S02 - SOW - Att 13 - Const Sch - 02132026 - EHRM Infra Upgrades - Constr Togus.pdf
PDF 882 KB Posted
- Attached to
- Electronic Health Record Modernization Infrastructure Upgrades - Construction - Togus, ME
- Solicitation number
- 36C77626R0062
About this file
This is a project schedule (Gantt chart) for the Togus EHRM (Electronic Health Records Management) Construction project, reissued December 22, 2025. The project runs for 523 working days (730 calendar days) from February 2, 2026, to February 2, 2028. The schedule encompasses a comprehensive Electronic Health Records system implementation at the Togus Veterans Medical Center, involving construction of a new Main Computer Room (MCR), site and utility work, and renovation of multiple technology rooms across multiple buildings.
The project is organized into major phases including submittal and procurement (60 days for materials and equipment with lead times ranging from 30 to 120 days for long-lead items such as UPS systems, CRAC units, electrical panels, and fiber optic cabling); site and utility work (80 days starting July 2026); construction of a new MCR (395 days from April 2026 to October 2027); and sequential renovation of 21 technology rooms (TRs) across Buildings 200/200E, 202, 204, 205, 206, 207, 208, 209, 210, 211, 212, 221, 323, 239, 203, 240, 248, and 255, plus Building 300. Each technology room renovation follows a standardized sequence: ICRA (Infection Control Risk Assessment), abatement, demolition, new walls/floors/doors, CRAC installation, electrical and lighting, security, fire suppression, telecom infrastructure, cabling, testing, DDC (Direct Digital Control), and punch-list closeout. The project concludes with closeout activities, operations and maintenance documentation, as-builts, training, and warranty tasks scheduled for January 31 through February 2, 2028.
View the file
Other files
Show 40 more
Latest 50 of 57 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish Predecessors
1 Togus EHRM Construction - NTP 2/3/2026 (523 Working Days, 730 Calendar Days)
523 days Mon 2/2/26 Wed 2/2/28
2 Submittals for Materials & Equipment 60 days Mon 2/2/26 Fri 4/24/26
3 Submittal Process 60 days Mon 2/2/26 Fri 4/24/26
4 Lead-Time Long-Lead Materials & Equipment 120 days Mon 4/27/26 Fri 10/9/26 3
5 Lead Time - Light Gauge Steel 30 days Mon 4/27/26 Fri 6/5/26 3
6 Lead Time - MCR Flooring 60 days Mon 4/27/26 Fri 7/17/26 3
7 Lead Time - UPS 120 days Mon 4/27/26 Fri 10/9/26 3
8 Lead Time - Fire Protection Equipment 60 days Mon 4/27/26 Fri 7/17/26 3
9 Lead Time - Data Cable & Fiber 60 days Mon 4/27/26 Fri 7/17/26 3
10 Lead Time - Electrical Panels, Electrical Wire and Cabling 60 days Mon 4/27/26 Fri 7/17/26 3
11 Lead Time - CRAC and compressors 120 days Mon 4/27/26 Fri 10/9/26 3
12 Lead Time - Architectural - Doors & Hardware 60 days Mon 4/27/26 Fri 7/17/26 3
13 Site and Utility Work 80 days Mon 7/20/26 Fri 11/6/26
14 Trenching for New Exterior Fiber Runs 10 days Mon 7/20/26 Fri 7/31/26 9
15 Install New Ductbanks 15 days Mon 8/3/26 Fri 8/21/26 14
16 Install New Exterior Fiber Loops 10 days Mon 8/24/26 Fri 9/4/26 15
17 Install Exterior Electrical 30 days Mon 7/20/26 Fri 8/28/26 10
18 Patch Asphalt 5 days Mon 8/24/26 Fri 8/28/26 16SS
19 Patch Concrete 5 days Mon 8/24/26 Fri 8/28/26 16SS
20 Restore Landscaping 10 days Mon 9/7/26 Fri 9/18/26 16
21 Housekeeping pads 5 days Mon 7/20/26 Fri 7/24/26 17SS
22 Install Condensing Units 5 days Mon 10/12/26 Fri 10/16/26 11,21
23 Install CRAC piping to TRs 20 days Mon 10/12/26 Fri 11/6/26 22SS
24 New Main Computer Room (MCR) 395 days Mon 4/27/26 Fri 10/29/27
25 Survey and Layout 5 days Mon 4/27/26 Fri 5/1/26 3
26 Erosion Control 4 days Mon 5/4/26 Thu 5/7/26 25
27 Clear and Grub 5 days Fri 5/8/26 Thu 5/14/26 26
28 Excavation, Rock Removal 30 days Fri 5/15/26 Thu 6/25/26 27
29 Retaining Wall Earthwork 7 days Fri 6/26/26 Mon 7/6/26 28
30 Retaining Wall Formwork 5 days Tue 7/7/26 Mon 7/13/26 29
31 Pour Retaining Wall 5 days Tue 7/14/26 Mon 7/20/26 30
32 Underground Utilities, Stub Out 20 days Tue 7/21/26 Mon 8/17/26 31
33 Subgrade Preparation 8 days Tue 8/18/26 Thu 8/27/26 32
34 Foundation Formwork 14 days Fri 8/28/26 Wed 9/16/26 33
35 Pour Foundation 7 days Thu 9/17/26 Fri 9/25/26 34
36 Slab On Grade Preparation 11 days Mon 9/28/26 Mon 10/12/26 35
37 Pour Slab on Grade 3 days Tue 10/13/26 Thu 10/15/26 36
38 Structural Steel 40 days Fri 10/16/26 Thu 12/10/26 37
39 New Exterior Walls 40 days Fri 12/11/26 Thu 2/4/27 38
40 Roof 15 days Fri 2/5/27 Thu 2/25/27 38,39
41 New interior walls, floors, doors 40 days Fri 2/26/27 Thu 4/22/27 40
42 Install Electrical Panels 20 days Fri 4/23/27 Thu 5/20/27 41
43 Install Power Distribution 10 days Fri 5/21/27 Thu 6/3/27 10,42
44 Install UPS Units 10 days Fri 6/4/27 Thu 6/17/27 7,43
45 Test UPS Units 5 days Fri 6/18/27 Thu 6/24/27 44
46 Install Lighting 5 days Fri 6/4/27 Thu 6/10/27 10,43
47 Install CRAC Units 14 days Fri 5/21/27 Wed 6/9/27 41,42,11
48 Security 5 days Fri 5/21/27 Thu 5/27/27 41,42
49 Fire suppression, FEC 21 days Fri 4/23/27 Fri 5/21/27 41
50 Telecom racks and switches 40 days Fri 5/21/27 Thu 7/15/27 41,42
51 Cable Tray and raceways 16 days Fri 7/16/27 Fri 8/6/27 50,9
52 New Data Drops 5 days Mon 8/9/27 Fri 8/13/27 51
53 Land Data Cabling On Switches 7 days Mon 8/16/27 Tue 8/24/27 52
54 Test New Data Cabling and Outlets 3 days Wed 8/25/27 Fri 8/27/27 53
55 DDC 1 day Mon 8/30/27 Mon 8/30/27 47,48,49,53,54
56 Migrate MCR 30 days Tue 8/31/27 Mon 10/11/27 55
57 Clean and punch 14 days Tue 10/12/27 Fri 10/29/27 56
58 Building 200/200E - TR#7A 65 days Mon 7/20/26 Fri 10/16/26
