This federal contract opportunity notice provides details for Project # 695-19-131 to renovate and expand the dialysis clinic at the Clement J. Zablocki VA Medical Center in Milwaukee, WI. The contractor shall demolish and reconstruct 7AS of building 111 to create a new 11,000 square foot dialysis clinic, including demolition, various construction trades, medical equipment, and specialty furnishings. Sole source items and hazardous materials abatement are required. The project value is estimated between $2-5 million with a 540-day period of performance. The solicitation for this project will be posted on May 13, 2020 to FedBizOpps with a bid opening on June 16, 2020 and a pre-bid conference. Pursuant to applicable regulations, the solicitation will be issued as a 100% Service Disabled Veteran Owned Small Business set-aside.
View the file
Other files
Show 40 more
Latest 50 of 72 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 33
0002 06-10-2020
695-20-3-6942-0013
695-19-131
36C252
Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101
Milwaukee WI 53214-1476
36C252
Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101
Milwaukee WI 53214-1476
To all Offerors/Bidders
36C25220B0021
05-13-2020
X
X X
11:00 AM (local time) 06-23-2020
See continuation page for changed to the solicitation.
Continue to monitor Contract Opportunities for any and all changes to this solicitation.
Jerrod Schleis Contracting Officer
36C25220B0021 0002
Amendment of Solicitation Amendment 0002 Solicitation 36C25220B0021 Upgrade Renovate and Expand Dialysis Clinic Project Number 695-19-131 Clement J. Zablocki VAMC, Milwaukee, WI
This Amendment consists of information regarding a virtual bid opening, eleven amended specification sections, thirteen amended drawing sheets, a sign in roster from the May 28, 2020 site visit, responses to requests for information, project photographs, and an updated wage determination.
The following changes are hereby provided by amendment:
VIRTUAL BID OPENING INFORMATION:
1) Due to the national COVID pandemic, the bid opening process is being changed from a public in-person activity to a public, live-streaming activity.
2) The virtual bid opening will be available to the public via WebEX at
a) https://veteransaffairs.webex.com/veteransaffairs/j.php?MTID=m6300e1ebf07cc6775c52 3649a31e75dc (Meeting will be available to be accessed 15 min prior to bid opening)
b) Meeting number (access code): 199 073 7518
c) Meeting password: Proj.695-19-131
3) Offerors SHALL submit a bid bond no later than 4:00PM (local time), the day prior bid opening to the location listed below, via USPS mail, FEDEX, or UPS. Failure to provide a bid bond by the appropriate date and time will render the bid unresponsive and ineligible for award. Hand-deliveries are NOT an option as the delivery location is locked to the public.
ADDRESS: Great Lakes Acquisition Center Honey Creek Business Park 115 South 84th Street - Suite 101
Milwaukee, WI 53214-1476
Attn: Jerrod Schleis
4) Bids shall be provided via email to the Contracting Officer at Jerrod.Schleis@va.gov on or before the date and time specified for receipt of bids. A hard copy submission is not required. Any bids not provided electronically or received electronically after date and time specified for receipt of bids will be processed in accordance with FAR 52.214-7 Late Submission, Modifications, and Withdrawals of Bids (Nov 1999)
SPECIFICATIONS (attached):
1) 00 01 00 – TABLE OF CONTENTS – Modified
2) 01 74 19 – CONSTRUCTION WASTE MANAGEMENT – Modified to note LEED standards are not required.
3) 01 91 00 – COMMISSIONING REQUIREMENTS – Modified to note LEED standards are not required.
4) 03 30 53 – CAST IN PLACE CONCRETE – Added
5) 09 05 16 – FLOOR PREP – Modified regarding floor infill, leveling and drying
6) 10 14 00 – SIGNAGE – Modified to clarify Sole Source vendor requirements and that VA
Signage Design Guide does not apply
7) 10 21 23 – CUBICLE CURTAIN TRACKS – Removed LEED requirements
8) 12 24 00 – WINDOW SHADES – Modified to clarify Basis of Design details
9) 22 07 11 – PLUMBING INSULATION – Modified to remove cellular glass insulation products and replace with standard fiberglass plumbing insulation
10) 22 11 00 – FACILITY WATER DISTRIBUTION – Modified to support Total Water Sole
Source plumbing requirements
11) 28 05 13 – CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY –
Modified regarding cable tray requirements
DRAWINGS (attached):
1) AD101 – SEVENTH FLOOR DEMO PLAN
a) MODFIED Note #7
2) AE501 – BUILDING DETAILS
a) MODIFIED Details #4 and #14
3) AE601 – DOOR AND WINDOW SCHEDULE
a) MODIFIED Details #8 and #11
b) MODIFIED Window Schedule
4) AI101 – FINISH WALL TREATMENT PLAN
a) MODIFIED Plan to show specific window treatments WC-1, WC-2 and WC-3 locations
5) AI201 – INTERIOR FINISHES ELEVATIONS
a) MODIFIED Toilet Accessory and Partition Schedule
6) AI901 – SIGNAGE PLAN
a) MODIFIED Plan sign locations
b) MODIFIED Signage General Note D
7) EP100 – BASEMENT FLOOR OVERALL PLAN
a) MODFIED Plan (locations and room numbers)
b) ADDED Sheet Notes describing infection control requirements and need for work off-shift
8) EP401 – ONE LINE DIAGRAMS
a) MODFIED Detail #7
9) ET101D – SEVENTH FLOOR DEMOLITION PLAN
a) MODIFIED Plan to show location of additional abandoned Fire Alarm box to relocate above ceiling
10) ET102 – SEVENTH FLOOR SYSTEMS PLAN – DIVISION 28
a) ADDED Sheet Notes #6 and #7
b) ADDED Keynote #8
c) MODIFIED Plan to show existing Fire Apparatus closet location
11) GC101 – INFECTION CONTROL/PHASING PLAN
a) MODIFIED IC PLAN NOTES #3, #8 and #10
b) MODIFIED Plan to show location of IC wall for Note #8
12) MD101 – MECHANICAL DEMOLITION FLOOR PLAN – 7th FLOOR
a) MODIFIED General Note #3
13) QH101 – SEVENTH FLOOR EQUIPMENT PLAN
a) MODIFIED Equipment Schedule
SITE VISIT SIGN IN ROSTER (attached):
1) See attached roster from May 28, 2020 site visit.
REQUESTS FOR INFORMAITON (see page 4):
1) The RFIs from prospective offerors collected through the date of this amendment have been answered below. Answers resulting in changes to contract specifications, drawings, and/or the statement of work are reflected above.
PROJECT PHOTOGRAPHS (attached):
1) Ceiling pictures of route for EP100, feeder from EDH-307-Q-4 panel through ceiling in
B0427, B0429, B0223 and corridor to B0130A EC are attached.
WAGE DETERMINATION (attached):
1) See attached wage determination dated 6/5/2020
Renovate and Expand Dialysis Clinic Solicitation Number: 36C25220B0021
Project Number: 695-19-131 Solicitation Requests for Information
1. The project calls for connection of nurse call system to the Jeron server rack on the 3rd floor. Is there a pair of MM dark fiber available from the closet 7128 to the 3rd floor patch panel? Is the required pair MM fiber jumpers from the patch panel to the server rack part of this project?
Yes, there are available pairs of OM1 multimode fiber with SC connectors from both our 7A N&S closets to our 3rd floor server room for Nurse Call. As indicated in detail 3/ET501 and keynote #7 on ET101, new MM fiber shall be provided from the Nurse Call terminal cabinet to the server rack in the third floor. Provide jumpers required for termination of the patch panel to new nurse call head end equipment.
2. Demo drawing ET101D Keyed note #3 calls for the removal of recessed fire alarm junction box. The note is only indicated at one location on the drawing. There are (2) additional locations of these panels, outside of 7252 and stair 4, are these locations also to be removed?
The recessed FA j-box in the vicinity of Stair 4 must also be removed and relocated above ceiling. However, the FA j-box outside Room 7252 is just outside the project area and is part of 7AN and is not included.
3. Are any of the existing nurse call devices that are being removed to be saved and turned over to the owner?
No. Any remaining Nurse Call appurtenance/device shall be removed in its entirety – including all wiring – and disposed of by the Contractor.
4. The 4” acid chase is shown throughout the system and should only be run in the ceiling.
When it enters into the wall chase/cabinet, typically the tubing is ran and clicked to the wall.
The chase in the ceiling is usually run in schedule 40 or schedule PVC with open ends at bends. The acid piping will be run in ½” polypropylene tubing with ASTM# is D335.
No change required. The plans show the route of the piping only; the Contractor shall coordinate with the sole-source vendor make the open sections as needed for piping.
5. The RODI dialysis water piping is shown as polypropylene schedule 80 or polyethylene schedule 80. The RODI dialysis water piping should be 1” schedule 80 PVC piping with sweeping 45 degree ells (no 90 degree ells).
Change to specification section 22 11 00 has been made; see amendment. Paragraph 2.3.F.
F Dialysis Water Piping:
1. Acid Tubing:
a. polypropylene tubing with ASTM# is D335
2. Reverse Osmosis (RO) Water Piping:
a. ASTM D1785, Schedule 80 PVC, piping with sweeping 45-degree ells (no 90 degree ells).
6. Figure 7 on sheet EP401 shows transformer T/EPLQ711 between panels EPH-W and EUL-
Q, however figure 1 on sheet EP300 has a new transformer T/EULQ711 in room 7126 with those two panels.
a. Are these two transformers one-in-the-same?
Only one transformer is to be provided in room 7126.
b. If so which is the proper designation for this transformer?
The designation for this transformer is “T/EULQ711”.
7. What are the site conditions in the basement along the route shown on EP100 for the new feeder between EDH-307-Q-4 and EPH-Q?
See pictures of route end of this RFI document for ceiling actual route. Note that electrical closet for vertical riser is B0130A. EP100 has been modified.
a. Ceiling type?
2x2 acoustical lay-in ceiling with 2x2 light fixtures in all corridors and offices. Ceiling is hard gypsum lid (with some access panels) in Women’s Locker Room B0223.
b. Clearance above ceiling?
Concrete deck is 13-ft AFF in basement.
c. The corridor appears to be non-patient care, what are the limitations for working in corridor and rooms along that route?
Work in this corridor shall be off-shift. See revised drawing EP100 with General Note about infection control and workplan required prior to work beginning.
8. What are the deck-to-deck heights for the levels between the basement and seventh floor so that a vertical length of the feeder can be calculated?
Concrete decks between floors are approximately 14-in thick. Deck-to-Deck spacing between Basement, 1st and 2nd Floors is 13-ft. Deck-to-Deck spacing between 3rd, 4th, 5th, 6th and 7th floors is 10-ft.
