This is a Pre-Construction Risk Assessment (PCRA) template used by the Veterans Health Administration (VHA) for evaluating safety risks associated with construction, renovation, and maintenance activities at VA facilities.

The document provides a baseline framework for categorizing construction activities into three risk levels—Inspection/Upkeep, Small-scale, and Large-scale—each with corresponding control measures. For the specific project documented, Project 402-22-700 (EHRM Infrastructure Upgrades), the activity is classified as Large-scale, involving new construction of a Main Computer Room (a standalone IT building) within the hillside behind Building 209 and new trenchwork for cabling across the campus. Control measures for Large-scale activities include excavation safety plans, dust control plans, dig-safe paperwork, and fall protection and confined entry plans as applicable. The assessment requires coordination with affected adjacent areas, identification of points of contact, and communication of construction plans to relevant departments. An Infection Control Risk Assessment (ICRA) is required for this project and must be conducted in conjunction with this PCRA. The document includes a fillable permit form that must be posted at the project site, signed by the Project Manager (Abigail Campbell), Safety Officer (George Porter), and Chair of the Construction Safety Committee, with required supporting documentation including hazard analyses and control plans made available to all workers.

View the file

Other files

File Type Posted
S30 - SAM - Special Notice - Cancellation - 36C77626R0062_2 - EHRM Infra Upgrades - Togus.pdf PDF
S06 - Amend 0002 - Att 03 - Corrected Agenda - RFP - 07202026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0002 - 36C77626R0062 - 07202026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - Att 02 - SV - Attendance SHT - 06292026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - 36C77626R0062 - 07142026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - RFIs - 07132026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S06 - Amend 0001 - Att 01 - Rvd Structural Drwg - 06192026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - Att 03 - SV - Agenda - RFP - 06292026 - EHRM Infra - Togus.pdf PDF
S02 - SOW - Att 05 - Drwg - Vol 3 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 13 - Const Sch - 02132026 - EHRM Infra Upgrades - Constr Togus.pdf PDF
S02 - SOW - Att 26 - Cut Sheet 04 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 03 -Prj Info Sheet for KTR - EHRM Infra Upgrade - Togus.docx DOCX document
S02 - SOW - Att 03 - Drwg - Vol 1C - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 22 - TS-000 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 07 - 852.219-75 - 06172026 - EHRM Infra Upgrade - Togus.pdf PDF
S02 - Att 04 - Memo - Brand Name - 04092026 - EHRM Infra Upgrade - Togus.pdf PDF
S02 - SOW - Att 35 - Cut Sheet 13 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 17 - Memo - Phy Sec Compliance - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 27 - Cut Sheet 05 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 09 - Specs - Vol 3- 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 30 - Cut Sheet 08 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 24 - Cut Sheet 02 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 05 - Division Cost Breakdown - EHRM Infra Upgrade - Togus.xlsx XLSX spreadsheet
S02 - SOW - Att 29 - Cut Sheet 07 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 37 - Cut Sheet 15 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 16 - Submittal Reg - 02182026 - EHRM Infra - Upgrades - Constr - Togus.xlsx XLSX spreadsheet
S02 - SOW - Att 14 - Design Calcs - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 18 - Memo - Prj Stnd Compliance - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 40 - Cut Sheet 18 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 33 - Cut Sheet 11 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 01 - Drwg - Vol 1A - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 38 - Cut Sheet 16 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 06 - Drwg - Vol 4 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 11 - Haz Mat Report - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 12 - Geotechnical Report - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 32 - Cut Sheet 10 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 08 - Specs - Vol 1 - Div 02-14 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 20 - PCRA 2 - Cabling and Data Outlets - EHRM Infra Upgrades - Constr - Togus.pdf PDF
RFP - EHRM Infra Upgrade - 36C77626R0062 - 06172026 - Togus.pdf PDF
S02 - SOW - Att 19 - PCRA 1 - TR Constr - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 07 - Specs - Vol 1 - Div 00-01 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 15 - Design Narrative - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 23 - Cut Sheet 01 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 31 - Cut Sheet 09 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 02 - PPQ - EHRM Infra Upgrade - Togus.docx DOCX document
S02 - SOW - Att 02 - Drwg - Vol 1B - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 34 - Cut Sheet 12 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 01 - SOW - 05112026 - EHRM Infra Upgrades - Togus.pdf PDF
S02 - SOW - Att 10 - Specs - Vol 4 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 36 - Cut Sheet 14 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHA Pre-Construction Risk Assessment (PCRA)

VHA-PCRA-2023-1.0 Page 1 of 6

PCRA Introductory Information and Instructions

Use this template as a baseline for performing facility Pre-Construction Risk Assessments (PCRA) for Construction, Renovation, and Maintenance work (referred to as the “activity” in this document). The template provides minimum requirements for categorizing activity type(s) and safety risk to determine the level of precautions needed to prevent impact related to Construction, Renovation and Maintenance on patients, employees, and contractors.

