About this file
This is a proposal submission document from Ayres Associates Inc. in response to RFP #8914-0-2020-BG issued by the City of Madison Engineering Division for environmental consulting services. The City seeks qualified environmental consulting firms to provide environmental site assessment services on an as-needed basis for properties owned or being considered for purchase by the City or within rights of way during construction activities. Rather than a specific scope of work, this umbrella contract will be task-ordered, with individual City departments defining the scope of services and requesting site-specific work plans and cost estimates with not-to-exceed dollar amounts prior to initiating on-site activities. Ayres submitted its proposal on February 12, 2020, and acknowledged receipt of two addenda issued on February 3 and February 12, 2020. The proposal includes completed required forms, qualifications documentation, technical experience, and references demonstrating the firm's environmental consulting capabilities across multiple project phases.
Ayres Associates Inc., a Wisconsin-based employee-owned firm with 60 years in business and approximately 300 employees across 11 offices in four states, proposes to provide services from its Madison office staffed by 41 environmental and redevelopment professionals. The firm's proposed team includes Ben Peotter, PE, as Project Director and QA/QC manager, and Keely Campbell, PG, as Project Manager, supported by hydrogeologists, geologists, and technicians with specialized expertise in Phase I and II environmental site assessments, remediation planning, brownfield redevelopment, and grant administration. Ayres identified Wisconsin-certified subcontractors including GESTRA Engineering (MBE-certified drilling services) and CT Laboratories (WBE-certified laboratory analysis), demonstrating commitment to minority and women-owned business participation. The proposal references five completed projects in Wisconsin municipalities including the Village of Waunakee, City of Prairie du Chien, and City of Marinette, with contract values ranging from $200,000 to $650,000. Professional liability insurance with claims-made coverage was provided with limits of $5,000,000 per claim and $10,000,000 aggregate as evidence of insurance capability.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
www.AyresAssociates.com
800.800.5191 | 5201 E. Terrace Drive, Suite 200 | Madison, WI 53718
February 14, 2020
City of Madison City-County Building, Room 407 210 Martin Luther King, Jr. Blvd Madison, WI 53703-3346
Re: Environmental Consulting Services | RFP # 8914-0-2020-BG
Dear Selection Committee Members:
Madison’s history and heritage captures the imagination of visionaries. Ayres is eager to have the opportunity to work with you to generate momentum to move the City’s environmental projects forward, in service of strengthening our community as a whole.
The broad and innovative thinking behind a successful environmental program requires a team that’s comfortable with an approach that considers more than just the project at hand. You need a partner who appreciates how Madison works and can dovetail the City’s broader needs with project initiatives to leverage widespread impacts. You need a partner who not only understands environmental science but also can think Beyond the Brownfield (or ERP site, or redevelopment candidate). Ayres is that partner!
Our experience managing environmental assessment and revitalization efforts nationwide means we know what it takes to transform a property from a liability into a pearl of the community. Our years of municipal experience here in the Midwest have given us firsthand knowledge of the development barriers communities face, while honing our abilities to help the City of Madison in removing those barriers. When we are done, you will have more than a box of project reports to review; your communities will also have building permits, development agreements, and site plans in front of them.
For us, thinking Beyond the Brownfield means we’re aligning project activities so they bolster broader initiatives.
We’re wired to think about your goals first so we can meet the City’s aspirations with the funding you have available. Ultimately, this means leveraging the funds to advance your overall program for success. We think you’ll agree that our holistic approach to environmental projects means that hiring Ayres is the choice that’s in the best interest of the City.
Our people make this possible. The Ayres approach brings you a team of experts in executing environmental studies, formulating cleanup strategies, and implementing remediation efforts as well as urban planning experts to help seamlessly link together your community development initiatives. We’ve marshaled an outstanding group of professionals who will help to ensure your ultimate vision as we implement environmental strategic initiatives in your community. Our revitalization experts, public engagement pros, and visionary planners will make sure our superior environmental scientists are framing their deliverables to anticipate and support investment in the community.
The Ayres team has the ability to help establish a solid planning future on which your vision for tomorrow can be built. While the following pages will undoubtedly demonstrate that Ayres can help you deliver on the technical science behind your environmental projects over the contract period, the primary driver of delivering a more thriving community tomorrow is what makes us stand out from the crowd. We’re creating a foundation for lasting change that will improve the City of Madison long beyond the last assessment and cleanup project.
We are confident that we can successfully provide all required services, and we are eager to expand our relationship with the City of Madison by working with you. Thank you for considering the Ayres team.
Sincerely, Ayres Associates Inc
Ben J. Peotter, PE Project Director / QA/QC 608.443.1206; PeotterB@AyresAssociates.com
Keely H. Campbell, PG Project Manager 608.443.1262; CampbellK@AyresAssociates.com
3AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON
Table of Contents
Introductory Letter....................................................................Page 1
Table of Contents..................................................................... Page 3
Tab 1: Required Forms
| Form A: Signature Affidavit............................................ Page 5 |
| Form B: Receipt of Forms and Submittal Checklist.... Page 7 |
| Form C: Vendor Profile Information...............................Page 9 |
| Form D: Cost Proposal........................................................... ** |
| Form E: References.......................................................... Page 11 |
Tab 2: Qualifications and Technical Experience
| Firm Background and Key Staff...................................Page 13 |
| Project Team.....................................................................Page 15 |
| Experience........................................................................Page 23 |
| References........................................................................Page 35 |
| Insurance.........................................................................Page 37 |
** Cost Proposal provided as separate document.
Page Intentionally left blank.
5AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISONRev. 07/28/2016-FormA-SignatureAffidavit.doc
Form A: Signature Affidavit
RFP #: 8914-0-2020-BG Environmental Consulting Services
This form must be returned with your response.
