This document provides details for a federal contract opportunity to renovate and expand a dialysis clinic at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The contract scope includes demolition of an existing vacant ward and reconstruction of the space to accommodate the hospital's dialysis clinic, which is relocating from the fifth floor. Construction work encompasses trades such as demolition, concrete, electrical, plumbing, HVAC, architectural, and specialty furnishings to support the dialysis mission. Hazardous materials abatement for asbestos is also required. The total renovated space will be approximately 11,000 square feet. The project magnitude price range is between $2,000,000 and $5,000,000. The solicitation is scheduled to post on May 13, 2020 with a bid opening on June 16, 2020. The contract will have a period of performance of 540 calendar days. This opportunity is a 100% set-aside for Service Disabled Veteran Owned Small Businesses, and the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12 is the contracting agency.

View the file

Other files

File Type Posted
Amend 0005 00 01 10 TABLE OF CONTENTS.pdf PDF
Amend 0005 22 67 19.16 REVERSE-OSMOSIS WATER EQUIPMENT.pdf PDF
S06 36C25220B0021 0005.pdf PDF
Amend 0005 01 91 00 COMMISSIONING REQUIREMENTS.pdf PDF
Amend 0005 01 01 10 SN SPECIAL NOTES.pdf PDF
Amend 0005 11 73 00 CEILING MOUNT PATIENT LIFT.pdf PDF
Amend 0005 14 92 00 PNEUMATIC TUBE SYSTEM.pdf PDF
Amend 0003 Photos Revised.pdf PDF
S06 36C25220B0021 0004.pdf PDF
AI601 - FINISH SCHEDULES.pdf PDF
Wage Determination 6.19.20.pdf PDF
Amend 0003 Photos.pdf PDF
SECTION 10 21 23 - CUBICLE CURTAIN TRACKS.pdf PDF
36C25220B0021 0003.pdf PDF
S06 Att Amend 0002 00 01 10 - TABLE OF CONTENTS.pdf PDF
S06 Att Amend 0002 EP100 - BASEMENT FLOOR OVERALL PLAN.pdf PDF
S06 Att Amend 0002 AI201 - INTERIOR FINISHES ELEVATIONS.pdf PDF
S06 Att Amend 0002 AE601 - DOOR_WINDOW SCHEDULE.pdf PDF
S06 36C25220B0021 0002.pdf PDF
S06 Att Amend 0002 28 05 13 - CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY.pdf PDF
S06 Att Amend 0002 10 21 23 - CUBICLE CURTAIN TRACKS.pdf PDF
S06 Att Amend 0002 01 74 19 - CONSTRUCTION WASTE MANAGEMENT.pdf PDF
S06 Att Amend 0002 GC101 - INFECTION CONTROL_PHASING PLAN.pdf PDF
S06 Att Amend 0002 09 05 16 - FLOOR PREP1.pdf PDF
S06 Att Amend 0002 ET102 - SEVENTH FLOOR SYSTEMS PLAN - DIVISION 28.pdf PDF
S06 Att Amend 0002 AD101 - SEVENTH FLOOR DEMOLITION PLAN.pdf PDF
S06 Att Amend 0002 MD101 - MECHANICAL DEMOLITION FLOOR PLAN - 7TH FLOOR.pdf PDF
S06 Att Amend 0002 10 14 00 - SIGNAGE.pdf PDF
S06 Att Amend 0002 12 24 00 - WINDOW SHADES.pdf PDF
S06 Att Site Visit Sign In 5.28.20.pdf PDF
S06 Att Amend 0002 03 30 53 - CAST-IN-PLACE CONCRETE.pdf PDF
S06 Att Amend 0002 QH101 - SEVENTH FLOOR EQUIPMENT PLAN.pdf PDF
S06 Att Amend 0002 01 91 00 - COMMISSIONING REQUIREMENTS.pdf PDF
S06 Att Amend 0002 22 07 11 - PLUMBING INSULATION.pdf PDF
S06 Att Amend 0002 ET101D - SEVENTH FLOOR DEMOLITION PLAN.pdf PDF
S06 Att Amend 0002 22 11 00 - FACILITY WATER DISTRIBUTION.pdf PDF
S06 Att Amend 0002 AE501 - BUILDING DETAILS.pdf PDF
S06 Att Amend 0002 AI901 - SIGNAGE PLAN.pdf PDF
S06 Att Amend 0002 AI101 - FINISH WALL TREATMENT PLAN.pdf PDF
S06 Att Amend 0002 EP401 - ONE LINE DIAGRAM.pdf PDF
S06 Att Wage Determination 6.5.20.pdf PDF
Site Visit Sign In 5.20.20.pdf PDF
36C25220B0021 0001.docx DOCX document
Amend 0001 Specification 22 63 00.pdf PDF
Amend 0001 Specification 00 01 10.pdf PDF
Amend 0001 Specification 08 14 00.pdf PDF
Amend 0001 Specification 09 06 00.pdf PDF
Amend 0001 J_A Patient Ceiling Lift.pdf PDF
36C25220B0021-011.pdf PDF
36C25220B0021-012.pdf PDF
Show 40 more