Ensure that the activity statement of work and any drawings available are used for the PCRA assessment and included in the project file with the completed PCRA.

Communication and coordination of all types of activity with affected areas are to be included among the control measures. The development of communication and coordination plans must begin during the activity planning phase.

Facilities may customize this template to incorporate site-specific information and requirements.

NOTE: This VHA PCRA template pertains specifically to non-infection-related safety for Construction, Renovation, and Maintenance activities. It must be used in conjunction with the VHA Infection Control Risk Assessment (ICRA) for the activity, if required, which specifically addresses infection risks outside the scope of this PCRA.

PERMIT: See the last page of this document for a fillable permit form to be used for posting at the activity site.

Activity Location:

Activity Name, Number, and/or Brief Description:

Table 1 - Construction, Renovation, and/or Maintenance Activity Type and Control Measures NOTE: If any of the bulleted criteria in a higher activity type pertains to the work that will be done (even if the other criteria are in a lower type), use the higher activity type for the VHA PCRA.

Controls defined in Table 1 for the activity must be in place before the activity begins and maintained until work is completed and the area is activated. Control measures for each activity must also include the control measures in the preceding row(s).

As the activity progresses, a full re-evaluation of remaining activity type and risk is required prior to changing the level of control measures.

Activity Type determined from Table 1:

Activity Type and Description Control Measures

Large Scale

Campus Wide and Hillside behind building 209, see attached plans

Project 402-22-700 EHRM Infrastructure Upgrades project is to upgrade the facility infrastructure to support the new Electronic Health Record Modernization (EHRM) system in accordance with VA OEHRM Site Infrastructure Requirements

PCRA 3 – The new construction of the Main Computer Room. A stand alone IT building to be built within the hillside behind existing building B209. Also all new trenchwork of cabling on site.

VHA-PCRA-2023-1.0 Page 2 of 6

Inspection/upkeep generally defined as follows:

• Work can be completed in a single shift, not to exceed 10 hours.

• Patients, employees and/or visitors may be in the area depending on the activity.

• Work that does not create dust or debris.

• Work that does not create vapors or fumes.

• Removal of ceiling tile or access to mechanical or electrical chase for visual inspection that will not impair fire safety systems and are limited to 1 tile per 50 square feet with limited exposure time (not to exceed an hour for each tile) within the shift.

• Minor interior updates (e.g., replacing floor or ceiling tiles, carpentry work to include hanging signage, and painting with hand tools) that do not create vibration or noise.

• Limited building system maintenance that does not require Lock Out Tag Out (LOTO) such as plumbing on potable systems limited to faucet replacement, steam trap replacement etc. and electrical work such as replacement of bulbs, receptacles, or switches.

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team.

Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved where a contact is in place. For internal work the shop involved must work with Safety to ensure proper precautions are in place.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact to patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small scale Construction, Renovation and general maintenance/repair work, generally defined as follows:

• Prolonged work that may take longer than a single shift but not exceeding six months.

• Patients and employees are not to be in the area until activity is completed.

• Work that creates some noise and vibration due to power tool use.

• Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may o disturb asbestos, lead or silica o create the potential for falling objects o create vibration and/or noise in excess of 80 dB(A) in surrounding areas.

o cause penetrations in fire or smoke barrier

• Plumbing work such as the installation of new sinks, showers and toilets and associated plumbing that requires utility outages or work on the steam system that may require:

o LOTO o The use of compressed gas cylinders

• Electrical work such as installation of conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. Electrical work such as installation of cabling/wiring/conduit for a single device, installation of new device such as a light fixture that require LOTO.

• Air Handler and/or fan shutdown/startup and HVAC work such as replacement of a single diffuser, single terminal unit, a single device and the installation of ductwork, diffusers, and terminal units for an area that may require:

o Work on ladders o Rigging, hoisting or lifting of equipment or materials overhead

• Modification of existing fire alarm and suppression systems requiring system outages and ILSMs or obstruction of exits and or impact on corridors.

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. Where construction, Renovation and maintenance are done in an accredited facility, and ILSM assessment is required to be done and ILSMs put into place in accordance with TJC LS.01.02.01 and the local facility policy including Fire watch if necessary. Staff is trained and the ILSM is verified regularly

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.

