Specification 117300 Ceiling Mounted Patient Lift.pdf
PDF 101 KB Posted
- Attached to
- Z1DA--Modernize Building 22 506-21-102 Federal contract opportunity
- Solicitation number
- 36C25023B0005
About this file
This document includes a specification for ceiling mounted patient lift systems and a pre-solicitation notice for a related construction project. The specification outlines requirements for a ceiling track system, lift unit, motors, batteries, charger, straps, and slings for patient lifts. Key details include a 650-pound lifting capacity, emergency lowering and stopping devices, and fire-retardant cab material. The pre-solicitation notice provides advance notice of an upcoming invitation for bids for construction work at a Veterans Affairs medical center, including modernizing Building 22. The project value is estimated between $5-10 million and is a 100% set-aside for SDVOSBs. The solicitation is expected to be issued on November 30, 2022 via SAM.gov. Questions should be directed to the named contracting officer by email only.
View the file
Other files for this federal contract opportunity
Show all 49
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum #2 Ann Arbor VAMC - Modernize Building 22 #506-21-102
08-01-20
11 73 00 - 1
SECTION 11 73 00
CEILING MOUNTED PATIENT LIFT SYSTEM
PART 1 - GENERAL
1.1 DESCRIPTION
Ceiling Mounted Patient Lift Systems for the transfer of physically challenged patients are specified in this section. Lift Motor is furnished and installed by the VA. Structural support and track system are furnished and installed by the Contractor.
1.2 RELATED WORK
A. Section 01 00 00, GENERAL REQUIREMENTS: Requirements for pre-test of equipment.
B. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS: Seismic requirements for non-structural equipment.
C. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS: General
Electrical Requirements and items, which are common to sections of
Division 26.
1.3 QUALITY ASSURANCE
A. Certification for compliance is required for Ceiling Mounted Patient
Lift Systems. Certifications shall be provided by the manufacturer who will conduct testing to ensure that the ceiling lift and charging system are safe and in compliance with ISO 10535 & UL 60601-1.
B. Inspection of equipment after installation is required prior to use for patient movement. Inspection shall be in accordance with manufacturer’s installation checklist and the facilities installation checklist
(Patient Safety Alert AL14-07).
1.4 SUBMITTALS
A. Submit in accordance with specification Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA, AND SAMPLES.
1. Shop drawings shall show structural supports to the underside of structure. Structural calculations for the support of the track and its attachment to ceiling structure shall be submitted. Shop drawings used in the quoting phase shall be PDFs, and either 2D CAD files or 3D BIM files showing structural support to underside of structure. Shop drawings shall also provide general room layout with bed position and all obstructions to ceiling lift.
2. Once the purchase order is accepted by the vendor, a set of stamped drawings shall be provided by the vendor. Shop drawings and
08-01-20
11 73 00 - 2 structural calculations shall be signed and stamped by a registered structural engineer, and shall meet all code requirements in the jurisdiction having authority. Structural engineer shall ensure ceiling minimum structure capacity shall support the loads specified in the shop and installation drawings and be in compliance with local structural and seismic codes.
3. Shop drawings shall show obstructions such as curtains, lights and sprinklers, and coordinate their relocation.
B. Certificates of Compliance from Manufacturer
C. Manufacturer's Literature and Data:
1. Lifting Capacity (by VA vendor)
2. Lifting Speed (by VA vendor)
3. Vertical Axis Motor (by VA vendor)
4. Emergency Brake (by VA vendor)
5. Emergency Lowering Device (by VA vendor)
6. Emergency Stopping Device (by VA vendor)
7. Electronic Soft-Start and Soft-Stop Motor Control (by VA vendor)
8. Current Limiter for Circuit Protection (by VA vendor)
9. All equipment anchors and supports. Submittals shall include weights, dimensions, center of gravity of the structural support, standard connections, manufacturer's recommendations and behavior problems (e.g., vibration, thermal expansion,) associated with equipment or piping so that the proposed installation can be properly reviewed. (by Contractor) D. Individual Room layouts showing location of lift system installation shall be approved before proceeding with installation of lifts.