In signing Proposals, we certify that we have not, either directly or indirectly, entered into any agreement or participated in any collusion or otherwise take any action in restraint of free competition; that no attempt has been made to induce any other person or firm to submit or not to submit Proposals, that Proposals have been independently arrived at, without collusion with any other Proposers, competitor or potential competitor; that Proposals have not been knowingly disclosed prior to the opening of Proposals to any other Proposers or competitor; that the above statement is accurate under penalty of perjury.
The undersigned, submitting this Proposals, hereby agrees with all the terms, conditions, and specifications required by the City in this Request for Proposals, declares that the attached Proposals and pricing are in conformity therewith, and attests to the truthfulness of all submissions in response to this solicitation.
Proposers shall provide the information requested below. Include the legal name of the Proposers and signature of the person(s) legally authorized to bind the Proposers to a contract.
COMPANY NAME
SIGNATURE DATE
PRINT NAME OF PERSON SIGNING
Ayres Associates Inc
2/12/2020
Ben J. Peotter
Rev. 07/28/2016-FormA-SignatureAffidavit.doc
Form A: Signature Affidavit
RFP #: 8914-0-2020-BG Environmental Consulting Services
This form must be returned with your response.
In signing Proposals, we certify that we have not, either directly or indirectly, entered into any agreement or participated in any collusion or otherwise take any action in restraint of free competition; that no attempt has been made to induce any other person or firm to submit or not to submit Proposals, that Proposals have been independently arrived at, without collusion with any other Proposers, competitor or potential competitor; that Proposals have not been knowingly disclosed prior to the opening of Proposals to any other Proposers or competitor; that the above statement is accurate under penalty of perjury.
The undersigned, submitting this Proposals, hereby agrees with all the terms, conditions, and specifications required by the City in this Request for Proposals, declares that the attached Proposals and pricing are in conformity therewith, and attests to the truthfulness of all submissions in response to this solicitation.
Proposers shall provide the information requested below. Include the legal name of the Proposers and signature of the person(s) legally authorized to bind the Proposers to a contract.
COMPANY NAME
SIGNATURE DATE
PRINT NAME OF PERSON SIGNING
Ayres Associates Inc
2/12/2020
Ben J. Peotter
AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON 7
Ingenuity, Integrity, and Intelligence.
Rev. 07/28/2016-FormB-Receipt.doc
Form B: Receipt of Forms and Submittal Checklist
RFP #: 8914-0-2020-BG Environmental Consulting Services
This form must be returned with your response.
Proposers hereby acknowledge the receipt and/or submittal of the following forms:
Forms Initial to
Acknowledge
SUBMITTAL
Initial to Acknowledge
RECEIPT
Description of Services/Commodities N/A
Form A: Signature Affidavit
Form B: Receipt of Forms and Submittal Checklist
Form C: Vendor Profile
Form D: Cost Proposal
Form E: References
Appendix A: Standard Terms & Conditions N/A
Appendix B: Contract for Purchase of Services N/A
Addendum #
Addendum #
Addendum #
Addendum #
VENDOR NAME
COMPANY NAME
BP
BP
BP
BP
BP
Ayres Associates Inc
Ayres Associates Inc
1 Monday, February 3, 2020
BP
BP
BP
BP
BP
BP
BP
BP
BPN/A
2 Wednesday, February 12, 2020 N/A BP
Rev. 07/28/2016-FormB-Receipt.doc
Form B: Receipt of Forms and Submittal Checklist
RFP #: 8914-0-2020-BG Environmental Consulting Services
This form must be returned with your response.
Proposers hereby acknowledge the receipt and/or submittal of the following forms:
Forms Initial to
Acknowledge
SUBMITTAL
Initial to Acknowledge
RECEIPT
Description of Services/Commodities N/A
Form A: Signature Affidavit
Form B: Receipt of Forms and Submittal Checklist
Form C: Vendor Profile
Form D: Cost Proposal
Form E: References
Appendix A: Standard Terms & Conditions N/A
Appendix B: Contract for Purchase of Services N/A
Addendum #
Addendum #
Addendum #
Addendum #
VENDOR NAME
COMPANY NAME
BP
BP
BP
BP
BP
Ayres Associates Inc
Ayres Associates Inc
1 Monday, February 3, 2020
BP
BP
BP
BP
BP
BP
BP
BP
BPN/A
2 Wednesday, February 12, 2020 N/A BP
AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON 9
Rev. 07/28/2016-RFP-FormC-VendorProfile.doc
Form C: Vendor Profile
RFP #: 8914-0-2020-BG Environmental Consulting Services
This form must be returned with your response.
COMPANY INFORMATION
COMPANY NAME (Make sure to use your complete, legal company name.)
FEIN (If FEIN is not applicable, SSN collected upon award)
CONTACT NAME (Able to answer questions about proposal.) TITLE
TELEPHONE NUMBER FAX NUMBER
ADDRESS CITY STATE ZIP
AFFIRMATIVE ACTION CONTACT
If the selected contractor employs 15 or more employees and does aggregate annual business with the City of $50,000 or more, the contractor will be required to file an Affirmative Action Plan and comply with the City of Madison Affirmative Action Ordinance, Section 39.02(9)(e), within thirty (30) days contract signature. Vendors who believe they are exempt based on number of employees or annual aggregate business must file a request for exemption. Link to information and applicable forms:
https://www.cityofmadison.com/civil-rights/contract-compliance/vendors-suppliers
CONTACT NAME TITLE
TELEPHONE NUMBER FAX NUMBER
ADDRESS CITY STATE ZIP
ORDERS/BILLING CONTACT
Address where City purchase orders/contracts are to be mailed and person the department contacts concerning orders and billing.
CONTACT NAME TITLE
TELEPHONE NUMBER FAX NUMBER
ADDRESS CITY STATE ZIP
LOCAL VENDOR STATUS
The City of Madison has adopted a local preference purchasing policy granting a scoring preference to local suppliers. Only suppliers registered as of the bid’s due date will receive preference. Learn more and register at the City of Madison website.
