Environmental Consulting Services Proposal
This is a proposal submitted by The Sigma Group, Inc. to the City of Madison Engineering Division in response to RFP #8914-0-2020-BG for environmental consulting services. The proposal was submitted on February 14, 2020, for an umbrella contract under which selected firms will provide environmental site assessment services on an as-needed basis. Services requested include Phase I Environmental Site Assessments (ESAs), Phase II ESAs, remedial action planning, regulatory interaction, and related environmental consulting activities for properties owned or being considered for purchase by the City of Madison, as well as work conducted in the right of way during construction activities. The contract term is three years with annual percent price increases permitted. The City anticipates selecting 2 to 3 qualified vendors and expects to conduct approximately 3 to 6 Phase I ESAs or WisDOT Hazardous Materials Assessments, one Phase II ESA/site investigation, and contaminated soil oversight on one right-of-way project annually.
The City's total contract budget is projected between $50,000 and $100,000 annually with no minimum guaranteed. Unit pricing was required for Phase I ESAs, Phase II ESAs, and typical associated work including vapor testing, with asbestos and lead-based paint pricing to be estimated on a case-by-case basis. The City stated this is the first competitive bidding round for this contract. The evaluation criteria allocate 65 percent of the final score to Qualifications, Experience, and References (evaluated equally), with the remaining 35 percent allocated to cost. For each specific project, firms will be asked to submit a scope of work and budget; the City may request all firms to bid or select a single firm based on project schedule and capacity considerations. The Sigma Group's proposal emphasizes its 26-year history serving the City of Milwaukee, Wisconsin Department of Natural Resources, and multiple counties, complemented by a team of Professional Engineers, Geologists, Hydrogeologists, and certified specialists, along with partnerships with Woman Business Enterprises and Minority Business Enterprises as subcontractors.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Madison Environmental Consulting Services
RFP #8914-0-2020-BG
Submitted by:
The Sigma Group, Inc.
Submitted: February 14, 2020
The Sigma Group, Inc.
1300 West Canal Street
Milwaukee, WI 53233
414.643.4200 www.thesigmagroup.com
TABLE OF CONTENTS
FIRM BACKGROUND
PROJECT TEAM
RELEVANT EXPERIENCE
RESUMES
INSURANCE
FORMS
Form A: Signature Affidavit Form B: Receipt of Forms and Submittal Checklist Form C: Vendor Profile Form E: References
ADDENDUM 1
FIRM BACKGROUND
Serving the public and private sectors since 1991, Sigma assists clients by managing the planning, project delivery, and costs for land development, redevelopment and infrastructure improvements as well as navigating the myriad of environmental, health and safety regulations. Sigma’s Wisconsin-based staff of 70 includes registered Professional Engineers in the civil, environmental, and chemical disciplines; Professional Land Surveyors;
Construction Inspectors; certified asbestos and lead supervisors/inspectors; Certified Hazardous Materials Managers, Professional Geologists, and Professional Hydrogeologists, as well as engineering technicians, inspectors, scientists and compliance specialists.
In 2003, Sigma redeveloped a brownfield site as its headquarters in Milwaukee’s Menomonee River Valley. Our building and site showcase many examples of our consulting expertise including sustainable building and land practices, brownfield remediation, habitat restoration, stormwater management, and facilities services.
Sigma focuses on creating functional, innovative solutions that optimize results for the project, the client and the community that sensitively balance economics and the protection of natural resources.
Our diverse range of services, expertise and can-do attitude enable our clients to achieve a successful balance between today’s challenges and the long-term need to preserve important resources.
Professional Engineers
Professional Geologists/Hydrogeologists
Professional Surveyors & Technicians
Certified UAS Remote Pilots
TECHNICAL & FIELD EXPERTISE | Sigma Staff
Civil, environmental, chemical, and mechanical engineers
Geologists, hydrogeologists, and scientists Professional land surveyors Certified hazmat inspectors and supervisors Certified Hazardous Materials Managers Computer-based modeling specialists UAS pilots Construction and stormwater specialists
A SUSTAINABLE HISTORY | Brownfield Redevelopment
2015 Social Impact Award – The Valley Passage Brownfield Redevelopment
2009 Phoenix Award Winner – Menomonee Valley Brownfield Redevelopment
2006 Phoenix Award Winner – Sheboygan Harbor Brownfield Redevelopment
Sigma’s office is located on a former brownfield site
Several staff are LEED accredited Redevelopment projects in the urban setting Ecologically-minded restoration initiatives
ADVANCED TECHNOLOGY | Highly-skilled professionals
Computer-based modeling Aerial imaging/surveying 3-D laser scanning GIS services
AWARD WINNING | Driven by results
Top 20 Wisconsin Engineering Firms – Business Journal, 2019
5th Largest Milwaukee Area Environmental Consultants – Business Journal, 2018
Fi el d Se rv ic es
City of Madison Engineering
The Sigma Group, Inc.
Kristin Kurzka, P.E., P.G.
Senior Project Manager
Phase I
Dale Palkowski Phase I ESA Lead
Mairead Rauch, E.I.T Staff Engineer
Phase II & Remediation
Adam Roder, P.E., P.G.
Senior Engineer
Stephen Meer, P.E.
Senior Engineer
Mafizul Islam, P.E.
Senior Engineer
Andrea Lorenz Project Engineer
Tim Wimmer, P.G.
Senior Project Manager
Jacob Krause, P.G.
Project Engineer
Justin VanWieringen, P.E.
Project Engineer
Ed Pencak, G.I.T.