E. Manufacturer’s Checklist for after installation inspection.
1.5 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are listed in the text by the basic designation only.
B. International Organization for Standardization (ISO):
10535-06................Hoist for the Transfer of Disabled Persons-
Requirements and Test Methods
C. Underwriters Laboratories (UL):
60601-1(2003)...........Medical Electrical Equipment: General
Requirements for Safety
08-01-20
11 73 00 - 3
94-2013.................UL Standards for Safety Test for Flammability of Plastic Materials for Parts in Devices and
Appliances-Fifth Edition
D. International Electromagnetic Commission (IEC):
60601-1-2(2015).........Medical electrical equipment – Part 1-2:
General requirements for basic safety and essential performance – Collateral Standard:
Electromagnetic disturbances – Requirements and tests.
E. VA Patient Safety Alert AL14-07 (latest version)
PART 2 - PRODUCTS
2.1 CEILING TRACK SYSTEM (BY CONTRACTOR)
A. The Ceiling Track shall be made from high strength extruded aluminum or
VA approved equal. Provide anchor supports at ceiling substrate.
B. Installed rail shall be security tested for 1.5 times greater than the motor’s weight capacity and maximum allowable deflection of a horizontal rail is no more than 1mm (1/16th inch) per 200mm (7.87 inch) of track length. (As per ISO 10535 standards.)
2.2 LIFT UNIT (BY VA VENDOR)
A. The Lift Unit shall be constructed of a steel frame system driven by a gear reduced high torque motor or VA approved equal.
B. The Lift system shall have the following features.
1. Lifting capacity: 650 lbs for bariatric lifts
2. Electronic soft-start and soft-stop motor control
3. Emergency lowering device
4. Emergency stopping device
5. Current limiter for circuit protection in case of overload.
6. Safety device that stops the motor to lift when batteries are low.
7. Horizontal axis motor
8. Emergency brake (in case of mechanical failure)
9. Strap length:
10. Cab: VO plastic–fire retardant, UL 94
2.3 MOTORS (BY VA VENDOR)
A. Vertical Movement-DC Motor
2.4 BATTERIES (BY VA VENDOR)
A. The life cycle (number of charging cycles) for batteries shall be in compliance with IEC 6100-1-2.
08-01-20
11 73 00 - 4
B. Provide rechargeable batteries with up to 35 transfers with a load of
200lbs (74kg) (for repositioning) a minimum of 17 transfers with its maximum load.
2.5 CHARGER (BY VA VENDOR)
A. Charger
2.6 STRAPS AND SLING (BY VA VENDOR)
A. The straps shall meet ISO 10535 guidelines. The straps shall ensure the patient’s safety by preventing the patient from falling out of the sling.
B. The sling shall meet ISO 10535 guidelines. The sling shall cradle the body of the patient. Bariatric slings shall be rated to a minimum of
650 lbs.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install support structure and track system per approved and sealed shop drawings. (By Contractor)
B. Install ceiling mounted patient lift system as per manufacturer's instruction and under the supervision of manufacturer's qualified representative and as shown on drawings. (by VA Vendor)
C. If the distance in between the suspended ceiling and anchors is more than 12” consult with manufacturer to determine if lateral braces will be required.
3.2 INSTRUCTION AND PERSONNEL TRAINING (BY VA VENDOR)
Training shall be provided for the required personnel to educate them on proper operation and maintenance for the lift system equipment.
3.3 TEST (BY VA VENDOR)
Conduct performance test, in the presence of the COR and/or Inspector of Record (IOR), and a manufacturer's field representative, to show that the patient lift system equipment and control devices operate properly and in accordance with design, specification, and code requirements.
3.4 INSPECTION
1. Inspection of installed ceiling mounted patient lift systems shall be conducted in accordance with the manufacturer’s installation checklist and the VA installation checklist (Patient Safety Alert
AL14-07) prior to use for patient movement.
2. Periodic Inspection shall be provided by the manufacturer on a yearly basis in compliance with ISO 10535. (by VA Vendor)
08-01-20
11 73 00 - 5