S02 - SOW - Att 13 - Const Sch - 02132026 - EHRM Infra Upgrades - Constr Togus.pdf

PDF 882 KB Posted

Attached to
Electronic Health Record Modernization Infrastructure Upgrades - Construction - Togus, ME
Solicitation number
36C77626R0062
Issued by

About this file

This is a project schedule (Gantt chart) for the Togus EHRM (Electronic Health Records Management) Construction project, reissued December 22, 2025. The project runs for 523 working days (730 calendar days) from February 2, 2026, to February 2, 2028. The schedule encompasses a comprehensive Electronic Health Records system implementation at the Togus Veterans Medical Center, involving construction of a new Main Computer Room (MCR), site and utility work, and renovation of multiple technology rooms across multiple buildings.

The project is organized into major phases including submittal and procurement (60 days for materials and equipment with lead times ranging from 30 to 120 days for long-lead items such as UPS systems, CRAC units, electrical panels, and fiber optic cabling); site and utility work (80 days starting July 2026); construction of a new MCR (395 days from April 2026 to October 2027); and sequential renovation of 21 technology rooms (TRs) across Buildings 200/200E, 202, 204, 205, 206, 207, 208, 209, 210, 211, 212, 221, 323, 239, 203, 240, 248, and 255, plus Building 300. Each technology room renovation follows a standardized sequence: ICRA (Infection Control Risk Assessment), abatement, demolition, new walls/floors/doors, CRAC installation, electrical and lighting, security, fire suppression, telecom infrastructure, cabling, testing, DDC (Direct Digital Control), and punch-list closeout. The project concludes with closeout activities, operations and maintenance documentation, as-builts, training, and warranty tasks scheduled for January 31 through February 2, 2028.

View the file

Other files

File Type Posted
S30 - SAM - Special Notice - Cancellation - 36C77626R0062_2 - EHRM Infra Upgrades - Togus.pdf PDF
S06 - Amend 0002 - Att 03 - Corrected Agenda - RFP - 07202026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0002 - 36C77626R0062 - 07202026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - Att 02 - SV - Attendance SHT - 06292026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - 36C77626R0062 - 07142026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - RFIs - 07132026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S06 - Amend 0001 - Att 01 - Rvd Structural Drwg - 06192026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - Att 03 - SV - Agenda - RFP - 06292026 - EHRM Infra - Togus.pdf PDF
S02 - SOW - Att 05 - Drwg - Vol 3 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 26 - Cut Sheet 04 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 03 -Prj Info Sheet for KTR - EHRM Infra Upgrade - Togus.docx DOCX document
S02 - SOW - Att 03 - Drwg - Vol 1C - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 22 - TS-000 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 07 - 852.219-75 - 06172026 - EHRM Infra Upgrade - Togus.pdf PDF
S02 - Att 04 - Memo - Brand Name - 04092026 - EHRM Infra Upgrade - Togus.pdf PDF
S02 - SOW - Att 35 - Cut Sheet 13 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 17 - Memo - Phy Sec Compliance - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 27 - Cut Sheet 05 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 09 - Specs - Vol 3- 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 30 - Cut Sheet 08 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 24 - Cut Sheet 02 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 05 - Division Cost Breakdown - EHRM Infra Upgrade - Togus.xlsx XLSX spreadsheet
S02 - SOW - Att 29 - Cut Sheet 07 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 37 - Cut Sheet 15 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 16 - Submittal Reg - 02182026 - EHRM Infra - Upgrades - Constr - Togus.xlsx XLSX spreadsheet
S02 - SOW - Att 14 - Design Calcs - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 18 - Memo - Prj Stnd Compliance - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 21 - PCRA 3 - MCR and Trench Work - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 40 - Cut Sheet 18 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 33 - Cut Sheet 11 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 01 - Drwg - Vol 1A - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 38 - Cut Sheet 16 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 06 - Drwg - Vol 4 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 11 - Haz Mat Report - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 12 - Geotechnical Report - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 32 - Cut Sheet 10 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 08 - Specs - Vol 1 - Div 02-14 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 20 - PCRA 2 - Cabling and Data Outlets - EHRM Infra Upgrades - Constr - Togus.pdf PDF
RFP - EHRM Infra Upgrade - 36C77626R0062 - 06172026 - Togus.pdf PDF
S02 - SOW - Att 19 - PCRA 1 - TR Constr - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 07 - Specs - Vol 1 - Div 00-01 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 15 - Design Narrative - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 23 - Cut Sheet 01 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 31 - Cut Sheet 09 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 02 - PPQ - EHRM Infra Upgrade - Togus.docx DOCX document
S02 - SOW - Att 02 - Drwg - Vol 1B - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 34 - Cut Sheet 12 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 01 - SOW - 05112026 - EHRM Infra Upgrades - Togus.pdf PDF
S02 - SOW - Att 10 - Specs - Vol 4 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 36 - Cut Sheet 14 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Duration Start Finish Predecessors