9. Sheet EL101 notes 8 and 9 identify life safety circuits for exit and egress lighting from panel
ELH-LS-91-1.
a. Is circuit 7 currently existing on 7th floor and available for reuse?
Circuit #7 from panel ELH-LS-91-1, currently serves the 7th floor and is available for reuse.
b. If not, where is panel ELH-LS-91-1 located in relation to the electrical rooms on 7th floor?
This panel is located 9th floor, 9AN, Room 9126EC. Exactly two floors above 7126EC.
10. Is ELL-LS-91-1 circuit 11 for the new Med Gas Alarm panel already existing on 7th floor?
a. If not, where is panel ELL-LS-91-1 located in relation to the electrical rooms on 7th floor?
This panel is located 9th floor, 9AN, Room 9126EC. Exactly two floors above 7126EC.
11. Keyed Note 1 on sheet EL101 calls for (5) new light fixtures in corridor C7B01, are these to be type CN to match inside the project area?
a. If not, are they to match the existing?
These new lights shall be same 2x2 LED type “CN” as specified in the project area. See light fixture schedule sheet EP601.
12. The room finish/signage schedule says corridor C7A11 received WSF-3 flooring, but the finish floor treatment plan hatch is for WSF – 1. Please confirm what flooring is needed in this location.
C7A11 will receive WSF-1. Room Finish Schedule sheet AI601 has been revised.
13. M4100 equipment is shown in Exam Room 7103 but not on the Equipment Schedule. What is this piece of equipment and who will be providing it?
Label has been deleted and drawing has been updated. Refer to DG107 for all med gas information.
14. Drawing IF101 & IF 102 shows all the furniture, but there is no furniture specification. Who will be providing and installing the furniture?
See Sole Source Justification document for “Modular Furniture”. All built-in furniture is sole sourced to Herman-Miller. Contactor shall contact local design representative and request quote for the construction project. Local design representative who participated in the production of the project documents is:
Building Service, Inc.(BSI) W222 N630 Cheaney Road Waukesha, Wisconsin 53186 292-955-6400
15. Will the VA supply the dumpsters?
No. Dumpster shall be provided by the Contractor and Contractor shall contract with local firm to pick up and replace with empty dumpster as required by the volume of demo material/debris produced. Contractor is responsible for construction waste manifests per the Specification 01 74 19. VA will provide location for Contractor’s dumpster at east end of Building 111 Loading Dock during demolition activities. After major demo is complete, the VA may require the dumpster to be relocated – location to be determined. Multiple other Building 111 contracts are coincident.
16. Door Types D3 and D4, are those Stile and Rail Window doors or are they standard full glass cut outs?
These are standard full glass cut outs.
17. General note M on sheet GC101 says that all demolition materials shall be removed from the space before 7AM or after 4PM but does not mention rules for material stocking. Can materials be stocked through the corridor during normal business hours or must it be done before 7AM or after 4PM as well?
No storage of debris or construction materials shall be allowed outside the project area.
Large quantities of material delivery shall be prior to 7am or after 4pm to not interfere with hospital operations.
18. Due to the current Covid-19 situation, would the government consider accepting electronic bids in lieu of hard copies?
Due to the current Covid-19 situation, electronic bids will be required. Hard copies of bid documents are not required, and a virtual bid opening will be held in lieu of an in person bid opening. Refer to page 2 of amendment 0002 for additional information.
19. At the walkthrough, the 7th floor corridors appeared to be sheet vinyl. Does the contractor need to protect the floors with 1/4" Masonite from the work area to the elevators to protect the floors during construction? If yes, can this be left down during the duration of the project?
Any “finishes to remain” shall be the responsibility of the Contractor to protect during construction or replace (if damaged in the opinion of the COR) at the end of the construction project. See Specification 01 00 00 section 1.7, paragraph E.
20. Will there be any utility shutdown and/or drain down fees when shutting off and/or draining down utilities? If yes, please clarify what fees will be applicable.
The Contractor shall pay no utility outage fees.
21. Will the VA be performing draindowns and recharge with their building engineers or is the general contractor responsible for this?
VA shops personnel (plumbers, electricians and mechanics) shall functionally “turn off” or isolate equipment at the beginning of each utility outage – that is, VA shall be responsible for closing valves, turning breakers off, or securing power to fans or air handling units. At the completion of the Contractor’s “work”, the VA will again re-energize or re-fill the utility.
The Contractor is responsible for the work during the outage. Regarding the perimeter heating/cooling system, the Contractor is responsible to coordinate with the VA and collect/salvage any glycol fluids to return to the Building 111 system.
22. Will the contractor be allowed exclusive use of a freight elevator? How many of the freight elevators will the contractor be allowed to use during construction?
Not exclusive use. The B-bank Service and Freight elevators (B-9, B-10, B-11 and B-12) are for shared use between Nutrition and Food Service employees, other Contractors and hospital staff (patient transportation). Contractors will share use of B-bank elevators for movement of materials/debris. These elevators are 6ft wide, 7ft deep and just under 8ft tall.
They are rated for 5,500 lbs. One of the elevators (B-12) has an extra “bump out” in the ceiling for long materials (6ft wide, 2ft deep and 2ft tall). The Contractor shall install temporary elevator protection and may leave in place for the duration of the project. Refer to the Special Notes Specification.
23. Can temporary elevator protection be left in place during the duration of the project?
Elevators are shared. Contractor may leave protection in place, however, it may not impede usage by others (especially VA staff) moving food service carts or patients. The B-bank Service and Freight elevators (B-9, B-10, B-11 and B-12) are for Contractor use for movement of materials/debris. These elevators are 6ft wide, 7ft deep and just under 8ft tall.
They are rated for 5,500 lbs. One of the elevators (B-12) has an extra “bump out” in the ceiling for long materials (6ft wide, 2ft deep and 2ft tall). The Contractor shall install temporary elevator protection and may leave in place for the duration of the project. Refer to the Special Notes Specification.
24. Are there specific hours that the contractor will be allowed to use the loading dock for deliveries? Will the contractor be allowed to leave a dumpster at the loading dock for the duration of the project? If the VA is allowing us access to one of their dumpsters, will there be any charges to the contractor and what will those be?
See answer to questions #15 and #17. Large quantities of material delivery shall be prior to 7am or after 4pm to not interfere with hospital operations. Dumpster shall be provided by the Contractor and Contractor shall contract with local firm to pick up and replace with empty dumpster as required by the volume of demo material/debris produced. Contractor is responsible for construction waste manifests per the Specification 01 74 19. VA will provide location for Contractor’s dumpster at east end of Building 111 Loading Dock.
25. Will there be Department of Public Health inspections on this project?
No.
26. Will this project be subject to sales tax?
The Contractor is responsible to for all applicable federal, state, and local taxes. Refer to FAR 52.229-3 Federal, State, and Local Taxes (FEB 2013) for additional information.
27. Please provide the dimensions of the freight elevator that will be used by the contractor.
Yes. The B-bank Service and Freight elevators (B-9, B-10, B-11 and B-12) are for Contractor use for movement of materials/debris. These elevators are 6ft wide, 7ft deep and just under 8ft tall. They are rated for 5,500 lbs. One of the elevators (B-12) has an extra “bump out” in the ceiling for long materials (6ft wide, 2ft deep and 2ft tall). The Contractor shall install temporary elevator protection and may leave in place for the duration of the project. Refer to the Special Notes Specification.
28. Please provide the weight capacity of the freight elevator that will be used by the contractor.
Yes. The B-bank Service and Freight elevators (B-9, B-10, B-11 and B-12) are for Contractor use for movement of materials/debris. These elevators are 6ft wide, 7ft deep and just under 8ft tall. They are rated for 5,500 lbs. One of the elevators (B-12) has an extra “bump out” in the ceiling for long materials (6ft wide, 2ft deep and 2ft tall). The Contractor shall install temporary elevator protection and may leave in place for the duration of the project. Refer to the Special Notes Specification.
29. Can infection control barricades on the 6th floor be left in place for the duration of each of the (7) phases or will the contractor be required to set up and take down all 6th floor barricades every day.
Temporary plastic infection control barriers will be allowed to remain in place during the entirety of each 6th Floor sub-phase for plumbing/piping demolition, relocation and new work.
The Contractor shall NOT set up and take down these barriers every day – the VA intends to turn over these rooms (each sub-phase) to the contractor for their work for the entire duration. Negative air must be maintained, and ceilings must be returned to full coverage for fire protection purposes at the end of each day, however.
30. If infection control barricades on the 6th floor are allowed to stay in place for the duration of each phase, can the contractor complete work behind the barricades during regular business hours or will all 6th floor work need to be completed during off hours?
The VA intends to turn over each 6th Floor sub-phase to the contractor for the duration of his work. VA will move persons and mobile equipment out of each space in the sub-phase and the Contractor shall be responsible for other fixed equipment protection (cover with plastic or move into the hall for convenience). If Contractor abides by noise and vibration policies per our Specifications 01 00 00 and 01 01 10-SN, he may work inside the sub-phase during regular business hours (7am-4pm). Note – if there are problems, loud noises or excessive vibrations that affect patient care, or the Contractor begins to fall behind, the Contractor may certainly work additional shifts as well inside the sub-phase infection control barriers.
31. Will the VA provide storage for items that are specified to be salvaged and reinstalled or will the contractor be responsible for providing storage for these items?
Not Applicable. Whatever equipment is left in 7AS shall be disposed of by the Contractor.
There is no identified equipment or materials to be salvaged, stored and turned over to the Government.
32. Please verify that all loose furniture, equipment and sharps will be removed from the work area prior to the start of construction.
Yes – VA will remove loose furniture, equipment and sharps from the 7AS work area prior to start of construction.
33. Plan note 2 on sheet AD101 refers to removing mounted equipment from the space. Will these items be disposed of or returned back to the VA?
All items on demolition sheets are to be disposed of by the Contractor. No items are to be salvaged or returned to the VA (except for room signage).
34. Plan note 2 on sheet AD101 refers to demolition work in the corridor. Will corridor work be allowed during normal hours or will it have to be after hours?
All work outside of the Contractor’s primary Infection Control and Construction Barrier (including the work noted in this question), shall be performed off-shift but only upon receipt and approval of a Contractor supplied work and infection control plan.
35. Sheet 1/MM400 – Will the concrete for the mechanical pads require any material testing? If yes, please specify what will be required. Please verify any concrete mix design requirements.
03 30 53 Cast-In-Place Concrete specification provided in Amendment.
36. Sheet 13/AE601 – No alterations to the existing masonry openings are shown on the drawings for the new louvers. Please verify that the louvers will fit into the existing window openings as shown on the drawings.
Sizing of louver was based on masonry opening of windows and should not require any modifications.
37. Sheet 9/MM500 – No steel reinforcement is shown beneath the concrete pads in the mechanical room 7140. Please verify that no steel angle will need to be added below the concrete floor slabs to help support the additional loads from the new mechanical equipment and concrete pads.
Existing slab can support the additional loads. No additional steel will be required.
38. Detail 8/AE601 shows the header for the ICU doors. Please verify that no steel angle will be required here kicked back for lateral support for the door frame as none is shown.
Provide metal stud kickers at 4’-0” O.C. See revised detail on 8/AE601.
39. 17/AI201 shows the interior elevation of the 7110 Bays. Is the face of the frame around the
Dialysis Water Box PL-4?
Yes, the face of the dialysis water box casework is to be PL-4.
40. Detail 14/AE501 shows a typical exterior wall at a window sill. Between the 1/2" exterior glass mat sheathing and the existing exterior wall there is a 3" gap with friction fit rockwool batt insulation. The insulation is only shown at the top +/- 6" of the wall section, is this the correct detail or will it be required the full height of the wall section?
This detail is correct. The rockwool is for thermal control at the window. The cavity below will still allow for air movement between floors and in the rest of the wall, but not at the window.
41. Detail 14/AE501 shows a typical exterior wall window sill. No air barrier is shown on the outside of the 1/2" exterior glass mat sheathing. Please confirm no air barrier will be required at exterior walls.
No air barrier will be required under the window sills.
42. Note 8 on sheet GC101 says to "verify existing door is 45 minute fire rated" and "if door is not 45 minute fire rated, remove existing door leaf and frame and provide 45 minute door, frame and hardware." Can someone please read the label on the side of the door at the east end of corridor C7B10A and tell us if this door is 45 minute fire rated? If nobody can tell us this, can we set up a time to come into the hospital and inspect the door?
Refer to updated GC101 Note 8. KTR to build barrier instead (corridor side).
43. There is no manufacturer listed for the transaction window shown in the Window Schedule on sheet AE601. Please provide the basis of design.
Use CRL Horizontal Sliding “Daisy” Pass-Thru Assembly with D4 Header and Jambs as the Basis of Design for the transaction window.
44. The Window Schedule on AE601 shows Type C windows to be aluminum fire rated framing with fire rated glazing. Please confirm this is correct. This type of framing is very expensive and is not called out in the specifications. A fire rated opening could be achieved using a fire rated hollow metal frame with fire rated glass. Please confirm we are to include aluminum fire rated framing and if so, provide a specification for it.
Window Type C shall be a hollow metal frame. Window Type B shall also be a hollow metal frame to match even though it is not required to be fire-rated. See updated drawing AE601.
45. If the Type C windows on the window schedule are going to be aluminum fire rated framing they will not be manufactured by the same vendor as the aluminum storefront. Spec Section 084113 – Section 2.3 – B – calls for all aluminum framing to be by one single source. Please confirm that having two different sources is acceptable.
Refer to Question #44.
46. RP-1 (Resin Panel) is shown on the finish schedule on sheet AI601 but is not found in the drawings. Please provide locations for RP-1.
RP-1 is not included in this project. It has been removed from the Finish Schedule in the updated drawing AI601.
47. Are there existing as-built drawings of building 111 available? Note 6 & 8 on GC101 say to verify the fire rating of certain walls and doors in the space and the only way we can do this without coming back to the space and opening the ceiling is by viewing the existing drawings.
Contractor shall assume that the walls identified require stud/drywall and fire-caulking at penetrations along the entire length above room ceiling height where noted by Notes 6 and 8 to create a 1-hour fire-rated construction barrier.
48. Note 6 on GC101 refers to removing a door and infilling the door opening as applicable.
Please provide the existing finishes that we are to match in Office 7200. If this office has wallcovering, will attic stock be available for the contractor to use?
Provide standard drywall and paint finish only (P-1 paint) on the 7200 side of the wall.
49. Sheet GC101 Note 8 – Please provide the finishes in Corridor C7B10A. If the door at the east end of the corridor needs to be replaced due to its fire rating, we will need to match the existing finishes in the corridor. If the corridor walls have wallcovering, will attic stock be provided? If no attic stock is provided, can we match the existing finishes as close as possible?
Rather than replace the door/frame/hardware, the Contractor shall install a temporary 1-hour rated construction barrier on the corridor side of the wall to establish the 1-hour barrier for the project. The doors shall be protected from the inside by the Contractor by tape/plastic.
Refer to GC101 changed drawing and Note. Contractor should paint drywall construction barrier with Sherwin Williams Accessible Beige, fire caulk all borders and ensure ceiling grid is modified accordingly.
50. Specification 09 05 16-5, 3.2 D, says to prepare concrete substrate by abrasive blasting.
Please verify if all concrete substrates that are to receive new flooring are going to require abrasive blasting. If this is not required, please clarify which concrete substrates are required to be abrasively blasted. If abrasive blasting is required, will the contractor be allowed to do this during normal business hours (noise concerns).
All concrete to receive new flooring except for those areas infilled after mortar bed removal shall be prepared by abrasive blasting per the specification. This work shall be completed off shift by the Contractor.
51. Due to the amount of wall locations being moved and MEP cores being infilled, a majority of the floor is going to require skimming the floor for preparation. Will the floor areas receiving the skim coating product require moisture mitigation or will the dry time of 16 hours from the specification section 09 15 16-4, 2.2 G for floor coverings, be adequate drying time so that moisture mitigation will not be required?
Specification 09 15 16-4. 2.2 G revised to read “Dry Time: Contractor to follow manufacturer’s recommendations on drying time for all underlayment floor coverings. All underlayment must be completely cured before installation of finished flooring.”
52. For details 4 and 14/AE501 how is the 1/2" exterior glass mat sheathing to be attached to the stud with only a 3" gap between the existing wall and the new stud? Please advise.
The glass mat sheathing ONLY occurs under the windows where the existing fan coil units are being removed. This is a small section of the overall wall furring. Previous contractors have fabricated this small portion of the wall on the floor and then lifted the stud section into place for drywall finishing.
53. Detail 4/AE501 has a 5 1/2" steel stud at the window sill and detail 14/AE501 has a 6" steel stud for the typical exterior window sill. Please confirm that the only location that calls for 5 1/2" steel studs is at the patient bay.
Detail 14 has been modified to show 5-1/2” steel studs. This detail occurs under every window where window cabinet unit heating/cooling systems are removed. The existing wall cavity is deeper where the existing fan coil units are being removed. These areas require thicker furring to align with the furred walls on either side of the windows.
54. Typical exterior walls are wall type F3A.Gt per General Note K on sheet AE102. This wall does not show any glass mat sheathing between the metal studs and existing masonry walls as shown in detail 14/AE501 of a typical exterior wall at a window sill. Please verify this is correct.
Detail 14/AE501 is the detail for only under the window sills; detail 14 was updated to reflect 5-1/2” studs. Refer to Question #53. The rest of the exterior wall furring will be F3A.Gt.
This detail will only occur under the window sills where the existing fan coil units are being removed.
55. Detail 4/AE501 shows the exterior header wall type to be F3B.Gi but we do not see this wall type shown on the AE002 wall types. Please provide this wall type.
The F3B.Gi should be F3B.Gt. The exterior walls will require thermal insulation and not just sound insulation. Detail 4/AE501 has been revised.
56. Details 14 and 4/AE501 show the exterior wall framing below the window sill to have 1/2" exterior glass mat sheathing. The header framing shown in 4/AE501 does not have any glass mat sheating. Why is glass mat sheathing required at the low wall and not required at the header?
The area below the window sill shall have a 3” air gap in the cavity and will require glass mat sheathing. The rest of the wall will not have an air gap. Refer to Questions #52 through #55.
57. Sheet QH101 Equipment Schedule item A1030 is a double stacked locker by Scranton.
Please provide the product specifications for the lockers. Scranton manufactures two different plastic lockers (Duralife and Tuftec).
Lockers shall be Duralife double-stacked and shall not be provided by Herman-Miller vendor.
58. Does the hospital have swing stage equipment available to use for the installation of the louvers if required?
No. Install louvers from the inside. Fall protection required when window(s) removed.
59. Detail 13/AE601 has a note to "match louvers installed in mechanical room on 8A." We did not see the louvers on 8A at the walkthrough, please provide the finish that we are to match.
8A louver provided by RUSKIN of Kansas City, MO (816-761-7476). Fluropon or 70% PVDF finish standard color MEDIUM BRONZE (72).
60. Sheet AE601 and Specification 08 90 00 section 2.10 – Please provide the finish that is required on the louvers as the specifications list multiple finishes. If the louvers are to be painted, please provide the paint requirements.
8A louver provided by RUSKIN of Kansas City, MO (816-761-7476). Fluropon or 70% PVDF finish standard color MEDIUM BRONZE (72).
61. There are a few signs that show up on the AI901 floor plan but not shown in the details on sheet AI902. See below:
a. E7.F (found at entry to Corridor C7A10A)
E7.F deleted. E8 locations provided. E8 signage is accounted for in the Additional Misc.
Signage on AI901. Sheet AI901 has been updated in the Amendment.
b. E2.6 (found at Waiting Room 7100)
E2.6 revised to be E2.G. Refer to 290/Sign Systems for signage type.
c. G6F (found at Waiting Room 7100)
G6F removed. G6 sign added to match signage schedule.
d. G6B (found at Waiting Room 7100)
G6B removed.
e. E5.G (found at Treatment Bays 1 through 10)
E5.G added to signage plan. Refer to 290/Sign Systems for signage type. Final location to be provided by the VA prior to installation.
62. None of the signs shown on AI902 are to scale, nor do they reference VA Signage Design
Guide codes (to identify desired sizes). Please provide direction on desired sizes by either adding details to AI902 or referencing VA Signage Design Guide codes.
The VA Signage Design Guide does not apply for the interior signage required on this project. References to the VA Signage Design Guide will be deleted from the Construction Documents. VA interior signage is sole-sourced through 2/90 Sign Systems. Refer to J&A documents in solicitation. No substitutions will be allowed. Coordinating with 2/90 Sign Systems (Alexa Hoerner; 616-656-4342 or alexahoerner@290signs.com) , Contractor shall reference the sign schedule and sign types shown AI901 and AI902. Contractor shall inform 2/90 that they need quote for VA Milwaukee Dialysis project – vendor has already prepared and is ready to share with all potential bidders.
63. Sheet AI902 – Please confirm that Sign Types E9.G and E1.G are to be blade-mounted
(perpendicular to wall so they are visible from down the hallway).
Sign Type E9.G is flag/blade mount. Sign Type E1.G is a two-sided, ceiling mount. VA interior signage is sole-sourced through 2/90 Sign Systems. Refer to J&A documents in solicitation. No substitutions will be allowed. Coordinating with 2/90 Sign Systems (Alexa Hoerner; 616-656-4342 or alexahoerner@290signs.com) , Contractor shall inform 2/90 that they need quote for VA Milwaukee Dialysis project – vendor has already prepared and is ready to share with all potential bidders.