Staff Engineer
Chelsea Ames Staff Engineer
Tom McCoy Senior Technician
Su b
Co ns ul ta nt s
Seymour Environmental Services
Mark Fryman Hydrogeologist
Robyn Seymour President
CT Laboratories
Pace Analytical
PROJECT TEAM
The Sigma team combines the skills and abilities needed to perform the requested environmental consulting services in a timely and cost-effective manner. The project team is comprised of qualified professionals who possess a thorough understanding of environmental rules and regulations coupled with applied experience to move both simple and complex projects forward in a sensible manner.
Sigma is committed to bringing qualified partners to projects and has partnered with Seymour Environmental Services, a City of Madison certified Woman Business Enterprise (WBE); CT Laboratories a WI-certified WBE;
Pace Analytical; GESTRA Engineering, a City of Madison certified Minority Business Enterprise (MBE); and On- Site Engineering, a City of Madison certified WBE, based on their demonstrated professionalism, responsiveness, and efficiency. Sigma has strong working relationships with each of these sub consultants primarily through our contracts with various municipalities and governmental entities.
Sigma is committed to forming affirmative partnerships with qualifying disadvantaged business enterprises.
We consistently meet and exceeded participation requirements for past and current standing contracts.
Resumes for all Project Team members are attached in the Resume section, starting on p. 19 of this submittal.
Other qualified staff, as appropriate
GESTRA Engineering
On-Site Env. Services
Subcontractor Team Members
Seymour Environmental Services (WBE) 2531 Dyreson Rd., McFarland, WI 53558
Robyn Seymour 608-838-9120 rseymour@chorus.net
Seymour Environmental Services, Inc. (Seymour) was established in 1996 and is a full-service environmental firm specializing in site-specific approaches to environmental issues. Seymour’s clients include industrial and commercial companies, government agencies and homeowners in Wisconsin, Illinois, and Iowa.
Seymour designs and implements cost effective solutions to achieve environmental compliance and site closure.
Seymour is 100% owned and operated by Robyn Seymour. As a woman-owned small business, Seymour is also eligible to participate in state disadvantaged DBE programs that provide for equal opportunity for women- and minority-owned businesses seeking contracts for state government-funded projects (49 CFR 29). Seymour has been certified as a DBE by Wisconsin.
Areas of Expertise Leaking Underground Storage Tank
Investigation/Remediation Spill Response/Spill Prevention Planning and Compliance Dry Cleaning Site Cleanup Storm Water Pollution Planning and
Compliance Underground and Aboveground Storage
Tank Closure and Evaluation Site Assessments
Remedial Investigation Remedial Action Planning and
Implementation Transport and Fate Groundwater Modeling RCRA and CERCLA Investigations Solid Waste Management GIS Services Regulatory Compliance Ecological Services NEPA/WEPA support
CT Laboratories (WBE) 1230 Lange Ct., Baraboo, WI 53913
Dennis Linley 608-356-2760 dlinley@ctlaboratories.com
CT Laboratories LLC is a locally owned, WI‐certified WBE with 30 years’ experience providing analytical testing services in support of projects such as brownfields assessment, remediation, and monitoring efforts in Wisconsin and nationwide.
Area of Expertise QAPP-Approved Environmental Laboratory
Pace Analytical Minneapolis 1700 Elm St. SE Suite 200, Minneapolis, MN, 55414 Kristen Hogberg 612.607.6407 Krisen.hogberg@pacelabs.com
Pace Analytical Green Bay 1241 Bellevue St., Suite 9, Green Bay, WI 54302 Laurie Woelfel 920.321.9404
Pace delivers the highest standard of testing and scientific services in the market; offering the most advanced solutions in the industry, backed by truly transparent data, a highly trained team, and the service and support that comes from four decades of experience. Pace has a national network of 32 environmental laboratories, four life service labs, two scientific professional services locations, and 48 service centers.
Areas of Expertise QAPP-Approved Environmental Laboratory Vapor Sample Analysis
Gestra Engineering, Inc. (MBE) 2223 Industrial Drive, Monona, WI 53713
Contact: Douglas Dettmers, P.E.
Phone: 414-933-7444 (ext 13) E-mail: douglas.dettmers@gestrainc.com
Gestra Engineering, Inc. is a Madison and Milwaukee based consulting firm specializing in geotechnical, civil and construction materials engineering, laboratory testing and geotechnical/environmental drilling. Gestra was founded in 2000 to provide Government Agencies, Municipalities, Engineers, Architects, and Contractors with high quality and cost-efficient engineering services. Our projects range in size and complexity from large infrastructure development projects to small challenging assignments. Gestra’s most recent award was the Wisconsin Department of Transportation’s (WisDOT) “Secretary’s Golden Shovel Award” in 2015.
Areas of Expertise Geotechnical Engineering Environmental Drilling Material Testing
On-site Environmental Services (WBE) PO Box 280, Sun Prairie, WI 53590
Contact: Kim Kapugi Phone: 608-837-8992 E-mail: onsiteenv@gmail.com
On-site Environmental Services, Inc. is a certified woman-owned business with Wisconsin Department of Administration, City of Madison, Dane County, and Milwaukee Metropolitan Sewage District. On-site Environmental Services is a small business operating three Geoprobe units, specializing in direct push soil and groundwater sampling and monitoring well installation since 1993.
Areas of Expertise Direct Push and Dual Tube soil and groundwater sampling Permanent and temporary small diameter well installation NR141 2” monitoring well and piezometer installation Soil gas sampling Injections for site remediation activities PFAS Sampling Protocol
Project Team Key Personnel
Kristin Kurzka, P.E., P.G.
Senior Project Manager 25+ years of experience
Ms. Kurzka will serve as the primary point of contact. Kristin has personal drive, technical skills, and a comprehensive understanding of Phase I, Phase II, site investigations, and remedial action planning of contaminated sites. Kristin has been the project manager for several USEPA Site Assessment projects including: the current WDNR WAM program, the USEPA Menomonee Valley Brownfield Pilot Project; the Menomonee Valley Business Center (former Milwaukee Road/CMC Shops); City of Racine EPA-funded Petroleum Site Assessment Grant program and several site-specific USEPA Assessment and Cleanup Fund projects. A former WDNR Southcentral staffer, Kristin is well respected by the regulatory agencies as she seeks to build consensus in developing reasonable approaches and cost-effective solutions to challenging issues.
