This document appears to be the Panel Schedules for the Electrical system of the Kilauea Visitor Center (KVC) project at Hawaii Volcanoes National Park. The project is part of Phase II, which includes rehabilitation of the existing KVC, demolition and replacement of the existing comfort station, and expansion of the KVC lanai. The electrical panel schedules provide details on the electrical loads, circuit breakers, and wiring for the various electrical systems serving the KVC facility, including lighting, receptacles, HVAC, and backup generator components. The related federal contract opportunity is Solicitation Number 140P2024R0114 for the HAVO 305150 Phase II, Kilauea Visitor Center (KVC) project, issued by the National Park Service.

View the file

Other files

File Type Posted
B08_Attachment_6_HAVO_305150_Wage_Determination_9_6_2024_0009.pdf PDF
Sol_140P2024R0114_Amd_0009.pdf PDF
B09_Attachment_25_-_Amd_08_Solicitation_QA_HAVO_305150_0008.xlsx XLSX spreadsheet
Sol_140P2024R0114_Amd_0008.pdf PDF
B09_Attachment_51_-_A8-A20-A22-A24-A25-A26_REV_0008.pdf PDF
B09_Attachment_48_-_C9_WATER_PLAN_AND_PROFILE_II_REV_0007.pdf PDF
B09_Attachment_36_-_08_31_13_-_ACCESS_DOORS_AND_FRAMES_0007.pdf PDF
B09_Attachment_30_-_08_14_33_-_STILE_AND_RAIL_WOOD_DOORS_0007.pdf PDF
B09_Attachment_41_-_09_29_00_-_GYPSUM_BOARD_0007.pdf PDF
B08_Attachment_6_HAVO_305150_Wage_Determination_7_19_2024_0007.pdf PDF
B09_Attachment_38_-_08_80_00_-_GLAZING_0007.pdf PDF
B09_Attachment_46_-_A22-A28-A51_REV_0007.pdf PDF
B09_Attachment_44_-_10_28_00_-_TOILET_ACCESSORIES_0007.pdf PDF
B09_Attachment_43_-_09_51_13_-_ACOUSTICAL_PANEL_CEILINGS_0007.pdf PDF
B09_Attachment_32_-_06_20_13_-_Exterior_Finish_Carpentry_0007.pdf PDF
B09_Attachment_40_-_08_91_19_-_FIXED_LOUVERS_0007.pdf PDF
B09_Attachment_47_-_C6_C11_C16_REV_0007.pdf PDF
B09_Attachment_49_-_E15_REV_0007.pdf PDF
B09_Attachment_28_-_07_92_00_-_Joint_Sealants_0007.pdf PDF
B09_Attachment_29_-_08_12_13_-_Hollow_Metal_Frames_0007.pdf PDF
B09_Attachment_37_-_08_71_00_-_Door_Hardware_0007.pdf PDF
B09_Attachment_25_-_Amd_07_Solicitation_QA_HAVO_305150_0007.xlsx XLSX spreadsheet
B09_Attachment_35_-_07_72_00_-_Roof_Accessories_0007.pdf PDF
B09_Attachment_34_-_07_62_00_-_Sheet_Metal_Flashing_and_Trim_0007.pdf PDF
B09_Attachment_33_-_07_21_00_-_Thermal_Insulation_0007.pdf PDF
B09_Attachment_42_-_09_30_13_-_CERAMIC_TILING_0007.pdf PDF
B09_Attachment_31_-_01_77_00A_Closeout-OperationMaintenance-Requirements_0007.pdf PDF
B09_Attachment_39_-_08_83_00_-_MIRRORS_0007.pdf PDF
Sol_140P2024R0114_Amd_0007.pdf PDF
B09_Attachment_45_-_33_14_16___Site_Water_Utility_Distribution_0007.pdf PDF
B09_Attachment_27_-_01_33_23-A_SubmittalList-ReviewEstimate_0007.pdf PDF
B09_Attachment_26_-_00_-_Table_of_Contents_0007.pdf PDF
Attachment_23_-_Pre-proposal_Site_Visit_Sign-in_Roster_7_31_2024_0006.pdf PDF
Attachment_21_-_01_33_23-A_SubmittalList-ReviewEstimate_0006.pdf PDF
Attachment_18_-_R1_A42_CD_HAVO_KVC_0006.pdf PDF
Attachment_24_-_HAVO_305150B_Prebid_Meeting_Notes_7-31-24_0006.pdf PDF
Attachment_17_-_R1_A36_CD_HAVO_KVC_0006.pdf PDF
Sol_140P2024R0114_Amd_0006.pdf PDF
Attachment_25_-_Amd_06_Solicitation_QA_HAVO_305150_0006.xlsx XLSX spreadsheet
Attachment_22_-_01_77_00A_Closeout-OperationMaintenance-Requirements_0006.pdf PDF
Attachment_20_-_SECTION_08_71_00_-_DOOR_HARDWARE_-_REV_2_0006.pdf PDF
Attachment_19_-_R1_A49_CD_HAVO_KVC_0006.pdf PDF
Sol_140P2024R0114_Amd_0005.pdf PDF
B09_Attachment_15_-_Cold_Fluid-Applied_Waterproofing-rev1_07_14_16_0004.pdf PDF
B09_Attachment_16_-_S1_Basement-81_0004.pdf PDF
Sol_140P2024R0114_Amd_0004.pdf PDF
Sol_140P2024R0114_Amd_0003.pdf PDF
B09_Attachment_14_-_Site_Visit_Tri_Fold_HAVO_305150B_-_AMENDMENT_3_0003.pdf PDF
B09_Attachment_13_-_HAVO_305150_Prebid_Site_Visit_Insructions_0003.pdf PDF
B08_Attachment_2_HAVO305150_FinalCDDrawings_0002.pdf PDF
Show 40 more