Latest 50 of 72 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Milwaukee VAMC 08-01-16

695-19-131 Renovate & Expand Dialysis Clinic Amendment #4

Milwaukee, WI 53295 June 25, 2020

08 71 13.11 - 1

SECTION 08 71 13.11

LOW ENERGY POWER ASSIST DOOR OPERATORS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Low-energy, power-assisted automatic swing door operators.

1.2 RELATED REQUIREMENTS

A. Commissioning; Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.

B. Steel Doors; Section 08 11 13, HOLLOW METAL DOORS AND FRAMES.

C. Wood Doors; Section 08 14 00, INTERIOR WOOD DOORS.

D. Aluminum Frames Entrance Work; Section 08 41 13, ALUMINUM-FRAMED

ENTRANCES AND STOREFRONTS.

E. Door Hardware; Section 08 71 00, DOOR HARDWARE.

F. Finish Color, Section 09 06 00, SCHEDULE FOR FINISHES.

G. Electric General Wiring, Connections and Equipment Requirements;

Division 26, ELECTRICAL.

1.3 APPLICABLE PUBLICATIONS

A. Comply with references to extent specified in this section.

B. ASTM International (ASTM):

1. B209-14 - Aluminum and Aluminum-Alloy Sheet and Plate.

2. B221-14 - Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes.

C. Builders Hardware Manufacturers Association, Inc. (BHMA):

1. 156.19-07 - Power Assist and Low Energy Power Operated Doors.

1.4 PREINSTALLATION MEETINGS

A. Conduct preinstallation meeting at project site minimum 30 days before beginning Work of this section.

1. Required Participants:

a. Contracting Officer's Representative.

b. Contractor.

c. Installer.

d. Other installers responsible for adjacent and intersecting work, including electrical wiring installers.

08 71 13.11 - 2

1.5 SUBMITTALS

A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

B. Submittal Drawings:

1. Show size, configuration, and fabrication and installation details.

C. Manufacturer's Literature and Data:

1. Description of each product.

2. Maintenance manuals.

3. Installation instructions.

4. Warranty.

D. Samples:

1. Door Operator: Full sized, complete assembly.

2. Approved samples may be incorporated into work.

E. Certificates: Certify products comply with specifications.

1. Show door operator shall be UL Listed for specified application.

F. Operation and Maintenance Data:

1. Care instructions for each exposed finish product.

2. Start-up, maintenance, troubleshooting, emergency, and shut-down instructions for each operational product.

1.6 QUALITY ASSURANCE

A. Manufacturer Qualifications:

1. Regularly manufactures specified products.

B. Installer Qualifications:

1. Regularly installs specified products.

1.7 DELIVERY

A. Deliver products in manufacturer's original sealed packaging.

B. Mark packaging, legibly. Indicate manufacturer's name or brand, type, color, production run number, and manufacture date.

C. Before installation, return or dispose of products within distorted, damaged, or opened packaging.

1.8 STORAGE AND HANDLING

A. Store products indoors in dry, weathertight conditioned facility.

B. Protect products from damage during handling and construction operations.

08 71 13.11 - 3

1.9 WARRANTY

A. Construction Warranty: FAR clause 52.246-21, "Warranty of

Construction."

B. Manufacturer's Warranty: Warrant automatic door operators against material and manufacturing defects.

1. Warranty Period: two years.

PART 2 - PRODUCTS

2.1 SYSTEM DESCRIPTION

A. Power assisted automatic door equipment accommodating normal traffic as well as the weight of the doors; UL approved and comply with applicable codes.

2.2 SYSTEM PERFORMANCE

A. Opening Force: Maximum 67 N (15 lbf.).

B. Cycle Tests: 300,000 cycles.

1. Use the widest and heaviest door specified as a test specimen.

Narrower or lighter doors of the same configurations will be considered to meet the cycle test requirements.

2.3 MATERIALS

A. Aluminum:

1. Sheet: ASTM B209.

2. Extrusions: ASTM B221.

2.4 PRODUCTS - GENERAL

A. Low-Energy Automatic Door Operators shall be Tormax 1301 Series or equal manufacturer.

2.5 LOW-ENERGY AUTOMATIC DOOR OPERATORS

A. Conform to ANSI/BHMA A156.19 and A156.10.

B. Life Safety: Shall meet NFPA 101 Life Safety Code requirements per subsection 7.2.1.9, Powered Door Leaf Operation.

C. ADA requirements: Shall meet or be adjustable to meet applicable ADA requirements and be available for indoor and outdoor use.

D. Door Limits: Shall be rated for use on doors weighing up to 500 lbs and on door leaves up to 48-in wide.

E. Mounting: Surface-mounted on either right-hand or left-hand installed doors. Operator shall allow for either in-swing or outswing mounting.

08 71 13.11 - 4

F. Enclosure: Self-contained within an extruded aluminum housing (alloy

6063-T6) to conceal operator mechanism and mounting brackets and with removable access cover with an overall maximum size of 5-1/2 inches wide by 6 inches deep.

G. Open Angle (max): Shall allow for up to 110-degrees of opening.

H. Safety Features:

1. Adjustable time delay.

2. Adjustable speed for opening and closing operations.

3. Adjustable backcheck.

4. Decals indicating "In" or "Do Not Enter" installed on both faces of each door where shown conforming to the requirements of ANSI/

BHMA A156.19.

5. Re-activation sensor mounted on the push-side door face near the top detect any person standing in the door swing path and prevent the door from closing.

6. The operator shall be programmable or adjustable to compensate for and overcome wind and stack pressures.

7. Motion sensor to detect any person standing in the door swing path and prevent the door from opening.

a. Adjustable door sensor system providing complete operation and safety zone coverage.

I. Power Units:

1. Operator power unit shall utilize non-hydraulic componentry and be available for subassembly replacement for ease of maintenance/ repair.

2. Self-contained electric circuits for automatic operators located on each floor of the building.

3. Interruption or failure of power circuits for operators located on one floor of the building shall not interfere with continuous performance of automatic operated doors located on other floors.

4. Power units designed to not interfere with continuous performance of automatic operated doors located on other floors in the case of power interruption or failure.

5. Capacity and size of power circuits according to automatic operator manufacturer's specifications.

08 71 13.11 - 5

2.6 OPERATION

A. Traffic Operation:

1. Double Doors: Double egress.

B. Operator: Electromechanical; surface-mounted.

1. Operators to have checking mechanism providing cushioning action at last part of door travel, in both opening and closing cycle.

2. Operators to recycle doors instantaneously to full open position from any point in closing cycle when control switch is reactivated.

3. Operators to allow manual door control in event of power failure.

C. Controls: Solid-state type.

D. Activation: Wave-plate switch.

2.7 FINISHES

A. Aluminum Anodized Finish: NAAMM AMP 500.

1. Clear Anodized Finish: AA-C22A41; Class I Architectural, 0.7 mil thick.

2. Color Anodized Finish: AA-C22A42 or AA-C22A44; Class I

Architectural, 0.7 mil thick.

3. Clear Anodized Finish: AA-C22A31; Class II Architectural, 0.4 mil thick.

4. Color Anodized Finish: AA-C22A32 or AA-C22A34; Class II

Architectural, 0.4 mil thick.

B. Aluminum Paint finish:

1. Baked-Enamel or Powder-Coat: AAMA 2603; dry film thickness of

1.5 mil.

2.8 ACCESSORIES

A. Signage: BHMA standard for operation and door type specified.

B. Guide Rails: Aluminum bar with anodized baked-enamel or powder-coat finish.

C. Fasteners: Corrosion-resistant, compatible with adjoining materials.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine conditions effecting work, including door and frame preparation and electrical rough-ins.

08 71 13.11 - 6

3.2 INSTALLATION - GENERAL

A. Install products according to manufacturer's instructions and approved submittal drawings.

1. When manufacturer's instructions deviate from specifications, submit proposed resolution for Contracting Officer's Representative consideration.

B. Coordinate installation of equipment with other related work.

C. Mount manual controls and power disconnect switches recessed or semi-flush in partitions.

D. Secure operator components to adjacent construction with suitable fastenings. Conceal conduits, piping, and electric equipment in finish work.

E. Install power units and controls in locations indicated.

1. Where units are to be mounted on walls, provide metal supports or shelves for the units.

3.3 ADJUSTING

A. All equipment, including time delay switches, to be accessible for maintenance and adjustment.

B. Adjust operators to function properly for the type o£ traffic

(pedestrians) expected to pass through doors.

C. Adjust each door leaf of pairs of doors to open and close in synchronization.

D. On pairs of doors, adjust operators allowing either door to be opened manually without the other door opening.

3.4 DEMONSTRATION AND TRAINING

A. Instruct VA personnel in proper door operator operation and maintenance.

1. Trainer: Manufacturer approved instructor.

B. Submit training plan and trainer qualifications. See Section 01 91 00 -

GENERAL COMMISSIONING REQUIREMENTS.

C. Acceptance Condition: After completing work, operate door operators 15 consecutive calendar days without breakdown.

- - - E N D - - -