Areas of Expertise Environmental Assessment Brownfield Redevelopment Soil/Groundwater Investigations Grant Writing/Procurement Demolition Planning
Education M.S. in Environmental Engineering, Milwaukee School of
Engineering, 1998 B.S. in Geological Engineering, University of Wisconsin-
Madison, 1994 B.S. in Geology, University of Wisconsin-Madison, 1994 OSHA 40-Hour Health & Safety Training
Professional Recognition Professional Engineer, WI E-34222-006 Professional Geologist/Hydrogeologist, WI 1367 - 13
Contact Information:
kkurzka@thesigmagroup.com 414.643.4127
Adam Roder, P.G., P.E.
Senior Project Manager/Engineer Phase II Environmental Site Assessment Lead 20+ years of experience
Mr. Roder is a Senior Project Manager/Engineer responsible for designing and implementing subsurface investigations, interpreting soil and groundwater data, designing, and implementing remediation strategies, performing computer analyses, completing reports for clients and regulatory agencies, and managing projects.
Areas of Expertise Soil/Groundwater / Vapor Investigations &
Remediation Brownfield Redevelopment Voluntary Party Liability Exemption (VPLE) Program Methane / Vapor Intrusion Evaluation & Mitigation
Education B.S. in Geological Engineering, University of
Wisconsin-Madison, 1997 B.S. in Geology, University of Wisconsin-Madison, “The Remediation Course” by Princeton
Groundwater, Inc., October 2005 OSHA 40-Hour Health & Safety Training
Professional Recognition Professional Engineer, Wisconsin No. E-35739 Professional Engineer, Illinois No. 062-058177 Professional Geologist / Hydrogeologist, WI 1369-13
Contact Information:
aroder@thesigmagroup.com 414.643.4134
Dale Palkowski Project Scientist Phase I Environmental Site Assessment Lead 25+ years of experience
Mr. Palkowski is a Project Scientist managing Phase I ESAs. He has completed thousands of Phase I ESAs and has a thorough and knowledgeable understanding of historic and current industrial processes. Dale has over 25 years of experience in environmental consulting.
Areas of Expertise Phase I Environmental Site Assessments
Education B.S., Business Administration, Marquette Univ., Professional Recognition Site Assessor, WI No. 00560
Contact Information:
dpalkowski@thesigmagroup.com 414.643.4149
Mairead Rauch, E.I.T.
Staff Engineer 4 years
Mairead conducts Phase I Environmental Site Assessments, reviews historical records, and environmental database information to evaluate environmental conditions. Mairead has conducted Phase I work for a variety of clients and has specific knowledge in regard to completing investigation work near water bodies.
Areas of Expertise Phase I Environmental Site Assessments Historic Records Screening Environmental Impact Assessment Environmental Compliance
Education B.S. Environmental Resources and Forest Engineering, Minor in Urban Environmental Science – SUNY College of Environmental Science and Forestry, May
M.S. Civil Engineering, Environmental Engineering specialty – Marquette University, December 2017
Contact Information:
mracuch@thesigmagroup.com 414.643.4122
Mafizul Islam, P.E.
Senior Engineer Remediation Activities Lead 30+ years of experience
Mafizul is a Senior Engineer with over 30 years of experience in remedial investigation and feasibility studies, evaluation and design of remedial action measures, closed landfill development, and construction management services during remedial action and brownfield site development activities. His expertise includes landfill remediation, hazardous waste treatment, flow system modeling and predicting contaminant movement, designing vapor extraction and groundwater pumping systems, determination of hydraulic parameters by field, laboratory and analytical methods, bioremediation of recalcitrant organic compounds, data acquisition systems, telemetry, CAD and computer simulations.
Areas of Expertise Remedial Investigations & Feasibility Studies Subsurface Flow & Contaminant Transport
Modeling Remediation of Petroleum, Chlorinated Solvent &
Metal Impacted Sites Brownfield Redevelopment Voluntary Party Liability Exemption Program Evaluation of Subsurface Vapor Migration Vapor / Methane Control System Design &
Operation Landfill Remediation & Redevelopment Enhanced Bioremediation & In Situ Treatment
Technologies Bio-augmentation & Chemical Oxidation
Education B.S. in Civil Engineering, Bangladesh University of Engineering & Technology, Dhaka, Bangladesh, 1981
M.S. in Civil Engineering, Clemson University, Clemson, South Carolina, 1985
“The Remediation Course” by Princeton Groundwater, Inc., March 2005
Illinois EPA “Tiered Approach to Corrective Action Objectives” Training, September 1997
Professional Recognition Professional Engineer, Wisconsin No. 25891 Professional Engineer, Michigan No. 48246
Contact Information:
mislam@thesigmagroup.com 414.643.4149
Stephen Meer, P.E.
15+ years of experience
Mr. Meer provides environmental engineering services for a variety of municipal, commercial, and industrial clients. His experience includes managing environmental site assessments, field investigations, remediation projects and developing remedial and closure strategies for sites. Stephen is responsible for managing individual projects from initial investigation through regulatory case closure and developing cost-effective strategies for managing risks associated with redevelopment of brownfield sites.
Areas of Expertise Geosynthetic Clay Liners Methane Abatement System Installation Soil/Groundwater Investigations Vapor Intrusion Investigation/Mitigation Wetland Restoration Radon Remediation System Design and Installation
Education M.S. in Geological Engineering, UW-Madison, 2003 B.S. in Agricultural Engineering, UW-Madison, 2001
Professional Recognition Professional Engineer, Wisconsin No. E-39390
OSHA HAZWOPER (29 CFR 1910.120)
AARST-NRPP Certified Residential Radon Measurement and Mitigation Provider, Multifamily Measurement Certification smeer@thesigmagroup.com 414.643.4124
Robyn Seymour, P.G.