CHECK ONLY ONE:
Yes, we are a local vendor and have registered on the City of Madison website under the following category: www.cityofmadison.com/business/localPurchasing No, we are not a local vendor or have not registered.
Ayres Associates Inc
390965082
Ben Peotter
608.443.1206
PeotterB@AyresAssociates.com
5201 E. Terrace Drive, Suite 200
Project Director
608.299.2184
Madison WI 53718
Carie Sommer
715.834.3161
SommerC@AyresAssociates.com
3433 Oakwood Hills Parkway
Human Resources Director
715.831.7500
Eau Claire WI 54701
Stephanie Betley
715.834.3161
BetleyS@AyresAssociates.com
3433 Oakwood Hills Parkway
Project Accountant Supervisor
715.831.7500
Eau Claire WI 54701
X Professional Services
Rev. 07/28/2016-RFP-FormC-VendorProfile.doc
Form C: Vendor Profile
RFP #: 8914-0-2020-BG Environmental Consulting Services
This form must be returned with your response.
COMPANY INFORMATION
COMPANY NAME (Make sure to use your complete, legal company name.)
FEIN (If FEIN is not applicable, SSN collected upon award)
CONTACT NAME (Able to answer questions about proposal.) TITLE
TELEPHONE NUMBER FAX NUMBER
ADDRESS CITY STATE ZIP
AFFIRMATIVE ACTION CONTACT
If the selected contractor employs 15 or more employees and does aggregate annual business with the City of $50,000 or more, the contractor will be required to file an Affirmative Action Plan and comply with the City of Madison Affirmative Action Ordinance, Section 39.02(9)(e), within thirty (30) days contract signature. Vendors who believe they are exempt based on number of employees or annual aggregate business must file a request for exemption. Link to information and applicable forms:
https://www.cityofmadison.com/civil-rights/contract-compliance/vendors-suppliers
CONTACT NAME TITLE
TELEPHONE NUMBER FAX NUMBER
ADDRESS CITY STATE ZIP
ORDERS/BILLING CONTACT
Address where City purchase orders/contracts are to be mailed and person the department contacts concerning orders and billing.
CONTACT NAME TITLE
TELEPHONE NUMBER FAX NUMBER
ADDRESS CITY STATE ZIP
LOCAL VENDOR STATUS
The City of Madison has adopted a local preference purchasing policy granting a scoring preference to local suppliers. Only suppliers registered as of the bid’s due date will receive preference. Learn more and register at the City of Madison website.
CHECK ONLY ONE:
Yes, we are a local vendor and have registered on the City of Madison website under the following category: www.cityofmadison.com/business/localPurchasing No, we are not a local vendor or have not registered.
Ayres Associates Inc
390965082
Ben Peotter
608.443.1206
PeotterB@AyresAssociates.com
5201 E. Terrace Drive, Suite 200
Project Director
608.299.2184
Madison WI 53718
Carie Sommer
715.834.3161
SommerC@AyresAssociates.com
3433 Oakwood Hills Parkway
Human Resources Director
715.831.7500
Eau Claire WI 54701
Stephanie Betley
715.834.3161
BetleyS@AyresAssociates.com
3433 Oakwood Hills Parkway
Project Accountant Supervisor
715.831.7500
Eau Claire WI 54701
X Professional Services
AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON 11
COMPANY NAME
Rev. 07/28/2016-FormE-References.doc
Form E: References
RFP #: 8914-0-2020-BG Environmental Consulting Services
This form must be returned with your response.
REFERENCE #1 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
REFERENCE #2 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
REFERENCE #3 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
Village of Waunakee
500 W. Main Street
608.850.5227 tschmidt@waunakee.com
October 2001 - Ongoing
Waunakee Alloy Phase I ESA, Phase II Assessment, Site Remediation, and Grant Assistance, as well as community center brownfield redevelopment.
Todd Schmidt
Waunakee WI 53597
608.850.5628
Ongoing $400,000
City of Prairie du Chien
214 E. Blackhawk Avenue
608.326.6340 gfrable@prairieduchien-wi.gov
2005-Ongoing
Grant preparation, Phase I and II ESAs, site investigations, soil remediation, hazardous materials surveys and abatement, and demo-lition with specifications and oversight. Also assisted the City with site civil design, water quality basin design, and grant management.
Garth Frable
Prairie du Chien WI 53821
Ongoing $400,000
City of Marinette
1905 Hall Avenue
715.732.5135 bus. 715.923.0227 cell bmiller@marinette.wi.us
Multiple contracts, 2004-2018
Hattie Street redevelopment, grant assistance, Postorino Paint, Phase I and II ESA, WDNR closure, Colonial Building, Jozaitis/Menekaunee Harbor
Ayres Associates Inc
Brian Miller
Marinette WI 54143
2018 $500,000
COMPANY NAME
Rev. 07/28/2016-FormE-References.doc
Form E: References
RFP #: 8914-0-2020-BG Environmental Consulting Services
This form must be returned with your response.
REFERENCE #1 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
REFERENCE #2 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
REFERENCE #3 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
Village of Waunakee
500 W. Main Street
608.850.5227 tschmidt@waunakee.com
October 2001 - Ongoing
Waunakee Alloy Phase I ESA, Phase II Assessment, Site Remediation, and Grant Assistance, as well as community center brownfield redevelopment.
Todd Schmidt
Waunakee WI 53597
608.850.5628
Ongoing $400,000
City of Prairie du Chien
214 E. Blackhawk Avenue
608.326.6340 gfrable@prairieduchien-wi.gov
2005-Ongoing
Grant preparation, Phase I and II ESAs, site investigations, soil remediation, hazardous materials surveys and abatement, and demo-lition with specifications and oversight. Also assisted the City with site civil design, water quality basin design, and grant management.
Garth Frable
Prairie du Chien WI 53821
Ongoing $400,000
City of Marinette
1905 Hall Avenue
715.732.5135 bus. 715.923.0227 cell bmiller@marinette.wi.us
Multiple contracts, 2004-2018
Hattie Street redevelopment, grant assistance, Postorino Paint, Phase I and II ESA, WDNR closure, Colonial Building, Jozaitis/Menekaunee Harbor
Ayres Associates Inc
Brian Miller
Marinette WI 54143
2018 $500,000
Form E: References
RFP #: 8914-0-2020-BG Environmental Consulting Services
COMPANY NAME
FormE-References.doc
REFERENCE #4 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
REFERENCE #5 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
City of Baraboo Ed Geick
101 South Boulevard
608.355.2715 bus. 608.963.4237 cell egeick@cityofbaraboo.com
2008-2015
Administering grants and conducting environmental work required to rehabilitate brownfield sites in City of Baraboo. Work includes Phase I and Phase II Environmental Site Assessments at priority brownfield sites relating to six EPA grants.
Baraboo WI 53913
608.355.2719
2015 $650,000
Ariens Company, Brillion Iron Works LLC Mark Olsen
655 W. Ryan Street Brillion WI 54110
920.756.4649 direct 920.606.7884 cell molsen@ariensco.com
2018-Ongoing
Characterizing, remediating, and redeveloping the closed Brillion Iron Works foundry site. Relevant work includes Phase I and II ESAs, site investigation, remediation planning and coordination, funding strategy and grant assistance.
Ongoing $200,000
Ayres Associates Inc
COMPANY NAME
Rev. 07/28/2016-FormE-References.doc
Form E: References
RFP #: 8914-0-2020-BG Environmental Consulting Services
This form must be returned with your response.
REFERENCE #1 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
REFERENCE #2 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
REFERENCE #3 – CLIENT INFORMATION
COMPANY NAME CONTACT NAME
ADDRESS CITY STATE ZIP
TELEPHONE NUMBER FAX NUMBER
CONTRACT PERIOD YEAR COMPLETED TOTAL COST
DESCRIPTION OF THE PERFORMED WORK
Village of Waunakee
500 W. Main Street
608.850.5227 tschmidt@waunakee.com
October 2001 - Ongoing
Waunakee Alloy Phase I ESA, Phase II Assessment, Site Remediation, and Grant Assistance, as well as community center brownfield redevelopment.
Todd Schmidt
Waunakee WI 53597
608.850.5628
Ongoing $400,000
City of Prairie du Chien
214 E. Blackhawk Avenue
608.326.6340 gfrable@prairieduchien-wi.gov
2005-Ongoing
Grant preparation, Phase I and II ESAs, site investigations, soil remediation, hazardous materials surveys and abatement, and demo-lition with specifications and oversight. Also assisted the City with site civil design, water quality basin design, and grant management.
Garth Frable
Prairie du Chien WI 53821
Ongoing $400,000
City of Marinette
1905 Hall Avenue
715.732.5135 bus. 715.923.0227 cell bmiller@marinette.wi.us
Multiple contracts, 2004-2018
Hattie Street redevelopment, grant assistance, Postorino Paint, Phase I and II ESA, WDNR closure, Colonial Building, Jozaitis/Menekaunee Harbor
Ayres Associates Inc
Brian Miller
Marinette WI 54143
2018 $500,000
AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON
Legal Name:
Ayres Associates Inc
Madison Office:
5201 E. Terrace Drive, Suite 200 Madison, WI 53718
Corporate Headquarters:
3433 Oakwood Hills Parkway Eau Claire, WI 54701
Contact Information:
Ben Peotter, PE Manager – Environmental Services PeotterB@AyresAssociates.com 608.443.1206
Years in Business: 60
Ayres is a nationwide team of experts and innovative problem-solvers. We stand behind thousands of projects that strengthen communities and our country’s infrastructure, economy, and environment every day. We serve our clients from a network of 11 offices in four states (Wisconsin, Colorado, Florida, and Wyoming), with five of those offices in Wisconsin (Green Bay, Eau Claire, Madison, River Falls, and Waukesha).
Services for this contract will be provided from our Madison office, currently staffed by 41 professionals specializing in environmental and redevelopment consulting, geospatial services, landscape architecture, and transportation engineering. We have always been employee-owned and have approximately 300 employees company wide. Our services and specialty areas include:
Respected in the Industry
Since 1972 Ayres has been ranked among the top 500 architectural/engineering firms in the nation by Engineering News-Record magazine. We have provided study, environmental planning, design, and related construction administration services for more than 30,000 projects nationwide. Ayres is a predominately public-sector professional services engineering firm; it always has been.
This emphasis on public-sector clients frees us from the conflicts of interest that can hamper other firms. We will have the City’s best interests at heart throughout the contract.
Environmental Services Experience
Ayres has more than 60 years of environmental management experience in all phases of environmental assessments (EAs) and hazardous waste assessment and management. Our clients include local, state, and federal agencies;
industrial and commercial enterprises; financial institutions; developers; and a variety of other organizations. Environmental and redevelopment consulting is provided by our staff of nearly 20 highly qualified professionals, most located within Wisconsin, with specialized skills in remediation planning and coordination, environmental investigation, hydrogeology, wetland delineation, geology, inventory of and abatement plans for hazardous materials, brownfield development services, and other associated areas.
Firm Background & Key Staff
Brownfield services Environmental services Solid waste management Municipal engineering Grant/planning services Transportation/traffic Survey services
Construction services Geospatial mapping/GIS Bridge design/inspection Landscape architecture Subsurface/utilities Architecture Water resources
AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON
Project Team Ayres’ project leadership and primary staff involvement will be composed of personnel experienced in all phases of environmental site assessment and remedial action planning. Ben Peotter, PE, will be your project manager. He meets the federal definition of “environmental professional” as defined by 40 CFR §312.10. Full resumes for Ben and key staff are included in the following pages.
Experience Ben Jeff Chris Emily Keely Tom Bill
Conducting brownfield inventories X X X X
Conducting environmental investigations and cleanups X X X X X X X
EPA project experience X X X X X X X
Development/redevelopment experience and market feasibility research X X
Redevelopment planning and community involvement related to brownfields X X X X
Performance of environmental inventories using GIS in conjunction with EPA grants X X X X
Designing and managing brownfield remediation strategies X X X X X X X
Regulatory and Scientific/Technical Knowledge EPA, WDNR, and WEDC grant implementation X X X X X
Federal and Wisconsin environmental statutes and regulations X X X X X X X
EPA and WDNR environmental and other federal laws and regulations X X X X X X X
OSHA and other health and safety rules related to brownfields X X X X X X X
ESAs and contaminated site remediation X X X X X X X
EPA grant reporting and requirements, federal procurement, and MBE/SBE/WBE compliance X X X
“To be honest, the results produced by (the) team at Ayres Associates for the City of Marinette have been nothing short of remarkable.
...These people know what they are doing and they get the job done promptly and at a fair price. I would never hesitate to utilize their services.”
Jonathan Sbar, City Attorney, City of Marinette
City of Madison
Field Reporting
& Geology
Technician
Emily Thompson
Christopher Kubicki
Geologist
Bill Honea, PG
Assistant
Project Manager
Keely Campbell, PG
Project Manager
Ben Peotter, PE
Environmental Driller
(MBE Certified)
GESTRA Engineers
Environmental Lab
(WBE Certified)
CT Laboratories
Hydrogeology
Jeff Steiner, PG, PH, CPG
Tom Gaieck, PG
Ayres
CT Laboratories
GESTRA Engineers
Key
17AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON
Total Experience
20 Years
Registrations
Registered Professional Engineer, WI, MN
Certifications
Hazardous Waste Operations and Emergency Response 40-Hour Training and 8-Hour Refresher
Education
BS, Geological Engineering/ Geology, University of Wisconsin-Madison
Training
SWANA Landfill Gas, 2007
Ben Peotter, PE Project Manager, QA/QC
Ben oversees our development division’s work in brownfield revitalization, planning, environmental impact assessments and statements, environmental site assessments and remediation, and landfill monitoring and engineering.
Ben has worked as an environmental, geotechnical, and civil consultant since 1999. Ben uses his exceptional oral and written communication skills as well as his interpersonal, analytical, and leadership abilities to skillfully coordinate and conduct public meetings and workshops related to environmental and sustainability projects. He has experience in brownfield redevelopment, environmental investigation and remediation, landfill design and construction, biogas-to-energy systems, feasibility studies for renewable energy projects, geotechnical stability analysis, surface water runoff design and analysis, regulatory permitting, and municipal engineering. Ben’s responsibilities include project management; environmental impact statements and assessments (EISs and EIAs); brownfield redevelopments; grant writing; solid waste management, design, and permitting; and facilitation of client and public relations.
He works effectively with regulatory personnel, including Wisconsin Department of Natural Resources and U.S. Environmental Protection Agency officials. Ben has played a lead role in developing Wisconsin Environmental Policy Act-compliant EIA/EIS reports for large and complex projects with the State of Wisconsin and the University of Wisconsin System..
Select Experience
• Heartland Housing Phase II ESA, 7933 Tree Lane, Madison
• Aelco Foundries Phase I & II ESAs and Hazardous Materials Surveys, Grant
Services, Milwaukee
• Village of Waunakee, EPA Brownfield Redevelopment Projects, Waunakee
• 2501 University Avenue Remediation 2018, Madison
• Ethan Allen Phase I ESA, Delafield
• Coleman & Oconto Phase II ESAs, Coleman & Oconto
• Bay Lake Petroleum Phase I & II ESAs, Green Bay
• Holum Street Phase I ESA, DeForest
• Pischke Motors Phase I ESA, West Salem
• Marquette School Phase I ESA, Kewaunee
• University Avenue Asbestos Survey, Madison
• Quality Wood Treating Company Site Investigation and Remediation, Prairie du Chien
• Beaver Dam Community Hospital SAG Phase I ESA, Beaver Dam
• Charter Street Heating Plant Rebuild EIS, Madison
• Palatka Phase I & II ESAs - Petroleum, Palatka, FL
• UW-Madison Vet Medicine EIA, Madison
• Marshfield Clinic Phase I ESA, 9601 Townline Road, Minocqua
6 Years
Registrations
Registered Professional Geologist, WI
Certifications
Hazardous Waste Operations and Emergency Response 24- Hour Training, Environmental Trainers
Education
BS, Geological Sciences, Florida State University
Training
PEC Safeland USA Training, 2014
Hydrogen Sulfide Awaremess Training, 2016
Keely Campbell, PG Geologist, Assistant Project Manager
Keely joined Ayres in 2016, bringing three years of experience in petroleum geology, structural geology, and tectonics. She has experience in field data collection and sampling activities, including geologic and geophysical surveying;
on-site petroleum geology sampling; hard rock, soft sediment, and soil sampling;
hydrogeologic sampling and analysis, and well installation and monitoring.
Keely works on Phase I and II environmental site assessments (ESAs), site investigations, National Environmental Policy Act environmental assessments, local, state, and federal grant writing, implementation, and management, and a variety of regulatory compliance projects. She has significant experience in site assessment and characterization, groundwater monitoring, solid waste reporting and permitting, brownfield site assessments, site investigations, and regulatory reporting for federal, state, and private clients.