VHA-PCRA-2023-1.0 Page 3 of 6

• Architectural, structural, or any other work that may cause vapors or fumes such as:

o Roofing work o Flooring work o Painting or other large-scale use of such substances.

Large-scale construction, renovation, or maintenance generally defined as follows:

• Work exceeding 6 months in duration.

• Patients and employees are not to be in the area until activity is completed.

• Excavation or heavy equipment use taking place o Dig safe required utility location o Trench safety o Dust control plan o Equipment exhaust, Noise, Vibration

• Confined space entry required (permit required or not)

• Requires crane work o General crane work o Lift over buildings

• Includes elevated work o Roof work, fall protection o Window work, scaffolding and fall protection o Odor control

• Welding, cutting or use of torches requiring burn permits

• Demolition of building components and infrastructure including removal of multiple doors, walls, framing, ceilings, flooring, piping, electrical and HVAC that may o require asbestos, lead or silica abatement o create the potential for falling objects o create vibration and/or noise in excess of 90 dB(A) in surrounding areas.

o cause breaches to fire or smoke barrier

• The installation building components such as new walls, ceilings and doors including framing, drywall and associated plaster work that requires transport of significant materials through building and up elevators i.e., weight limits of floors and elevators

• Plumbing work requiring LOTO and system shutdown and startup such as the installation of:

o new medical gas systems, o steam/heating hot water, condensate systems, o Potable water and sanitary drainage, multiple sinks, showers and toilets including associated plumbing.

• Electrical work such as installation of electrical feeders, distribution panels, conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. requiring LOTO and system isolation.

• Installation of fire alarm and suppression systems requiring outages of those systems and ILSMs or closure of exits/corridors

• Mechanical work such as the installation of air handling equipment, associated ductwork, diffusers, heat exchangers, All control measures in the two rows above and the following Activity Hazard Analyses and Control Plans (check all that apply):

1. Excavation safety plan in place ☐

2. Dust control plan in place ☐

3. Pollution prevention plan in place ☐

4. Dig safe paper work in place ☐

5. Crane lift plan in place ☐

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained ☐

7. Confined entry plan in place and staff trained ☐

VHA-PCRA-2023-1.0 Page 4 of 6 terminal units and controls requiring lifting and support of equipment and systems.

Table 2. Affected Adjacent Area Assessment In addition to the minimum precautions noted above for the Activity Type, it is critical that the activity be coordinated with the areas adjacent to the activity to ensure operations in those areas are not disrupted or impacted. List the adjacent areas in Table 2 below and develop activity-specific coordination plans and associated communication plans with each area to address activity work that could impact or disrupt the operation of the areas, in general as follows:

• If adjacent area is vacant (e.g., work outside, construction of new building, etc.):

o Coordination is typically not necessary other than potentially traffic flow and pedestrian access.

• If adjacent area is non-continuously occupied (e.g., areas where outpatient care is provided, employee health, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., conduct work after hours).

• If adjacent area is occupied continuously (e.g., areas where inpatient care is provided, residential areas such as Community Living Centers, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., move affected party temporarily).

Area Service(s)/Type(s) of Area(s)

(e.g., OR, Unit/Ward, Sterile Processing, Administrative, etc)*

Point of Contact

(POC)

POC Contact Information

Construction plan communicated to POC?

Activity Area** New Build Abigail Campbell 207-623-8411 Upcoming

Area Above

Area Below

Adjacent Area 1

Adjacent Area 2

Adjacent Area 3

Adjacent Area 4

* There may be more than one Service/type of area for each row. List all. The information entered on this table must be used in the ICRA if required.

** List the area(s) in which the construction/renovation/maintenance activity will occur.

Infection Control Risk Assessment (ICRA)

Consult with Infection Prevention and Control regarding the assessment of potential infection risks associated with the activity and the need for control measures. See VHA Directive 7715 and the VHA ICRA Template for

FMS

VHA-PCRA-2023-1.0 Page 5 of 6 more information.

Is an ICRA required for the Activity? Yes ☒ No ☐

VHA-PCRA-2023-1.0

Pre-Construction Risk Assessment (PCRA) Permit This page must be posted at the entrance to the project area, or other designated area

Unique permit number:

Location and brief description of construction/renovation/maintenance Project manager Abigail Campbell Project start date TBD Contact phone number 207-623-8411 Completion date TBD Contractor or lead shop TBD Permit expiration date

Activity Type Inspection/Upkeep, Small-scale, or Large-scale)

Activity Type Control measures to be in place for the duration of the activity (Check the box for the Activity Type to indicate the Control Measures)

Inspection/Upkeep

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small-scale

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. ILSMs in place and staff trained on situation

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor and documented on their daily log.