President 25+ years of experience
Ms. Seymour has over 28 years of experience in the environmental field. She has successfully managed the investigation and remediation of many contaminated sites from initial site assessment to site closure. Her projects include UST sites, dry cleaners and manufacturing facilities. She is thoroughly familiar with the Wisconsin Department of Natural Resources requirements for conducting environmental work under the PECFA program.
Education B.S. Geology, University of Wisconsin, Madison OSHA 40-Hour Health and Safety Certification
Professional Recognition State of Wisconsin Professional Geologist (G-1060) Certified Hydrogeologist, Wisconsin State of Wisconsin Certified Site Assessor and PECFA Consultant (41580) Contact Information:
rseymour@chorus.net 608-838-9120
Mark Fryman Hydrogeologist 30+ years of experience
Mr. Fryman has over 30 years of experience in the management of environmental projects including underground storage tank sites, manufacturing facilities, residential and commercial properties for both public sector clients such as the DOD, EPA, WDNR, and private sector clients such as banks, dry cleaners, gasoline stations, and utility companies. His responsibilities include project management, quality assurance review, scheduling, and budgeting. His capabilities include soil and groundwater investigations, groundwater and surface water modeling, remediation alternatives analysis and design, and the development of site-specific cleanup standards under NR 720.
Education M.S. Geology, Kent State University B.S. Geology, Kent State University
Professional Recognition Certified Hydrogeologist, Wisconsin State of Wisconsin Certified PECFA Consultant OSHA 40-Hour Health and Safety Certification National Ground Water Association, Wisconsin Ground Water Association mfryman@chorus.net
RELEVANT EXPERIENCE
Sigma currently has master services agreements and on-call contracts for environmental consulting services with the City of Milwaukee, the Milwaukee Metropolitan Sewerage District (MMSD), the Wisconsin Department of Natural Resources (WDNR), Milwaukee County, Walworth County, and Waukesha County. As example, Sigma has been serving the City of Milwaukee as the environmental/civil engineering consultant since 1993 assisting with the revitalization of the Menomonee River Valley, the 30th Street Corridor, the Harbor District, Walker’s Point, and the redevelopment of Century City (the former Tower Automotive site) as well as many smaller targeted sites being positioned for redevelopment. Sigma is one of three firms currently contracted with the WDNR to provide environmental consulting services within the Wisconsin Assessment Monies (WAM) program to address brownfields sites where closed or closing industrial plants are acting as impediments to economic redevelopment.
To demonstrate Sigma’s capabilities, experience, and qualifications to provide Phase I, Phase II, and remediation services our proposal features highlighted projects conducted under master service agreements with the following entities:
RELEVANT EXPERIENCE & REFERENCES
Client reference information is provided below. Complete reference information is provided in the attached
Form E.
City of Milwaukee Dave Misky
Assistant Executive Director Redevelopment Authority
David.misky@milwaukee.gov 414.286.8682
Milwaukee County
Stevan Keith, P.E.
Environmental Services Unit Leader
Milwaukee County DAS/AE&ES
Stevan.Keith@milwaukeecountywi.gov 414.278.4355
Wisconsin WDNR/City of Janesville Nancy McDonald
Economic Development Coordinator City of Janesville mcdonaldna@ci.janesville.wi.us 608.755.3180
Madison Private Development
Opus Development Margaret Knowlton
Margaret.knowlton@opus-group.com
Campbell Capital Group Michael Campbell
678.485.3672
Waukesha County Steven Todd, R.S.
Department of Parks & Land Use stodd@waukeshacounty.gov 262.896.8300
Walworth County Joe Kroll, P.E.
County Engineer Department of Public Works jkroll@co.walworth.wi.us 262.741.3441 mailto:David.misky@milwaukee.gov mailto:Stevan.Keith@milwaukeecountywi.gov mailto:mcdonaldna@ci.janesville.wi.us mailto:Margaret.knowlton@opus-group.com mailto:stodd@waukeshacounty.gov mailto:jkroll@co.walworth.wi.us
City of Milwaukee 1993-Present Master Services Agreement AAI Phase I ESAs AAI Phase II ESAs Remedial Action Planning Regulatory Interaction Grant Administration Stakeholder Interaction
Serving as the master services consultant during the past 26 years, Sigma has assisted the City with numerous projects funded through the USEPA’s Hazardous and Petroleum Site Assessment Brownfield Grant program, site-specific clean-up grants, and a site assessment pilot grant.
Sigma has worked with the City on simple projects, including historic service station assessments, to complex large-scale projects with multi-agency jurisdiction, complex grant and financing structures, and significant stakeholder participation.
Century City Brownfield Redevelopment 2006-Present
The Century City site, an approximately 85-acre parcel, was previously owned by A.O. Smith and Tower Automotive and operated as a sprawling automotive component manufacturing complex.
The site is located in the City’s 30th Street Corridor within a mixed residential and industrial setting.
Once an industrial hub with thousands of jobs filled by neighboring residents, the property has become a blight on the surrounding area and an example of the neglect plaguing the inner City. To address the immediate risks associated with the vacant and deteriorating property, the City acquired the parcel in 2006, developed a master plan, and has begun redeveloping the site into a modern and sustainable business park.
Sigma currently holds the Century City master contract for Architectural and Engineering services and has completed environmental site assessments, remedial action planning, and civil engineering services for topographic and utilities mapping, demolition planning, stormwater management master planning services.