Latest 50 of 72 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OF

PMIS/PKG NO.

DRAWING NO.SUB SHEET NO.

HAWAII VOLCANOES NATIONAL PARK

KILAUEA VISITOR CENTER

DESIGNED:

CADD:

TECH REVIEW:

DATE:

187007

SHEET

HAVO 305150B

/1 /2

:5 :5 A M

C R e v it P r o je c t s \M

E P H A V O K V C R r a y m o n d c 1.

r v t

E25E25E25E25

PANEL SCHEDULES PANEL SCHEDULES PANEL SCHEDULES PANEL SCHEDULES −−−−

ELECTRICALELECTRICALELECTRICALELECTRICAL

MJ,DO

HN, DO

MO

05/24/2024

Total NEC Demand Current: 0.0 A

Total Connected Current: 0.0 A

Total NEC Demand: 0.0 VA

Total Connected Load: 0.0 VA

Load Type Connected Load NEC Demand Factor NEC Demand Load Panel Totals

E = Existing Load 30-day metered (125%) EL = Elevator (Demand as per NEC Table... W = Water Heater (125%)

R = Receptacles (to 10kVA100%, over 10 kVA... G = General Load (Non-continuous) (100%) L = Lighting (125%) H = Heating (100%)

Motor (125% largest Motor + 100% remaining... K = Kitchen (Demand as per NEC Table 220.56) C = Continuous Load (125%) X = X-Rays (Demand per NEC...

