This is a Cost Proposal Form (Form D) submitted by RPS Group, Incorporated in response to RFP #8914-0-2020-BG for Environmental Consulting Services issued by the City of Madison, Wisconsin. The RFP seeks proposals from qualified environmental consulting firms to provide environmental site assessment services on an as-needed basis for land owned or being considered for purchase by the City, as well as for right-of-way construction activities. The cost proposal includes four example scenarios: Phase 1 Environmental Site Assessment (ESA) for a 10,000 square foot former industrial facility; WisDOT Hazardous Material Assessment for a 0.25-mile stretch of county highway; Phase 2 ESA involving seven borings to 10 feet below ground surface, three borings to 15 feet, installation of three groundwater monitoring wells, two rounds of groundwater sampling for volatile organic compounds (VOCs), RCRA metals and polycyclic aromatic hydrocarbons (PAHs), soil sampling analysis, well and boring abandonment, and report preparation; and right-of-way construction oversight for two weeks requiring onsite screening of soils for contamination during utility excavation. The proposal was submitted on February 13, 2020.
RPS Group's pricing for the four example scenarios totals $15,579 for personnel costs alone and $28,330 when including subcontractor costs. The firm provided detailed hourly rate schedules for personnel ranging from $63 for Administrative Assistant positions to $195 for senior leadership roles including Vice President, Senior Vice President, and President positions. Equipment rates include daily charges for specialized field instruments such as photoionization detectors ($100/day), water quality meters ($150/day), and ground penetrating radar ($600/day). Subcontractor rates include drilling services ($2,200-$3,000 per day depending on scope), ground penetrating radar ($600/day), and laboratory analysis rates for various sample types ranging from $60 to $250 per sample. As an umbrella contract, pricing is subject to negotiation and any increases or additions must be agreed upon in writing by both parties prior to project commencement.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
rpsgroup.com
REQUEST FOR PROPOSALS
CITY OF MADISON
RFP #: 8914-0-2020-BG
Title: Environmental Consulting Services Cost Proposal
RFP # 8914-0-2020-BG
Environmental Consulting
Services RPS Group, Inc.
February 13, 2020
Rev. 07/28/2016-FormD-CostProposal.doc
Form D: Cost Proposal
RFP #: 8914-0-2020-BG Environmental Consulting Services
This form must be returned with your response.
Any pricing increases or additions must be agreed upon in writing by both parties.
Please provide costs for each of the example budgets below, if you prefer, you may submit this on a separate spreadsheet:
Number Example Staff Rates Hours
1. Phase 1 ESA for a 10,000 sq ft former industrial facility
2. WisDOT Hazardous Material Assessment for a 0.25-mile stretch of county highway at the edge of the City
3. Example Phase 2 ESA: Assume 7 borings to 10 feet bgs, 3 borings to 15 feet, installation/development of 3 groundwater wells in the deeper borings, 2 rounds of groundwater sampling for VOCs/RCRA metals/PAHs, collection and analysis of two soil samples per boring for RCRA metals/VOCs/PCBs, abandonment of borings/wells per NR 141, report preparation and submittal to DNR for review. Include all costs typically associated with a Phase 2 ESA, including laboratory costs, creating site maps, surveying, project oversight, coordination with the DNR project manager, etc.
Consultant I Director Manager II
Senior Consultant Manager II Senior Vice President
Senior Consultant (field) Senior Consultant (rpt.)
CAD Operator Manager II Senior Vice President Consultant I (abandon)
Ground Penetrating Radar Driller (2 days) Soil Samples (14 samples) Groundwater Samples (6 samples)
$ 600
$ 6,500 $ 3,800 $ 1,850
Rev. 07/28/2016-FormD-CostProposal.doc
4. Right of way construction oversight:
Assume a two-week project that requires an engineer or hydrogeologist is onsite for 6 hours a day, 5 days a week to screen soils for contamination associated with utility excavation in the right of way.
Costs should include a simple post-construction report with photos and a marked up map, as well as any associated project management.
GRAND TOTAL for examples 1-4 listed above (Rates x Hours):
Please provide an equipment rate sheet and hourly rate schedule by personnel in the space below, or on a separate spreadsheet:
COMPANY NAME
RPS Group, Incorporated
Senior Consultant (field) Senior Consultant (rpt) CAD Operator Manager II Senior Vice President
$ 15,579 (personnel only) $ 28,330 (with subcontractors)
EQUIPMENT RATE SHEET
The equipment rate sheet for RPS Group, Incorporated for the City of Madison Environmental Consulting
Services project is presented below.
Equipment Unit Unit Rate ($)
Photoionization Detector Day $ 100
Water Level Indicator Day $ 40
Peristaltic Pump Day $ 50
Water Quality Meter Day $ 150
Air Sampling Disposable Equipment Each $ 10
Disposable Gloves Day $ 10
Disposable Bags for Soil Screening Day $ 10
SUBCONTRACTOR RATE SHEET
The subcontractor rate sheet for RPS Group, Incorporated for the City of Madison Environmental Consulting
Services project is presented below.
Equipment Unit Unit Rate ($)
Drilling – soil borings only Day $ 2,200
Drilling – soil borings and up to 3 permanent monitoring wells
Day $ 3,000
Ground Penetrating Radar Day $ 600
VOC Samples (soil and groundwater) Each $ 80
PAH Samples (soil and groundwater) Each $ 80
PCB Samples (soil and groundwater) Each $ 60
RCRA Metals Samples (soil and groundwater)
Each $ 100
VOC Samples (sub-slab soil gas) Each $ 250
PERSONNEL RATE SHEET
The personnel rate sheet for RPS Group, Incorporated for the City of Madison Environmental Consulting
Services project is presented below.
Title Hourly Rate ($)
Administrative Assistant $ 63
CAD Operator $ 72
Consultant I $ 78
Consultant II $ 95
Consultant III $ 112
Senior Consultant $ 126
Principal Consultant $ 158
Manager II $ 168
Director $ 195
Vice President $ 195