Former Esser Paint 2008-Present
Esser Paint, an abandoned paint manufacturing and distribution facility with six buildings constructed between the late 1890s and 1931, located in Milwaukee’s 30th Street industrial corridor presented many redevelopment challenges.
The facility totaled 35,000 SF and was located on 1½ City blocks. Four buildings were positioned on a 20-foot high retaining wall immediately adjacent to an active railroad ravine. The site had 17 USTs in three tank farms and five above ground storage tanks within buildings and basements. Tanks contained residual paint manufacturing raw materials or products.
Prior to the City taking ownership Sigma assisted the City in estimating the level of risk associated with environmental investigation, closure, and future development. Sigma performed a Phase I ESA, several iterative phases of Phase II soil and groundwater investigations to evaluate subsurface conditions on and off-site and designed and implemented remedial action activities in cooperation with the WDNR.
Sigma also performed pre-demolition asbestos, lead-based paint, and hazardous materials inspections of the buildings. Sigma assisted the Milwaukee Department of City Development and the Department of Neighborhood Services with developing a demolition scope of work, specifications, bidding documents, bid review, and contractor selection. Sigma performed oversight during abatement and demolition to verify that the activities were being performed in accordance with the project specifications and applicable regulatory requirements.
The south parcel was converted into a community vegetable garden while the larger north property was redeveloped as a low-income housing complex.
USEPA – Funded Brownfield Pilot Project and the City of Milwaukee Menomonee River Valley Brownfield Redevelopment 1993-Present
The Menomonee River Valley is an area of land, approximately 1,500-acres (2.5 sq. miles), located just southwest of downtown Milwaukee. Beginning in the mid- to late- 1800’s, the natural course of the Menomonee River was channeled, and the adjacent Valley filled and developed. Historical land uses included light to heavy industry, coal yards, shipping channelization, stockyards, meat processing, tanning, coal gasification, warehousing, and mineral storage. At the center was the sprawling Milwaukee Road Shops properties that at one time employed over 10,000 workers for railroad manufacturing and maintenance.
Consequently, properties within the Menomonee River Valley were perceived as environmental liabilities. This negative perception was the result of the economic liability associated with the traditional regulatory policies, which required a site-by-site investigation/remediation strategy to address groundwater contamination.
The goals of the Brownfield Pilot Project were to define soils and groundwater quality in an area-wide “aqua-shed” approach and to dispel the negative perception of liabilities associated with potential redevelopment. The project outcome generated baseline environmental information that could be used to facilitate streamlined appropriate decisions for redevelopment within the Valley. The study accomplished this through the generation of the “Environmental Management Considerations for Site Redevelopment in Milwaukee’s Menomonee Valley” guidance document prepared by Sigma.
To establish the baseline approach for conducting subsurface investigation activities, Sigma performed extensive historical land use research and environmental site assessments that established the history of the properties and the surrounding area including a review of various regulatory and governmental databases and information sources.
Federal and state research data sources included:
RCRA- 2 TSDFs CERCLA- 8 sites Emergency Response Notification System
(ERNS)-8 sites WI Registered USTs-100 sites WI LUST-60 sites Emergency Response Program -40 sites WI solid waste/landfill- 1 site WI Spill List- 70 sites
Together, with the WDNR, USEPA, City of Milwaukee, the US Army Corp of Engineers, and private developers, Sigma has provided planning and technical services for the completion of comprehensive soil and groundwater quality investigations, remedial actions, land surveying, riverbank stabilization and site improvements over the full range of project sites in the Valley setting which has led to numerous brownfield redevelopments; Canal Street, Reed Street Yards, Harley-Davidson Museum, Miller Park, Sigma’s headquarters building, Three Bridges Park, and the Menomonee River Valley Riverwalk guidelines.
Milwaukee County 1998-Present Master Services Agreement Phase I ESAs Phase II ESAs Remedial Action Planning Regulatory Interaction
Warnimont Park 2013-Present
Former Manke Dump Site: A site inspection conducted by the WDNR in 2013 at the former Manke Dump area along the Lake Michigan bluff in Warnimont Park, identified non-compliance issues including erosion from runoff channels, inadequate diversion of stormwater run-on and the presence of exposed waste on the ground due to slope failure. The dump was the legacy of former military operations at the site. Sigma was engaged to field survey the area to capture existing conditions;
develop a plan for capping the waste mass, and to prepare a re‐grading plan for the area to control stormwater erosion and to restore the bluff with native grasses. Sigma also provided construction services.
Former Gun Range Site Closure: The County was named as the Responsible Party of hazardous substance discharge as a result of the lead shot and residual materials that were deposited during the operation of the Gun Club located as the northern part of the Park from 1932 until 2015. Areas impacted by the Gun Club’s activities include, the top and face of the bluff, the beach below, and near shore bottom of Lake Michigan.
Sigma conducted site investigations of the bluff which indicated levels of lead and PAHs in the soil greater than WDNR standards. Sigma is assisting the County and positioning the site for case closure by designing an engineered cap with native vegetation. Additionally, an offshore sediment investigation, requested by the WDNR, will be performed in the Spring of 2020.
Milwaukee Regional Medical Center (MRMC) 2015-Present
To allow for the expansion of services provided at the County owned MRMC complex and to prepare for the transfer of properties from the County to various MRMC entities including Froedtert Health, Children’s Wisconsin, and the Medical College of Wisconsin, infrastructure improvements were necessary to support the complex’s function and to keep pace with the healthcare industry. Sigma is assisting the County and MRMC entities with the following activities:
Phase I and II ESAs: Conducted Phase I and II ESAs of various parcels as part of land acquisition due diligence. Parcels included the former County power plant, a WisDOT parcel along I-41, large parking lots, and the man-made stormwater ponds.