Large-scale

All control measures in both rows above and the following Activity Hazard Analyses and Control Plans as applicable (check all that apply):

1. Excavation safety plan in place ☐

2. Dust control plan in place ☒

3. Pollution prevention plan in place ☐

4. Dig safe paperwork in place ☐

5. Crane lift plan in place ☐

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained ☐

7. Confined entry plan in place and staff trained ☐

*The location of all Activity Hazard Analyses and Control Plans (excavation, dust, pollution, etc.) as applicable shall be identified on this permit and shall be made available to all workers on the job.

Additional requirements:

Is an Infection Control Risk Assessment (ICRA) required for the Activity? Yes ☒ No ☐ Infection Prevention and Control signature:

Date:

Project Manager signature Date

Safety Officer signature Date

Chair, Construction Safety Committee signature

Date

Campus Wide and Hillside behind building 209 see attached plans:
Project 40222700 EHRM Infrastructure Upgrades project is to upgrade the facility infrastructure to support the new Electronic Health Record Modernization EHRM system in accordance with VA OEHRM Site Infrastructure Requirements PCRA 3 The new construction of the Main Computer Room A stand alone IT building to be built within the hillside behind existing building B209 Also all new trenchwork of cabling on site:
Large Scale:
Activity Type and Description:
Control Measures:
All control measures in the row above and the following 1 Hazard communication chemical inventory required to be provided by the contractor and approved 2 Where construction Renovation and maintenance are done in an accredited facility and ILSM assessment is required to be done and ILSMs put into place in accordance with TJC LS010201 and the local facility policy including Fire watch if necessary Staff is trained and the ILSM is verified regularly 3 Hot Work or burn permits in place and staff trained 4 LOTO procedures in place and staff trained on their use 5 Site visits will be reviewed using the criteria in standardized guide 6 Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log:
Architectural structural or any other work that may cause vapors or fumes such as o Roofing work o Flooring work o Painting or other largescale use of such substances:
All control measures in the two rows above and the following Activity Hazard Analyses and Control Plans check all that apply 1 Excavation safety plan in place 2 Dust control plan in place 3 Pollution prevention plan in place 4 Dig safe paper work in place 5 Crane lift plan in place a Crane placement b Crane swing c Crane load evaluation 6 Fall protection plan in place and staff trained 7 Confined entry plan in place and staff trained:
Excavation safety plan in place: Off
Dust control plan in place: Off
Pollution prevention plan in place: Off
Dig safe paper work in place: Off
Crane lift plan in place: Off
Fall protection plan in place and staff trained: Off
undefined: Off
terminal units and controls requiring lifting and support of equipment and systems:
Area:
Point of Contact POC:
POC Contact Information:
Activity Area:
New BuildArea Above:
Abigail Campbell FMSArea Above:
2076238411Area Above:
UpcomingArea Above:
New BuildArea Below:
Abigail Campbell FMSArea Below:
2076238411Area Below:
UpcomingArea Below:
New BuildAdjacent Area 1:
Abigail Campbell FMSAdjacent Area 1:
2076238411Adjacent Area 1:
UpcomingAdjacent Area 1:
New BuildAdjacent Area 2:
Abigail Campbell FMSAdjacent Area 2:
2076238411Adjacent Area 2:
UpcomingAdjacent Area 2:
New BuildAdjacent Area 3:
Abigail Campbell FMSAdjacent Area 3:
2076238411Adjacent Area 3:
UpcomingAdjacent Area 3:
New BuildAdjacent Area 4:
Abigail Campbell FMSAdjacent Area 4:
2076238411Adjacent Area 4:
UpcomingAdjacent Area 4:
No: On
Unique permit number:
Project manager:
Abigail Campbell:
Contact phone number:
2076238411:
TBD:
1 Excavation safety plan in place: Off
3 Pollution prevention plan in place: Off
4 Dig safe paperwork in place: Off
5 Crane lift plan in place: Off
6 Fall protection plan in place and staff trained: Off
7 Confined entry plan in place and staff trained: Off
No_2: Off
2024-03-04T11:55:45-0500
VIRGILEA HAMM
2024-03-01T14:49:40-0500
ABIGAIL CAMPBELL
2024-03-01T14:27:43-0500
GEORGE PORTER
2024-03-01T14:28:02-0500
GEORGE PORTER

File details come from the government source that posted it. Updated .