1 Togus EHRM Construction - NTP 2/3/2026 (523 Working Days, 730 Calendar Days)

523 days Mon 2/2/26 Wed 2/2/28

2 Submittals for Materials & Equipment 60 days Mon 2/2/26 Fri 4/24/26

3 Submittal Process 60 days Mon 2/2/26 Fri 4/24/26

4 Lead-Time Long-Lead Materials & Equipment 120 days Mon 4/27/26 Fri 10/9/26 3

5 Lead Time - Light Gauge Steel 30 days Mon 4/27/26 Fri 6/5/26 3

6 Lead Time - MCR Flooring 60 days Mon 4/27/26 Fri 7/17/26 3

7 Lead Time - UPS 120 days Mon 4/27/26 Fri 10/9/26 3

8 Lead Time - Fire Protection Equipment 60 days Mon 4/27/26 Fri 7/17/26 3

9 Lead Time - Data Cable & Fiber 60 days Mon 4/27/26 Fri 7/17/26 3

10 Lead Time - Electrical Panels, Electrical Wire and Cabling 60 days Mon 4/27/26 Fri 7/17/26 3

11 Lead Time - CRAC and compressors 120 days Mon 4/27/26 Fri 10/9/26 3

12 Lead Time - Architectural - Doors & Hardware 60 days Mon 4/27/26 Fri 7/17/26 3

13 Site and Utility Work 80 days Mon 7/20/26 Fri 11/6/26

14 Trenching for New Exterior Fiber Runs 10 days Mon 7/20/26 Fri 7/31/26 9

15 Install New Ductbanks 15 days Mon 8/3/26 Fri 8/21/26 14

16 Install New Exterior Fiber Loops 10 days Mon 8/24/26 Fri 9/4/26 15

17 Install Exterior Electrical 30 days Mon 7/20/26 Fri 8/28/26 10

18 Patch Asphalt 5 days Mon 8/24/26 Fri 8/28/26 16SS

19 Patch Concrete 5 days Mon 8/24/26 Fri 8/28/26 16SS

20 Restore Landscaping 10 days Mon 9/7/26 Fri 9/18/26 16

21 Housekeeping pads 5 days Mon 7/20/26 Fri 7/24/26 17SS

22 Install Condensing Units 5 days Mon 10/12/26 Fri 10/16/26 11,21

23 Install CRAC piping to TRs 20 days Mon 10/12/26 Fri 11/6/26 22SS

24 New Main Computer Room (MCR) 395 days Mon 4/27/26 Fri 10/29/27

25 Survey and Layout 5 days Mon 4/27/26 Fri 5/1/26 3

26 Erosion Control 4 days Mon 5/4/26 Thu 5/7/26 25

27 Clear and Grub 5 days Fri 5/8/26 Thu 5/14/26 26

28 Excavation, Rock Removal 30 days Fri 5/15/26 Thu 6/25/26 27

29 Retaining Wall Earthwork 7 days Fri 6/26/26 Mon 7/6/26 28

30 Retaining Wall Formwork 5 days Tue 7/7/26 Mon 7/13/26 29

31 Pour Retaining Wall 5 days Tue 7/14/26 Mon 7/20/26 30

32 Underground Utilities, Stub Out 20 days Tue 7/21/26 Mon 8/17/26 31

33 Subgrade Preparation 8 days Tue 8/18/26 Thu 8/27/26 32

34 Foundation Formwork 14 days Fri 8/28/26 Wed 9/16/26 33

35 Pour Foundation 7 days Thu 9/17/26 Fri 9/25/26 34

36 Slab On Grade Preparation 11 days Mon 9/28/26 Mon 10/12/26 35

37 Pour Slab on Grade 3 days Tue 10/13/26 Thu 10/15/26 36

38 Structural Steel 40 days Fri 10/16/26 Thu 12/10/26 37

39 New Exterior Walls 40 days Fri 12/11/26 Thu 2/4/27 38

40 Roof 15 days Fri 2/5/27 Thu 2/25/27 38,39

41 New interior walls, floors, doors 40 days Fri 2/26/27 Thu 4/22/27 40

42 Install Electrical Panels 20 days Fri 4/23/27 Thu 5/20/27 41

43 Install Power Distribution 10 days Fri 5/21/27 Thu 6/3/27 10,42

44 Install UPS Units 10 days Fri 6/4/27 Thu 6/17/27 7,43

45 Test UPS Units 5 days Fri 6/18/27 Thu 6/24/27 44

46 Install Lighting 5 days Fri 6/4/27 Thu 6/10/27 10,43

47 Install CRAC Units 14 days Fri 5/21/27 Wed 6/9/27 41,42,11

48 Security 5 days Fri 5/21/27 Thu 5/27/27 41,42

49 Fire suppression, FEC 21 days Fri 4/23/27 Fri 5/21/27 41

50 Telecom racks and switches 40 days Fri 5/21/27 Thu 7/15/27 41,42

51 Cable Tray and raceways 16 days Fri 7/16/27 Fri 8/6/27 50,9

52 New Data Drops 5 days Mon 8/9/27 Fri 8/13/27 51

53 Land Data Cabling On Switches 7 days Mon 8/16/27 Tue 8/24/27 52

54 Test New Data Cabling and Outlets 3 days Wed 8/25/27 Fri 8/27/27 53

55 DDC 1 day Mon 8/30/27 Mon 8/30/27 47,48,49,53,54

56 Migrate MCR 30 days Tue 8/31/27 Mon 10/11/27 55

57 Clean and punch 14 days Tue 10/12/27 Fri 10/29/27 56

58 Building 200/200E - TR#7A 65 days Mon 7/20/26 Fri 10/16/26

59 ICRA 2 days Mon 7/20/26 Tue 7/21/26 12,5

60 Abatement 3 days Wed 7/22/26 Fri 7/24/26 59

61 Demolition 3 days Mon 7/27/26 Wed 7/29/26 60

62 New walls, floors, doors 5 days Thu 7/30/26 Wed 8/5/26 12,61,5

63 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 62,11

64 Electrical and Lighting 5 days Thu 8/6/26 Wed 8/12/26 62,10

65 Security 5 days Thu 8/6/26 Wed 8/12/26 62,10

66 Fire suppression, FEC 3 days Thu 8/6/26 Mon 8/10/26 62,8

67 Telecom racks and switches 3 days Thu 8/6/26 Mon 8/10/26 62,9

68 Cable Tray and raceways 3 days Tue 8/11/26 Thu 8/13/26 67

69 New cable from outlets to TRs 5 days Fri 8/14/26 Thu 8/20/26 68

70 New outlet connections 3 days Fri 8/21/26 Tue 8/25/26 69

71 Land cable on switches 2 days Wed 8/26/26 Thu 8/27/26 70

72 Test new telecom outlets / system 2 days Fri 8/28/26 Mon 8/31/26 71

73 DDC 1 day Tue 9/1/26 Tue 9/1/26 72

74 Demo old cable 3 days Tue 9/1/26 Thu 9/3/26 72

75 Clean and punch 3 days Fri 9/4/26 Tue 9/8/26 74

76 Building 200/200E - TR#7B 37 days Wed 9/9/26 Thu 10/29/26

77 ICRA 2 days Wed 9/9/26 Thu 9/10/26 75

78 Abatement 3 days Fri 9/11/26 Tue 9/15/26 77

79 Demolition 3 days Wed 9/16/26 Fri 9/18/26 78

80 New walls, floors, doors 5 days Mon 9/21/26 Fri 9/25/26 12,5,79

81 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 80,11

82 Electrical and Lighting 5 days Mon 9/28/26 Fri 10/2/26 80,10

83 Security 5 days Mon 9/28/26 Fri 10/2/26 80,10

84 Fire suppression, FEC 3 days Mon 9/28/26 Wed 9/30/26 80,8

85 Telecom racks and switches 3 days Mon 9/28/26 Wed 9/30/26 80,9

86 Cable Tray and raceways 3 days Thu 10/1/26 Mon 10/5/26 85

87 New cable from outlets to TRs 5 days Tue 10/6/26 Mon 10/12/26 86