Select Experience
• Madison Country Day School Phase I ESA, Waunakee
• Heartland Housing Phase II ESA, 7933 Tree Lane, Madison
• Heartland Housing Phase I ESA, 1202 S. Park St., Madison
• Phase I ESA, 211 Pioneer Drive, Wisconsin Dells, Supervisor, Wisconsin Dells
• Sonnentag Complex Pre-Site Demo Approvals and Permits, Eau Claire
• Ethan Allen Phase I ESA, Delafield
• Cannery Trail Residence Development, Phase I ESA, Eau Claire
• SSM Health, Phase II ESA, 1312 South Park St., Madison
• Lamar Phase I & II ESA Hazardous, Lamar, CO
• City of Palatka, Phase I & II ESAs-Petroleum, Palatka, FL
• City of Palatka, Phase I &II ESAs-Hazardous, Palatka, FL
• Marshfield Clinic Phase I ESAs, 14 Parcels, Various Locations, WI
• Marshfield Clinic Ladysmith Park Property Preliminary Geotechnical
Evaluation and Limited Phase II ESA, Ladysmith
• Phase I ESA, 2802 E. Johnson Street, Madison
• Phase I ESA, 640 W. Washington Ave., Madison
• Phase I ESA, 902 Reiner Road, Madison
• Johnson Bank Phase I ESA, 21 S. Austin Road, Janesville
• Blugold Real Estate, Phase I ESA, 226 Roller Ave., Beaver Dam
• Madison Family Dentist Associates, Phase I ESA, Madison
• Montrose Site Investigation/Planning-Hazardous, Montrose, CO
19AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON
34 Years
Registrations
Registered Professional Geologist, WI, KS, NE
Registered Professional Hydrologist, WI
Certified Professional Geologist, US
Certifications
Hazardous Waste Operations and Emergency Response 40-Hour Training and 8-Hour Refresher
Education
BS, Geology with Emphasis in Hydrogeology, University of Wisconsin-Oshkosh, 1986
Jeff Steiner, PG, PH, CPG Senior Hydrogeologist/Field Manager
Jeff joined Ayres in 1998 with 12 years of experience in environmental consulting for industrial, municipal, and regulatory clients, and 1.5 years of regulatory experience with the Wisconsin Department of Natural Resources.
He has assisted clients seeking solutions to problems in groundwater resource management, groundwater development, waste management, and environmental protection.
As a project manager/hydrogeologist he is responsible for all aspects of project development, implementation, and management, including the preparation and presentation of proposals, assessment of regulatory impact, project design and oversight, schedule and budget management, technical analysis and report preparation, and regulatory and client liaison.
Select Experience
| • | State Preservation Storage Facility Site Sampling Activities, Madison |
| • | Alexander Co. Novation Campus Lot 2 Phase I ESA, Madison |
| • | Artisan Village Phase I ESA, Madison |
| • | 301 West Beltline Highway Phase I ESA, Madison |
| • | Nor-Lake Site Closure Plan & Continuation, Hudson |
| • | Bay Lake Petroleum Phase I & II ESAs, Green Bay |
| • | Montrose Site Investigation/Planning-Hazardous, Petroleum, Montrose, CO |
| • | Former Getzen Musical Instrument Property Investigation and Remediation, |
Elkhorn
| • | Getzen Site Closure Reporting 2018, Elkhorn |
| • | Icke Landfill/Novation Technology Campus EPA Brownfield Redevelopment, |
Madison
• Waunakee Alloy Grant Assistance, Phase I and II ESAs, and Hazardous
Materials Cleanup, Waunakee
| • | Douglas Site/Investigation Planning-Petroleum, Hazardous, Douglas, WY |
| • | Laramie Site/Investigation Planning-Petroleum, Hazardous, Laramie, WY |
| • | Marquette School Demolition Clearance Oversight, Kewaunee |
| • | Town of Springfield Phase I ESA, Springfield |
| • | Lamar Phase I & II ESAs-Hazardous, Lamar, CO |
33 Years
Registrations
Registered Professional Geologist, WI, FL, WY, AZ
Education
BS, Earth Science, University of Wisconsin-River Falls, 1985
Thomas Gaieck, PG Hydrogeologist
Thomas joined Ayres in 1992. His responsibilities include Phase I, II, and III site assessments; groundwater and soil investigations; remediation design;
construction services; and pre-acquisition site assessments. His brownfield experience included environmental sampling, air permitting, stormwater permitting, Tier 2 reporting, auditing, training, and emergency oil spill response.
His additional brownfield experience includes soil, groundwater, vapor, concrete, and asbestos sampling.
He facilitates collaboration and communication with clients, peers, regulatory agencies, and subcontractors to meet project objectives and deadlines.
Currently, he’s working on several projects in Madison and Dane County and working on EPA and WEDC Brownfield Grants conducting Phase I and II ESAs, vapor evaluation and system commissioning, remedial action plans, and project closure for clients.
Total Experience
8 Years
Registrations
Registered Professional Geologist, WI, WY, AZ
Education
BS, Geology, University of Tennessee
Bill Honea, PG Geologist
Bill joined Ayres in 2015 with five years of environmental consulting experience and a strong regulatory compliance background. He has conducted Phase I and II ESAs, groundwater monitoring; brownfield site investigations, and asbestos-containing material inspections and completed regulatory reporting for federal, state, and private clients. Bill has prepared work plans, Health and Safety Plans, National Pollutant Discharge Elimination System permits, and monitoring reports, and he has provided technical support for municipal water, wastewater, gas, and electrical system operations. This technical support includes environmental sampling, air permitting, stormwater permitting, Tier 2 reporting, auditing, training, and emergency oil spill response. His field experience includes soil, groundwater, vapor, concrete, and asbestos sampling. He facilitates collaboration and communication with clients, peers, regulatory agencies, and subcontractors to meet project objectives and deadlines.
21AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON
2 Years
Education
MS, Water Science and Management, New Mexico State University
BS, Environmental Science, Montana State University
Christopher Kubicki Technician
Chris joined Ayres in 2019, bringing two years of experience as an environmental scientist and hydrologist. His experience includes site assessment and characterization, wetland delineation, groundwater sampling, and temperature logging monitoring wells. Chris conducts site assessments and investigations, prepares technical reports, and prepares Sampling and Analysis Plans and Quality Assurance Project Plans for investigation and remediation projects. His field experience includes soil, groundwater, vapor, and concrete sampling.
