This federal construction solicitation and related technical specifications call for renovation and expansion of the dialysis clinic at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The project includes demolition of an existing vacant ward to build a new 11,000 square foot dialysis clinic, along with associated construction services such as concrete, electrical, plumbing, mechanical, and architectural work. Specialty furnishings and a dedicated air handling unit are required. Hazardous materials abatement for asbestos is also included. The solicitation is scheduled to be posted to FedBizOpps on May 13, 2020 with a bid opening on June 16, 2020 and a 540-day period of performance. The price range is estimated between $2-5 million. The procurement is set aside 100% for Service-Disabled Veteran Owned Small Businesses and offerors must be verified as SDVOSBs or VOSBs in the VIP database at time of submission.

View the file

Other files

File Type Posted
Amend 0005 00 01 10 TABLE OF CONTENTS.pdf PDF
Amend 0005 22 67 19.16 REVERSE-OSMOSIS WATER EQUIPMENT.pdf PDF
Amend 0005 08 71 13.11 LOW ENERGY DOOR OPERATORS.pdf PDF
S06 36C25220B0021 0005.pdf PDF
Amend 0005 01 91 00 COMMISSIONING REQUIREMENTS.pdf PDF
Amend 0005 01 01 10 SN SPECIAL NOTES.pdf PDF
Amend 0005 11 73 00 CEILING MOUNT PATIENT LIFT.pdf PDF
Amend 0005 14 92 00 PNEUMATIC TUBE SYSTEM.pdf PDF
Amend 0003 Photos Revised.pdf PDF
S06 36C25220B0021 0004.pdf PDF
AI601 - FINISH SCHEDULES.pdf PDF
Wage Determination 6.19.20.pdf PDF
Amend 0003 Photos.pdf PDF
SECTION 10 21 23 - CUBICLE CURTAIN TRACKS.pdf PDF
36C25220B0021 0003.pdf PDF
S06 Att Amend 0002 00 01 10 - TABLE OF CONTENTS.pdf PDF
S06 Att Amend 0002 EP100 - BASEMENT FLOOR OVERALL PLAN.pdf PDF
S06 Att Amend 0002 AI201 - INTERIOR FINISHES ELEVATIONS.pdf PDF
S06 Att Amend 0002 AE601 - DOOR_WINDOW SCHEDULE.pdf PDF
S06 36C25220B0021 0002.pdf PDF
S06 Att Amend 0002 28 05 13 - CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY.pdf PDF
S06 Att Amend 0002 01 74 19 - CONSTRUCTION WASTE MANAGEMENT.pdf PDF
S06 Att Amend 0002 GC101 - INFECTION CONTROL_PHASING PLAN.pdf PDF
S06 Att Amend 0002 09 05 16 - FLOOR PREP1.pdf PDF
S06 Att Amend 0002 ET102 - SEVENTH FLOOR SYSTEMS PLAN - DIVISION 28.pdf PDF
S06 Att Amend 0002 AD101 - SEVENTH FLOOR DEMOLITION PLAN.pdf PDF
S06 Att Amend 0002 MD101 - MECHANICAL DEMOLITION FLOOR PLAN - 7TH FLOOR.pdf PDF
S06 Att Amend 0002 10 14 00 - SIGNAGE.pdf PDF
S06 Att Amend 0002 12 24 00 - WINDOW SHADES.pdf PDF
S06 Att Site Visit Sign In 5.28.20.pdf PDF
S06 Att Amend 0002 03 30 53 - CAST-IN-PLACE CONCRETE.pdf PDF
S06 Att Amend 0002 QH101 - SEVENTH FLOOR EQUIPMENT PLAN.pdf PDF
S06 Att Amend 0002 01 91 00 - COMMISSIONING REQUIREMENTS.pdf PDF
S06 Att Amend 0002 22 07 11 - PLUMBING INSULATION.pdf PDF
S06 Att Amend 0002 ET101D - SEVENTH FLOOR DEMOLITION PLAN.pdf PDF
S06 Att Amend 0002 22 11 00 - FACILITY WATER DISTRIBUTION.pdf PDF
S06 Att Amend 0002 AE501 - BUILDING DETAILS.pdf PDF
S06 Att Amend 0002 AI901 - SIGNAGE PLAN.pdf PDF
S06 Att Amend 0002 AI101 - FINISH WALL TREATMENT PLAN.pdf PDF
S06 Att Amend 0002 EP401 - ONE LINE DIAGRAM.pdf PDF
S06 Att Wage Determination 6.5.20.pdf PDF
Site Visit Sign In 5.20.20.pdf PDF
36C25220B0021 0001.docx DOCX document
Amend 0001 Specification 22 63 00.pdf PDF
Amend 0001 Specification 00 01 10.pdf PDF
Amend 0001 Specification 08 14 00.pdf PDF
Amend 0001 Specification 09 06 00.pdf PDF
Amend 0001 J_A Patient Ceiling Lift.pdf PDF
36C25220B0021-011.pdf PDF
36C25220B0021-012.pdf PDF
Show 40 more

Latest 50 of 72 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Milwaukee VAMC 05-01-15

695-19-131 Renovate & Expand Dialysis Clinic 100% Construction Documents

Milwaukee, WI 53295 March 26, 2020

10 21 23 - 1

SECTION 10 21 23

CUBICLE CURTAIN TRACKS

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies cubicle curtain track (C.C.T.) This is sole sourced to Curtain Track Rail Support System (CTRSS), Barrier Free Lift

RX-6001 and cubical curtain fabric .

1.2 RELATED WORK

A. Steel shapes for suspending track assembly: Section 05 50 00, METAL

FABRICATIONS.

B. Acoustical ceiling tile and suspension systems Section 09 51 00, ACOUSTICAL CEILINGS.

1.3 SUBMITTALS

A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT

DATA, AND SAMPLES.

B. Samples:

1. 305 mm (12 inch) long piece of cubicle curtain track with carrier access and end stop.

C. Shop Drawings: Showing layout of tracks and method of anchorage.

D. Manufacturer's Literature and Data:

1. Cubicle curtain track.

1.4 DELIVERY, STORAGE AND HANDLING

A. Deliver material in original package marked to identify the contents, brand name, and the name of the manufacturer or supplier.

B. Store in dry and protected location. Store so as to not bend or warp the tracks.

C. Do not open packages until contents are needed for installation, unless verification inspection is required.

1.5 WARRANTY

A. Construction Warranty: Cubicle curtain tracks are subject to the terms of the Article “Warranty of Construction,” FAR clause 52.246-21.

1.6 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.

10 21 23 - 2

B. ASTM International (ASTM):

B221-14.................Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Shapes, and Tubes

B221M-13................Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Shapes, and Tubes (Metric)

B456-11.................Electrodeposited Coatings for Copper Plus

Nickel Plus Chromium and Nickel Plus Chromium

C. Aluminum Association (AA):

DAF 45-09...............Designation System for Aluminum Finishes

D. American Architectural Manufacturers Association (AAMA):

2603-13.................Voluntary Specification, Performance

Requirements and Test Procedures for Pigmented

Organic Coatings on Aluminum Extrusions and

Panels

E. The National Association of Architectural Metal Manufacturers (NAAMM):

AMP 500 Series..........Metal Finishes Manual

PART 2 - PRODUCTS

2.1 CUBICLE CURTAIN TRACKS

A. Basis of Design were On The Right Track.

B. Wall Mounted Type:

1. Contractor shall submit bid using only flat track system and curtain fabric specified.

2. The Flat Track system cannot use ceiling supports and needs to be engineered to mount from wall to wall. Each Flat Track installation must have custom bends as needed pursuant to each location’s requirement. The track system must be seamless and manufactured as one solid track to increase overall strength and meet the facilities requirements.

3. The Flat Track will include custom “Easy On – Easy Off” cubicle curtains that works with the Flat Track support system. Cubicle

Curtains must be manufactured as one continuous curtain across the length of the Flat Track rail, the cubicle system must not use enclosed carrier track hooks and meet all other requirements needed by the facility such as using fabric that meets or exceeds NFPA701 standards.