88 New outlet connections 3 days Tue 10/13/26 Thu 10/15/26 87

89 Land cable on switches 2 days Fri 10/16/26 Mon 10/19/26 88

90 Test new telecom outlets / system 2 days Tue 10/20/26 Wed 10/21/26 89

91 DDC 1 day Thu 10/22/26 Thu 10/22/26 90

92 Demo old cable 3 days Thu 10/22/26 Mon 10/26/26 90

93 Clean and punch 3 days Tue 10/27/26 Thu 10/29/26 92

94 Building 200/200E - TR#8A 37 days Fri 10/30/26 Mon 12/21/26

95 ICRA 2 days Fri 10/30/26 Mon 11/2/26 93

96 Abatement 3 days Tue 11/3/26 Thu 11/5/26 95

97 Demolition 3 days Fri 11/6/26 Tue 11/10/26 96

98 New walls, floors, doors 5 days Wed 11/11/26 Tue 11/17/26 12,97,5

99 Install CRAC 5 days Wed 11/18/26 Tue 11/24/26 98,11

100 Electrical and Lighting 5 days Wed 11/18/26 Tue 11/24/26 98,10

101 Security 5 days Wed 11/18/26 Tue 11/24/26 98,10

102 Fire suppression, FEC 3 days Wed 11/18/26 Fri 11/20/26 98,8

103 Telecom racks and switches 3 days Wed 11/18/26 Fri 11/20/26 98,9

104 Cable Tray and raceways 3 days Mon 11/23/26 Wed 11/25/26 103

105 New cable from outlets to TRs 5 days Thu 11/26/26 Wed 12/2/26 104

106 New outlet connections 3 days Thu 12/3/26 Mon 12/7/26 105

107 Land cable on switches 2 days Tue 12/8/26 Wed 12/9/26 106

108 Test new telecom outlets / system 2 days Thu 12/10/26 Fri 12/11/26 107

109 DDC 1 day Mon 12/14/26 Mon 12/14/26 108

110 Demo old cable 3 days Mon 12/14/26 Wed 12/16/26 108

111 Clean and punch 3 days Thu 12/17/26 Mon 12/21/26 110

112 Building 200/200E - TR#9A 37 days Tue 12/22/26 Wed 2/10/27

113 ICRA 2 days Tue 12/22/26 Wed 12/23/26 111

114 Abatement 3 days Thu 12/24/26 Mon 12/28/26 113

115 Demolition 3 days Tue 12/29/26 Thu 12/31/26 114

116 New walls, floors, doors 5 days Fri 1/1/27 Thu 1/7/27 12,115,5

117 Install CRAC 5 days Fri 1/8/27 Thu 1/14/27 116,11

118 Electrical and Lighting 5 days Fri 1/8/27 Thu 1/14/27 116,10

119 Security 5 days Fri 1/8/27 Thu 1/14/27 116,10

120 Fire suppression, FEC 3 days Fri 1/8/27 Tue 1/12/27 116,8

121 Telecom racks and switches 3 days Fri 1/8/27 Tue 1/12/27 116,9

122 Cable Tray and raceways 3 days Wed 1/13/27 Fri 1/15/27 121

123 New cable from outlets to TRs 5 days Mon 1/18/27 Fri 1/22/27 122

124 New outlet connections 3 days Mon 1/25/27 Wed 1/27/27 123

125 Land cable on switches 2 days Thu 1/28/27 Fri 1/29/27 124

126 Test new telecom outlets / system 2 days Mon 2/1/27 Tue 2/2/27 125

127 DDC 1 day Wed 2/3/27 Wed 2/3/27 126

128 Demo old cable 3 days Wed 2/3/27 Fri 2/5/27 126

129 Clean and punch 3 days Mon 2/8/27 Wed 2/10/27 128

130 Building 200/200E - TR#9B 37 days Thu 2/11/27 Fri 4/2/27

131 ICRA 2 days Thu 2/11/27 Fri 2/12/27 129

132 Abatement 3 days Mon 2/15/27 Wed 2/17/27 131

133 Demolition 3 days Thu 2/18/27 Mon 2/22/27 132

134 New walls, floors, doors 5 days Tue 2/23/27 Mon 3/1/27 12,133,5

135 Install CRAC 5 days Tue 3/2/27 Mon 3/8/27 134,11

136 Electrical and Lighting 5 days Tue 3/2/27 Mon 3/8/27 134,10

137 Security 5 days Tue 3/2/27 Mon 3/8/27 134,10

138 Fire suppression, FEC 3 days Tue 3/2/27 Thu 3/4/27 134,8

139 Telecom racks and switches 3 days Tue 3/2/27 Thu 3/4/27 134,9

140 Cable Tray and raceways 3 days Fri 3/5/27 Tue 3/9/27 139

141 New cable from outlets to TRs 5 days Wed 3/10/27 Tue 3/16/27 140

142 New outlet connections 3 days Wed 3/17/27 Fri 3/19/27 141

143 Land cable on switches 2 days Mon 3/22/27 Tue 3/23/27 142

144 Test new telecom outlets / system 2 days Wed 3/24/27 Thu 3/25/27 143

Togus EHRM Construction - NTP 2/3/2026 (523 Working Days, 730 Calendar Days)

Submittals for Materials & Equipment

Submittal Process

Lead-Time Long-Lead Materials & Equipment

Lead Time - Light Gauge Steel

Lead Time - MCR Flooring

Lead Time - UPS

Lead Time - Fire Protection Equipment

Lead Time - Data Cable & Fiber

Lead Time - Electrical Panels, Electrical Wire and Cabling

Lead Time - CRAC and compressors

Lead Time - Architectural - Doors & Hardware

Site and Utility Work

Trenching for New Exterior Fiber Runs

Install New Ductbanks

Install New Exterior Fiber Loops

Install Exterior Electrical

Patch Asphalt

Patch Concrete

Restore Landscaping

Housekeeping pads

Install Condensing Units

Install CRAC piping to TRs

New Main Computer Room (MCR)

Survey and Layout

Erosion Control

Clear and Grub

Excavation, Rock Removal

Retaining Wall Earthwork

Retaining Wall Formwork

Pour Retaining Wall

Underground Utilities, Stub Out

Subgrade Preparation

Foundation Formwork

Pour Foundation

Slab On Grade Preparation

Pour Slab on Grade

Structural Steel

New Exterior Walls

Roof

New interior walls, floors, doors

Install Electrical Panels

Install Power Distribution

Install UPS Units

Test UPS Units

Install Lighting

Install CRAC Units

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New Data Drops

Land Data Cabling On Switches

Test New Data Cabling and Outlets

DDC

Migrate MCR

Clean and punch

Building 200/200E - TR#7A

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 200/200E - TR#7B

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 200/200E - TR#8A

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 200/200E - TR#9A

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 200/200E - TR#9B

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

J F M A M J J A S O N D J F M A M J J A S O N D J F Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028

Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress

Togus EHRM Reissued 12-22-2025

145 DDC 1 day Fri 3/26/27 Fri 3/26/27 144

146 Demo old cable 3 days Fri 3/26/27 Tue 3/30/27 144

147 Clean and punch 3 days Wed 3/31/27 Fri 4/2/27 146

148 Building 200/200E - TR#10A 37 days Mon 4/5/27 Tue 5/25/27

149 ICRA 2 days Mon 4/5/27 Tue 4/6/27 12,130,5

150 Abatement 3 days Wed 4/7/27 Fri 4/9/27 149

151 Demolition 3 days Mon 4/12/27 Wed 4/14/27 150

152 New walls, floors, doors 5 days Thu 4/15/27 Wed 4/21/27 12,151,5

153 Install CRAC 5 days Thu 4/22/27 Wed 4/28/27 152,11

154 Electrical and Lighting 5 days Thu 4/22/27 Wed 4/28/27 152,10

155 Security 5 days Thu 4/22/27 Wed 4/28/27 152,10

156 Fire suppression, FEC 3 days Thu 4/22/27 Mon 4/26/27 152,8

157 Telecom racks and switches 3 days Thu 4/22/27 Mon 4/26/27 152,9

158 Cable Tray and raceways 3 days Tue 4/27/27 Thu 4/29/27 157

159 New cable from outlets to TRs 5 days Fri 4/30/27 Thu 5/6/27 158

160 New outlet connections 3 days Fri 5/7/27 Tue 5/11/27 159

161 Land cable on switches 2 days Wed 5/12/27 Thu 5/13/27 160

162 Test new telecom outlets / system 2 days Fri 5/14/27 Mon 5/17/27 161

163 DDC 1 day Tue 5/18/27 Tue 5/18/27 162

164 Demo old cable 3 days Tue 5/18/27 Thu 5/20/27 162

165 Clean and punch 3 days Fri 5/21/27 Tue 5/25/27 164

166 Building 200/200E - TR#10B 37 days Wed 5/26/27 Thu 7/15/27

167 ICRA 2 days Wed 5/26/27 Thu 5/27/27 165

168 Abatement 3 days Fri 5/28/27 Tue 6/1/27 167

169 Demolition 3 days Wed 6/2/27 Fri 6/4/27 168

170 New walls, floors, doors 5 days Mon 6/7/27 Fri 6/11/27 12,169,5

171 Install CRAC 5 days Mon 6/14/27 Fri 6/18/27 170,11

172 Electrical and Lighting 5 days Mon 6/14/27 Fri 6/18/27 170,10

173 Security 5 days Mon 6/14/27 Fri 6/18/27 170,10

174 Fire suppression, FEC 3 days Mon 6/14/27 Wed 6/16/27 170,8

175 Telecom racks and switches 3 days Mon 6/14/27 Wed 6/16/27 170,9

176 Cable Tray and raceways 3 days Thu 6/17/27 Mon 6/21/27 175

177 New cable from outlets to TRs 5 days Tue 6/22/27 Mon 6/28/27 176

178 New outlet connections 3 days Tue 6/29/27 Thu 7/1/27 177

179 Land cable on switches 2 days Fri 7/2/27 Mon 7/5/27 178

180 Test new telecom outlets / system 2 days Tue 7/6/27 Wed 7/7/27 179

181 DDC 1 day Thu 7/8/27 Thu 7/8/27 180

182 Demo old cable 3 days Thu 7/8/27 Mon 7/12/27 180

183 Clean and punch 3 days Tue 7/13/27 Thu 7/15/27 182

184 Building 200/200E - TR#11 37 days Fri 7/16/27 Mon 9/6/27

185 ICRA 2 days Fri 7/16/27 Mon 7/19/27 183

186 Abatement 3 days Tue 7/20/27 Thu 7/22/27 185

187 Demolition 3 days Fri 7/23/27 Tue 7/27/27 186

188 New walls, floors, doors 5 days Wed 7/28/27 Tue 8/3/27 12,187,5

189 Install CRAC 5 days Wed 8/4/27 Tue 8/10/27 188,11

190 Electrical and Lighting 5 days Wed 8/4/27 Tue 8/10/27 188,10

191 Security 5 days Wed 8/4/27 Tue 8/10/27 188,10

192 Fire suppression, FEC 3 days Wed 8/4/27 Fri 8/6/27 188,8

193 Telecom racks and switches 3 days Wed 8/4/27 Fri 8/6/27 188,9

194 Cable Tray and raceways 3 days Mon 8/9/27 Wed 8/11/27 193

195 New cable from outlets to TRs 5 days Thu 8/12/27 Wed 8/18/27 194

196 New outlet connections 3 days Thu 8/19/27 Mon 8/23/27 195

197 Land cable on switches 2 days Tue 8/24/27 Wed 8/25/27 196

198 Test new telecom outlets / system 2 days Thu 8/26/27 Fri 8/27/27 197

199 DDC 1 day Mon 8/30/27 Mon 8/30/27 198

200 Demo old cable 3 days Mon 8/30/27 Wed 9/1/27 198

201 Clean and punch 3 days Thu 9/2/27 Mon 9/6/27 200

202 Building 200/200E - TR#12 37 days Tue 9/7/27 Wed 10/27/27

203 ICRA 2 days Tue 9/7/27 Wed 9/8/27 201

204 Abatement 3 days Thu 9/9/27 Mon 9/13/27 203

205 Demolition 3 days Tue 9/14/27 Thu 9/16/27 204

206 New walls, floors, doors 5 days Fri 9/17/27 Thu 9/23/27 12,205,5

207 Install CRAC 5 days Fri 9/24/27 Thu 9/30/27 206,11

208 Electrical and Lighting 5 days Fri 9/24/27 Thu 9/30/27 206,10

209 Security 5 days Fri 9/24/27 Thu 9/30/27 206,10

210 Fire suppression, FEC 3 days Fri 9/24/27 Tue 9/28/27 206,8

211 Telecom racks and switches 3 days Fri 9/24/27 Tue 9/28/27 206,9

212 Cable Tray and raceways 3 days Wed 9/29/27 Fri 10/1/27 211

213 New cable from outlets to TRs 5 days Mon 10/4/27 Fri 10/8/27 212

214 New outlet connections 3 days Mon 10/11/27 Wed 10/13/27 213

215 Land cable on switches 2 days Thu 10/14/27 Fri 10/15/27 214

216 Test new telecom outlets / system 2 days Mon 10/18/27 Tue 10/19/27 215

217 DDC 1 day Wed 10/20/27 Wed 10/20/27 216

218 Demo old cable 3 days Wed 10/20/27 Fri 10/22/27 216

219 Clean and punch 3 days Mon 10/25/27 Wed 10/27/27 218

220 Building 200/200E - TR#13 65 days Mon 7/20/26 Fri 10/16/26

221 ICRA 2 days Mon 7/20/26 Tue 7/21/26 12,5

222 Abatement 3 days Wed 7/22/26 Fri 7/24/26 221

223 Demolition 3 days Mon 7/27/26 Wed 7/29/26 222

224 New walls, floors, doors 5 days Thu 7/30/26 Wed 8/5/26 12,223,5

225 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 224,11

226 Electrical and Lighting 5 days Thu 8/6/26 Wed 8/12/26 224,10

227 Security 5 days Thu 8/6/26 Wed 8/12/26 224,10

228 Fire suppression, FEC 3 days Thu 8/6/26 Mon 8/10/26 224,8

229 Telecom racks and switches 3 days Thu 8/6/26 Mon 8/10/26 224,9

230 Cable Tray and raceways 3 days Tue 8/11/26 Thu 8/13/26 229

231 New cable from outlets to TRs 5 days Fri 8/14/26 Thu 8/20/26 230

232 New outlet connections 3 days Fri 8/21/26 Tue 8/25/26 231

233 Land cable on switches 2 days Wed 8/26/26 Thu 8/27/26 232

234 Test new telecom outlets / system 2 days Fri 8/28/26 Mon 8/31/26 233

235 DDC 1 day Tue 9/1/26 Tue 9/1/26 234

236 Demo old cable 3 days Tue 9/1/26 Thu 9/3/26 234

237 Clean and punch 3 days Fri 9/4/26 Tue 9/8/26 236

238 Building 202 - TR#207E 37 days Wed 9/9/26 Thu 10/29/26

239 ICRA 2 days Wed 9/9/26 Thu 9/10/26 237

240 Abatement 3 days Fri 9/11/26 Tue 9/15/26 239

241 Demolition 3 days Wed 9/16/26 Fri 9/18/26 240

242 New walls, floors, doors 5 days Mon 9/21/26 Fri 9/25/26 12,241,5

243 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 242,11

244 Electrical and Lighting 5 days Mon 9/28/26 Fri 10/2/26 242,10

245 Security 5 days Mon 9/28/26 Fri 10/2/26 242,10

246 Fire suppression, FEC 3 days Mon 9/28/26 Wed 9/30/26 242,8

247 Telecom racks and switches 3 days Mon 9/28/26 Wed 9/30/26 242,9

248 Cable Tray and raceways 3 days Thu 10/1/26 Mon 10/5/26 247

249 New cable from outlets to TRs 5 days Tue 10/6/26 Mon 10/12/26 248

250 New outlet connections 3 days Tue 10/13/26 Thu 10/15/26 249

251 Land cable on switches 2 days Fri 10/16/26 Mon 10/19/26 250

252 Test new telecom outlets / system 2 days Tue 10/20/26 Wed 10/21/26 251

253 DDC 1 day Thu 10/22/26 Thu 10/22/26 252

254 Demo old cable 3 days Thu 10/22/26 Mon 10/26/26 252

255 Clean and punch 3 days Tue 10/27/26 Thu 10/29/26 254

256 Building 204 - TR#19 37 days Fri 10/30/26 Mon 12/21/26

257 ICRA 2 days Fri 10/30/26 Mon 11/2/26 255

258 Abatement 3 days Tue 11/3/26 Thu 11/5/26 257

259 Demolition 3 days Fri 11/6/26 Tue 11/10/26 258

260 New walls, floors, doors 5 days Wed 11/11/26 Tue 11/17/26 12,259,5

261 Install CRAC 5 days Wed 11/18/26 Tue 11/24/26 260,11

262 Electrical and Lighting 5 days Wed 11/18/26 Tue 11/24/26 260,10

263 Security 5 days Wed 11/18/26 Tue 11/24/26 260,10

264 Fire suppression, FEC 3 days Wed 11/18/26 Fri 11/20/26 260,8

265 Telecom racks and switches 3 days Wed 11/18/26 Fri 11/20/26 260,9

266 Cable Tray and raceways 3 days Mon 11/23/26 Wed 11/25/26 265

267 New cable from outlets to TRs 5 days Thu 11/26/26 Wed 12/2/26 266

268 New outlet connections 3 days Thu 12/3/26 Mon 12/7/26 267

269 Land cable on switches 2 days Tue 12/8/26 Wed 12/9/26 268

270 Test new telecom outlets / system 2 days Thu 12/10/26 Fri 12/11/26 269

271 DDC 1 day Mon 12/14/26 Mon 12/14/26 270

272 Demo old cable 3 days Mon 12/14/26 Wed 12/16/26 270

273 Clean and punch 3 days Thu 12/17/26 Mon 12/21/26 272

274 Building 205 - TR#20 37 days Thu 12/17/26 Fri 2/5/27

275 ICRA 2 days Thu 12/17/26 Fri 12/18/26 272

276 Abatement 3 days Mon 12/21/26 Wed 12/23/26 275

277 Demolition 3 days Thu 12/24/26 Mon 12/28/26 276

278 New walls, floors, doors 5 days Tue 12/29/26 Mon 1/4/27 12,5,277

279 Install CRAC 5 days Tue 1/5/27 Mon 1/11/27 278,11

280 Electrical and Lighting 5 days Tue 1/5/27 Mon 1/11/27 278,10

281 Security 5 days Tue 1/5/27 Mon 1/11/27 278,10

282 Fire suppression, FEC 3 days Tue 1/5/27 Thu 1/7/27 278,8

283 Telecom racks and switches 3 days Tue 1/5/27 Thu 1/7/27 278,9

284 Cable Tray and raceways 3 days Fri 1/8/27 Tue 1/12/27 283

285 New cable from outlets to TRs 5 days Wed 1/13/27 Tue 1/19/27 284

286 New outlet connections 3 days Wed 1/20/27 Fri 1/22/27 285

287 Land cable on switches 2 days Mon 1/25/27 Tue 1/26/27 286

288 Test new telecom outlets / system 2 days Wed 1/27/27 Thu 1/28/27 287

289 DDC 1 day Fri 1/29/27 Fri 1/29/27 288

DDC

Demo old cable

Clean and punch

Building 200/200E - TR#10A

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 200/200E - TR#10B

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 200/200E - TR#11

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 200/200E - TR#12

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 200/200E - TR#13

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 202 - TR#207E

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 204 - TR#19

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 205 - TR#20

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

J F M A M J J A S O N D J F M A M J J A S O N D J F Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028

Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress

290 Demo old cable 3 days Fri 1/29/27 Tue 2/2/27 288

291 Clean and punch 3 days Wed 2/3/27 Fri 2/5/27 290

292 Building 205 - TR#21 37 days Mon 2/8/27 Tue 3/30/27

293 ICRA 2 days Mon 2/8/27 Tue 2/9/27 291

294 Abatement 3 days Wed 2/10/27 Fri 2/12/27 293

295 Demolition 3 days Mon 2/15/27 Wed 2/17/27 294

296 New walls, floors, doors 5 days Thu 2/18/27 Wed 2/24/27 12,5,295

297 Install CRAC 5 days Thu 2/25/27 Wed 3/3/27 296,11

298 Electrical and Lighting 5 days Thu 2/25/27 Wed 3/3/27 296,10

299 Security 5 days Thu 2/25/27 Wed 3/3/27 296,10

300 Fire suppression, FEC 3 days Thu 2/25/27 Mon 3/1/27 296,8

301 Telecom racks and switches 3 days Thu 2/25/27 Mon 3/1/27 296,9

302 Cable Tray and raceways 3 days Tue 3/2/27 Thu 3/4/27 301

303 New cable from outlets to TRs 5 days Fri 3/5/27 Thu 3/11/27 302

304 New outlet connections 3 days Fri 3/12/27 Tue 3/16/27 303

305 Land cable on switches 2 days Wed 3/17/27 Thu 3/18/27 304

306 Test new telecom outlets / system 2 days Fri 3/19/27 Mon 3/22/27 305

307 DDC 1 day Tue 3/23/27 Tue 3/23/27 306

308 Demo old cable 3 days Tue 3/23/27 Thu 3/25/27 306

309 Clean and punch 3 days Fri 3/26/27 Tue 3/30/27 308

310 Building 205 - TR#22 37 days Wed 3/31/27 Thu 5/20/27

311 ICRA 2 days Wed 3/31/27 Thu 4/1/27 309

312 Abatement 3 days Fri 4/2/27 Tue 4/6/27 311

313 Demolition 3 days Wed 4/7/27 Fri 4/9/27 312

314 New walls, floors, doors 5 days Mon 4/12/27 Fri 4/16/27 12,313,5

315 Install CRAC 5 days Mon 4/19/27 Fri 4/23/27 314,11

316 Electrical and Lighting 5 days Mon 4/19/27 Fri 4/23/27 314,10

317 Security 5 days Mon 4/19/27 Fri 4/23/27 314,10

318 Fire suppression, FEC 3 days Mon 4/19/27 Wed 4/21/27 314,8

319 Telecom racks and switches 3 days Mon 4/19/27 Wed 4/21/27 314,9

320 Cable Tray and raceways 3 days Thu 4/22/27 Mon 4/26/27 319

321 New cable from outlets to TRs 5 days Tue 4/27/27 Mon 5/3/27 320

322 New outlet connections 3 days Tue 5/4/27 Thu 5/6/27 321

323 Land cable on switches 2 days Fri 5/7/27 Mon 5/10/27 322

324 Test new telecom outlets / system 2 days Tue 5/11/27 Wed 5/12/27 323

325 DDC 1 day Thu 5/13/27 Thu 5/13/27 324

326 Demo old cable 3 days Thu 5/13/27 Mon 5/17/27 324

327 Clean and punch 3 days Tue 5/18/27 Thu 5/20/27 326

328 Building 206 - TR#23 400 days Mon 7/20/26 Fri 1/28/28

329 ICRA 2 days Fri 5/21/27 Mon 5/24/27 327

330 Abatement 3 days Tue 5/25/27 Thu 5/27/27 329

331 Demolition 3 days Fri 5/28/27 Tue 6/1/27 330

332 New walls, floors, doors 5 days Wed 6/2/27 Tue 6/8/27 12,5,331

333 Install CRAC 5 days Wed 6/9/27 Tue 6/15/27 332,11

334 Electrical and Lighting 5 days Wed 6/9/27 Tue 6/15/27 332,10

335 Security 5 days Wed 6/9/27 Tue 6/15/27 332,10

336 Fire suppression, FEC 3 days Wed 6/9/27 Fri 6/11/27 332,8

337 Telecom racks and switches 3 days Wed 6/9/27 Fri 6/11/27 332,9

338 Cable Tray and raceways 3 days Mon 6/14/27 Wed 6/16/27 337

339 New cable from outlets to TRs 5 days Thu 6/17/27 Wed 6/23/27 338

340 New outlet connections 3 days Thu 6/24/27 Mon 6/28/27 339

341 Land cable on switches 2 days Tue 6/29/27 Wed 6/30/27 340

342 Test new telecom outlets / system 2 days Thu 7/1/27 Fri 7/2/27 341

343 DDC 1 day Mon 7/5/27 Mon 7/5/27 342

344 Demo old cable 3 days Mon 7/5/27 Wed 7/7/27 342

345 Clean and punch 3 days Thu 7/8/27 Mon 7/12/27 344

346 Building 206 - TR#24 400 days Mon 7/20/26 Fri 1/28/28

347 ICRA 2 days Tue 7/13/27 Wed 7/14/27 345

348 Abatement 3 days Thu 7/15/27 Mon 7/19/27 347

349 Demolition 3 days Tue 7/20/27 Thu 7/22/27 348

350 New walls, floors, doors 5 days Fri 7/23/27 Thu 7/29/27 349,12,5

351 Install CRAC 5 days Fri 7/30/27 Thu 8/5/27 350,11

352 Electrical and Lighting 5 days Fri 7/30/27 Thu 8/5/27 350,10

353 Security 5 days Fri 7/30/27 Thu 8/5/27 350,10

354 Fire suppression, FEC 3 days Fri 7/30/27 Tue 8/3/27 350,8

355 Telecom racks and switches 3 days Fri 7/30/27 Tue 8/3/27 350,9

356 Cable Tray and raceways 3 days Wed 8/4/27 Fri 8/6/27 355

357 New cable from outlets to TRs 5 days Mon 8/9/27 Fri 8/13/27 356

358 New outlet connections 3 days Mon 8/16/27 Wed 8/18/27 357

359 Land cable on switches 2 days Thu 8/19/27 Fri 8/20/27 358

360 Test new telecom outlets / system 2 days Mon 8/23/27 Tue 8/24/27 359

361 DDC 1 day Wed 8/25/27 Wed 8/25/27 360

362 Demo old cable 3 days Wed 8/25/27 Fri 8/27/27 360

363 Clean and punch 3 days Mon 8/30/27 Wed 9/1/27 362

364 Building 206 - TR#25 400 days Mon 7/20/26 Fri 1/28/28

365 ICRA 2 days Thu 9/2/27 Fri 9/3/27 363

366 Abatement 3 days Mon 9/6/27 Wed 9/8/27 365

367 Demolition 3 days Thu 9/9/27 Mon 9/13/27 366

368 New walls, floors, doors 5 days Tue 9/14/27 Mon 9/20/27 367,12,5

369 Install CRAC 5 days Tue 9/21/27 Mon 9/27/27 368,11

370 Electrical and Lighting 5 days Tue 9/21/27 Mon 9/27/27 368,10

371 Security 5 days Tue 9/21/27 Mon 9/27/27 368,10

372 Fire suppression, FEC 3 days Tue 9/21/27 Thu 9/23/27 368,8

373 Telecom racks and switches 3 days Tue 9/21/27 Thu 9/23/27 368,9

374 Cable Tray and raceways 3 days Fri 9/24/27 Tue 9/28/27 373

375 New cable from outlets to TRs 5 days Wed 9/29/27 Tue 10/5/27 374

376 New outlet connections 3 days Wed 10/6/27 Fri 10/8/27 375

377 Land cable on switches 2 days Mon 10/11/27 Tue 10/12/27 376

378 Test new telecom outlets / system 2 days Wed 10/13/27 Thu 10/14/27 377

379 DDC 1 day Fri 10/15/27 Fri 10/15/27 378

380 Demo old cable 3 days Fri 10/15/27 Tue 10/19/27 378

381 Clean and punch 3 days Wed 10/20/27 Fri 10/22/27 380

382 Building 207 - TR#26 400 days Mon 7/20/26 Fri 1/28/28

383 ICRA 2 days Mon 7/20/26 Tue 7/21/26 12,5

384 Abatement 3 days Wed 7/22/26 Fri 7/24/26 383

385 Demolition 3 days Mon 7/27/26 Wed 7/29/26 384

386 New walls, floors, doors 5 days Thu 7/30/26 Wed 8/5/26 385,12,5

387 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 386,11

388 Electrical and Lighting 5 days Thu 8/6/26 Wed 8/12/26 386,10

389 Security 5 days Thu 8/6/26 Wed 8/12/26 386,10

390 Fire suppression, FEC 3 days Thu 8/6/26 Mon 8/10/26 386,8

391 Telecom racks and switches 3 days Thu 8/6/26 Mon 8/10/26 386,9

392 Cable Tray and raceways 3 days Tue 8/11/26 Thu 8/13/26 391

393 New cable from outlets to TRs 5 days Fri 8/14/26 Thu 8/20/26 392

394 New outlet connections 3 days Fri 8/21/26 Tue 8/25/26 393

395 Land cable on switches 2 days Wed 8/26/26 Thu 8/27/26 394

396 Test new telecom outlets / system 2 days Fri 8/28/26 Mon 8/31/26 395

397 DDC 1 day Tue 9/1/26 Tue 9/1/26 396

398 Demo old cable 3 days Tue 9/1/26 Thu 9/3/26 396

399 Clean and punch 3 days Fri 9/4/26 Tue 9/8/26 398

400 Building 207 - TR#28 400 days Mon 7/20/26 Fri 1/28/28

401 ICRA 2 days Wed 9/9/26 Thu 9/10/26 399

402 Abatement 3 days Fri 9/11/26 Tue 9/15/26 401

403 Demolition 3 days Wed 9/16/26 Fri 9/18/26 402

404 New walls, floors, doors 5 days Mon 9/21/26 Fri 9/25/26 403,12,5

405 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 404,11

406 Electrical and Lighting 5 days Mon 9/28/26 Fri 10/2/26 404,10

407 Security 5 days Mon 9/28/26 Fri 10/2/26 404,10

408 Fire suppression, FEC 3 days Mon 9/28/26 Wed 9/30/26 404,8

409 Telecom racks and switches 3 days Mon 9/28/26 Wed 9/30/26 404,9

410 Cable Tray and raceways 3 days Thu 10/1/26 Mon 10/5/26 409

411 New cable from outlets to TRs 5 days Tue 10/6/26 Mon 10/12/26 410

412 New outlet connections 3 days Tue 10/13/26 Thu 10/15/26 411

413 Land cable on switches 2 days Fri 10/16/26 Mon 10/19/26 412

414 Test new telecom outlets / system 2 days Tue 10/20/26 Wed 10/21/26 413

415 DDC 1 day Thu 10/22/26 Thu 10/22/26 414

416 Demo old cable 3 days Thu 10/22/26 Mon 10/26/26 414

417 Clean and punch 3 days Tue 10/27/26 Thu 10/29/26 416

418 Building 208 - TR#29 400 days Mon 7/20/26 Fri 1/28/28

419 ICRA 2 days Fri 10/30/26 Mon 11/2/26 417

420 Abatement 3 days Tue 11/3/26 Thu 11/5/26 419

421 Demolition 3 days Fri 11/6/26 Tue 11/10/26 420

422 New walls, floors, doors 5 days Wed 11/11/26 Tue 11/17/26 421,12,5

423 Install CRAC 5 days Wed 11/18/26 Tue 11/24/26 422,11

424 Electrical and Lighting 5 days Wed 11/18/26 Tue 11/24/26 422,10

425 Security 5 days Wed 11/18/26 Tue 11/24/26 422,10

426 Fire suppression, FEC 3 days Wed 11/18/26 Fri 11/20/26 422,8

427 Telecom racks and switches 3 days Wed 11/18/26 Fri 11/20/26 422,9

428 Cable Tray and raceways 3 days Mon 11/23/26 Wed 11/25/26 427

429 New cable from outlets to TRs 5 days Thu 11/26/26 Wed 12/2/26 428

430 New outlet connections 3 days Thu 12/3/26 Mon 12/7/26 429

431 Land cable on switches 2 days Tue 12/8/26 Wed 12/9/26 430

432 Test new telecom outlets / system 2 days Thu 12/10/26 Fri 12/11/26 431

433 DDC 1 day Mon 12/14/26 Mon 12/14/26 432

434 Demo old cable 3 days Mon 12/14/26 Wed 12/16/26 432

Demo old cable

Clean and punch

Building 205 - TR#21

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 205 - TR#22

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 206 - TR#23

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 206 - TR#24

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 206 - TR#25

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 207 - TR#26

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 207 - TR#28

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 208 - TR#29

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

J F M A M J J A S O N D J F M A M J J A S O N D J F Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028

Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress

435 Clean and punch 3 days Thu 12/17/26 Mon 12/21/26 434

436 Building 209 - TR#30 400 days Mon 7/20/26 Fri 1/28/28

437 ICRA 2 days Tue 12/22/26 Wed 12/23/26 435

438 Abatement 3 days Thu 12/24/26 Mon 12/28/26 437

439 Demolition 3 days Tue 12/29/26 Thu 12/31/26 438

440 New walls, floors, doors 5 days Fri 1/1/27 Thu 1/7/27 439,12,5

441 Install CRAC 5 days Fri 1/8/27 Thu 1/14/27 440,11

442 Electrical and Lighting 5 days Fri 1/8/27 Thu 1/14/27 440,10

443 Security 5 days Fri 1/8/27 Thu 1/14/27 440,10

444 Fire suppression, FEC 3 days Fri 1/8/27 Tue 1/12/27 440,8

445 Telecom racks and switches 3 days Fri 1/8/27 Tue 1/12/27 440,9

446 Cable Tray and raceways 3 days Wed 1/13/27 Fri 1/15/27 445

447 New cable from outlets to TRs 5 days Mon 1/18/27 Fri 1/22/27 446

448 New outlet connections 3 days Mon 1/25/27 Wed 1/27/27 447

449 Land cable on switches 2 days Thu 1/28/27 Fri 1/29/27 448

450 Test new telecom outlets / system 2 days Mon 2/1/27 Tue 2/2/27 449

451 DDC 1 day Wed 2/3/27 Wed 2/3/27 450

452 Demo old cable 3 days Wed 2/3/27 Fri 2/5/27 450

453 Clean and punch 3 days Mon 2/8/27 Wed 2/10/27 452

454 Building 209 - TR#31 400 days Mon 7/20/26 Fri 1/28/28

455 ICRA 2 days Thu 2/11/27 Fri 2/12/27 453

456 Abatement 3 days Mon 2/15/27 Wed 2/17/27 455

457 Demolition 3 days Thu 2/18/27 Mon 2/22/27 456

458 New walls, floors, doors 5 days Tue 2/23/27 Mon 3/1/27 457,12,5

459 Install CRAC 5 days Tue 3/2/27 Mon 3/8/27 458,11

460 Electrical and Lighting 5 days Tue 3/2/27 Mon 3/8/27 458,10

461 Security 5 days Tue 3/2/27 Mon 3/8/27 458,10

462 Fire suppression, FEC 3 days Tue 3/2/27 Thu 3/4/27 458,8

463 Telecom racks and switches 3 days Tue 3/2/27 Thu 3/4/27 458,9

464 Cable Tray and raceways 3 days Fri 3/5/27 Tue 3/9/27 463

465 New cable from outlets to TRs 5 days Wed 3/10/27 Tue 3/16/27 464

466 New outlet connections 3 days Wed 3/17/27 Fri 3/19/27 465

467 Land cable on switches 2 days Mon 3/22/27 Tue 3/23/27 466

468 Test new telecom outlets / system 2 days Wed 3/24/27 Thu 3/25/27 467

469 DDC 1 day Fri 3/26/27 Fri 3/26/27 468

470 Demo old cable 3 days Fri 3/26/27 Tue 3/30/27 468

471 Clean and punch 3 days Wed 3/31/27 Fri 4/2/27 470

472 Building 210 - TR#32 400 days Mon 7/20/26 Fri 1/28/28

473 ICRA 2 days Mon 4/5/27 Tue 4/6/27 471

474 Abatement 3 days Wed 4/7/27 Fri 4/9/27 473

475 Demolition 3 days Mon 4/12/27 Wed 4/14/27 474

476 New walls, floors, doors 5 days Thu 4/15/27 Wed 4/21/27 475,12,5

477 Install CRAC 5 days Thu 4/22/27 Wed 4/28/27 476,11

478 Electrical and Lighting 5 days Thu 4/22/27 Wed 4/28/27 476,10

479 Security 5 days Thu 4/22/27 Wed 4/28/27 476,10

480 Fire suppression, FEC 3 days Thu 4/22/27 Mon 4/26/27 476,8

481 Telecom racks and switches 3 days Thu 4/22/27 Mon 4/26/27 476,9

482 Cable Tray and raceways 3 days Tue 4/27/27 Thu 4/29/27 481

483 New cable from outlets to TRs 5 days Fri 4/30/27 Thu 5/6/27 482

484 New outlet connections 3 days Fri 5/7/27 Tue 5/11/27 483

485 Land cable on switches 2 days Wed 5/12/27 Thu 5/13/27 484

486 Test new telecom outlets / system 2 days Fri 5/14/27 Mon 5/17/27 485

487 DDC 1 day Tue 5/18/27 Tue 5/18/27 486

488 Demo old cable 3 days Tue 5/18/27 Thu 5/20/27 486

489 Clean and punch 3 days Fri 5/21/27 Tue 5/25/27 488

490 Building 211 - TR#33 400 days Mon 7/20/26 Fri 1/28/28

491 ICRA 2 days Wed 5/26/27 Thu 5/27/27 489

492 Abatement 3 days Fri 5/28/27 Tue 6/1/27 491

493 Demolition 3 days Wed 6/2/27 Fri 6/4/27 492

494 New walls, floors, doors 5 days Mon 6/7/27 Fri 6/11/27 493,12,5

495 Install CRAC 5 days Mon 6/14/27 Fri 6/18/27 494,11

496 Electrical and Lighting 5 days Mon 6/14/27 Fri 6/18/27 494,10

497 Security 5 days Mon 6/14/27 Fri 6/18/27 494,10

498 Fire suppression, FEC 3 days Mon 6/14/27 Wed 6/16/27 494,8

499 Telecom racks and switches 3 days Mon 6/14/27 Wed 6/16/27 494,9

500 Cable Tray and raceways 3 days Thu 6/17/27 Mon 6/21/27 499

501 New cable from outlets to TRs 5 days Tue 6/22/27 Mon 6/28/27 500

502 New outlet connections 3 days Tue 6/29/27 Thu 7/1/27 501

503 Land cable on switches 2 days Fri 7/2/27 Mon 7/5/27 502

504 Test new telecom outlets / system2 days Tue 7/6/27 Wed 7/7/27 503

505 DDC 1 day Thu 7/8/27 Thu 7/8/27 504

506 Demo old cable 3 days Thu 7/8/27 Mon 7/12/27 504

507 Clean and punch 3 days Tue 7/13/27 Thu 7/15/27 506

508 Building 212 - TR#34 400 days Mon 7/20/26 Fri 1/28/28

509 ICRA 2 days Mon 7/20/26 Tue 7/21/26 12,5

510 Abatement 3 days Wed 7/22/26 Fri 7/24/26 509

511 Demolition 3 days Mon 7/27/26 Wed 7/29/26 510

512 New walls, floors, doors 5 days Thu 7/30/26 Wed 8/5/26 511,12,5

513 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 512,11

514 Electrical and Lighting 5 days Thu 8/6/26 Wed 8/12/26 512,10

515 Security 5 days Thu 8/6/26 Wed 8/12/26 512,10

516 Fire suppression, FEC 3 days Thu 8/6/26 Mon 8/10/26 512,8

517 Telecom racks and switches 3 days Thu 8/6/26 Mon 8/10/26 512,9

518 Cable Tray and raceways 3 days Tue 8/11/26 Thu 8/13/26 517

519 New cable from outlets to TRs5 days Fri 8/14/26 Thu 8/20/26 518

520 New outlet connections 3 days Fri 8/21/26 Tue 8/25/26 519

521 Land cable on switches 2 days Wed 8/26/26 Thu 8/27/26 520

522 Test new telecom outlets / system2 days Fri 8/28/26 Mon 8/31/26 521

523 DDC 1 day Tue 9/1/26 Tue 9/1/26 522

524 Demo old cable 3 days Tue 9/1/26 Thu 9/3/26 522

525 Clean and punch 3 days Fri 9/4/26 Tue 9/8/26 524

526 Building 221 - TR#35 363 days Wed 9/9/26 Fri 1/28/28

527 ICRA 2 days Wed 9/9/26 Thu 9/10/26 525

528 Abatement 3 days Fri 9/11/26 Tue 9/15/26 527

529 Demolition 3 days Wed 9/16/26 Fri 9/18/26 528

530 New walls, floors, doors 5 days Mon 9/21/26 Fri 9/25/26 529,12,5

531 Install CRAC 5 days Mon 10/12/26 Fri 10/16/26 530,11

532 Electrical and Lighting 5 days Mon 9/28/26 Fri 10/2/26 530,10

533 Security 5 days Mon 9/28/26 Fri 10/2/26 530,10

534 Fire suppression, FEC 3 days Mon 9/28/26 Wed 9/30/26 530,8

535 Telecom racks and switches3 days Mon 9/28/26 Wed 9/30/26 530,9

536 Cable Tray and raceways 3 days Thu 10/1/26 Mon 10/5/26 535

537 New cable from outlets to TRs5 days Tue 10/6/26 Mon 10/12/26 536

538 New outlet connections 3 days Tue 10/13/26 Thu 10/15/26 537

539 Land cable on switches 2 days Fri 10/16/26 Mon 10/19/26 538

540 Test new telecom outlets / system2 days Tue 10/20/26 Wed 10/21/26 539

541 DDC 1 day Thu 10/22/26 Thu 10/22/26 540

542 Demo old cable 3 days Thu 10/22/26 Mon 10/26/26 540

543 Clean and punch 3 days Tue 10/27/26 Thu 10/29/26 542

544 Building 323 - TR#36 326 days Fri 10/30/26 Fri 1/28/28

545 ICRA 2 days Fri 10/30/26 Mon 11/2/26 543

546 Abatement 3 days Tue 11/3/26 Thu 11/5/26 545

547 Demolition 3 days Fri 11/6/26 Tue 11/10/26 546

548 New walls, floors, doors5 days Wed 11/11/26 Tue 11/17/26 547,12,5

549 Install CRAC 5 days Wed 11/18/26 Tue 11/24/26 548,11

550 Electrical and Lighting 5 days Wed 11/18/26 Tue 11/24/26 548,10

551 Security 5 days Wed 11/18/26 Tue 11/24/26 548,10

552 Fire suppression, FEC 3 days Wed 11/18/26 Fri 11/20/26 548,8

553 Telecom racks and switches3 days Wed 11/18/26 Fri 11/20/26 548,9

554 Cable Tray and raceways3 days Mon 11/23/26 Wed 11/25/26 553

555 New cable from outlets to TRs5 days Thu 11/26/26 Wed 12/2/26 554

556 New outlet connections3 days Thu 12/3/26 Mon 12/7/26 555

557 Land cable on switches 2 days Tue 12/8/26 Wed 12/9/26 556

558 Test new telecom outlets / system2 days Thu 12/10/26 Fri 12/11/26 557

559 DDC 1 day Mon 12/14/26 Mon 12/14/26 558

560 Demo old cable 3 days Mon 12/14/26 Wed 12/16/26 558

561 Clean and punch 3 days Thu 12/17/26 Mon 12/21/26 560

562 Building 201 - TR#37A 289 days Tue 12/22/26 Fri 1/28/28

563 ICRA 2 days Tue 12/22/26 Wed 12/23/26 561

564 Abatement 3 days Thu 12/24/26 Mon 12/28/26 563

565 Demolition 3 days Tue 12/29/26 Thu 12/31/26 564

566 New walls, floors, doors5 days Fri 1/1/27 Thu 1/7/27 565,12,5

567 Install CRAC 5 days Fri 1/8/27 Thu 1/14/27 566,11

568 Electrical and Lighting5 days Fri 1/8/27 Thu 1/14/27 566,10

569 Security 5 days Fri 1/8/27 Thu 1/14/27 566,10

570 Fire suppression, FEC 3 days Fri 1/8/27 Tue 1/12/27 566,8

571 Telecom racks and switches3 days Fri 1/8/27 Tue 1/12/27 566,9

572 Cable Tray and raceways3 days Wed 1/13/27 Fri 1/15/27 571

573 New cable from outlets to TRs5 days Mon 1/18/27 Fri 1/22/27 572

574 New outlet connections3 days Mon 1/25/27 Wed 1/27/27 573

575 Land cable on switches2 days Thu 1/28/27 Fri 1/29/27 574

576 Test new telecom outlets / system2 days Mon 2/1/27 Tue 2/2/27 575

577 DDC 1 day Wed 2/3/27 Wed 2/3/27 576

578 Demo old cable 3 days Wed 2/3/27 Fri 2/5/27 576

579 Clean and punch 3 days Mon 2/8/27 Wed 2/10/27 578

Clean and punch

Building 209 - TR#30

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 209 - TR#31

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 210 - TR#32

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 211 - TR#33

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 212 - TR#34

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 221 - TR#35

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 323 - TR#36

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

Building 201 - TR#37A

ICRA

Abatement

Demolition

New walls, floors, doors

Install CRAC

Electrical and Lighting

Security

Fire suppression, FEC

Telecom racks and switches

Cable Tray and raceways

New cable from outlets to TRs

New outlet connections

Land cable on switches

Test new telecom outlets / system

DDC

Demo old cable

Clean and punch

J F M A M J J A S O N D J F M A M J J A S O N D J F Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028

Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress

580 Building 239 - TR#37B252 days Thu 2/11/27 Fri 1/28/28

581 ICRA 2 days Thu 2/11/27 Fri 2/12/27 579

582 Abatement 3 days Mon 2/15/27 Wed 2/17/27 581

583 Demolition 3 days Thu 2/18/27 Mon 2/22/27 582

584 New walls, floors, doors5 days Tue 2/23/27 Mon 3/1/27 583,12,5

585 Install CRAC 5 days Tue 3/2/27 Mon 3/8/27 584,11

586 Electrical and Lighting5 days Tue 3/2/27 Mon 3/8/27 584,10

587 Security 5 days Tue 3/2/27 Mon 3/8/27 584,10

588 Fire suppression, FEC 3 days Tue 3/2/27 Thu 3/4/27 584,8

589 Telecom racks and switches3 days Tue 3/2/27 Thu 3/4/27 584,9

590 Cable Tray and raceways3 days Fri 3/5/27 Tue 3/9/27 589

591 New cable from outlets to TRs5 days Wed 3/10/27 Tue 3/16/27 590

592 New outlet connections3 days Wed 3/17/27 Fri 3/19/27 591

593 Land cable on switches2 days Mon 3/22/27 Tue 3/23/27 592

594 Test new telecom outlets / system2 days Wed 3/24/27 Thu 3/25/27 593

595 DDC 1 day Fri 3/26/27 Fri 3/26/27 594

596 Demo old cable 3 days Fri 3/26/27 Tue 3/30/27 594

597 Clean and punch 3 days Wed 3/31/27 Fri 4/2/27 596

598 Building 203 - TR#17215 days Mon 4/5/27 Fri 1/28/28

599 ICRA 2 days Mon 4/5/27 Tue 4/6/27 597

600 Abatement 3 days Wed 4/7/27 Fri 4/9/27 599

601 Demolition 3 days Mon 4/12/27 Wed 4/14/27 600

602 New walls, floors, doors5 days Thu 4/15/27 Wed 4/21/27 601,12,5

603 Install CRAC 5 days Thu 4/22/27 Wed 4/28/27 602,11

604 Electrical and Lighting5 days Thu 4/22/27 Wed 4/28/27 602,10

605 Security 5 days Thu 4/22/27 Wed 4/28/27 602,10

606 Fire suppression, FEC 3 days Thu 4/22/27 Mon 4/26/27 602,8

607 Telecom racks and switches3 days Thu 4/22/27 Mon 4/26/27 602,9

608 Cable Tray and raceways3 days Tue 4/27/27 Thu 4/29/27 607

609 New cable from outlets to TRs5 days Fri 4/30/27 Thu 5/6/27 608

610 New outlet connections3 days Fri 5/7/27 Tue 5/11/27 609

611 Land cable on switches2 days Wed 5/12/27 Thu 5/13/27 610

612 Test new telecom outlets /

2 days Fri 5/14/27 Mon 5/17/27 611

613 DDC 1 day Tue 5/18/27 Tue 5/18/27 612

614 Demo old cable3 days Tue 5/18/27 Thu 5/20/27 612

615 Clean and punch3 days Fri 5/21/27 Tue 5/25/27 614

616 Building 240 - TR#3937 days Wed 5/26/27 Thu 7/15/27

617 ICRA 2 days Wed 5/26/27 Thu 5/27/27 615

618 Abatement 3 days Fri 5/28/27 Tue 6/1/27 617

619 Demolition 3 days Wed 6/2/27 Fri 6/4/27 618

620 New walls, floors, doors5 days Mon 6/7/27 Fri 6/11/27 619,12,5

621 Install CRAC 5 days Mon 6/14/27 Fri 6/18/27 620,11

622 Electrical and Lighting5 days Mon 6/14/27 Fri 6/18/27 620,10

623 Security 5 days Mon 6/14/27 Fri 6/18/27 620,10

624 Fire suppression, FEC 3 days Mon 6/14/27 Wed 6/16/27 620,8

625 Telecom racks and switches3 days Mon 6/14/27 Wed 6/16/27 620,9

626 Cable Tray and raceways3 days Thu 6/17/27 Mon 6/21/27 625

627 New cable from outlets to TRs5 days Tue 6/22/27 Mon 6/28/27 626

628 New outlet connections3 days Tue 6/29/27 Thu 7/1/27 627

629 Land cable on switches2 days Fri 7/2/27 Mon 7/5/27 628

630 Test new telecom outlets /

2 days Tue 7/6/27 Wed 7/7/27 629

631 DDC 3 days Thu 7/8/27 Mon 7/12/27 630

632 Demo old cable3 days Thu 7/8/27 Mon 7/12/27 630

633 Clean and punch3 days Tue 7/13/27 Thu 7/15/27 632

634 Building 248 - TR#40141 days Fri 7/16/27 Fri 1/28/28

635 ICRA 2 days Fri 7/16/27 Mon 7/19/27 633

636 Abatement 3 days Tue 7/20/27 Thu 7/22/27 635

637 Demolition 3 days Fri 7/23/27 Tue 7/27/27 636

638 New walls, floors, doors5 days Wed 7/28/27 Tue 8/3/27 637,12,5

639 Install CRAC 5 days Wed 8/4/27 Tue 8/10/27 638,11

640 Electrical and Lighting5 days Wed 8/4/27 Tue 8/10/27 638,10

641 Security 5 days Wed 8/4/27 Tue 8/10/27 638,10

642 Fire suppression, FEC 3 days Wed 8/4/27 Fri 8/6/27 638,8

643 Telecom racks and switches3 days Wed 8/4/27 Fri 8/6/27 638,9

644 Cable Tray and raceways3 days Mon 8/9/27 Wed 8/11/27 643

645 New cable from outlets to TRs5 days Thu 8/12/27 Wed 8/18/27 644

646 New outlet connections3 days Thu 8/19/27 Mon 8/23/27 645

647 Land cable on switches2 days Tue 8/24/27 Wed 8/25/27 646

648 Test new telecom outlets /

2 days Thu 8/26/27 Fri 8/27/27 647

649 DDC 1 day Mon 8/30/27 Mon 8/30/27 648

650 Demo old cable3 days Mon 8/30/27 Wed 9/1/27 648

651 Clean and punch3 days Thu 9/2/27 Mon 9/6/27 650

652 Building 248 - TR#41104 days Tue 9/7/27 Fri 1/28/28

653 ICRA 2 days Tue 9/7/27 Wed 9/8/27 651

654 Abatement3 days Thu 9/9/27 Mon 9/13/27 653

655 Demolition3 days Tue 9/14/27 Thu 9/16/27 654

656 New walls, floors, doors5 days Fri 9/17/27 Thu 9/23/27 655,12,5

657 Install CRAC5 days Fri 9/24/27 Thu 9/30/27 656,11

658 Electrical and Lighting5 days Fri…

This is the start of the file's text. The full file is on GovTribe.