This is a cost proposal submitted by TRC Environmental Corporation to the City of Madison, Wisconsin Engineering Division in response to RFP #8914-0-2020-BG for environmental consulting services. The proposal was prepared on February 14, 2020, and provides pricing for an umbrella contract under which TRC would provide environmental site assessment services on an as-needed basis for properties owned or being considered for purchase by the City, as well as services during right-of-way construction activities. The proposal includes four example scenarios with defined scopes of work: Phase 1 Environmental Site Assessment for a 10,000 square foot former industrial facility; WisDOT Hazardous Material Assessment for a 0.25-mile stretch of county highway; Phase 2 Environmental Site Assessment including soil borings, groundwater monitoring wells, laboratory sampling and analysis; and Right-of-Way Construction Oversight for utility excavation screening. Each example scenario includes detailed assumptions regarding site access, timeline, equipment availability, and potential limitations such as weather delays or unsafe conditions.

The grand total not-to-exceed cost for all four example projects is $31,517.48, with individual project costs ranging from $2,610.47 for the Phase 1 ESA to $13,892.22 for the Phase 2 ESA. Labor costs are based on a tiered rate schedule effective through December 31, 2020, ranging from $68.46 per hour for Field Technicians to $190.46 per hour for Contract Managers. The proposal includes detailed breakdowns of labor, subcontract costs (including laboratory services and equipment rentals), and direct expenses such as vehicle mileage, equipment rentals, meals, and fuel. A 10 percent markup is applied to non-labor costs and expenses, though this markup does not apply to equipment and laboratory unit rates. The proposal includes comprehensive equipment rate tables for various monitoring and sampling equipment available on a daily or weekly basis, with rates effective through December 31, 2020, subject to annual calendar year escalation for future invoicing.

View the file

Other files

File Type Posted
Hyde.pdf PDF
Stantec Environmental Consulting Services Technical Proposal.pdf PDF
Stantec Environmental Consulting Services Cost Proposal.pdf PDF
ETC - Technical.pdf PDF
Hyde Proposal.pdf PDF
ProSource Technologies - Technical Proposal - RFP 8914-0-2020-BG.pdf PDF
RFP8914-0-2020-BG - The Sigma Group - Cost Proposal Environmental Consulting Services - City of Madison - 19181.pdf PDF
ETC -Cost.pdf PDF
Merjent.pdf PDF
RFP8914-0-2020-BG - The Sigma Group - Environmental Consulting Services Propsoal - City of Madison - 19181.pdf PDF
Merjent_City of Madison Proposal_Att A_Form D RFP 8914-0-2020-BG.pdf PDF
Ayres - TechnicalCompressed.pdf PDF
SEH Submittal - Technical Proposal RFP 8914-0-2020-BG.pdf PDF
Shannon Wilson.pdf PDF
Professional Environmental Engineers Inc (2).pdf PDF
Shannon Wilson - Cost.pdf PDF
SCS Form D.pdf PDF
SEH Submittal - Cost Proposal RFP 8914-0-2020-BG.pdf PDF
RPS Group.pdf PDF
Ayres - Technical.pdf PDF
9296 Environmental Consulting Services.pdf PDF
Professional Environmental Engineers Inc.pdf PDF
RPS Form D.pdf PDF
RFP 9296 Qs and As.pdf PDF
Ayres - Cost.pdf PDF
SCS Engineers.pdf PDF
ProSource Technologies - Cost Proposal - RFP 8914-0-2020-BG.pdf PDF
TRC Environmental Corporation.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COST PROPOSAL FOR

Environmental Consulting Services

RFP #: 8914-0-2020-BG

Prepared by:

TRC Environmental Corporation 708 Heartland Trail, Madison, WI 53717

(608) 826-3600 | TRCcompanies.com

Prepared for:

The City of Madison February 14, 2020

Example No. 1: Phase 1 ESA $2,610.47

Example No. 2: WisDOT Hazardous Material Assessment $3,482.89

Example No. 3: Phase 2 ESA $13,892.22

Example No. 4: Right-of-Way Construction Oversight $11,531.90

GRAND TOTAL COST (NOT TO EXCEED): $31,517.48

A detailed breakdown of costs for each example is provided in the following pages followed by assumptions and rate tables for labor and equipment.