87th Street Realignment Soil Management: Served as the environmental engineer for both the MRMC/Froedtert Health’s 87th Street realignment and Parking Structure construction. Sigma’s involvement included subsurface investigation activities to assess soil conditions in the proposed work areas and determinations of potential soil management options. Multiple areas of elevated PAH and lead concentrations were discovered in the fill; requiring soil management protocols during construction under Ch. NR 718 regulations.
Over 2,500-CY of PAH and lead-impacted soil received WDNR pre-approval to be reused on-site.
Up to 8,000-CY of impacted soil encountered during the 87th Street reconstruction that was hauled to a licensed landfill for use as alternative daily cover.
Sigma’s coordination with County and facility representatives was key in minimizing disruptions to traffic flow and parking availability and to ensure existing utilities are not damaged and hospital services were not interrupted.
Milwaukee County Potential Acquisition of Former Distribution Center
Given the upcoming highway reconfiguration project, Milwaukee County was evaluating several parcels to house relocated County operations.
Sigma was retained to conduct a Phase I ESA on an 11-acre property in Wauwatosa. The Phase I ESA revealed RECs including the historic use of the property as a gravel pit and associated filling, former underground storage tanks, and a former landfill immediately adjacent to the property in connection with the property. Sigma is currently in the process of completing a Phase II ESA with soil and groundwater testing which will further evaluate the identified RECs.
Wisconsin Department of Natural Resources (WDNR)/City of Janesville
Master Services Agreement Phase I ESAs Phase II ESAs Regulatory Interaction
Wisconsin Assessment Monies Program 2010-Present
Sigma was selected by the WDNR to provide environmental assessment services as part of their efforts to expedite cleanup and revitalization of closed industrial and commercial facilities. The WDNR requested AAI Phase I ESAs, to evaluate property history to identify potential historic releases. Phase I ESAs information was invaluable in maximizing funding monies while preparing a scope of work for Phase II activities.
To date, Sigma has completed Phase I ESAs of over 24 neglected or underutilized industrial and commercial facilities. The RECs identified at each of the properties were recommended for further assessment through Phase II investigation, redevelopment plans, and to leverage for additional redevelopment funding.
As examples, Sigma has conducted AAI Phase I ESAs for a powder coating facility looking to expand business within Racine; a former pre-cast concrete panel and block manufacturing facility located in Pewaukee; a former brewery and cheese manufacturer proposed for historic designation and renovation by private parties as a World Cheese Discovery Center; a former metal and electronic component manufacturer in St. Francis; a former bulk petroleum recycler/storage facility and former bulk oil/gasoline distributor in Two Rivers; a former foundry in Schofield; and a former shoe factory in Edgerton.
Phase II ESA activities included a commercial laundry in Racine and; multiple 30th Street corridor industries in Milwaukee.
City of Janesville 2019-Present Sigma supported the City of Janesville’s redevelopment Reflection Plaza project plans by conducting AAI Phase I and Phase II ESAs of nine areas along the Rock River. The work was funded by the WDNR WAM program with strong leadership by the City of Janesville. The project involved both public and private property ownership being coordinated by the City.
Project areas consisted of parcels ranging from 0.4-
2.0 acres and included a variety of historic land uses including:
Hardware warehouse Harness factory Auto dealer Paint store Wholesale and retail stores Machine shop Coreset manufacturer Contractor shop Pencil manufacturer Awning manufacturer Auto repair Cold storage Photography shop Junkyard Gas stations
The Phase II activities included both soil quality assessments and groundwater quality assessments using Sigma’s Geoprobe soil boring equipment conducted in accordance with WDNR NR141, NR700, and following procedures defined by the program QAPP.
Waukesha County 2002-Present Master Services Agreement Phase I ESAs Phase II ESAs Regulatory Interaction
Sigma has been providing ongoing environmental consulting under both the Asbestos and Indoor Air Quality Consulting Services and Environmental Consulting Services master services agreements with the County for over 15 years. Services include due diligence, pre-demolition hazardous materials inspections, subsurface investigation, monitoring, regulatory reporting, site/civil/construction engineering for the highway department, roadway improvement, and redevelopment projects.
Phase I /II Environmental Site Assessments 2002-Present Sigma conducted multiple AAI Phase I WisDOT Hazardous Materials Assessments and Phase II environmental site assessments for acquisition of properties for urban redevelopment, roadway, and parkland improvement projects.
Wanaki Golf Course, Menomonee Falls:
Conducted AAI Phase I and II in advance of facility improvements where land disturbing activities were likely to occur. The Phase I identified an abandoned septic system and former UST’s as Recognized Environmental Conditions (RECs).
Sigma is currently performing the Phase II activities to determine if there were residual impacts at the maintenance operations.
Merrill Hills Road Improvements, Waukesha: As part of the County and WDOT’s road widening project, Sigma conduct a hazardous materials assessment in accordance with WisDOT FDM 21- 35-5 and Phase II subsurface investigation to address a leaking fuel oil UST that required removal to accommodate and new buried utility corridor.
The UST removal was coordinated by Sigma were impacted soils were encountered. A limited investigation was then performed to define the impacts which resulted in the WDNR granting a No Further Action based on results.
Highway Department Salt Storage Sigma was retained to improve the management of run-off and wash water for Highway Department salt storage facilities throughout the County. The work consisted of subsurface investigation of chlorides in groundwater, remediation, and site design, bidding, and construction management of upgrades to five County salt storage facilities including New Berlin, Sussex, Nashotah, Highway Operations Center, and North Prairie. Upgrades primarily consisted of reconstructing the drainage area, for brine collection, at the salt dome apron areas and removal and replacement of underground brine tanks and installation of high-level alarms.
Activities at the New Berlin substation included the completion of a NR716 compliant site investigation of the run-off from truck wash bay and salt storage operations. Investigation activities included advancement of soil borings and installation of monitoring wells to characterize total chloride impacts. Subsequent groundwater monitoring activities were performed to demonstrate concentrations and migration of impacts had stabilized as a result of the implemented site improvement.