C. Curtain Carriers: Carriers are integral to the curtain.

10 21 23 - 3

1. The Flat Track support beam is designed to work with an Easy On/

Easy Off open C-type fast install and removal curtain system. Cubicle curtains are manufactured flat and typically sized approximately 10% wider than the track length, unless specified otherwise. The curtain height and width will remain consistent 68 inch x 80 inch and curtains should be finished approximately 8-10 inches above finished floor, as suggested by Joint Commission’s patient privacy standards. This distance will allow for ease in periodic floor cleaning and prevents mop and/or floor cleaner from coming in direct contact with cubicle curtain, soiling the treatment. The cubicle curtains should be 68 inch x 80 inch and they must use a commercial grade of molded synthetic polymer C-type rings that allow for Easy On-Easy Off handling by environmental services and nursing staff. Th ring system must mount on the .25 inch x 1.5 inch Flat Track and must glide effortlessly without binding over the life of the curtain. The C-type rings will be inserted and spaced 6.75 inch apart on a 4.75 inch NFPA approved vinyl breathable mesh fabric that is integrated to ½ inch vertical and horizontal hole size opening mesh (minimum 70% open) allows for fire sprinkler penetration in the unfortunate case of fire. The mesh will be required to have a minimum 18 inch drop from sprinkler head to fabric. If the distance of the Flat Track is farther than the 18 inch drop, then mesh may not be necessary to meet patient privacy standards.

The bottom hem of the cubicle curtain is double folded and 2 inches.

The side hems are double folded and 1 inch. All hems and seams are sewn with a double needle lock stitch. All vertical seams are serge and sewn with a double needle lock stitch for maximum durability.

2. The cubicle fabric will contain the following characteristics to be approved by the facility: meet NFPA 701 flame spread requirements for vertical flammability (flame spread certification paperwork must be supplied.

3. Fabric: As indicated in Finish Schedule with written approval upon submittal prior to fabrication. A minimum 10% “attic stock” of curtains will be left for future use.

2.4 FASTENERS

A. Exposed Fasteners, Screws and Bolts: The Flat Track support beam is secured to the wall(s) using 4 each ¼ inch Hilti Toggle Bolt’s. The bolts shall be brilliant white in color to match the mounting plate.

10 21 23 - 4

2.5 FINISHES

A. Aluminum: Finishing shall consist of a cleaning process consisting of a degreasing and rinse cycle followed by a hot air drying prior to finishing. The finish shall be powder coated with U.V. resistant TGIC polyester “brilliant white” in color. Finished coat shall be 3 to 5 millimeters thick with a cure temperature of 375 to 400 degrees

Fahrenheit. An optional antimicrobial powder coat finish is available.

The antimicrobial powder coating technology uses environmentally sustainable silver ions to resist growth and spread of microbes even on lightly scratched surface.

2.6 FABRICATION

A. The Flat Track support beam is 1.5 inches high, .25 inches thick having a .25 inch radius on top and bottom of the track and weighs .816 pounds per foot. Vertical ceiling supports are not required for this product for lengths under 12 feet. The curtain support beam deflection for an

8 foot length loaded at the center at 35 pounds is 1/2 inch without permanent deformation. The curtain support will be attached to the walls at both ends using a .1875 inch thick by 2 inch wide by 4 inch high mounting plate having 4 chamfered 5/16 inch mounting holes. The base plates will be welded to the curtain support bar 360 degrees around with a minimum of .125 inch fillet aluminum weld. All radius bends will be smooth rolled from one continuous piece of 6036 T6 high grade aluminum and inspected for weld fractures and stress prior to finishing.

E. Shop assemble components and package complete with anchors and fittings.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install tracks after finish painting and ceiling finishing operations are complete.

B. The Flat Track system must be mounted halfway between the ceiling and the top of the door jamb/ opening into each room. The System will allow the curtains to stack without interference from patients walking into the room.

D. Anchor surface mounted curtain tracks to concrete, plaster and gypsum board.

10 21 23 - 5

H. Remove damaged or defective components and replace with new components or repair to the original condition.

I. Install track rigid, plumb, level and true, and securely anchored to the overhead construction.

J. Verify that carrier units operate smoothly and easily over the full range of travel.

- - - E N D - - -