Form D - Cost Proposal

Total Cost of all example projects

TRC Environmental Corporation

\\madison-vfp\Records\-\WPMSN\PJT2\379886\9990\1-Form D - Cost Proposal.xlsx

LABOR TOTAL: $2,193.27

TASK POSITION TITLE RATE COST

Contract Manager $190.46 $190.46

Project Supervisor $145.22 $363.05

Engineer/Hydrogeologist $95.26 $0.00

Scientist $81.00 $1,174.50

Field Technician $68.46 $0.00

CADD, GIS $76.09 $152.18

Administrative Support $78.27 $313.08

TOTAL LABOR $2,193.27

SUBCONTRACT COSTS TOTAL: $407.00

SUBCONTRACTOR SUBCONTRACTED SERVICES QUANTITY UNIT RATE COST

EDR Standard Package 1 Each $370.00 $370.00

Markup 10% $37.00

TOTAL CONTRACTORS $407.00

DIRECT EXPENSES TOTAL: $10.20

ITEM QUANTITY UNIT UNIT PRICE COST

Equipment Vehicle Mileage 20 Mile $0.51 $10.20

TOTAL DIRECT EXPENSES $10.20

TOTAL COST (NOT TO EXCEED): $2,610.47

Form D - Cost Proposal

Example No. 1: Phase 1 ESA for a 10,000 sq ft former industrial facility

HOURS

2.5

TRC Environmental Corporation

14.5

Example No. 1: Phase 1 ESA for a 10,000 sq ft former industrial facility

LABOR TOTAL: $3,250.65

Contract Manager $190.46 $0.00

Project Supervisor $145.22 $798.71

Engineer/Hydrogeologist $95.26 $0.00

Scientist $81.00 $1,984.50

Field Technician $68.46 $0.00

CADD, GIS $76.09 $76.09

Administrative Support $78.27 $391.35

TOTAL LABOR $3,250.65

SUBCONTRACT COSTS TOTAL: $0.00

SUBCONTRACTOR SUBCONTRACTED SERVICES QUANTITY UNIT RATE COST

None 0 Each $0.00 $0.00

Markup 10% $0.00

TOTAL CONTRACTORS $0.00

DIRECT EXPENSES TOTAL: $232.24

ITEM QUANTITY UNIT UNIT PRICE COST

Equipment Vehicle Mileage 20 Mile $0.51 $10.20

SUBTOTAL, EQUIPMENT $10.20

Expenses Historical Documents 1 Allowance $200.00 $200.00

Markup 10% $22.04

SUBTOTAL, EXPENSES $222.04

TOTAL COST (NOT TO EXCEED): $3,482.89

Form D - Cost Proposal

Example No. 2: WisDOT Hazardous Material Assessment

HOURS

5.5

TRC Environmental Corporation

24.5

Example No. 2: WisDOT Hazardous Material Assessment

LABOR TOTAL: $7,113.57

Contract Manager $190.46 $0.00

Project Supervisor $145.22 $2,178.30

Engineer/Hydrogeologist $95.26 $4,000.92

Scientist $81.00 $243.00

Field Technician $68.46 $0.00

CADD, GIS $76.09 $456.54

Administrative Support $78.27 $234.81

TOTAL LABOR $7,113.57

SUBCONTRACT COSTS TOTAL: $5,754.65

SUBCONTRACTOR SUBCONTRACTED SERVICES QUANTITY UNIT RATE COST

WI-Certified Laboratory VOCs (8260) - water 8 Each $56.10 $448.80

RCRA 8 Metals (6010/7470/7471) - water 8 Each $66.00 $528.00

PAHs (8270 SIM) - water 8 Each $79.20 $633.60

VOCs (8260) - soil 10 Each $56.10 $561.00

RCRA 8 Metals (6010/7470/7471) - soil 10 Each $66.00 $660.00

PCB Aroclors (8082) - soil 10 Each $67.10 $671.00

SUBTOTAL, LABORATORY COSTS $3,502.40

Services Provided

On-Site Environmental Geoprobe, well installation/abandonment 1 TM $2,047.50 $2,047.50

Markup 10% $204.75

SUBTOTAL, CONTRACTORS $2,252.25

DIRECT EXPENSES TOTAL: $1,024.00

ITEM QUANTITY UNIT UNIT PRICE COST

Equipment Vehicle Rental (TRC) 3 Day $70.00 $210.00

Water Level Indicator 3 Day $30.00 $90.00

Peristaltic Pump 3 Day $35.00 $105.00

Barrel filter 6 Each $22.00 $132.00

Silicon tubing (per ft) 6 Foot $3.00 $18.00

LDPE/HDPE tubing 120 Foot $0.15 $18.00

PID 1 Day $110.00 $110.00

Field book - standard 1 Each $7.00 $7.00

Soil sampling kit 1 Day $50.00 $50.00

PPE - Basic kit 1 Day $20.00 $20.00

PPE - Sampling gloves 1 Box $15.00 $15.00

GPS/Trimble or equivalent 1 Day $150.00 $150.00

SUBTOTAL, EQUIPMENT $925.00

Expenses Meals 3 Allowance $25.00 $75.00

Vehicle Gas 5 Gallon $3.00 $15.00

Markup 10% $9.00

SUBTOTAL, EXPENSES $99.00

TOTAL COST (NOT TO EXCEED): $13,892.22

Form D - Cost Proposal

Example No. 3: Phase 2 ESA

HOURS

Example No. 3: Phase 2 ESA

TRC Environmental Corporation

LABOR TOTAL: $9,623.90

Contract Manager $190.46 $0.00

Project Supervisor $145.22 $580.88

Engineer/Hydrogeologist $95.26 $8,573.40

Scientist $81.00 $0.00

Field Technician $68.46 $0.00

CADD, GIS $76.09 $0.00

Administrative Support $78.27 $469.62

TOTAL LABOR $9,623.90

SUBCONTRACT COSTS TOTAL: $0.00

SUBCONTRACTOR SUBCONTRACTED SERVICES QUANTITY UNIT RATE COST

None 0 Each $0.00 $0.00

Markup 10% $0.00

TOTAL CONTRACTORS $0.00

DIRECT EXPENSES TOTAL: $1,908.00

ITEM QUANTITY UNIT UNIT PRICE COST

Equipment Vehicle Rental (TRC) 2 Week $350.00 $700.00

PID 2 Week $270.00 $540.00

Field book - standard 1 Each $7.00 $7.00

Soil sampling kit 1 Week $200.00 $200.00

PPE - Basic kit 1 Week $60.00 $60.00

PPE - Sampling gloves 4 Box $15.00 $60.00

SUBTOTAL, EQUIPMENT $1,567.00

Expenses Meals 10 Allowance $25.00 $250.00

Vehicle Gas 20 Gallon $3.00 $60.00

Markup 10% $31.00

SUBTOTAL, EXPENSES $341.00

TOTAL COST (NOT TO EXCEED): $11,531.90

Form D - Cost Proposal

Example No. 4: Right-of-Way Construction Oversight

HOURS

Example No. 4: Right-of-Way Construction Oversight

TRC Environmental Corporation

RFP #8914-0-2020-BG

02/14/2020 | Proposal No. 379886 Madison, WI 1

City of Madison

Form D – Cost Proposal Assumptions

1.0 Phase 1 Environmental Site Assessment

Example scenario 1 is to complete a Phase 1 ESA for a 10,000 square foot (sq ft) former industrial facility.

Budget Assumptions

Access to the Site and all on-site structures will be coordinated by the Client or Client representative;

The Site visit can be conducted in two hours by one TRC professional;

The review of pertinent Site or adjoining property regulatory files or records can be completed within 2 hours;

Regulatory files for the Site and/or adjoining properties will be available digitally and fees for reproductions will not be required;

The search for environmental lien and activity and use limitations (AULs) will be performed by the Client and provided to TRC for review and incorporation into the Phase I ESA; and

No delays beyond TRC’s control will be encountered in performing the scope of services such as unforeseen travel circumstances, inclement weather, and conditions deemed unsafe by TRC personnel, etc.

2.0 WisDOT Hazardous Materials Assessment

Example scenario 2 is to complete a WisDOT Hazardous Material Assessment for a 0.25-mile stretch of county highway at the edge of the City.

Budget Assumptions

WDNR files are available online for BRRTS sites and file reviews at the WDNR are not required;

The Site visit can be conducted in two hours by one TRC professional;

The review of pertinent Site or adjoining property regulatory files or records can be completed within 2 hours;

An allowance of up to $200 is included for the costs to obtain historical aerial photographs;

Sanborn fire insurance maps are not available for this highway corridor;

No significant property acquisitions are planned, and the reconnaissance will be performed from the county highway right-of-way; and

No delays beyond TRC’s control will be encountered in performing the scope of services such as unforeseen travel circumstances, inclement weather, and conditions deemed unsafe by TRC personnel, etc.

Madison, WI 2

3.0 Phase 2 Environmental Site Assessment

Example scenario 3 is to complete a Phase 2 Environmental Site Assessment: Assume 7 borings to 10 feet bgs, 3 borings to 15 feet, installation/development of 3 groundwater wells in the deeper borings, 2 rounds of groundwater sampling for VOCs/RCRA metals/PAHs, collection and analysis of two soil samples per boring for RCRA metals/VOCs/PCBs, abandonment of borings/wells per NR 141, report preparation and submittal to DNR for review. Include all costs typically associated with a Phase 2 ESA, including laboratory costs, creating site maps, surveying, project oversight, coordination with the DNR project manager, etc.

Budget Assumptions

A site-specific Health and Safety Plan will be prepared by TRC prior to the commencement of field activities;

Access to the Site and all on-site structures will be coordinated by the Client or Client representative;

Standard 10-day turnaround time with laboratory;

Field work includes up to three eight-hour days by one TRC project engineer/geologist to complete soil sampling and two rounds of groundwater sampling;

NR 141 compliant groundwater monitoring wells are not necessary for the Phase 2 ESA. A variance from the DNR to use small diameter temporary monitoring wells will be submitted and approved prior to installation. The temporary wells will be constructed such that they can be left in place to collect the two rounds of groundwater sampling;

Wells will produce a sufficient volume of groundwater for the required analyses;

Groundwater samples will be collected using a peristaltic pump or bailer, low-flow stabilization is not required prior to sample collection;

Groundwater samples for metals analysis will be filtered in the field;

Investigation derived waste will be left on-site;

One duplicate sample will be submitted for analysis for each round of groundwater sampling;

All on-site work will be performed in Level D personal protective equipment;

Temporary monitoring wells will be abandoned by the drilling subcontractor; no oversight by TRC is proposed; and

No delays beyond TRC’s control will be encountered in performing the scope of services such as unforeseen travel circumstances, inclement weather, and conditions deemed unsafe by TRC personnel, etc.

4.0 Construction Oversight

Example Scenario 4 is to complete right of way construction oversight: Assume a two-week project that requires an engineer or hydrogeologist is onsite for 6 hours a day, 5 days a week to screen soils for contamination associated with utility excavation in the right of way. Costs should include a simple post-construction report with photos and a marked-up map, as well as any associated project management.

Madison, WI 3

Budget Assumptions

A site-specific Health and Safety Plan will be prepared by TRC prior to the commencement of field activities;

10 days have been budgeted for field-screening of potentially contaminated soil. On-site time will be as required by the contractor’s schedule but TRC assumes 6-hour days plus travel time (estimated at 15 minutes one way) for the onsite engineer and/or hydrogeologist;

Project plans, Special Provisions, and previous reports will be provided to TRC for review prior to commencement of oversight activities;

Previous investigative work has been completed along the right of way corridor and Special Provisions provide details for areas of concern and contaminated soil management.

Laboratory analytical data is available and representative of soil requiring offsite disposal and waste profile coordination and approvals will be completed by the City;

Railroad Protective Liability Insurance (RPLI) is not required;

Impacted groundwater will not be encountered during construction.

Agency submittals, if required, will be completed by the City;

All on-site work will be performed in Level D personal protective equipment; and

No delays beyond TRC’s control will be encountered in performing the scope of services such as unforeseen travel circumstances, inclement weather, and conditions deemed unsafe by TRC personnel, etc.

\\madison-vfp\Records\-\WPMSN\PJT2\379886\9990\3-Form D - Cost Proposal Labor Rate Schedule.docx Page 1 of 1

TRC Schedule of Charges - Employee Labor Rates Pricing effective through December 31, 2020

TITLE STAFF RATE

Contract Manager

Kris Krause, PE

$ 190.46

Ken Quinn, PG

John Rice, PE, PH

Bruce Iverson, PE

Jean Oliva, PE

Dean Epping, CHMM

John Tweddale, PG

James Wink

Project Supervisor

Mike Ursin, PG

$ 145.22

Dan Haak, PE

Alyssa Sellwood, PE

Meredith Westover, PG

Ted O'Connell

Steve Sellwood, PhD, PG

Engineer/Hydrogeologist

Andrew Stehn, PE

$ 95.26

Wes Braga

Tom Perkins

Ben Wachholz, PE

Peggy Popp

Scientist Lydia Auner

$ 81.00 Liz Hoerning

CADD, GIS $ 76.09

Administrative Support $ 78.27

Field Technician John Roelke $ 68.46

(1) A 10% Mark-up will be added to non-labor costs and expenses/ODCs. The markup does not apply to equipment & laboratory unit rates.

(2) Overtime rates will apply to non-exempt (hourly) staff in conformance with applicable law.

(3) TRC rates are subject to an annual calendar year escalation.

(4) Invoicing will apply TRC billing rates in conformance with the rate schedule in effect at the time of the services.

(5) For Litigation or Litigation Support Services, please request a copy of our Standard Rates for Litigation Services.

\\madison-vfp\Records\-\WPMSN\PJT2\379886\9990\4-Form D - Cost Proposal Equipment Rate Tables.docx Page 1 of 2

TRC Schedule of Charges - Equipment Rates Pricing effective through December 31, 2020

ITEM UNIT STANDARD RATE

WATER/MONITORING WELL SAMPLING

Water Quality Meter Day $ 25

Week $ 75

Water Quality Meter with Flow Cell Day $ 120

Week $ 360

Water Level Indicator Day $ 30

Week $ 90

Interface Probe Day $ 50

Week $ 120

Submersible Pressure Transducer, Levelogger Day $ 70

Week $ 210

Turbidity Meter Day $ 35

Week $ 105

Peristaltic Pump Day $ 35

Week $ 105

Bladder Pump Day $ 45

Week $ 135

Bladder Pump Control Box (<200') Day $ 65

Week $ 195

Compressor/CO2 for Bladder Pump Day $ 30

Week $ 90

Purge Pump Day $ 60

Week $ 180

Disposable Bladders Each $ 15

Grab Plate Replacement Kit Each $ 12

Bailer (HDPE) - Small Dia. Each $ 7

Bailer (HDPE) - Large Dia. Each $ 15

Barrel Filter Each $ 22

Silicon Tubing (per ft) Foot $ 3

Tygon Tubing (per ft) Foot $ 3

LDPE/HDPE Tubing Foot $ 0

SOIL/SEDIMENT SAMPLING

Hand Auger Day $ 15

Week $ 45

PID Day $ 110

Week $ 270

VAPOR/AIR SAMPLING

Landfill Gas Monitor Day $ 135

Week $ 405

Vapor Pin Each $ 55

High Purge Sampling Pin Each $ 20

\\madison-vfp\Records\-\WPMSN\PJT2\379886\9990\4-Form D - Cost Proposal Equipment Rate Tables.docx Page 2 of 2

TRC Schedule of Charges - Equipment Rates Pricing effective through December 31, 2020

ITEM UNIT STANDARD RATE

MISCELLANEOUS/TOOLS

Air Compressor Day $ 45

Week $ 135

Generator Day $ 80

Week $ 240

Padlock Each $ 20

Field Book - Standard Each $ 7

Metal Detector Day $ 40

Week $ 120

Clay Each $ 6

Hand Pump Day $ 10

Week $ 30

Hammer Drill Day $ 80

Week $ 240

Shop Vac Day $ 10

Week $ 30

55-gallon Drum Each $ 75

Groundwater Sampling Kit Day $ 50

Week $ 200

Soil/Sediment Sampling Kit Day $ 50

Week $ 200

PPE

PPE - Basic Kit Day $ 20

Week $ 60

PPE - Sampling Gloves (per box) Each $ 15

PPE-Tyvek & Boot Covers (per prsn/day) Day $ 60

MOBILE/DIGITAL

GPS/TRIMBLE or Equivalent Day $ 150

Week $ 600

Tablet/iPad Day $ 25

Week $ 100 www.TRCcompanies.com