Walworth County 2010-Present Phase II ESAs Storage Tank Removal Site Investigation Remedial Action Planning Regulatory Interaction
Sigma provides on-call environmental services to the County for tank management, investigation, pre-demolition and remediation related to park, roadway, and County facility improvements.
Leaking Underground Storage Tank Closure 2010-2019 Sigma conducted investigation activities for a leaking underground storage tank (LUST) removed in 1992 and a supply line release in 1997 at the County boiler house. In response to the releases, information collected by Sigma during the completion of an NR 716 Site Investigation identified low level contaminated soil and groundwater at the site. Based on Sigma’s findings, the WDNR issued site closure upon the completion of soil boring and groundwater monitoring activities for the LUST in 2014 and the supply line release in 2019 (with continuing obligations).
White River Park House Demolition/Tank Removal 2013-2014 As part of establishing a new County park, Sigma performed pre-demolition inspection (asbestos, lead-based paint, and hazardous materials inventory) of a two-story wood frame structure.
Sigma also managed the removal of two 300-gallon fuel storage UST’s conducting a tank system site assessment (TSSA), tank cleaning/removal, and tank waste disposal. Based on low-level fuel oil impacts detected in soil, Sigma negotiated “No Action Required” (NAR) with the WDNR.
County Highway NN Reconstruction 2015-2019 During highway reconstruction initiated in 2015, within CTH-NN right-of-way, soil with a petroleum odor were encountered, during earth moving activities in a roadway segment adjacent to the Aurora Lakeland Medical Clinic property. The County engaged Sigma to provide environmental oversight, investigation, and case closure in accordance with WDNR NR 700 regulations.
The excavated impacted soils were stockpiled, and composite samples revealed the presence of naphthalene and other petroleum constituents that exceeded standards. In response to the impacts, a Phase II ESA was conducted using Sigma’s Geoprobe soil boring equipment to evaluate the decree and extend of impacts for the approximate 0.5-mile roadway and to develop a plan for appropriate soil management. A soil management plan, incorporating landfill disposal and reuse of segregated low-level impacted soil beneath a proposed adjacent recreational trail, was approved by the WDNR.
Construction of an approximate 0.5 mile continued with Sigma field oversight to manage impacted material segregation, stockpiling, while assisting with the transport and disposal to a licensed landfill and the recreational trail area.
The WDNR issued site closure upon completion of the construction project and submittal of soil management documentation.
Madison Private Development Opus Development – Varsity Quarters
Sigma provided full-service environmental services for the redevelopment of the former Stadium View Bar & Eatery. The development transformed a high-traffic, underutilized, aging, and highly visible commercial corner, into a destination. The mixed-use corner redevelopment includes a first floor 7,500 SF KwikTrip below 6 stories of residential housing.
Sigma assisted the developer, beginning with a Phase I ESA; Phase II ESA; pre-demolition asbestos, lead-based paint, and hazardous materials inspections; and subsequent abatement and demolition specifications.
After the Site Investigation Report and Remedial Action Plan were approved by the WNDR’s VPLE committee, Sigma’s services continued throughout the soil, groundwater, and soil vapor remediation and site redevelopment work, which included underground storage tank removal and closure actions, disposal of a discovered buried drum, contaminated soil excavation and landfill disposal, installation of a passive subslab vapor venting system, groundwater monitoring, construction of engineered barriers, and post-construction verification testing of the subslab vapor venting system. The WDNR VPLE committee granted final case closure / Certificate of Completion in 2015.
Campbell Capital Group – The Marling
Sigma was retained to assist with pre-purchase due diligence activities, followed by environmental consulting services prior to and during the construction of The Marling development. Sigma worked closely with the developer to satisfy debt and equity partners and obtain regulatory concurrence working through the WDNR’s strict VPLE Program in order to facilitate redevelopment of the run-down lumberyard into an industrial-flare mixed-development.
Sigma’s pre-purchase due diligence work included completing an AAI Phase I Environmental Site Assessment; a review of existing hazardous building material assessments and associated recommendations related to further assessment and pre-demolition inspection. Sigma subsequently completed site investigation activities to further evaluate soil and groundwater conditions; prepared a WDNR Exemption to Build on a Historic Fill Site; prepared of a Soil Management Plan and performed soil management oversight during earthworks and construction; a vapor evaluation; and activities to obtaining regulatory closure via the VPLE Program in April of 2018.
The Marling development was recently recognized in the Daily Reporter 2018 Top Projects.
RESUMES
Kristin Kurzka, P.E, P.G.
Professional Profile Kristin is a Senior Engineer with responsibilities ranging from the oversight and direction of subsurface investigation and remediation for various brownfield redevelopment projects to assisting clients in securing public sector funding. She has over 25 years of regulatory and consulting experience having worked for the Wisconsin Department of Natural Resources (WDNR) South Central prior to joining The Sigma Group.
Areas of Expertise Environmental Assessment Brownfield Redevelopment Soil/Groundwater Investigations & Remediation Grant Writing/Procurement Demolition Planning Registrations / Certification Professional Engineer, WI E-34222-006 Professional Geologist/Hydrogeologist, WI 1367 - 13
Education / Training M.S. in Environmental Engineering, Milwaukee
School of Engineering, 1998 B.S. in Geological Engineering, University of
Wisconsin-Madison, 1994 B.S. in Geology, University of Wisconsin-Madison, OSHA 40-Hour Health & Safety Training
Representative Experience Wisconsin Plant Recovery Initiative – Wisconsin Department of Natural Resources Project Manager for the WDNR WAM program. Responsible for coordinating Phase I and Phase II activities for several diverse industrial/manufacturing, petroleum, commercial and residential land uses across central, southern and southeastern Wisconsin communities such as Janesville, Burlington, Edgerton, Milwaukee, and Racine. Responsible for completing activities in compliance with EPA funding guidelines and approved Quality Assurance Project Plan.