Total Experience
2 Years
Education
MS, Environmental Geoscience, Czech University of Life Sciences-Prague, 2017
BS, Biology, University of Wisconsin-Whitewater, 2014
Emily Thompson Technician
Emily joined Ayres’ environmental staff in 2019, bringing experience with groundwater treatment systems and site inspections. Emily conducts geological interpretations on projects, including groundwater and soil investigations.
She performs field investigations and assessments related to environmental contamination and environmental site assessments (ESAs). Emily assists with preparing reports and technical documents related to ESAs, environmental impact assessments and statements, and other environmental studies.
Emily also provides on-site construction quality control and observation for excavations and monitoring well installations associated with site investigations and remediation. She provides risk assessment and interpretive data management and assists with grant writing.
Partners/Subcontractors
CT Laboratories LLC has been in business since 1987. It is located in the heart of the Baraboo Bluffs in Baraboo and is a locally owned full-service laboratory.
CT Laboratories can analyze for volatiles, semi-volatiles, pesticides, PCBs, metals, and classical chemistry. It performs analyses most small laboratories don’t, such as explosives, volatile fatty acids, dissolved gases, and physical parameters. CT Laboratories has an in-house biological laboratory offering soil and water bacterial enumeration and drinking water coliform testing. It performs these tests on everything from clean drinking water samples to leachate, soil samples to wood-blocks, sediments to concrete cores, and oil to paint chips. CT understands that communication is the key to a successful project. Its clients are assigned a specific project manager to take care of their needs from initial project scoping and assistance with QAPP generation to fulfilling bottle requests and verifying sample receipt through addressing technical issues and final report generation.
Quality is not a given or an afterthought at CT Laboratories. Its quality assurance program is designed to ensure legally defensible data. From numerous performance evaluation studies, NELAP and other individual state audits, as well as its in-house program, CT Laboratories continually monitors its quality to ensure clients get the best results possible.
CT is a Wisconsin-certified WBE, DoD ELAP accredited, and maintains national accreditation through multiple NELAP certifications. It holds state certifications in several of the country’s most stringent programs.
GESTRA Engineering Inc. is a Wisconsin-certified MBE consulting firm in Monona, WI that specializes in geotechnical engineering. GESTRA was founded in 2000 and offers a wide range of environmental drilling and geotechnical drilling for site investigation and remediation services. It has developed a reputation for providing high-quality, cost-effective services and for finding appropriate solutions for difficult project requirements. Its experience and resources help ensure that projects will be accomplished in a safe, efficient and cost effective manner.
GESTRA Engineering is committed to providing the owner and environment consultant with the best value in environmental drilling and related services. GESTRA is a quality-based organization and follows all ASTM testing requirements when applicable. The organization complies with quality assurance and calibration requirements outlined in ASTM.
| • | Piezometer installation |
| • | Recovery well installation |
| • | Geoprobe direct push sampling |
| • | Pre-packed well installation |
| • | Dual tube sampling |
| • | Macro core sampling |
| • | Decontamination pads |
| • | Limited access equipment |
| • | Hand-held Geoprobe sampling |
| • | Monitoring well & boring abandonments grouting |
Working with disadvantaged businesses is a common practice for Ayres in environmental investigations, providing a win-win with great teaming partners – it isn’t something we just give lip service to. If awarded this work, we’ll be contracting with:
GESTRA Engineering (Geoprobe) – Our drilling partner for this contract is a Wisconsin-certified MBE consulting firm specializing in geotechnical engineering. GESTRA will perform environmental drilling for Phase II ESAs.
CT Laboratories (Baraboo, Wisconsin) – Classified as a woman-owned small business under NAICS code 541380, CT Laboratories is a Wisconsin accredited lab with whom we’ve worked on environmental sites for over 25 years.
AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON 23
Ayres has conducted thousands of Phase I environmental site assessments (ESAs) and hundreds of Phase II ESAs. Our environmental consulting services range from initial project visioning, planning, and due diligence to project implementation services that include brownfield site identification and prioritization, project resource procurement, brownfield redevelopment grant administration, community outreach and stakeholder involvement, oversight of remediation, construction, and development activities, and assistance with developer recruitment.
Ayres’ portfolio covers the entire spectrum of site conditions ranging from mildly contaminated grayfields to brownfield redevelopment areas that include multiple sites with multiple owners; Resource Conservation and Recovery Act/Comprehensive Environmental Response, Compensation, and Liability Act sites; and reclaimed landfills. Our experience and success in conducting site investigations and remedial action planning is evidenced by the number of projects we have completed for public sector municipalities, responsible parties, and brownfield developers.
We understand how City governments work and make decisions. Committees and boards need honest, streamlined information so they can use the facts to make informed decisions regarding environmental and redevelopment projects. The strength of our team lies in the vast amount of experience our scientists, engineers, architects, and planners have in guiding municipal clients through the financial, liability, and site access issues that arise during these projects.
In addition, Ayres frequently works with the Wisconsin Department of Transportation, usually conducting environmental work on five to 10 corridor projects per year throughout the state. We are very familiar with the FDM Chapter 21 requirements, protocol, and procedures on environmental sampling and reporting.
As a team member, we see the bigger picture on future redevelopment and end goals, and thus know how to best navigate the process to help you get there. We aren’t just a commodity provider, and that’s what sets us apart from others. We thoroughly understand the process, are experienced at assisting with public involvement, and are able to efficiently provide project deliverables to meet your schedule.
The projects and marketing materials featured on the following pages demonstrate Ayres’ capability, experience, and qualifications regarding all aspects of ESAs and remediation.
Experience Professional/Project Experience
Ingenuity
Integrity
Intelligence
Similar Projects
Sheridan Iron Works Phase I & II ESAs, Sheridan, WY Client: City of Sheridan Completed: October 2018 Key Staff: Ben Peotter, Jeff Steiner, Keely Campbell Reference: Robert Briggs, 307.675.4225, rbriggs@sheridanwy.net
Following completion of a Phase I ESA, the City of Sheridan retained Ayres Associates to prepare a work plan to evaluate the 1.59-acre Sheridan Iron Works property for potential redevelopment and to carry out site investigation activities, to be summarized in a Phase II ESA report. The purpose is to assess potential environmental impacts that may exist at the subject property and their potential impact on site redevelopment, if any, as a result of former operations associated with a foundry and metal working facility on the site and adjacent bulk petroleum storage facilities.