Load Type Definitions:

Notes:

Total Connected load Ph. C 0 A

Total Connected load Ph. B 0 A Total Demand Load: 0.0 kVA 0.0 A

Total Connected load Ph. A 0 A Panel Connected Load: 0.0 kVA 0.0 A

23 24

21 22

19 20

17 18

15 16

13 14

11 12

9 10

7 8

5 6

3 4

1 2

CKT Description/Location Type C.B. Pole Note

A B C A B C

Note Pole C.B. Type Description/Location CKT

Load (VA)

FOR AIC RATING SEE ONE-LINE DIAGRAM SUPPLIED FROM:

EQUIPMENT RATING: 120/208 V, 3PH, 4 WIRE LOCATION:

BUS AMPACITY: 100 A ENCLOSURE: TYPE 1

MAIN CIRCUIT BREAKER 100 A MOUNTING: SURFACE Accessories:

PANELBOARD: PVVC

Total NEC Demand Current: 0.0 A

Total Connected Current: 0.0 A

Total NEC Demand: 0.0 VA

Total Connected Load: 0.0 VA

Load Type Connected Load NEC Demand Factor NEC Demand Load Panel Totals

E = Existing Load 30-day metered (125%) EL = Elevator (Demand as per NEC Table... W = Water Heater (125%)

R = Receptacles (to 10kVA100%, over 10 kVA... G = General Load (Non-continuous) (100%) L = Lighting (125%) H = Heating (100%)

Motor (125% largest Motor + 100% remaining... K = Kitchen (Demand as per NEC Table 220.56) C = Continuous Load (125%) X = X-Rays (Demand per NEC...

Load Type Definitions:

Notes:

Total Connected load Ph. C 0 A

Total Connected load Ph. B 0 A Total Demand Load: 0.0 kVA 0.0 A

Total Connected load Ph. A 0 A Panel Connected Load: 0.0 kVA 0.0 A

23 24

21 22

19 20

17 18

15 16

13 14

11 12

9 10

7 8

5 6

3 4

1 2

CKT Description/Location Type C.B. Pole Note

A B C A B C

Note Pole C.B. Type Description/Location CKT

Load (VA)

FOR AIC RATING SEE ONE-LINE DIAGRAM SUPPLIED FROM:

EQUIPMENT RATING: 120/208 V, 3PH, 4 WIRE LOCATION:

BUS AMPACITY: 100 A ENCLOSURE: TYPE 4X

MAIN CIRCUIT BREAKER 100 A MOUNTING: SURFACE Accessories:

PANELBOARD: PVS

M 400.0 125.00% 500.0

R 3260.0 100.00% 3260.0 Total NEC Demand Current: 31.4 A

G 750.0 100.00% 750.0 Total Connected Current: 30.1 A

Motor 700.0 125.00% 875.0 Total NEC Demand: 11322.5 VA

L 750.0 125.00% 937.5 Total Connected Load: 10860.0 VA

H 5000.0 100.00% 5000.0

Load Type Connected Load NEC Demand Factor NEC Demand Load Panel Totals

E = Existing Load 30-day metered (125%) EL = Elevator (Demand as per NEC Table... W = Water Heater (125%)

R = Receptacles (to 10kVA100%, over 10 kVA... G = General Load (Non-continuous) (100%) L = Lighting (125%) H = Heating (100%)

Motor (125% largest Motor + 100% remaining... K = Kitchen (Demand as per NEC Table 220.56) C = Continuous Load (125%) X = X-Rays (Demand per NEC...

Load Type Definitions:

1. MANY OF THE ITEMS ASSIGNED TO CIRCUITS ARE EXISTING. REWIRE THEM AS REQUIED TO THIS NEW PANEL. PULL NEW WIRE IF REQUIRED FOR LENGTH.

2. ADJUST BREAKER SIZE PER GENERATOR MANUFACTURERS REQUIREMENTS.

3. PROVIDE 5mA GFCI CIRCUIT BREAKER.

Notes:

Total Connected load Ph. C 11 A

Total Connected load Ph. B 46 A Total Demand Load: 11.3 kVA 31.4 A

Total Connected load Ph. A 42 A Panel Connected Load: 10.9 kVA 30.1 A

29 30

27 28

25 26

23 24

21 22

19 20

17 18

15 16

13 SWITCHBOARD LIGHTS L 20 A 1 250 400 1 15 A M EF-3 14

11 SWITCHBOARD HEATER H 20 A 1 500 250 1 20 A L OUTSIDE POLE LIGHT 12

9 DAYTANK PUMP Motor 20 A 1 700 1,900 3 1 20 A R GEN. ROOM RECEPTACLES 10

7 GEN BATTERY CHARGER G 20 A 1 300 1,000 1 20 A R UPS 8

5 GENERATOR BLDG LIGHTS L 20 A 1 250 360 1 20 A R TELEPHONE TERMINSL 6

3 GEN. MOTORIZED LOUVERS G 20 A 1 150 2,250 -- -- -- -- -- 4

1 GEN. FUEL COOLER G 20 A 1 300 2,250 2 2 30 A H GEN. WATER JACKET HTR 2

CKT Description/Location Type C.B. Pole Note

A B C A B C

Note Pole C.B. Type Description/Location CKT

Load (VA)

FOR AIC RATING SEE ONE-LINE DIAGRAM SUPPLIED FROM:

EQUIPMENT RATING: 120/208 V, 3PH, 4 WIRE LOCATION:

BUS AMPACITY: 100 A ENCLOSURE: TYPE 1

MAIN CIRCUIT BREAKER 100 A MOUNTING: SURFACE Accessories:

PANELBOARD: GEN

Total NEC Demand Current: 10.4 A

Total Connected Current: 9.9 A

Total NEC Demand: 3746.0 VA

R 2880.0 100.00% 2880.0 Total Connected Load: 3572.8 VA

L 692.8 125.00% 866.0

Load Type Connected Load NEC Demand Factor NEC Demand Load Panel Totals

E = Existing Load 30-day metered (125%) EL = Elevator (Demand as per NEC Table... W = Water Heater (125%)

R = Receptacles (to 10kVA100%, over 10 kVA... G = General Load (Non-continuous) (100%) L = Lighting (125%) H = Heating (100%)

Motor (125% largest Motor + 100% remaining... K = Kitchen (Demand as per NEC Table 220.56) C = Continuous Load (125%) X = X-Rays (Demand per NEC...

Load Type Definitions:

1. PROVIDE 5mA GFCI CIRCUIT BREAKER.

Notes:

Total Connected load Ph. C 3 A

Total Connected load Ph. B 16 A Total Demand Load: 3.7 kVA 10.4 A

Total Connected load Ph. A 14 A Panel Connected Load: 3.6 kVA 9.9 A

29 30

27 28

25 26

23 24

21 22

19 20

17 EXHIBIT LIGHTING L 20 A 1 0 18

15 EXHIBIT LIGHTING L 20 A 1 0 16

13 EXHIBIT LIGHTING L 20 A 1 0 14

11 180 1 1 20 A R HALAU RECEPTACLE 12

9 HALAU RECEPTACLES R 20 A 1 1 540 23 1 20 A L LV1 LIGHTING 10

7 HALAU RECEPTACLES R 20 A 1 1 720 8

5 LIGHTING KVC L 20 A 1 124 6

3 HALAU LIGHTS L 20 A 1 504 720 1 1 20 A R HALAU RECEPTACLES 4

1 HALAU LIGHTS L 20 A 1 42 720 1 1 20 A R HALAU RECEPTACLES 2

CKT Description/Location Type C.B. Pole Note

A B C A B C

Note Pole C.B. Type Description/Location CKT

Load (VA)

FOR AIC RATING SEE ONE-LINE DIAGRAM SUPPLIED FROM:

EQUIPMENT RATING: 120/208 V, 3PH, 4 WIRE LOCATION:

BUS AMPACITY: 100 A ENCLOSURE: TYPE 4X

MAIN CIRCUIT BREAKER MOUNTING: SURFACE Accessories:

PANELBOARD: L1

markj Cloud markj Cloud

Sheets
E25 - PANEL SCHEDULES - ELECTRICAL