This document provides details for a federal construction contract opportunity to modernize Building 22 at the LTC Charles S. Kettles Veterans Administration Medical Center in Ann Arbor, Michigan. The solicitation will be for construction services with a magnitude of cost estimated between $5 million and $10 million. The contract type will be firm fixed price with an anticipated award within 120 days of bid opening. The acquisition is reserved as a 100% set-aside for verified Service-Disabled Veteran Owned Small Businesses. Offerors must be registered in the System for Award Management and Vendor Information Pages databases. The Department of Veterans Affairs intends to issue the solicitation on November 30th, with the bid due date and other event details to be provided then. All questions must be submitted in writing to the specified contracting officer by the date indicated in the forthcoming solicitation.
View the file
Other files for this federal contract opportunity
Show all 49
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LABORATORY
UNISEX TOILET
UNISEX TOILET
DATA/IT ROOM
COMMON EQUIPMENT
COMMON EQUIPMENT
PENTHOUSE STAIR
S2
ELEVATOR
Z2
PERCHLORIC ACID ROOM
LOBBY
C-101
STAIR-2
S1-2
ELECTRIC ROOM
USP-800
LABORATORY
COMMON EQUIPMENT
2 3 4 5
E
D
C
B
COMPUTER LAB
READING ROOM
SCINTILLATION COUNTER
AND FREEZER LAB
CORRIDOR
C-102
H.A.C.
109A
CORRIDOR
C-103
CELL/TISSUE CULTURE
ELECTRIC ROOM
1 1/2" G DN
3/4" LA DN
1" LVC DN
(E) 3/4" LA UP
1 1/2" LVC UP 2
1 1/4" G
3/4" LA
1" LVC
1" G
3/4" LA
1" LVC
1" G
3/4" LA
1" LVC
3/4" G
1/2" LA
1" LVC 3/4" LVC
1/2" LA
1/2" G
1 1/2" LVC
3/4" LA
3/4" G
3/4" LVC
1/2" LA
1/2" G
1/2" G
1/2" LA
3/4" LVC
H.A.C.
3/4" G UP 2
LABORATORY
LABORATORY
1" G
1" LVC
3/4" LA
3/4" G 3/4" G
1/2" LA
1" LVC
GPR-6
GPR-7 GPR-8
GPR-9
GPR-10
GPR-11
GPR-12
GPR-13 GPR-14
GPR-15 GPR-16
3/4" G
B
USP-800
LAB
G E N E R A L N O T E S:
A. CONTRACTOR TO FIELD VERIFY EXISTING CONDITIONS AND BRING TO THE ATTENTION OF THE COR IN WRITING ANY
DISCREPANCIES THAT MAY IMPACT THE PROGRESS OF WORK.
B. REFER TO SHEET P100 FOR LEGEND AND ABBREVIATIONS.
C. REFER TO SPECIFICATION SECTIONS 226200 VACUUM SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES, 226300 GAS SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES, AND 231123 FACILITY NATURAL GAS PIPING
FOR TESTING PROCEDURES.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
A u to d e s k D o c s /A n n A rb o r
V A
M o d e rn iz e B ld g
/F
F E
A n n A rb o r
M o d e rn iz e
B
M E
P rv t
/2
/2
:4
:2
A M
PL122
FIRST FLOOR PLUMBING NEW
WORK PLAN - GASES
09/02/2022 PP GP
MODERNIZE BUILDING 22 506-21-102
ANN ARBOR, MICHIGAN
100% BID DOCUMENTS
ANN ARBOR
VAMC
Approved: Veteran's Affairs Medical Center
N
1/8" = 1'-0"
FIRST FLOOR PLUMBING NEW WORK PLAN - GASES - PHASE 2
D R A W I N G N O T E S :
1 INSTALL 1/2" LA, 1/2" G, AND 3/4" LVC ROUGH-INS FOR FUTURE FUME HOOD.
2 CORE DRILL THROUGH FLOOR SLAB FOR INSTALLATION OF PIPING THROUGH FLOOR.
3 ROUTE 1/2" LA, 1/2" G, AND 3/4" LVC PIPING TO CEILING LAB GAS QUICK CONNECTS IN CEILING SERVICE PANEL. EACH CEILING SERVICE PANEL TO HAVE (4) LA, (4) G, AND (4) LVC CONNECTIONS. REFER TO SHEET AC142 FOR CEILING
SERVICE PANEL DETAIL.
4 ROUTE 1/2" LA, 1/2" G, AND 3/4" LVC PIPING DOWN IN WALL TO FUME HOOD.
5 CONNECT LABORATORY AIR PIPING TO EXISTING AT POINT SHOWN.
6 CONNECT LA, G, AND LVC PIPING TO EXISTING AT POINT SHOWN.
N
1/8" = 1'-0"
FIRST FLOOR PLUMBING NEW WORK PLAN - GASES - PHASE 1
No. Revisions: Date:
100% BID DOCUMENTS 09/02/2022
2 ADDENDUM 02 03/02/2023
09/02/2022
ALL PIPING LABELED AND REFERENCES TO
LABORATORY GAS (LG) HAVE BEEN CHANGED TO
NATURAL GAS (G)