Palatka Site Investigation, Palatka, FL Client: City of Palatka Completed: November 2018 Key Staff: Ben Peotter, Jeff Steiner, Keely Campbell Reference: Terrill Hill, Mayor, 386.329.0100, thill@palatka-fl.gov
The City of Palatka retained Ayres to evaluate potential environmental impacts that may exist at the former Florida Furniture Industries Inc property that were identified in a Phase I ESA and their possible impact on site redevelopment, should any exist. The work performed at the 21.3-acre property, located at 900 River Street and 201 Morris Street, included development of a Sampling and Analysis Plan and Health and Safety Plan, evaluation and analysis of existing environmental data, soil sampling in the unsaturated zone, installation of monitoring wells and collection of groundwater samples, hydraulic conductivity testing, laboratory analysis of soil and groundwater samples, and preparation of a Phase II ESA report.
AYRES | ENVIRONMENTAL CONSULTING SERVICES | CITY OF MADISON
Milwaukee Fortress Renovation Site Investigation and Remediation Planning, Milwaukee, WI Client: Milwaukee Fortress LLC Completed: 2019 Key Staff: Ben Peotter, Jeff Steiner, Thomas Gaieck Reference: Jeremiah Leigh, Project Manager, 608.268.8133, jl@alexandercompany.com
The Alexander Company, on behalf of Milwaukee Fortress LLC, revitalized the former F. Mayer Boot and Shoe Company building, now known as the Milwaukee Fortress Building, at 100 E. Pleasant Street. The 124-year-old, 193,988-square-foot building now includes 132 apartments with 25,000 square feet of office space on the first two floors.
Ayres was retained to provide consulting services on environmental issues and Housing and Urban Development financing. Ayres represented the owner at negotiations with the Wisconsin Department of Natural Resources (WDNR).
Our team performed an NR 716 site investigation to evaluate potential soil, groundwater, and soil vapor contamination. Based on the results of the site investigation, Ayres prepared a Remedial Action Options Report (RAOR) to evaluate remedial options necessary to address environmental impacts during renovation. A Remedial Action Implementation Plan for execution of remediation was also provided.
Brillion Iron Works Phase I & II ESAs, Brillion, WI Client: Ariens Company Completed: August 2018; site investigation still ongoing Key Staff: Keely Campbell, Bill Honea, Scott Wilson Reference: Mark R. Olsen, 900.756.4313, molsen@airensco.com
Ariens Company retained Ayres to prepare a Phase I ESA and subsequently a Phase II ESA work plan outlining the objective, scope, and rational of the assessment, to conduct a subsurface investigation, and to prepare a Phase II ESA report for the 145-acre Brillion Iron Works property in Brillion. Information was collected during the investigation from 46 direct push soil borings,27 groundwater samples, and two sub-slab vapor samples. The primary goal of this project was to determine site redevelopment impacts, including remediation costs, and to provide due diligence for the buyer to determine its underlying risk of acquisition before obtaining title to the property.
“[Ayres] had a really good understanding of the parameters that we had to work in and the budget constraints that we also had.
...I was quite impressed and very happy with the project.”
Rick Parish
Director of Parks and Recreation, City of Cheyenne, regarding Lake Minnehaha remediation project
BEFORE
Sonnentag Complex, Eau Claire, WI Client: Blugold Real Estate Foundation Inc.
Completed: December 2018 Key Staff: Ben Peotter, Keely Campbell, Jeff Steiner Reference: Coby Kohn, 715.836.5630, kohncoby@uwec.edu
Ayres was retained by Blugold Real Estate Foundation Inc.
to develop work plans, conduct investigation activities, and prepare summary reports for the 6.34-acre Fabick Cat site at 1211 Menomonie Street in Eau Claire. Ayres was also retained for similar services on adjacent parcels involved in the Sonnentag Complex project.
A Phase II ESA was conducted in September 2016 to evaluate likely soil and groundwater impacts from historical property uses identified in a Phase I ESA. A site investigation was then conducted by Ayres in December 2016 to determine the horizontal and vertical extent of impacts identified during the Phase II.
The site investigation included installing 17 direct push soil probes with five of the probes converted to wells. A supplemental site investigation was conducted in 2018 to further define the degree and extent of groundwater contamination at the Fabick Cat site and included installing and sampling five NR141 groundwater monitoring wells.
City of Delavan Redevelopment, Delavan, WI Client: City of Delavan Completed: May 2018 Key Staff: Tom Gaieck, Tim Shupert, Ben Peotter Reference: Mark Wendorf, Director of Public Works, 262.728.1891, Ext. 120, delavandpw@ci.delavan.wi.us
Ayres assisted the City with grant identification and preparation, hazardous materials assessments, soil and site investigations, remedial action plan design, construction oversight, and maintenance of groundwater monitoring systems for the Ann Street Corridor, which surrounds the railroad line in the older industrial/residential portion of Delavan. Ayres prepared asbestos abatement and demolition specifications for more than 200,000 square feet of structures and has handled demolition oversight, soil remediation, and design and construction of a water quality basin with associated green space. Working in tandem with Ayres, the City applied for and received more than $5.5 million in grants and loans from the state and EPA to address the needs of this formerly blighted industrial corridor.
Environmentally, this corridor cleanup was conducted using three soil vapor extraction systems to address the five commingled groundwater plumes containing petroleum and chlorinated hydrocarbon contaminants.
PCBs in the soil, related to facility operations, were also identified and remediated, along with areas of heavy metals.
The metals and groundwater concerns were addressed with a combination of U.S.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .