Amend 5 - ATT 22-518-22-700.Bedford.EHRM.IFC.Add1.B20.2060225.pdf
PDF 2 MB Posted
- Solicitation number
- 36C77626R0003
About this file
This document is an architectural drawing set for infrastructure upgrades at the Edith Nourse Memorial Veterans Hospital located at 200 Springs Road, Bedford, MA 01730. The project, identified as EHRM Infrastructure Upgrades (Project Number 518-22-700), is issued for construction and prepared by TRIPLE C - The A/E Group (Hartford, CT).
The drawings specify interior finishes and door modifications for Office 1B on the first level, including removal of existing doors and frames with installation of new 45-minute fire-rated hollow metal doors and frames. Interior finish requirements include walls painted in California Paints to match Benjamin Moore Manchester Tan HC-81 (eggshell) for walls and Benjamin Moore White Down OC-131 (semi-gloss) for metal doors and trim. The contractor is responsible for all costs associated with moving, storing, and returning furnishings and equipment, as well as disassembly and reassembly of systems furniture in accordance with manufacturer warranties. The drawings note potential asbestos abatement at floor penetrations and require coordination with mechanical, electrical, and door hardware specifications (Section 08 71 00). All material substitutions require owner approval through the VA Interior Design Department prior to installation. The document revision date is February 25, 2026.
View the file
Other files
Show 40 more
Latest 50 of 105 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHEET SYMBOL LEGEND
KEYNOTES
GENERAL NOTES
EXISTING CONSTRUCTION TO REMAIN
EXISTING CONSTRUCTION TO BE DEMOLISHED
NEW CONSTRUCTION, WITH PARTITION TYPE
A
A. SEE GENERAL NOTES AND PLANS FOR TYPICAL GENERAL PROJECT
REQUIREMENTS AND PROJECT LOCATION DRAWINGS.
B. SEE MECHANICAL AND ELECTRICAL DRAWINGS FOR ADDITIONAL
SYSTEMS INFORMATION.
C. DATE OF THIS DRAWING SET. CONTRACTOR SHALL FIELD VERIFY ALL
DIMENSIONS, CONDITIONS, AND SITE-SPECIFIC INFORMATION AT THE
TIME OF BIDDING.
D. CONTRACTOR IS RESPONSIBLE FOR ALL COSTS ASSOCIATED
WITH MOVING, STORING AND RETURNING FURNISHINGS AND
EQUIPMENT TO THE PROPOSED WORK AREA(S). ANY
DISASSEMBLY AND REASSEMBLY OF SYSTEMS FURNITURE IN THE
PROPOSED WORK AREAS IS THE RESPONSIBILITY OF THE
CONTRACTOR AND MUST FOLLOW THE MANUFACTURER'S
WARRANTY.
PARTITION RATING GRAPHICS:
4 HR FIRE BARRIER
3 HR FIRE BARRIER
2 HR FIRE & SMOKE BARRIER
2 HR FIRE BARRIER
2 HR FIRE BARRIER/SHAFT
1 HR FIRE & SMOKE BARRIER
1 HR FIRE BARRIER
1 HR FIRE BARRIER/SHAFT
SMOKE PARTITION (NON RATED)
NON RATED
PARTITION RATING GRAPHIC DESIGNATION: PRIORITY
1 HIGHEST
5 LOWEST
PARTITIONS REQUIRED TO BE SMOKE RESISTANT, FIRE
RESISTANT, OR BOTH FIRE AND SMOKE RESISTANT ARE SHOWN
GRAPHICALLY ON PLANS WITH HATCH PATTERNS.
20A-401
B8
OFFICE
1B1B
BREAK
RM
MOBILITY
MGR
OFFICE
1A1A
BREAK
RM
OFFICE
1B
110 SF
MOBILITY
MGR
OFFICE
1A1A
B
H W
-S H
-3 F
OFFICE
1B
110 SF
INTERIOR FINISHES
PAINT
FIELD
CALIFORNIA PAINTS*
TO MATCH BENJAMIN MOORE
MANCHESTER TAN HC-81
ARCHITECT/ENGINEERS:
INTERIOR FINISHES
Drawing Title
Approved: Project Director
Project Title
Location
Date Checked Drawn
NB KLM
Project Number
Board Number
Office of Construction and Facilities Management
*BASIS OF DESIGN
**MATCH EXISTING CAMPUS PAINT COLORS
EHRM INFRASTRUCTURE
UPGRADES
518-22-700
200 Springs Road, Bedford, MA 01730
EDITH NOURSE MEMORIAL VETERANS HOSPITAL
P-1
DIGITAL IMAGES MAY HAVE COLOR INACCURACIES, REFER
TO ACTUAL SAMPLE FOR TRUEST COLOR DEPICTION
PAINT
METAL DOORS & TRIM
CALIFORNIA PAINTS*
TO MATCH BENJAMIN MOORE
WHITE DOWN OC-131
P-2
E4
TYPICAL FRAME
H E
IG
H
T
2" WIDTH 2"
E6
FRAME TYPE ELEVATIONS DOOR TYPE ELEVATIONS
F
FLUSH
1/2" 1/2"
VARIES
SEE PLAN
WALL - SEE PLAN
FOR TYPE
SEALANT - EA. SIDE
& ALL AROUND,
TYP.
HOLLOW METAL
FRAME
/2
V
A R
IE
S
S E
E P
L A
N
/2
UNO
4" 2"
ADJACENT WALL
WHERE OCCURS
SEALANT - EA SIDE &
ALL AROUND, TYP.
HOLLOW METAL FRAME
WALL - SEE PLAN
FOR TYPE
OFFICE
1B1B
MOBILITY
MGR
OFFICE
1A1A
BREAK
RM
MOBILITY
MGR
OFFICE
1A1A
OFFICE
1B1B
BREAK
RM
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
TRIPLE C - The A/E Group
100 Pearl Street, 14th Floor
Hartford, CT 06103
MAT PERKINS
(860)270-0753
A u to d e s k D o c s /3
C
R
.P ro je c t.
-2
-7
.E H
R M
.I U
.B e d fo rd
.M A
.R
/5
-2 -7
.B e d fo rd .E
H R
M .A
R C
H .B
R
.r v t
/2
/2
:1
:5
A
M
20A-401
ARCHITECTURAL ENLARGED VIEWS - FIRST
LEVEL
518-22-700
06/04/2025 M. Perkins K. McDermott
ISSUED FOR
CONSTRUCTION
EHRM INFRASTRUCTURE
UPGRADES
200 Springs Rd, Bedford, MA 01730
NTS
C2
COLOR BOARD
3" = 1'-0" E4
HOLLOW METAL HEAD DETAIL
3" = 1'-0"
E6
HOLLOW METAL JAMB DETAIL
1/4" = 1'-0" E2
DOOR AND FRAME TYPES ELEVATIONS
1/32" = 1'-0" F8
FIRST LEVEL REFERENCE PLAN
1 PROVIDE TEMPORARY DUST TIGHT BARRIER AROUND WORK AREA
DURING ACTIVITIES WHICH PRODUCE DUST
2 REMOVE EXISTING DOOR AND FRAME
3 EXISTING CEILING TO REMAIN
4 NEW 45 MIN. FIRE RATED DOOR. SEE DOOR SCHEDULE AND
SPECIFICATIONS FOR ADDITIONAL INFORMATION. MODIFY DOOR AS
REQUIRED FOR NEW ACCESS CONTROL HARDWARE.
5 POTENTIAL ABATEMENT AT FLOOR FOR FLOOR PENETRATIONS.
REFER TO COVER SHEET FOR KNOWN ACM ITEMS WITHIN THIS
BUILDING.
1/4" = 1'-0" D8
ARCHITECTURAL FLOOR PLAN - FIRST LEVEL
- RM 1B - DEMO
1/4" = 1'-0" B8
ARCHITECTURAL FLOOR PLAN - FIRST LEVEL
- RM 1B - NEW
NOT TO SCALE
B4
FIRST LEVEL EXISTING RM 1B
DOOR AND FRAME SCHEDULE
IDENTIFICATION DIMENSIONS PANEL FRAME DETAIL FIRE
RATING
HARDWARE
NOTESLEVEL ROOM NO. ROOM NAME DOOR NO. W1 H T TYPE MATERIAL FINISH GLAZING UNDERCUT TYPE MATERIAL FINISH HEAD JAMB GROUP ELECTRICAL
LEVEL 1 1B OFFICE 1B 3' - 0" 7' - 0" 1 3/4" F HM P-2 NONE 3/8" 1 HM P-2 E4/ 20A-401 E6/ 20A-401 45 MIN. HW-SH-3F SEE SPEC 1
FINISH LEGEND
SYMBOL FINISH TYPE MANUFACTURER COLLECTION STYLE / TYPE COLOR SIZE SPEC SECTION NOTES
P-1 PAINT CALIFORNIA PAINTS* - EGGSHELL TO MATCH BENJAMIN MOORE MANCHESTER TAN HC-81 - 09 91 00 FIELD
P-2 PAINT CALIFORNIA PAINTS* - SEMI-GLOSS TO MATCH BENJAMIN MOORE WHITE DOWN OC-131 - 09 91 00 METAL DOORS & TRIM
ROOM FINISH SCHEDULE
LEVEL NO. NAME
FLOOR WALLS CEILING
NOTESFINISH BASE
NORTH EAST SOUTH WEST
MATERIAL FINISHMATERIAL FINISH MATERIAL FINISH MATERIAL FINISH MATERIAL FINISH
LEVEL 1 1B OFFICE EXISTING EXISTING GWB EXISTING GWB EXISTING GWB EXISTING GWB EXISTING EXISTING REPAIR EXISTING FINISHES AS NEEDED FOR NEW DOOR INSTALLATION.
*Materials are approved as basis of design, all material substitutions are subject to owner approval. Contractor to provide VA Interior Design Department with samples of all specified finish materials. VA COR/ Interior Design department shall approve all finishes prior to installation.
1/4" = 1'-0" B6
ARCHITECTURAL CEILING PLAN - FIRST
LEVEL - RM 1B - NEW
1/4" = 1'-0" D6
ARCHITECTURAL CEILING PLAN - FIRST
LEVEL - RM 1B - DEMO
1. SEE SPECIFICATIONS 08 71 00 FOR DOOR HARDWARE REQUIREMENTS. COORDINATE WITH ELECTRICAL.
Number Revisions: Date:
1 Revision 1 Date 1
02/25/2026
| Sheets |
| 20A-401 - ARCHITECTURAL ENLARGED VIEWS - FIRST LEVEL |
File details come from the government source that posted it. Updated .