EPA Petroleum and Hazardous Assessment Fund Programs - City of Milwaukee Project Manager for City of Milwaukee properties participating within the EPA Funded Petroleum and Hazardous Assessment Fund programs. Responsible for assisting the City with completion of Phase I Hazardous Materials Assessment (HMA), Phase II HMA and Remedial Options development. Completed all relevant EPA correspondence and compliance of all activities within the constraints of the grant program. Participated in Community outreach and awareness as technical advisor. Oversaw the development of the Quality Assurance Project Plan for the program.
Brownfield Redevelopment - City of Milwaukee Century City Project Manager for the City of Milwaukee Century City demolition and redevelopment planning. Responsible for coordinating hazardous material assessments, demolition, stormwater planning and the evaluation of a master plan for the proposed industrial park including concept, feasibility assessment and cost analysis. Also provide support with negotiations with the local POTW, as well as preparation of grant and funding assistance applications.
St. Louis and Superior Bay Waterfront Historic Records Screening-WDNR, Superior, Wisconsin Project Manager leading the effort to identify priority properties which have historically contributed to contaminated sediments within the St. Louis Bay and Lake Superior Bay waterfronts. The activities included a comprehensive historic records screening for a two square mile area comprising of over 200 parcels along the heavily industrialized. The records screening resulted in the identification of priority key parcels for which further assessment is to be conducted.
Brownfield Redevelopment – Menomonee Valley Industrial Center, Milwaukee, Wisconsin Project Manager for a City of Milwaukee due diligence investigation, remediation, geotechnical assessment and preparation, and stormwater management of the 100-acre former Milwaukee Road rail yard located in the Menomonee Valley. Project responsibilities included research and review of site history, investigation strategy development, coordination of field activities, data evaluation, remedial alternative consideration and implementation, geotechnical assessment coordination, stormwater plan development and implementation and construction management.
Closed Landfill Redevelopment – Ballpark Commons, Franklin, Wisconsin Project Manager for the engineering and design for the redesign of a methane control system and landfill cap relative to a proposed multi-use commercial and recreational facility on and immediately adjacent to a closed non-engineered landfill.
Representative for the developer, responsible for coordination with the design team and regulatory agency to obtain approval for the first extensive development on a closed landfill with the State of Wisconsin.
MMSD Kinnickinnic River Flood Management Project, Milwaukee, Wisconsin Project manager for the Phase I environmental assessments of 84 residential and commercial properties along the Kinnickinnic River for purposes of acquisition and deconstruction as part of the MMSD Flood Management project. The information obtained through the assessment activities was used to identify potential environmental risks for purposes of negating property acquisition and future material management considerations. Participated in Community Involvement sessions during MMSD outreach.
Adam J. Roder, P.E., P.G.
Professional Profile Adam is a Senior Engineer responsible for managing all aspects of environmental brownfield redevelopment projects: designing and implementing subsurface investigations; interpreting soil, groundwater, and soil vapor data;
designing and implementing remediation strategies; performing computer analyses; and completing reports for clients and regulatory agencies. He has over 21 years of experience as a geological engineer.
Areas of Expertise Soil / Groundwater / Vapor Investigations & Remediation Brownfield Redevelopment Voluntary Party Liability Exemption (VPLE) Program Methane / Vapor Intrusion Evaluation & Mitigation
Registrations / Certification Professional Engineer, Wisconsin No. E-35739 Professional Engineer, Illinois No. 062-058177 Professional Geologist, WI 1369-13 NR 712 Hydrogeologist
Education / Training B.S. in Geological Engineering, University of Wisconsin-
Madison, 1997 B.S. in Geology, University of Wisconsin-Madison, 1997 “The Remediation Course” by Princeton Groundwater, Inc., October 2005 OSHA 40-Hour Health & Safety Training
Presentations Sheboygan South Pier Redevelopment Project, presented at Wisconsin Ground Water Association annual meeting, February 2007
Case Study: Sheboygan South Pier Redevelopment Project, presented at Brownfields 2006 National Conference, November 2006
Representative Experience 30th Street Industrial Corridor, Milwaukee Project Manager for over a dozen Phase I ESAs and Phase II ESAs/site investigations at multiple parcels along N.
31st Street between W. Galena Street and W. Walnut Street. Site investigations included a geophysical assessment, installation of soil borings and monitoring wells, and analysis of soil and groundwater samples. Soil and groundwater data used to evaluate individual sites and overall neighborhood from an “area-wide” perspective to assess geologic conditions, site investigation/remedial strategies, and potential risks. At one parcel, active remediation via organic substrate infiltration was conducted over two years to reduce the chlorinated solvent mass through anaerobic biodegradation, followed by post-remediation groundwater sampling. In 2018, managed the environmental aspects of four contiguous parcels redeveloped as a community playground/park, which included on-site NR 718 soil management and capping the land with engineered barriers.
Stitchweld Apartments / Vim and Vigor Apartments, Milwaukee Project Manager for Phase I ESAs, site investigation, remedial action planning and implementation, and WDNR reporting and communications for both projects. The Stitchweld project involved the redevelopment of an approximately 6-acre industrial property in the Bayview neighborhood into a $40 million apartment complex with approximately 300 units. Environmental remediation work (source area excavations, NR 718 soil management, vapor mitigation, and engineered barriers) was dovetailed with the site redevelopment between 2016 and 2018, and WDNR closure was obtained in 2019. The Vim and Vigor project involves the redevelopment of two parcels (approximately 0.75 acres and 2.5 acres) in the former Pabst Brewery complex into $40 million apartment/mixed-use buildings with approximately 275 units.