59 ICRA 2 days Mon 7/20/26 Tue 7/21/26 12,5
60 Abatement 3 days Wed 7/22/26 Fri 7/24/26 59
61 Demolition 3 days Mon 7/27/26 Wed 7/29/26 60
62 New walls, floors, doors 5 days Thu 7/30/26 Wed 8/5/26 12,61,5
63 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 62,11
64 Electrical and Lighting 5 days Thu 8/6/26 Wed 8/12/26 62,10
65 Security 5 days Thu 8/6/26 Wed 8/12/26 62,10
66 Fire suppression, FEC 3 days Thu 8/6/26 Mon 8/10/26 62,8
67 Telecom racks and switches 3 days Thu 8/6/26 Mon 8/10/26 62,9
68 Cable Tray and raceways 3 days Tue 8/11/26 Thu 8/13/26 67
69 New cable from outlets to TRs 5 days Fri 8/14/26 Thu 8/20/26 68
70 New outlet connections 3 days Fri 8/21/26 Tue 8/25/26 69
71 Land cable on switches 2 days Wed 8/26/26 Thu 8/27/26 70
72 Test new telecom outlets / system 2 days Fri 8/28/26 Mon 8/31/26 71
73 DDC 1 day Tue 9/1/26 Tue 9/1/26 72
74 Demo old cable 3 days Tue 9/1/26 Thu 9/3/26 72
75 Clean and punch 3 days Fri 9/4/26 Tue 9/8/26 74
76 Building 200/200E - TR#7B 37 days Wed 9/9/26 Thu 10/29/26
77 ICRA 2 days Wed 9/9/26 Thu 9/10/26 75
78 Abatement 3 days Fri 9/11/26 Tue 9/15/26 77
79 Demolition 3 days Wed 9/16/26 Fri 9/18/26 78
80 New walls, floors, doors 5 days Mon 9/21/26 Fri 9/25/26 12,5,79
81 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 80,11
82 Electrical and Lighting 5 days Mon 9/28/26 Fri 10/2/26 80,10
83 Security 5 days Mon 9/28/26 Fri 10/2/26 80,10
84 Fire suppression, FEC 3 days Mon 9/28/26 Wed 9/30/26 80,8
85 Telecom racks and switches 3 days Mon 9/28/26 Wed 9/30/26 80,9
86 Cable Tray and raceways 3 days Thu 10/1/26 Mon 10/5/26 85
87 New cable from outlets to TRs 5 days Tue 10/6/26 Mon 10/12/26 86
88 New outlet connections 3 days Tue 10/13/26 Thu 10/15/26 87
89 Land cable on switches 2 days Fri 10/16/26 Mon 10/19/26 88
90 Test new telecom outlets / system 2 days Tue 10/20/26 Wed 10/21/26 89
91 DDC 1 day Thu 10/22/26 Thu 10/22/26 90
92 Demo old cable 3 days Thu 10/22/26 Mon 10/26/26 90
93 Clean and punch 3 days Tue 10/27/26 Thu 10/29/26 92
94 Building 200/200E - TR#8A 37 days Fri 10/30/26 Mon 12/21/26
95 ICRA 2 days Fri 10/30/26 Mon 11/2/26 93
96 Abatement 3 days Tue 11/3/26 Thu 11/5/26 95
97 Demolition 3 days Fri 11/6/26 Tue 11/10/26 96
98 New walls, floors, doors 5 days Wed 11/11/26 Tue 11/17/26 12,97,5
99 Install CRAC 5 days Wed 11/18/26 Tue 11/24/26 98,11
100 Electrical and Lighting 5 days Wed 11/18/26 Tue 11/24/26 98,10
101 Security 5 days Wed 11/18/26 Tue 11/24/26 98,10
102 Fire suppression, FEC 3 days Wed 11/18/26 Fri 11/20/26 98,8
103 Telecom racks and switches 3 days Wed 11/18/26 Fri 11/20/26 98,9
104 Cable Tray and raceways 3 days Mon 11/23/26 Wed 11/25/26 103
105 New cable from outlets to TRs 5 days Thu 11/26/26 Wed 12/2/26 104
106 New outlet connections 3 days Thu 12/3/26 Mon 12/7/26 105
107 Land cable on switches 2 days Tue 12/8/26 Wed 12/9/26 106
108 Test new telecom outlets / system 2 days Thu 12/10/26 Fri 12/11/26 107
109 DDC 1 day Mon 12/14/26 Mon 12/14/26 108
110 Demo old cable 3 days Mon 12/14/26 Wed 12/16/26 108
111 Clean and punch 3 days Thu 12/17/26 Mon 12/21/26 110
112 Building 200/200E - TR#9A 37 days Tue 12/22/26 Wed 2/10/27
113 ICRA 2 days Tue 12/22/26 Wed 12/23/26 111
114 Abatement 3 days Thu 12/24/26 Mon 12/28/26 113
115 Demolition 3 days Tue 12/29/26 Thu 12/31/26 114
116 New walls, floors, doors 5 days Fri 1/1/27 Thu 1/7/27 12,115,5
117 Install CRAC 5 days Fri 1/8/27 Thu 1/14/27 116,11
118 Electrical and Lighting 5 days Fri 1/8/27 Thu 1/14/27 116,10
119 Security 5 days Fri 1/8/27 Thu 1/14/27 116,10
120 Fire suppression, FEC 3 days Fri 1/8/27 Tue 1/12/27 116,8
121 Telecom racks and switches 3 days Fri 1/8/27 Tue 1/12/27 116,9
122 Cable Tray and raceways 3 days Wed 1/13/27 Fri 1/15/27 121
123 New cable from outlets to TRs 5 days Mon 1/18/27 Fri 1/22/27 122
124 New outlet connections 3 days Mon 1/25/27 Wed 1/27/27 123
125 Land cable on switches 2 days Thu 1/28/27 Fri 1/29/27 124
126 Test new telecom outlets / system 2 days Mon 2/1/27 Tue 2/2/27 125
127 DDC 1 day Wed 2/3/27 Wed 2/3/27 126
128 Demo old cable 3 days Wed 2/3/27 Fri 2/5/27 126
129 Clean and punch 3 days Mon 2/8/27 Wed 2/10/27 128
130 Building 200/200E - TR#9B 37 days Thu 2/11/27 Fri 4/2/27
131 ICRA 2 days Thu 2/11/27 Fri 2/12/27 129
132 Abatement 3 days Mon 2/15/27 Wed 2/17/27 131
133 Demolition 3 days Thu 2/18/27 Mon 2/22/27 132
134 New walls, floors, doors 5 days Tue 2/23/27 Mon 3/1/27 12,133,5
135 Install CRAC 5 days Tue 3/2/27 Mon 3/8/27 134,11
136 Electrical and Lighting 5 days Tue 3/2/27 Mon 3/8/27 134,10
137 Security 5 days Tue 3/2/27 Mon 3/8/27 134,10
138 Fire suppression, FEC 3 days Tue 3/2/27 Thu 3/4/27 134,8
139 Telecom racks and switches 3 days Tue 3/2/27 Thu 3/4/27 134,9
140 Cable Tray and raceways 3 days Fri 3/5/27 Tue 3/9/27 139
141 New cable from outlets to TRs 5 days Wed 3/10/27 Tue 3/16/27 140
142 New outlet connections 3 days Wed 3/17/27 Fri 3/19/27 141
143 Land cable on switches 2 days Mon 3/22/27 Tue 3/23/27 142
144 Test new telecom outlets / system 2 days Wed 3/24/27 Thu 3/25/27 143
Togus EHRM Construction - NTP 2/3/2026 (523 Working Days, 730 Calendar Days)
Submittals for Materials & Equipment
Submittal Process
Lead-Time Long-Lead Materials & Equipment
Lead Time - Light Gauge Steel
Lead Time - MCR Flooring
Lead Time - UPS
Lead Time - Fire Protection Equipment
Lead Time - Data Cable & Fiber
Lead Time - Electrical Panels, Electrical Wire and Cabling
Lead Time - CRAC and compressors
Lead Time - Architectural - Doors & Hardware
Site and Utility Work
Trenching for New Exterior Fiber Runs
Install New Ductbanks
Install New Exterior Fiber Loops
Install Exterior Electrical
Patch Asphalt
Patch Concrete
Restore Landscaping
Housekeeping pads
Install Condensing Units
Install CRAC piping to TRs
New Main Computer Room (MCR)
Survey and Layout
Erosion Control
Clear and Grub
Excavation, Rock Removal
Retaining Wall Earthwork
Retaining Wall Formwork
Pour Retaining Wall
Underground Utilities, Stub Out
Subgrade Preparation
Foundation Formwork
Pour Foundation
Slab On Grade Preparation
Pour Slab on Grade
Structural Steel
New Exterior Walls
Roof
New interior walls, floors, doors
Install Electrical Panels
Install Power Distribution
Install UPS Units
Test UPS Units
Install Lighting
Install CRAC Units
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New Data Drops
Land Data Cabling On Switches
Test New Data Cabling and Outlets
DDC
Migrate MCR
Clean and punch
Building 200/200E - TR#7A
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 200/200E - TR#7B
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 200/200E - TR#8A
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 200/200E - TR#9A
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 200/200E - TR#9B
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
J F M A M J J A S O N D J F M A M J J A S O N D J F Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028
Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress
Togus EHRM Reissued 12-22-2025
145 DDC 1 day Fri 3/26/27 Fri 3/26/27 144
146 Demo old cable 3 days Fri 3/26/27 Tue 3/30/27 144
147 Clean and punch 3 days Wed 3/31/27 Fri 4/2/27 146
148 Building 200/200E - TR#10A 37 days Mon 4/5/27 Tue 5/25/27
149 ICRA 2 days Mon 4/5/27 Tue 4/6/27 12,130,5
150 Abatement 3 days Wed 4/7/27 Fri 4/9/27 149
151 Demolition 3 days Mon 4/12/27 Wed 4/14/27 150
152 New walls, floors, doors 5 days Thu 4/15/27 Wed 4/21/27 12,151,5
153 Install CRAC 5 days Thu 4/22/27 Wed 4/28/27 152,11
154 Electrical and Lighting 5 days Thu 4/22/27 Wed 4/28/27 152,10
155 Security 5 days Thu 4/22/27 Wed 4/28/27 152,10
156 Fire suppression, FEC 3 days Thu 4/22/27 Mon 4/26/27 152,8
157 Telecom racks and switches 3 days Thu 4/22/27 Mon 4/26/27 152,9
158 Cable Tray and raceways 3 days Tue 4/27/27 Thu 4/29/27 157
159 New cable from outlets to TRs 5 days Fri 4/30/27 Thu 5/6/27 158
160 New outlet connections 3 days Fri 5/7/27 Tue 5/11/27 159
161 Land cable on switches 2 days Wed 5/12/27 Thu 5/13/27 160
162 Test new telecom outlets / system 2 days Fri 5/14/27 Mon 5/17/27 161
163 DDC 1 day Tue 5/18/27 Tue 5/18/27 162
164 Demo old cable 3 days Tue 5/18/27 Thu 5/20/27 162
165 Clean and punch 3 days Fri 5/21/27 Tue 5/25/27 164
166 Building 200/200E - TR#10B 37 days Wed 5/26/27 Thu 7/15/27
167 ICRA 2 days Wed 5/26/27 Thu 5/27/27 165
168 Abatement 3 days Fri 5/28/27 Tue 6/1/27 167
169 Demolition 3 days Wed 6/2/27 Fri 6/4/27 168
170 New walls, floors, doors 5 days Mon 6/7/27 Fri 6/11/27 12,169,5
171 Install CRAC 5 days Mon 6/14/27 Fri 6/18/27 170,11
172 Electrical and Lighting 5 days Mon 6/14/27 Fri 6/18/27 170,10
173 Security 5 days Mon 6/14/27 Fri 6/18/27 170,10
174 Fire suppression, FEC 3 days Mon 6/14/27 Wed 6/16/27 170,8
175 Telecom racks and switches 3 days Mon 6/14/27 Wed 6/16/27 170,9
176 Cable Tray and raceways 3 days Thu 6/17/27 Mon 6/21/27 175
177 New cable from outlets to TRs 5 days Tue 6/22/27 Mon 6/28/27 176
178 New outlet connections 3 days Tue 6/29/27 Thu 7/1/27 177
179 Land cable on switches 2 days Fri 7/2/27 Mon 7/5/27 178
180 Test new telecom outlets / system 2 days Tue 7/6/27 Wed 7/7/27 179
181 DDC 1 day Thu 7/8/27 Thu 7/8/27 180
182 Demo old cable 3 days Thu 7/8/27 Mon 7/12/27 180
183 Clean and punch 3 days Tue 7/13/27 Thu 7/15/27 182
184 Building 200/200E - TR#11 37 days Fri 7/16/27 Mon 9/6/27
185 ICRA 2 days Fri 7/16/27 Mon 7/19/27 183
186 Abatement 3 days Tue 7/20/27 Thu 7/22/27 185
187 Demolition 3 days Fri 7/23/27 Tue 7/27/27 186
188 New walls, floors, doors 5 days Wed 7/28/27 Tue 8/3/27 12,187,5
189 Install CRAC 5 days Wed 8/4/27 Tue 8/10/27 188,11
190 Electrical and Lighting 5 days Wed 8/4/27 Tue 8/10/27 188,10
191 Security 5 days Wed 8/4/27 Tue 8/10/27 188,10
192 Fire suppression, FEC 3 days Wed 8/4/27 Fri 8/6/27 188,8
193 Telecom racks and switches 3 days Wed 8/4/27 Fri 8/6/27 188,9
194 Cable Tray and raceways 3 days Mon 8/9/27 Wed 8/11/27 193
195 New cable from outlets to TRs 5 days Thu 8/12/27 Wed 8/18/27 194
196 New outlet connections 3 days Thu 8/19/27 Mon 8/23/27 195
197 Land cable on switches 2 days Tue 8/24/27 Wed 8/25/27 196
198 Test new telecom outlets / system 2 days Thu 8/26/27 Fri 8/27/27 197
199 DDC 1 day Mon 8/30/27 Mon 8/30/27 198
200 Demo old cable 3 days Mon 8/30/27 Wed 9/1/27 198
201 Clean and punch 3 days Thu 9/2/27 Mon 9/6/27 200
202 Building 200/200E - TR#12 37 days Tue 9/7/27 Wed 10/27/27
203 ICRA 2 days Tue 9/7/27 Wed 9/8/27 201
204 Abatement 3 days Thu 9/9/27 Mon 9/13/27 203
205 Demolition 3 days Tue 9/14/27 Thu 9/16/27 204
206 New walls, floors, doors 5 days Fri 9/17/27 Thu 9/23/27 12,205,5
207 Install CRAC 5 days Fri 9/24/27 Thu 9/30/27 206,11
208 Electrical and Lighting 5 days Fri 9/24/27 Thu 9/30/27 206,10
209 Security 5 days Fri 9/24/27 Thu 9/30/27 206,10
210 Fire suppression, FEC 3 days Fri 9/24/27 Tue 9/28/27 206,8
211 Telecom racks and switches 3 days Fri 9/24/27 Tue 9/28/27 206,9
212 Cable Tray and raceways 3 days Wed 9/29/27 Fri 10/1/27 211
213 New cable from outlets to TRs 5 days Mon 10/4/27 Fri 10/8/27 212
214 New outlet connections 3 days Mon 10/11/27 Wed 10/13/27 213
215 Land cable on switches 2 days Thu 10/14/27 Fri 10/15/27 214
216 Test new telecom outlets / system 2 days Mon 10/18/27 Tue 10/19/27 215
217 DDC 1 day Wed 10/20/27 Wed 10/20/27 216
218 Demo old cable 3 days Wed 10/20/27 Fri 10/22/27 216
219 Clean and punch 3 days Mon 10/25/27 Wed 10/27/27 218
220 Building 200/200E - TR#13 65 days Mon 7/20/26 Fri 10/16/26
221 ICRA 2 days Mon 7/20/26 Tue 7/21/26 12,5
222 Abatement 3 days Wed 7/22/26 Fri 7/24/26 221
223 Demolition 3 days Mon 7/27/26 Wed 7/29/26 222
224 New walls, floors, doors 5 days Thu 7/30/26 Wed 8/5/26 12,223,5
225 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 224,11
226 Electrical and Lighting 5 days Thu 8/6/26 Wed 8/12/26 224,10
227 Security 5 days Thu 8/6/26 Wed 8/12/26 224,10
228 Fire suppression, FEC 3 days Thu 8/6/26 Mon 8/10/26 224,8
229 Telecom racks and switches 3 days Thu 8/6/26 Mon 8/10/26 224,9
230 Cable Tray and raceways 3 days Tue 8/11/26 Thu 8/13/26 229
231 New cable from outlets to TRs 5 days Fri 8/14/26 Thu 8/20/26 230
232 New outlet connections 3 days Fri 8/21/26 Tue 8/25/26 231
233 Land cable on switches 2 days Wed 8/26/26 Thu 8/27/26 232
234 Test new telecom outlets / system 2 days Fri 8/28/26 Mon 8/31/26 233
235 DDC 1 day Tue 9/1/26 Tue 9/1/26 234
236 Demo old cable 3 days Tue 9/1/26 Thu 9/3/26 234
237 Clean and punch 3 days Fri 9/4/26 Tue 9/8/26 236
238 Building 202 - TR#207E 37 days Wed 9/9/26 Thu 10/29/26
239 ICRA 2 days Wed 9/9/26 Thu 9/10/26 237
240 Abatement 3 days Fri 9/11/26 Tue 9/15/26 239
241 Demolition 3 days Wed 9/16/26 Fri 9/18/26 240
242 New walls, floors, doors 5 days Mon 9/21/26 Fri 9/25/26 12,241,5
243 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 242,11
244 Electrical and Lighting 5 days Mon 9/28/26 Fri 10/2/26 242,10
245 Security 5 days Mon 9/28/26 Fri 10/2/26 242,10
246 Fire suppression, FEC 3 days Mon 9/28/26 Wed 9/30/26 242,8
247 Telecom racks and switches 3 days Mon 9/28/26 Wed 9/30/26 242,9
248 Cable Tray and raceways 3 days Thu 10/1/26 Mon 10/5/26 247
249 New cable from outlets to TRs 5 days Tue 10/6/26 Mon 10/12/26 248
250 New outlet connections 3 days Tue 10/13/26 Thu 10/15/26 249
251 Land cable on switches 2 days Fri 10/16/26 Mon 10/19/26 250
252 Test new telecom outlets / system 2 days Tue 10/20/26 Wed 10/21/26 251
253 DDC 1 day Thu 10/22/26 Thu 10/22/26 252
254 Demo old cable 3 days Thu 10/22/26 Mon 10/26/26 252
255 Clean and punch 3 days Tue 10/27/26 Thu 10/29/26 254
256 Building 204 - TR#19 37 days Fri 10/30/26 Mon 12/21/26
257 ICRA 2 days Fri 10/30/26 Mon 11/2/26 255
258 Abatement 3 days Tue 11/3/26 Thu 11/5/26 257
259 Demolition 3 days Fri 11/6/26 Tue 11/10/26 258
260 New walls, floors, doors 5 days Wed 11/11/26 Tue 11/17/26 12,259,5
261 Install CRAC 5 days Wed 11/18/26 Tue 11/24/26 260,11
262 Electrical and Lighting 5 days Wed 11/18/26 Tue 11/24/26 260,10
263 Security 5 days Wed 11/18/26 Tue 11/24/26 260,10
264 Fire suppression, FEC 3 days Wed 11/18/26 Fri 11/20/26 260,8
265 Telecom racks and switches 3 days Wed 11/18/26 Fri 11/20/26 260,9
266 Cable Tray and raceways 3 days Mon 11/23/26 Wed 11/25/26 265
267 New cable from outlets to TRs 5 days Thu 11/26/26 Wed 12/2/26 266
268 New outlet connections 3 days Thu 12/3/26 Mon 12/7/26 267
269 Land cable on switches 2 days Tue 12/8/26 Wed 12/9/26 268
270 Test new telecom outlets / system 2 days Thu 12/10/26 Fri 12/11/26 269
271 DDC 1 day Mon 12/14/26 Mon 12/14/26 270
272 Demo old cable 3 days Mon 12/14/26 Wed 12/16/26 270
273 Clean and punch 3 days Thu 12/17/26 Mon 12/21/26 272
274 Building 205 - TR#20 37 days Thu 12/17/26 Fri 2/5/27
275 ICRA 2 days Thu 12/17/26 Fri 12/18/26 272
276 Abatement 3 days Mon 12/21/26 Wed 12/23/26 275
277 Demolition 3 days Thu 12/24/26 Mon 12/28/26 276
278 New walls, floors, doors 5 days Tue 12/29/26 Mon 1/4/27 12,5,277
279 Install CRAC 5 days Tue 1/5/27 Mon 1/11/27 278,11
280 Electrical and Lighting 5 days Tue 1/5/27 Mon 1/11/27 278,10
281 Security 5 days Tue 1/5/27 Mon 1/11/27 278,10
282 Fire suppression, FEC 3 days Tue 1/5/27 Thu 1/7/27 278,8
283 Telecom racks and switches 3 days Tue 1/5/27 Thu 1/7/27 278,9
284 Cable Tray and raceways 3 days Fri 1/8/27 Tue 1/12/27 283
285 New cable from outlets to TRs 5 days Wed 1/13/27 Tue 1/19/27 284
286 New outlet connections 3 days Wed 1/20/27 Fri 1/22/27 285
287 Land cable on switches 2 days Mon 1/25/27 Tue 1/26/27 286
288 Test new telecom outlets / system 2 days Wed 1/27/27 Thu 1/28/27 287
289 DDC 1 day Fri 1/29/27 Fri 1/29/27 288
DDC
Demo old cable
Clean and punch
Building 200/200E - TR#10A
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 200/200E - TR#10B
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 200/200E - TR#11
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 200/200E - TR#12
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 200/200E - TR#13
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 202 - TR#207E
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 204 - TR#19
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 205 - TR#20
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
J F M A M J J A S O N D J F M A M J J A S O N D J F Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028
Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress
290 Demo old cable 3 days Fri 1/29/27 Tue 2/2/27 288
291 Clean and punch 3 days Wed 2/3/27 Fri 2/5/27 290
292 Building 205 - TR#21 37 days Mon 2/8/27 Tue 3/30/27
293 ICRA 2 days Mon 2/8/27 Tue 2/9/27 291
294 Abatement 3 days Wed 2/10/27 Fri 2/12/27 293
295 Demolition 3 days Mon 2/15/27 Wed 2/17/27 294
296 New walls, floors, doors 5 days Thu 2/18/27 Wed 2/24/27 12,5,295
297 Install CRAC 5 days Thu 2/25/27 Wed 3/3/27 296,11
298 Electrical and Lighting 5 days Thu 2/25/27 Wed 3/3/27 296,10
299 Security 5 days Thu 2/25/27 Wed 3/3/27 296,10
300 Fire suppression, FEC 3 days Thu 2/25/27 Mon 3/1/27 296,8
301 Telecom racks and switches 3 days Thu 2/25/27 Mon 3/1/27 296,9
302 Cable Tray and raceways 3 days Tue 3/2/27 Thu 3/4/27 301
303 New cable from outlets to TRs 5 days Fri 3/5/27 Thu 3/11/27 302
304 New outlet connections 3 days Fri 3/12/27 Tue 3/16/27 303
305 Land cable on switches 2 days Wed 3/17/27 Thu 3/18/27 304
306 Test new telecom outlets / system 2 days Fri 3/19/27 Mon 3/22/27 305
307 DDC 1 day Tue 3/23/27 Tue 3/23/27 306
308 Demo old cable 3 days Tue 3/23/27 Thu 3/25/27 306
309 Clean and punch 3 days Fri 3/26/27 Tue 3/30/27 308
310 Building 205 - TR#22 37 days Wed 3/31/27 Thu 5/20/27
311 ICRA 2 days Wed 3/31/27 Thu 4/1/27 309
312 Abatement 3 days Fri 4/2/27 Tue 4/6/27 311
313 Demolition 3 days Wed 4/7/27 Fri 4/9/27 312
314 New walls, floors, doors 5 days Mon 4/12/27 Fri 4/16/27 12,313,5
315 Install CRAC 5 days Mon 4/19/27 Fri 4/23/27 314,11
316 Electrical and Lighting 5 days Mon 4/19/27 Fri 4/23/27 314,10
317 Security 5 days Mon 4/19/27 Fri 4/23/27 314,10
318 Fire suppression, FEC 3 days Mon 4/19/27 Wed 4/21/27 314,8
319 Telecom racks and switches 3 days Mon 4/19/27 Wed 4/21/27 314,9
320 Cable Tray and raceways 3 days Thu 4/22/27 Mon 4/26/27 319
321 New cable from outlets to TRs 5 days Tue 4/27/27 Mon 5/3/27 320
322 New outlet connections 3 days Tue 5/4/27 Thu 5/6/27 321
323 Land cable on switches 2 days Fri 5/7/27 Mon 5/10/27 322
324 Test new telecom outlets / system 2 days Tue 5/11/27 Wed 5/12/27 323
325 DDC 1 day Thu 5/13/27 Thu 5/13/27 324
326 Demo old cable 3 days Thu 5/13/27 Mon 5/17/27 324
327 Clean and punch 3 days Tue 5/18/27 Thu 5/20/27 326
328 Building 206 - TR#23 400 days Mon 7/20/26 Fri 1/28/28
329 ICRA 2 days Fri 5/21/27 Mon 5/24/27 327
330 Abatement 3 days Tue 5/25/27 Thu 5/27/27 329
331 Demolition 3 days Fri 5/28/27 Tue 6/1/27 330
332 New walls, floors, doors 5 days Wed 6/2/27 Tue 6/8/27 12,5,331
333 Install CRAC 5 days Wed 6/9/27 Tue 6/15/27 332,11
334 Electrical and Lighting 5 days Wed 6/9/27 Tue 6/15/27 332,10
335 Security 5 days Wed 6/9/27 Tue 6/15/27 332,10
336 Fire suppression, FEC 3 days Wed 6/9/27 Fri 6/11/27 332,8
337 Telecom racks and switches 3 days Wed 6/9/27 Fri 6/11/27 332,9
338 Cable Tray and raceways 3 days Mon 6/14/27 Wed 6/16/27 337
339 New cable from outlets to TRs 5 days Thu 6/17/27 Wed 6/23/27 338
340 New outlet connections 3 days Thu 6/24/27 Mon 6/28/27 339
341 Land cable on switches 2 days Tue 6/29/27 Wed 6/30/27 340
342 Test new telecom outlets / system 2 days Thu 7/1/27 Fri 7/2/27 341
343 DDC 1 day Mon 7/5/27 Mon 7/5/27 342
344 Demo old cable 3 days Mon 7/5/27 Wed 7/7/27 342
345 Clean and punch 3 days Thu 7/8/27 Mon 7/12/27 344
346 Building 206 - TR#24 400 days Mon 7/20/26 Fri 1/28/28
347 ICRA 2 days Tue 7/13/27 Wed 7/14/27 345
348 Abatement 3 days Thu 7/15/27 Mon 7/19/27 347
349 Demolition 3 days Tue 7/20/27 Thu 7/22/27 348
350 New walls, floors, doors 5 days Fri 7/23/27 Thu 7/29/27 349,12,5
351 Install CRAC 5 days Fri 7/30/27 Thu 8/5/27 350,11
352 Electrical and Lighting 5 days Fri 7/30/27 Thu 8/5/27 350,10
353 Security 5 days Fri 7/30/27 Thu 8/5/27 350,10
354 Fire suppression, FEC 3 days Fri 7/30/27 Tue 8/3/27 350,8
355 Telecom racks and switches 3 days Fri 7/30/27 Tue 8/3/27 350,9
356 Cable Tray and raceways 3 days Wed 8/4/27 Fri 8/6/27 355
357 New cable from outlets to TRs 5 days Mon 8/9/27 Fri 8/13/27 356
358 New outlet connections 3 days Mon 8/16/27 Wed 8/18/27 357
359 Land cable on switches 2 days Thu 8/19/27 Fri 8/20/27 358
360 Test new telecom outlets / system 2 days Mon 8/23/27 Tue 8/24/27 359
361 DDC 1 day Wed 8/25/27 Wed 8/25/27 360
362 Demo old cable 3 days Wed 8/25/27 Fri 8/27/27 360
363 Clean and punch 3 days Mon 8/30/27 Wed 9/1/27 362
364 Building 206 - TR#25 400 days Mon 7/20/26 Fri 1/28/28
365 ICRA 2 days Thu 9/2/27 Fri 9/3/27 363
366 Abatement 3 days Mon 9/6/27 Wed 9/8/27 365
367 Demolition 3 days Thu 9/9/27 Mon 9/13/27 366
368 New walls, floors, doors 5 days Tue 9/14/27 Mon 9/20/27 367,12,5
369 Install CRAC 5 days Tue 9/21/27 Mon 9/27/27 368,11
370 Electrical and Lighting 5 days Tue 9/21/27 Mon 9/27/27 368,10
371 Security 5 days Tue 9/21/27 Mon 9/27/27 368,10
372 Fire suppression, FEC 3 days Tue 9/21/27 Thu 9/23/27 368,8
373 Telecom racks and switches 3 days Tue 9/21/27 Thu 9/23/27 368,9
374 Cable Tray and raceways 3 days Fri 9/24/27 Tue 9/28/27 373
375 New cable from outlets to TRs 5 days Wed 9/29/27 Tue 10/5/27 374
376 New outlet connections 3 days Wed 10/6/27 Fri 10/8/27 375
377 Land cable on switches 2 days Mon 10/11/27 Tue 10/12/27 376
378 Test new telecom outlets / system 2 days Wed 10/13/27 Thu 10/14/27 377
379 DDC 1 day Fri 10/15/27 Fri 10/15/27 378
380 Demo old cable 3 days Fri 10/15/27 Tue 10/19/27 378
381 Clean and punch 3 days Wed 10/20/27 Fri 10/22/27 380
382 Building 207 - TR#26 400 days Mon 7/20/26 Fri 1/28/28
383 ICRA 2 days Mon 7/20/26 Tue 7/21/26 12,5
384 Abatement 3 days Wed 7/22/26 Fri 7/24/26 383
385 Demolition 3 days Mon 7/27/26 Wed 7/29/26 384
386 New walls, floors, doors 5 days Thu 7/30/26 Wed 8/5/26 385,12,5
387 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 386,11
388 Electrical and Lighting 5 days Thu 8/6/26 Wed 8/12/26 386,10
389 Security 5 days Thu 8/6/26 Wed 8/12/26 386,10
390 Fire suppression, FEC 3 days Thu 8/6/26 Mon 8/10/26 386,8
391 Telecom racks and switches 3 days Thu 8/6/26 Mon 8/10/26 386,9
392 Cable Tray and raceways 3 days Tue 8/11/26 Thu 8/13/26 391
393 New cable from outlets to TRs 5 days Fri 8/14/26 Thu 8/20/26 392
394 New outlet connections 3 days Fri 8/21/26 Tue 8/25/26 393
395 Land cable on switches 2 days Wed 8/26/26 Thu 8/27/26 394
396 Test new telecom outlets / system 2 days Fri 8/28/26 Mon 8/31/26 395
397 DDC 1 day Tue 9/1/26 Tue 9/1/26 396
398 Demo old cable 3 days Tue 9/1/26 Thu 9/3/26 396
399 Clean and punch 3 days Fri 9/4/26 Tue 9/8/26 398
400 Building 207 - TR#28 400 days Mon 7/20/26 Fri 1/28/28
401 ICRA 2 days Wed 9/9/26 Thu 9/10/26 399
402 Abatement 3 days Fri 9/11/26 Tue 9/15/26 401
403 Demolition 3 days Wed 9/16/26 Fri 9/18/26 402
404 New walls, floors, doors 5 days Mon 9/21/26 Fri 9/25/26 403,12,5
405 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 404,11
406 Electrical and Lighting 5 days Mon 9/28/26 Fri 10/2/26 404,10
407 Security 5 days Mon 9/28/26 Fri 10/2/26 404,10
408 Fire suppression, FEC 3 days Mon 9/28/26 Wed 9/30/26 404,8
409 Telecom racks and switches 3 days Mon 9/28/26 Wed 9/30/26 404,9
410 Cable Tray and raceways 3 days Thu 10/1/26 Mon 10/5/26 409
411 New cable from outlets to TRs 5 days Tue 10/6/26 Mon 10/12/26 410
412 New outlet connections 3 days Tue 10/13/26 Thu 10/15/26 411
413 Land cable on switches 2 days Fri 10/16/26 Mon 10/19/26 412
414 Test new telecom outlets / system 2 days Tue 10/20/26 Wed 10/21/26 413
415 DDC 1 day Thu 10/22/26 Thu 10/22/26 414
416 Demo old cable 3 days Thu 10/22/26 Mon 10/26/26 414
417 Clean and punch 3 days Tue 10/27/26 Thu 10/29/26 416
418 Building 208 - TR#29 400 days Mon 7/20/26 Fri 1/28/28
419 ICRA 2 days Fri 10/30/26 Mon 11/2/26 417
420 Abatement 3 days Tue 11/3/26 Thu 11/5/26 419
421 Demolition 3 days Fri 11/6/26 Tue 11/10/26 420
422 New walls, floors, doors 5 days Wed 11/11/26 Tue 11/17/26 421,12,5
423 Install CRAC 5 days Wed 11/18/26 Tue 11/24/26 422,11
424 Electrical and Lighting 5 days Wed 11/18/26 Tue 11/24/26 422,10
425 Security 5 days Wed 11/18/26 Tue 11/24/26 422,10
426 Fire suppression, FEC 3 days Wed 11/18/26 Fri 11/20/26 422,8
427 Telecom racks and switches 3 days Wed 11/18/26 Fri 11/20/26 422,9
428 Cable Tray and raceways 3 days Mon 11/23/26 Wed 11/25/26 427
429 New cable from outlets to TRs 5 days Thu 11/26/26 Wed 12/2/26 428
430 New outlet connections 3 days Thu 12/3/26 Mon 12/7/26 429
431 Land cable on switches 2 days Tue 12/8/26 Wed 12/9/26 430
432 Test new telecom outlets / system 2 days Thu 12/10/26 Fri 12/11/26 431
433 DDC 1 day Mon 12/14/26 Mon 12/14/26 432
434 Demo old cable 3 days Mon 12/14/26 Wed 12/16/26 432
Demo old cable
Clean and punch
Building 205 - TR#21
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 205 - TR#22
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 206 - TR#23
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 206 - TR#24
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 206 - TR#25
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 207 - TR#26
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 207 - TR#28
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 208 - TR#29
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
J F M A M J J A S O N D J F M A M J J A S O N D J F Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028
Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress
435 Clean and punch 3 days Thu 12/17/26 Mon 12/21/26 434
436 Building 209 - TR#30 400 days Mon 7/20/26 Fri 1/28/28
437 ICRA 2 days Tue 12/22/26 Wed 12/23/26 435
438 Abatement 3 days Thu 12/24/26 Mon 12/28/26 437
439 Demolition 3 days Tue 12/29/26 Thu 12/31/26 438
440 New walls, floors, doors 5 days Fri 1/1/27 Thu 1/7/27 439,12,5
441 Install CRAC 5 days Fri 1/8/27 Thu 1/14/27 440,11
442 Electrical and Lighting 5 days Fri 1/8/27 Thu 1/14/27 440,10
443 Security 5 days Fri 1/8/27 Thu 1/14/27 440,10
444 Fire suppression, FEC 3 days Fri 1/8/27 Tue 1/12/27 440,8
445 Telecom racks and switches 3 days Fri 1/8/27 Tue 1/12/27 440,9
446 Cable Tray and raceways 3 days Wed 1/13/27 Fri 1/15/27 445
447 New cable from outlets to TRs 5 days Mon 1/18/27 Fri 1/22/27 446
448 New outlet connections 3 days Mon 1/25/27 Wed 1/27/27 447
449 Land cable on switches 2 days Thu 1/28/27 Fri 1/29/27 448
450 Test new telecom outlets / system 2 days Mon 2/1/27 Tue 2/2/27 449
451 DDC 1 day Wed 2/3/27 Wed 2/3/27 450
452 Demo old cable 3 days Wed 2/3/27 Fri 2/5/27 450
453 Clean and punch 3 days Mon 2/8/27 Wed 2/10/27 452
454 Building 209 - TR#31 400 days Mon 7/20/26 Fri 1/28/28
455 ICRA 2 days Thu 2/11/27 Fri 2/12/27 453
456 Abatement 3 days Mon 2/15/27 Wed 2/17/27 455
457 Demolition 3 days Thu 2/18/27 Mon 2/22/27 456
458 New walls, floors, doors 5 days Tue 2/23/27 Mon 3/1/27 457,12,5
459 Install CRAC 5 days Tue 3/2/27 Mon 3/8/27 458,11
460 Electrical and Lighting 5 days Tue 3/2/27 Mon 3/8/27 458,10
461 Security 5 days Tue 3/2/27 Mon 3/8/27 458,10
462 Fire suppression, FEC 3 days Tue 3/2/27 Thu 3/4/27 458,8
463 Telecom racks and switches 3 days Tue 3/2/27 Thu 3/4/27 458,9
464 Cable Tray and raceways 3 days Fri 3/5/27 Tue 3/9/27 463
465 New cable from outlets to TRs 5 days Wed 3/10/27 Tue 3/16/27 464
466 New outlet connections 3 days Wed 3/17/27 Fri 3/19/27 465
467 Land cable on switches 2 days Mon 3/22/27 Tue 3/23/27 466
468 Test new telecom outlets / system 2 days Wed 3/24/27 Thu 3/25/27 467
469 DDC 1 day Fri 3/26/27 Fri 3/26/27 468
470 Demo old cable 3 days Fri 3/26/27 Tue 3/30/27 468
471 Clean and punch 3 days Wed 3/31/27 Fri 4/2/27 470
472 Building 210 - TR#32 400 days Mon 7/20/26 Fri 1/28/28
473 ICRA 2 days Mon 4/5/27 Tue 4/6/27 471
474 Abatement 3 days Wed 4/7/27 Fri 4/9/27 473
475 Demolition 3 days Mon 4/12/27 Wed 4/14/27 474
476 New walls, floors, doors 5 days Thu 4/15/27 Wed 4/21/27 475,12,5
477 Install CRAC 5 days Thu 4/22/27 Wed 4/28/27 476,11
478 Electrical and Lighting 5 days Thu 4/22/27 Wed 4/28/27 476,10
479 Security 5 days Thu 4/22/27 Wed 4/28/27 476,10
480 Fire suppression, FEC 3 days Thu 4/22/27 Mon 4/26/27 476,8
481 Telecom racks and switches 3 days Thu 4/22/27 Mon 4/26/27 476,9
482 Cable Tray and raceways 3 days Tue 4/27/27 Thu 4/29/27 481
483 New cable from outlets to TRs 5 days Fri 4/30/27 Thu 5/6/27 482
484 New outlet connections 3 days Fri 5/7/27 Tue 5/11/27 483
485 Land cable on switches 2 days Wed 5/12/27 Thu 5/13/27 484
486 Test new telecom outlets / system 2 days Fri 5/14/27 Mon 5/17/27 485
487 DDC 1 day Tue 5/18/27 Tue 5/18/27 486
488 Demo old cable 3 days Tue 5/18/27 Thu 5/20/27 486
489 Clean and punch 3 days Fri 5/21/27 Tue 5/25/27 488
490 Building 211 - TR#33 400 days Mon 7/20/26 Fri 1/28/28
491 ICRA 2 days Wed 5/26/27 Thu 5/27/27 489
492 Abatement 3 days Fri 5/28/27 Tue 6/1/27 491
493 Demolition 3 days Wed 6/2/27 Fri 6/4/27 492
494 New walls, floors, doors 5 days Mon 6/7/27 Fri 6/11/27 493,12,5
495 Install CRAC 5 days Mon 6/14/27 Fri 6/18/27 494,11
496 Electrical and Lighting 5 days Mon 6/14/27 Fri 6/18/27 494,10
497 Security 5 days Mon 6/14/27 Fri 6/18/27 494,10
498 Fire suppression, FEC 3 days Mon 6/14/27 Wed 6/16/27 494,8
499 Telecom racks and switches 3 days Mon 6/14/27 Wed 6/16/27 494,9
500 Cable Tray and raceways 3 days Thu 6/17/27 Mon 6/21/27 499
501 New cable from outlets to TRs 5 days Tue 6/22/27 Mon 6/28/27 500
502 New outlet connections 3 days Tue 6/29/27 Thu 7/1/27 501
503 Land cable on switches 2 days Fri 7/2/27 Mon 7/5/27 502
504 Test new telecom outlets / system2 days Tue 7/6/27 Wed 7/7/27 503
505 DDC 1 day Thu 7/8/27 Thu 7/8/27 504
506 Demo old cable 3 days Thu 7/8/27 Mon 7/12/27 504
507 Clean and punch 3 days Tue 7/13/27 Thu 7/15/27 506
508 Building 212 - TR#34 400 days Mon 7/20/26 Fri 1/28/28
509 ICRA 2 days Mon 7/20/26 Tue 7/21/26 12,5
510 Abatement 3 days Wed 7/22/26 Fri 7/24/26 509
511 Demolition 3 days Mon 7/27/26 Wed 7/29/26 510
512 New walls, floors, doors 5 days Thu 7/30/26 Wed 8/5/26 511,12,5
513 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 512,11
514 Electrical and Lighting 5 days Thu 8/6/26 Wed 8/12/26 512,10
515 Security 5 days Thu 8/6/26 Wed 8/12/26 512,10
516 Fire suppression, FEC 3 days Thu 8/6/26 Mon 8/10/26 512,8
517 Telecom racks and switches 3 days Thu 8/6/26 Mon 8/10/26 512,9
518 Cable Tray and raceways 3 days Tue 8/11/26 Thu 8/13/26 517
519 New cable from outlets to TRs5 days Fri 8/14/26 Thu 8/20/26 518
520 New outlet connections 3 days Fri 8/21/26 Tue 8/25/26 519
521 Land cable on switches 2 days Wed 8/26/26 Thu 8/27/26 520
522 Test new telecom outlets / system2 days Fri 8/28/26 Mon 8/31/26 521
523 DDC 1 day Tue 9/1/26 Tue 9/1/26 522
524 Demo old cable 3 days Tue 9/1/26 Thu 9/3/26 522
525 Clean and punch 3 days Fri 9/4/26 Tue 9/8/26 524
526 Building 221 - TR#35 363 days Wed 9/9/26 Fri 1/28/28
527 ICRA 2 days Wed 9/9/26 Thu 9/10/26 525
528 Abatement 3 days Fri 9/11/26 Tue 9/15/26 527
529 Demolition 3 days Wed 9/16/26 Fri 9/18/26 528
530 New walls, floors, doors 5 days Mon 9/21/26 Fri 9/25/26 529,12,5
531 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 530,11
532 Electrical and Lighting 5 days Mon 9/28/26 Fri 10/2/26 530,10
533 Security 5 days Mon 9/28/26 Fri 10/2/26 530,10
534 Fire suppression, FEC 3 days Mon 9/28/26 Wed 9/30/26 530,8
535 Telecom racks and switches3 days Mon 9/28/26 Wed 9/30/26 530,9
536 Cable Tray and raceways 3 days Thu 10/1/26 Mon 10/5/26 535
537 New cable from outlets to TRs5 days Tue 10/6/26 Mon 10/12/26 536
538 New outlet connections 3 days Tue 10/13/26 Thu 10/15/26 537
539 Land cable on switches 2 days Fri 10/16/26 Mon 10/19/26 538
540 Test new telecom outlets / system2 days Tue 10/20/26 Wed 10/21/26 539
541 DDC 1 day Thu 10/22/26 Thu 10/22/26 540
542 Demo old cable 3 days Thu 10/22/26 Mon 10/26/26 540
543 Clean and punch 3 days Tue 10/27/26 Thu 10/29/26 542
544 Building 323 - TR#36 326 days Fri 10/30/26 Fri 1/28/28
545 ICRA 2 days Fri 10/30/26 Mon 11/2/26 543
546 Abatement 3 days Tue 11/3/26 Thu 11/5/26 545
547 Demolition 3 days Fri 11/6/26 Tue 11/10/26 546
548 New walls, floors, doors5 days Wed 11/11/26 Tue 11/17/26 547,12,5
549 Install CRAC 5 days Wed 11/18/26 Tue 11/24/26 548,11
550 Electrical and Lighting 5 days Wed 11/18/26 Tue 11/24/26 548,10
551 Security 5 days Wed 11/18/26 Tue 11/24/26 548,10
552 Fire suppression, FEC 3 days Wed 11/18/26 Fri 11/20/26 548,8
553 Telecom racks and switches3 days Wed 11/18/26 Fri 11/20/26 548,9
554 Cable Tray and raceways3 days Mon 11/23/26 Wed 11/25/26 553
555 New cable from outlets to TRs5 days Thu 11/26/26 Wed 12/2/26 554
556 New outlet connections3 days Thu 12/3/26 Mon 12/7/26 555
557 Land cable on switches 2 days Tue 12/8/26 Wed 12/9/26 556
558 Test new telecom outlets / system2 days Thu 12/10/26 Fri 12/11/26 557
559 DDC 1 day Mon 12/14/26 Mon 12/14/26 558
560 Demo old cable 3 days Mon 12/14/26 Wed 12/16/26 558
561 Clean and punch 3 days Thu 12/17/26 Mon 12/21/26 560
562 Building 201 - TR#37A 289 days Tue 12/22/26 Fri 1/28/28
563 ICRA 2 days Tue 12/22/26 Wed 12/23/26 561
564 Abatement 3 days Thu 12/24/26 Mon 12/28/26 563
565 Demolition 3 days Tue 12/29/26 Thu 12/31/26 564
566 New walls, floors, doors5 days Fri 1/1/27 Thu 1/7/27 565,12,5
567 Install CRAC 5 days Fri 1/8/27 Thu 1/14/27 566,11
568 Electrical and Lighting5 days Fri 1/8/27 Thu 1/14/27 566,10
569 Security 5 days Fri 1/8/27 Thu 1/14/27 566,10
570 Fire suppression, FEC 3 days Fri 1/8/27 Tue 1/12/27 566,8
571 Telecom racks and switches3 days Fri 1/8/27 Tue 1/12/27 566,9
572 Cable Tray and raceways3 days Wed 1/13/27 Fri 1/15/27 571
573 New cable from outlets to TRs5 days Mon 1/18/27 Fri 1/22/27 572
574 New outlet connections3 days Mon 1/25/27 Wed 1/27/27 573
575 Land cable on switches2 days Thu 1/28/27 Fri 1/29/27 574
576 Test new telecom outlets / system2 days Mon 2/1/27 Tue 2/2/27 575
577 DDC 1 day Wed 2/3/27 Wed 2/3/27 576
578 Demo old cable 3 days Wed 2/3/27 Fri 2/5/27 576
579 Clean and punch 3 days Mon 2/8/27 Wed 2/10/27 578
Clean and punch
Building 209 - TR#30
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 209 - TR#31
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 210 - TR#32
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 211 - TR#33
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 212 - TR#34
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 221 - TR#35
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 323 - TR#36
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
Building 201 - TR#37A
ICRA
Abatement
Demolition
New walls, floors, doors
Install CRAC
Electrical and Lighting
Security
Fire suppression, FEC
Telecom racks and switches
Cable Tray and raceways
New cable from outlets to TRs
New outlet connections
Land cable on switches
Test new telecom outlets / system
DDC
Demo old cable
Clean and punch
J F M A M J J A S O N D J F M A M J J A S O N D J F Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028
Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress
580 Building 239 - TR#37B252 days Thu 2/11/27 Fri 1/28/28
581 ICRA 2 days Thu 2/11/27 Fri 2/12/27 579
582 Abatement 3 days Mon 2/15/27 Wed 2/17/27 581
583 Demolition 3 days Thu 2/18/27 Mon 2/22/27 582
584 New walls, floors, doors5 days Tue 2/23/27 Mon 3/1/27 583,12,5
585 Install CRAC 5 days Tue 3/2/27 Mon 3/8/27 584,11
586 Electrical and Lighting5 days Tue 3/2/27 Mon 3/8/27 584,10
587 Security 5 days Tue 3/2/27 Mon 3/8/27 584,10
588 Fire suppression, FEC 3 days Tue 3/2/27 Thu 3/4/27 584,8
589 Telecom racks and switches3 days Tue 3/2/27 Thu 3/4/27 584,9
590 Cable Tray and raceways3 days Fri 3/5/27 Tue 3/9/27 589
591 New cable from outlets to TRs5 days Wed 3/10/27 Tue 3/16/27 590
592 New outlet connections3 days Wed 3/17/27 Fri 3/19/27 591
593 Land cable on switches2 days Mon 3/22/27 Tue 3/23/27 592
594 Test new telecom outlets / system2 days Wed 3/24/27 Thu 3/25/27 593
595 DDC 1 day Fri 3/26/27 Fri 3/26/27 594
596 Demo old cable 3 days Fri 3/26/27 Tue 3/30/27 594
597 Clean and punch 3 days Wed 3/31/27 Fri 4/2/27 596
598 Building 203 - TR#17215 days Mon 4/5/27 Fri 1/28/28
599 ICRA 2 days Mon 4/5/27 Tue 4/6/27 597
600 Abatement 3 days Wed 4/7/27 Fri 4/9/27 599
601 Demolition 3 days Mon 4/12/27 Wed 4/14/27 600
602 New walls, floors, doors5 days Thu 4/15/27 Wed 4/21/27 601,12,5
603 Install CRAC 5 days Thu 4/22/27 Wed 4/28/27 602,11
604 Electrical and Lighting5 days Thu 4/22/27 Wed 4/28/27 602,10
605 Security 5 days Thu 4/22/27 Wed 4/28/27 602,10
606 Fire suppression, FEC 3 days Thu 4/22/27 Mon 4/26/27 602,8
607 Telecom racks and switches3 days Thu 4/22/27 Mon 4/26/27 602,9
608 Cable Tray and raceways3 days Tue 4/27/27 Thu 4/29/27 607
609 New cable from outlets to TRs5 days Fri 4/30/27 Thu 5/6/27 608
610 New outlet connections3 days Fri 5/7/27 Tue 5/11/27 609
611 Land cable on switches2 days Wed 5/12/27 Thu 5/13/27 610
612 Test new telecom outlets /
2 days Fri 5/14/27 Mon 5/17/27 611
613 DDC 1 day Tue 5/18/27 Tue 5/18/27 612
614 Demo old cable3 days Tue 5/18/27 Thu 5/20/27 612
615 Clean and punch3 days Fri 5/21/27 Tue 5/25/27 614
616 Building 240 - TR#3937 days Wed 5/26/27 Thu 7/15/27
617 ICRA 2 days Wed 5/26/27 Thu 5/27/27 615
618 Abatement 3 days Fri 5/28/27 Tue 6/1/27 617
619 Demolition 3 days Wed 6/2/27 Fri 6/4/27 618
620 New walls, floors, doors5 days Mon 6/7/27 Fri 6/11/27 619,12,5
621 Install CRAC 5 days Mon 6/14/27 Fri 6/18/27 620,11
622 Electrical and Lighting5 days Mon 6/14/27 Fri 6/18/27 620,10
623 Security 5 days Mon 6/14/27 Fri 6/18/27 620,10
624 Fire suppression, FEC 3 days Mon 6/14/27 Wed 6/16/27 620,8
625 Telecom racks and switches3 days Mon 6/14/27 Wed 6/16/27 620,9
626 Cable Tray and raceways3 days Thu 6/17/27 Mon 6/21/27 625
627 New cable from outlets to TRs5 days Tue 6/22/27 Mon 6/28/27 626
628 New outlet connections3 days Tue 6/29/27 Thu 7/1/27 627
629 Land cable on switches2 days Fri 7/2/27 Mon 7/5/27 628
630 Test new telecom outlets /
2 days Tue 7/6/27 Wed 7/7/27 629
631 DDC 3 days Thu 7/8/27 Mon 7/12/27 630
632 Demo old cable3 days Thu 7/8/27 Mon 7/12/27 630
633 Clean and punch3 days Tue 7/13/27 Thu 7/15/27 632
634 Building 248 - TR#40141 days Fri 7/16/27 Fri 1/28/28
635 ICRA 2 days Fri 7/16/27 Mon 7/19/27 633
636 Abatement 3 days Tue 7/20/27 Thu 7/22/27 635
637 Demolition 3 days Fri 7/23/27 Tue 7/27/27 636
638 New walls, floors, doors5 days Wed 7/28/27 Tue 8/3/27 637,12,5
639 Install CRAC 5 days Wed 8/4/27 Tue 8/10/27 638,11
640 Electrical and Lighting5 days Wed 8/4/27 Tue 8/10/27 638,10
641 Security 5 days Wed 8/4/27 Tue 8/10/27 638,10
642 Fire suppression, FEC 3 days Wed 8/4/27 Fri 8/6/27 638,8
643 Telecom racks and switches3 days Wed 8/4/27 Fri 8/6/27 638,9
644 Cable Tray and raceways3 days Mon 8/9/27 Wed 8/11/27 643
645 New cable from outlets to TRs5 days Thu 8/12/27 Wed 8/18/27 644
646 New outlet connections3 days Thu 8/19/27 Mon 8/23/27 645
647 Land cable on switches2 days Tue 8/24/27 Wed 8/25/27 646
648 Test new telecom outlets /
2 days Thu 8/26/27 Fri 8/27/27 647
649 DDC 1 day Mon 8/30/27 Mon 8/30/27 648
650 Demo old cable3 days Mon 8/30/27 Wed 9/1/27 648
651 Clean and punch3 days Thu 9/2/27 Mon 9/6/27 650
652 Building 248 - TR#41104 days Tue 9/7/27 Fri 1/28/28
653 ICRA 2 days Tue 9/7/27 Wed 9/8/27 651
654 Abatement3 days Thu 9/9/27 Mon 9/13/27 653
655 Demolition3 days Tue 9/14/27 Thu 9/16/27 654
656 New walls, floors, doors5 days Fri 9/17/27 Thu 9/23/27 655,12,5
657 Install CRAC5 days Fri 9/24/27 Thu 9/30/27 656,11
658 Electrical and Lighting5 days Fri…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .