N/A.

20. Fund Source. Enter the Fund Source Code for this item.

21. Funding Organization. Enter the code for the organization responsible for acquiring this facility.

22. Interest Code. Enter the code that reflects government interest or ownership in the facility.

23. Item Remarks. Remarks pertaining only to the item number identified in Item 9; show cost sharing.

24. Statement of Completion. Typed name, signature, title, and date of signature by the responsible transferring individual or agent.

25. Accepted By. Typed name, signature, title, and date of signature by the RPAO or accepting official.

26. Property Voucher Number. Next sequential number assigned by the RPAO in voucher register.

27. Construction Deficiencies. List construction deficiencies in project during contractor turnover inspection.

28. Project Remarks. Project level remarks and continuation of blocks.

DD FORM 1354 (BACK), AUG 2013

Page number of this page.:
Total number of pages.:
1. From (Organization name).:
3. Project/job number.:
4. Serial number.:
5. To (Organization - installation code, name, and service of Real Property Accountable Officer (RPAO)).:
6. Real Property Site Unique Identifier and site name or installation code and name.:
7. Contract number(s).:
8. Transaction details. a. Method. Press space bar to mark X if acquisition by construction.: Off
X if transfer between services.: Off
X if capital improvement.: Off
X if inventory adjustment.: Off
c. Type. X first box if draft, second box if final, or third box if interim.:
9. Item number, line 1 of 10. Use a separate item number for each facility.:
10.a. Facility number. Unique facility number identified in Real Property Inventory.:
10.b. Real property unique identifier.:
11. Category code.:
12. Catcode Description. Code name which describes the facility usage.:
13. Type of construction. P for Permanent, S for Semipermanent, T for Temporary.:
14. Sustainability code. Enter 1, 2, 3, or 4 (see instructions).:
14. Sustainability code. Enter 1, 2, 3, or 4 (see instructions).:
14. Sustainability code. Enter 1, 2, 3, or 4 (see instructions).:
14. Sustainability code. Enter 1, 2, 3, or 4 (see instructions).:
14. Sustainability code. Enter 1, 2, 3, or 4 (see instructions).:
14. Sustainability code. Enter 1, 2, 3, or 4 (see instructions).:
14. Sustainability code. Enter 1, 2, 3, or 4 (see instructions).:
14. Sustainability code. Enter 1, 2, 3, or 4 (see instructions).:
14. Sustainability code. Enter 1, 2, 3, or 4 (see instructions).:
14. Sustainability code. Enter 1, 2, 3, or 4 (see instructions).:
15. Area. Primary unit of measure (use the unit of measure associated with the category code selected in 11).:
16. Area. Primary Unit of Measure Quantity. The total area for the measure identified in item 14. Use negative numbers for demolition.:
Other. 17. Secondary unit of measure. Capacity or other measurement unit (e.g., LF, MB, EA, etc.).:
18. Secondary unit of measure quantity. Total capacity/other for measure identified in item 16.:
19. Cost. Cost for each facility. Show amount of increase only, or N/A.:
20. Fund source. Fund source code for this item.:
21. Funding Organization. Code for organization responsible for acquiring facility.:
22. Interest Code. Code that reflects government interest or ownership in facility.:
23. Item remarks. (Pertaining only to the item number in Column 9.):
9. Item number, line 2.:
10.a. Facility number. Unique facility number identified in Real Property Inventory.:
10.b. Real property unique identifier.:
11. Category code.:
12. Catcode Description. Code name which describes the facility usage.:
13. Type of construction. P for Permanent, S for Semipermanent, T for Temporary.:
14. Area. Primary unit of measure (use the unit of measure associated with the category code selected in 11).:
15. Area. Primary Unit of Measure Quantity. The total area for the measure identified in item 14. Use negative numbers for demolition.:
Other. 16. Secondary unit of measure. Capacity or other measurement unit (e.g., LF, MB, EA, etc.).:
17. Secondary unit of measure quantity. Total capacity/other for measure identified in item 16.:
18. Cost. Cost for each facility. Show amount of increase only, or N/A.:
19. Fund source. Fund source code for this item.:
20. Funding Organization. Code for organization responsible for acquiring facility.:
21. Interest Code. Code that reflects government interest or ownership in facility.:
22. Item remarks. (Pertaining only to the item number in Column 9.):
9. Item number, line 3:
10.a. Facility number. Unique facility number identified in Real Property Inventory.:
10.b. Real property unique identifier.:
11. Category code.:
12. Catcode Description. Code name which describes the facility usage.:
13. Type of construction. P for Permanent, S for Semipermanent, T for Temporary.:
14. Area. Primary unit of measure (use the unit of measure associated with the category code selected in 11).:
15. Area. Primary Unit of Measure Quantity. The total area for the measure identified in item 14. Use negative numbers for demolition.:
Other. 16. Secondary unit of measure. Capacity or other measurement unit (e.g., LF, MB, EA, etc.).:
17. Secondary unit of measure quantity. Total capacity/other for measure identified in item 16.:
18. Cost. Cost for each facility. Show amount of increase only, or N/A.:
19. Fund source. Fund source code for this item.:
20. Funding Organization. Code for organization responsible for acquiring facility.:
21. Interest Code. Code that reflects government interest or ownership in facility.:
22. Item remarks. (Pertaining only to the item number in Column 9.):
9. Item number, line 4.:
10.a. Facility number. Unique facility number identified in Real Property Inventory.:
10.b. Real property unique identifier.:
11. Category code.:
12. Catcode Description. Code name which describes the facility usage.:
13. Type of construction. P for Permanent, S for Semipermanent, T for Temporary.:
14. Area. Primary unit of measure (use the unit of measure associated with the category code selected in 11).:
15. Area. Primary Unit of Measure Quantity. The total area for the measure identified in item 14. Use negative numbers for demolition.:
Other. 16. Secondary unit of measure. Capacity or other measurement unit (e.g., LF, MB, EA, etc.).:
17. Secondary unit of measure quantity. Total capacity/other for measure identified in item 16.:
18. Cost. Cost for each facility. Show amount of increase only, or N/A.:
19. Fund source. Fund source code for this item.:
20. Funding Organization. Code for organization responsible for acquiring facility.:
21. Interest Code. Code that reflects government interest or ownership in facility.:
22. Item remarks. (Pertaining only to the item number in Column 9.):
9. Item number, line 5.:
10.a. Facility number. Unique facility number identified in Real Property Inventory.:
10.b. Real property unique identifier.:
11. Category code.:
12. Catcode Description. Code name which describes the facility usage.:
13. Type of construction. P for Permanent, S for Semipermanent, T for Temporary.:
14. Area. Primary unit of measure (use the unit of measure associated with the category code selected in 11).:
15. Area. Primary Unit of Measure Quantity. The total area for the measure identified in item 14. Use negative numbers for demolition.:
Other. 16. Secondary unit of measure. Capacity or other measurement unit (e.g., LF, MB, EA, etc.).:
17. Secondary unit of measure quantity. Total capacity/other for measure identified in item 16.:
18. Cost. Cost for each facility. Show amount of increase only, or N/A.:
19. Fund source. Fund source code for this item.:
20. Funding Organization. Code for organization responsible for acquiring facility.:
21. Interest Code. Code that reflects government interest or ownership in facility.:
22. Item remarks. (Pertaining only to the item number in Column 9.):
9. Item number, line 6.:
10.a. Facility number. Unique facility number identified in Real Property Inventory.:
10.b. Real property unique identifier.:
11. Category code.:
12. Catcode Description. Code name which describes the facility usage.:
13. Type of construction. P for Permanent, S for Semipermanent, T for Temporary.:
14. Area. Primary unit of measure (use the unit of measure associated with the category code selected in 11).:
15. Area. Primary Unit of Measure Quantity. The total area for the measure identified in item 14. Use negative numbers for demolition.:
Other. 16. Secondary unit of measure. Capacity or other measurement unit (e.g., LF, MB, EA, etc.).:
17. Secondary unit of measure quantity. Total capacity/other for measure identified in item 16.:
18. Cost. Cost for each facility. Show amount of increase only, or N/A.:
19. Fund source. Fund source code for this item.:
20. Funding Organization. Code for organization responsible for acquiring facility.:
21. Interest Code. Code that reflects government interest or ownership in facility.:
22. Item remarks. (Pertaining only to the item number in Column 9.):
9. Item number, line 7.:
10.a. Facility number. Unique facility number identified in Real Property Inventory.:
10.b. Real property unique identifier.:
11. Category code.:
12. Catcode Description. Code name which describes the facility usage.:
13. Type of construction. P for Permanent, S for Semipermanent, T for Temporary.:
14. Area. Primary unit of measure (use the unit of measure associated with the category code selected in 11).:
15. Area. Primary Unit of Measure Quantity. The total area for the measure identified in item 14. Use negative numbers for demolition.:
Other. 16. Secondary unit of measure. Capacity or other measurement unit (e.g., LF, MB, EA, etc.).:
17. Secondary unit of measure quantity. Total capacity/other for measure identified in item 16.:
18. Cost. Cost for each facility. Show amount of increase only, or N/A.:
19. Fund source. Fund source code for this item.:
20. Funding Organization. Code for organization responsible for acquiring facility.:
21. Interest Code. Code that reflects government interest or ownership in facility.:
22. Item remarks. (Pertaining only to the item number in Column 9.):
9. Item number, line 8.:
10.a. Facility number. Unique facility number identified in Real Property Inventory.:
10.b. Real property unique identifier.:
11. Category code.:
12. Catcode Description. Code name which describes the facility usage.:
13. Type of construction. P for Permanent, S for Semipermanent, T for Temporary.:
14. Area. Primary unit of measure (use the unit of measure associated with the category code selected in 11).:
15. Area. Primary Unit of Measure Quantity. The total area for the measure identified in item 14. Use negative numbers for demolition.:
Other. 16. Secondary unit of measure. Capacity or other measurement unit (e.g., LF, MB, EA, etc.).:
17. Secondary unit of measure quantity. Total capacity/other for measure identified in item 16.:
18. Cost. Cost for each facility. Show amount of increase only, or N/A.:
19. Fund source. Fund source code for this item.:
20. Funding Organization. Code for organization responsible for acquiring facility.:
21. Interest Code. Code that reflects government interest or ownership in facility.:
22. Item remarks. (Pertaining only to the item number in Column 9.):
9. Item number, line 9.:
10.a. Facility number. Unique facility number identified in Real Property Inventory.:
10.b. Real property unique identifier.:
11. Category code.:
12. Catcode Description. Code name which describes the facility usage.:
13. Type of construction. P for Permanent, S for Semipermanent, T for Temporary.:
14. Area. Primary unit of measure (use the unit of measure associated with the category code selected in 11).:
15. Area. Primary Unit of Measure Quantity. The total area for the measure identified in item 14. Use negative numbers for demolition.:
Other. 16. Secondary unit of measure. Capacity or other measurement unit (e.g., LF, MB, EA, etc.).:
17. Secondary unit of measure quantity. Total capacity/other for measure identified in item 16.:
18. Cost. Cost for each facility. Show amount of increase only, or N/A.:
19. Fund source. Fund source code for this item.:
20. Funding Organization. Code for organization responsible for acquiring facility.:
21. Interest Code. Code that reflects government interest or ownership in facility.:
22. Item remarks. (Pertaining only to the item number in Column 9.):
9. Item number, line 10.:
10.a. Facility number. Unique facility number identified in Real Property Inventory.:
10.b. Real property unique identifier.:
11. Category code.:
12. Catcode Description. Code name which describes the facility usage.:
13. Type of construction. P for Permanent, S for Semipermanent, T for Temporary.:
15. Area. Primary unit of measure (use the unit of measure associated with the category code selected in 11).:
16. Area. Primary Unit of Measure Quantity. The total area for the measure identified in item 14. Use negative numbers for demolition.:
Other. 17. Secondary unit of measure. Capacity or other measurement unit (e.g., LF, MB, EA, etc.).:
18. Secondary unit of measure quantity. Total capacity/other for measure identified in item 16.:
19. Cost. Cost for each facility. Show amount of increase only, or N/A.:
20. Fund source. Fund source code for this item.:
21. Funding Organization. Code for organization responsible for acquiring facility.:
22. Interest Code. Code that reflects government interest or ownership in facility.:
23. Item remarks. (Pertaining only to the item number in Column 9.):
23. Statement of Completion. a. Transferred by (name).:
Signature.:
c. Title (Area engineer/base engineer/DPW/Construction Agent).:
24.a. Accepted by (name).:
Signature.:
c. Title (DPW/RPAO).:
25. Property voucher number.:
2. Date prepared (4 digit year, 2 digit month, 2 digit day).:
7.a. Placed-in-Service Date (4 digit year, 2 digit month, 2 digit day).:
b. Date signed (4 digit year, 2 digit month, 2 digit day).:
b. Date signed (4 digit year, 2 digit month, 2 digit day).:
26. Construction deficiencies. Attach blank sheet for continuations.:
27. Project remarks. Attach blank sheet for continuations.:

File details come from the government source that posted it. Updated .