64. Sheet AI901 – At Patient Toilets at Rooms 7134A & 7145A & 7146A, the signage types called out are Type A1 - simple room number signs; should these be Type A9 restroom signage?
No. Provide sign type per schedule and drawing.
65. Specification Section 10 1400 at Subsection 2.5(A) states that signage must conform with
VA Signage Design Guide. The most current version we have is dated 12/2012. Please confirm this is the correct document to reference?
The VA Signage Design Guide does not apply for the interior signage required on this project. References to the VA Signage Design Guide will be deleted from the Construction Documents. VA interior signage is sole-sourced through 2/90 Sign Systems. Refer to J&A documents in solicitation. No substitutions will be allowed. Coordinating with 2/90 Sign Systems (Alexa Hoerner; 616-656-4342 or alexahoerner@290signs.com) , Contractor shall inform 2/90 that they need quote for VA Milwaukee Dialysis project – vendor has already prepared and is ready to share with all potential bidders.
66. Sheet AI901 Additional Misc. Signage has (2) lines that state "(2) sign frame" and the sign types are G1 and G7 for the (2) lines. Please advise the required sizes that correspond with the VA signage standards for these sign types.
G1 and G7 are standard frames VA Milwaukee uses for posting information. VA interior signage is sole-sourced through 2/90 Sign Systems. Refer to J&A documents in solicitation.
No substitutions will be allowed. Coordinating with 2/90 Sign Systems (Alexa Hoerner; 616- 656-4342 or alexahoerner@290signs.com) , Contractor inform 2/90 that they need quote for VA Milwaukee Dialysis project – vendor has already prepared and is ready to share with all potential bidders.
67. Sheet AI901 General Note "C" refers to the installation of salvaged signage. Please specify what signage is to be salvaged and reused on the project.
Refer to updated Notes on drawings AI901. Contractor shall be responsible for removing existing signage during demo and turn over to the VA. Salvaged signage will not be re-installed.
68. Sheet GI101 and Specification 10 44 33 – Do the new fire extinguisher cabinets need to be fire rated? Please specify a basis of design.
FECs are not required to be fire rated, basis of design added to QH101 Equipment List.
69. Please provide specifications/manufacturers for items A5107, B1300, K4665, M0506, M0507, R6070, and R6200 on the Equipment Schedule on sheet QH101.
QH101 Equipment List has been updated in the Amendment.
70. The Equipment Schedule on sheet QH101 depicts certain FF&E items with an "R" to be reused. Please specify what the responsibility of the contractor is with these items? Are these items being removed and salvaged by the contractor? Is the contractor to re-install these items?
Contractor has zero responsibility for these items. These items are moving from old Dialysis unit to new Dialysis suite.
71. The modular furniture scope of work shown in the plans on sheets IF101 and IF102 appears to be under direct contract with the VA but there are specifications regarding the modular furniture. Please verify that the contractor is not to include any work in relation to the modular furniture scope aside from wood blocking and coordination with the VA.
The Contractor’s statement above is incorrect. The modular furniture is sole-sourced to Herman-Miller furnishings. The Contractor must carry the cost of furniture procurement and installation. Refer to Question #14. Whether Contractor installs the furniture himself or utilizes the sole source distributor/dealer to install is to be determined by the Contractor and his sub-contract with the distributor/dealer.
72. Please provide locations for window coverings WC-1, WC-2, and WC-3. Based on notes 4 and 5 on sheet AI101, the only rooms to receive window shades are room 7117, 7139, and 7134A. Please confirm.
Refer to updated drawings, Sheet AI101 and updated specification 12 24 00.
WC-1; std horiz blinds; ALL windows except 7117, 7139 and Bays 1 through 5.
WC-2; roller shades; Dialysis Bays 1 through 5 WC-3; black out shades; 7117 and 7139
See General Note CC and Finish Plan Notes #4 and #5 on AI101. Plan notes denote rooms that will receive roller shades. See revised AI101.
73. Sheet FP107 and Specification 21 05 11 – Will upturned sprinkler heads be required during demolition?
There will never be upturned sprinkler heads on this project. Contractor should request to demo and fully remove existing sprinkler system piping prior to demo and abatement activities. VA will review and approve if construction barrier and heat detection system as required are installed. An active and functioning sprinkler system shall not be required during construction.
74. Specification 23 73 00 – Please verify that the specified new air handling unit shown in the Air Handling Unit Schedule on MM600 will fit in the freight elevator.
Engineer utilized best possible unit split for maximum size: 54” long x 93” wide x 79” tall.
The modular sections will fit in VA B-bank freight elevator.
75. Detail 14/MM500 has a note on the right side of the detail near the 7th floor ceiling line that says "New HWS & HWR piping above 8th floor ceiling to serve new air terminal units typ."
Please confirm that this note should refer to the 7th floor air terminal units. If this is actually referring to the 8th floor, please provide floor plans for the 8th floor work.
Note should read as follows: “New HWS & HWR Piping above 7th Floor Ceiling to Serve New Air Terminal Units (typ).”
76. MD102 shows the Seventh Floor Extended - Demolition Plan. General note 5 refers to work requirements in the corridors and does not mention that this work will need to be during off hours. Please verify that as long as the criteria in General Notes 5 - parts A, B, C, & D are followed, this work can be completed during normal business hours.
Contractor – please read General Note #5-part C again. This work must be off shift and take place between 5pm and 5am.
77. Sheet FP107 has a note near column lines B-C & 10-11 that states "Provide automatic sprinkler system. Provide new piping, heads, supports and hangers." Please verify that the fire protection scope of work includes complete removal of the existing system back to the riser and install of a new system consisting of all new mains, branch piping, and sprinkler heads.
See sheet FPD107 for demolition work, but the above understanding is correct. Automatic sprinkler system is design-build by a special trade contractor who regularly engages in this type of construction. Conform to Specification 21 13 13.
78. Sheet MD102 shows the Seventh Floor Extended Demolition Plan. The corridor where the pipe demolition is shown is labeled as C7B03B on MD102 but the same corridor is labeled C7B01 on sheet AD101. Please clarify.
On the A-wing side, the corridor is C7B01, on the C-wing side it becomes C7B03. Both drawings show the correct corridor for work. The label/tag is otherwise meaningless to the Contractor.
79. MD103 keynote 2 refers to the removal of the chilled water supply and return piping from the fan coil units. Is there any Glycol in the existing chilled water pipes?
Yes. Contractor is responsible for reclaiming VA glycol in sub-basement and return to Graphics (Building 113). VA pipefitters will assist during utility outages and work.
Contractor will need barrel to collect glycol.
80. Please provide the basis of design for the mechanical equipment shown on the schedules on sheets MM600, MM601 and MM602.
AHU-7140, filters, fans: Trane CSAA017 RRF-7140: Greenheck EQB-22-30 EF-7140: Greenheck BSQ-160-15
EF-7136: BSQ-80-7
HF-7136: Camfil CamSafe 2 VAV Boxes: Trane
Pumps: B&G HTG E-60 1.25x1.25, CLG E-60 2x2 SCP-7140 Condensate Pump: Sterlco 4226-GD Silencers: VAW RSL-15V60 ( Return), RSL-18V70 (Supply) Unit Heater: Modine HSB 47 Radiant Ceiling: Airtex HPH
81. General note 7 on sheet PS001 refers to owner supplied equipment. Please provide a list of owner supplied equipment with connection requirements for those items that will require plumbing connections.
There is no “owner-furnished” plumbing equipment. Disregard this note.
82. Specifications 22 13 00 - Part 2, provides specifications for both PVC and cast iron waste & vent piping. Please verify if any PVC piping will be allowed on this project.
The specification section 22 13 00 in the bid set does not have any cast iron listed in Part 2.
PVC materials for waste/vent are acceptable to the VA.
83. Note 3 on sheet MD102 says that all piping shall be abandoned in place. Please verify that there will be no demolition of piping required in the room with the existing FCUs. If any is required, please provide details.
That note is correct. All work associated with the demolition of supply and exhaust ductwork was to limit demolition to corridor to prevent any disruption of the two spaces supported by these services. The dual duct box, associated heating water piping and supply distribution ductwork have already been abandoned (they are not in service). The intent of the note was to clarify that no cost associated with its removal be provided as part of bidding process.
84. MD103 shows the piping demolition on the 6th floor plan. Will the piping being demoed back to the risers be capped at the riser? Can the contractor connect the new piping to the riser where the old piping was capped off? If not, will the riser need to be re-tapped into for the new piping connection?
As outlined in Keyed Notes #1, #2, #3, #6 and #7 depending on location, piping shall be removed back to vertical or horizontal tap into main riser, capped and insulated. Intent is to remove as much of unused piping as possible. For the new low-temperature piping supporting reheat coils, these can connect to existing branch lines at risers as shown in detail 14/MM500. This detail also shows intent of capping branch piping at riser mains.
85. Is the modular furniture being supplied pre-wired? Will there be one single point of connection for any power or will it need to be wired in the field? Please provide locations for FF&E power connections.
Herman-Miller modular furniture is sole-sourced. Reference Question #14 response for additional information. The furniture is not pre-wired, but it is non-powered. It is not necessary for the furniture to include wiring. The furniture will be placed against walls that have the necessary power/phone/data infrastructure.
86. Sheet EP100 shows the feeder route for the new equipment panel. Please verify that this is a new raceway and there is no empty conduit currently in place.
This is a new raceway to be provided by the Contractor.
87. Please provide the finishes of the basement corridor shown on sheet EP100. Will there be ceilings to remove and re-install or is it an open ceiling? Can work in the basement corridor be completed during normal hours?
Refer to Question #7. Note on EP100 has been added to clarify when work may be accomplished. Ceiling pictures are included at the end of this document for the basement route.
88. Specifications 28 05 13 - Part 2.1 - C, refers to cable trays. No cable trays are shown in the drawings. Please verify if any cable tray will be required and if yes, please provide drawings and detail to show it.
Cable tray(s) shall be used as the primary means of low voltage support and are shown on sheet ET101. J-hooks are to be used in confined spaces that cannot accommodate cable trays or raceways. Refer to specifications 27 05 33 part 3.1.A for typical raceway requirements for cabling systems. Note revisions to specification 28 05 13 to refer Contractor to requirements listed in Div 27.
89. Please verify that plenum rated cabling will be allowed to run open wire in J hooks through the ceilings. We are assuming that only conduit stub ups to the ceilings will be required and all low voltage cabling can be run open wire through J hooks in the ceilings per detail 4/ET501. Please confirm that this is correct.
Cable tray(s) shall be used as the primary means of low voltage support and are shown…