S02 - SOW - Att 08 - Specs - Vol 1 - Div 02-14 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf

PDF 5 MB Posted

Attached to
Electronic Health Record Modernization Infrastructure Upgrades - Construction - Togus, ME
Solicitation number
36C77626R0062
Issued by

About this file

This is a 100% Construction Documents Specification for the Electronic Health Record Modernization (EHRM) Infrastructure Upgrades project at Togus VA Medical Center in Augusta, Maine. The document comprises a comprehensive technical specification covering Divisions 02-14 and 21-33, establishing detailed requirements for selective demolition, hazardous materials handling, asbestos remediation, lead remediation, and construction of mechanical, electrical, plumbing, and structural systems.

The specification requires the contractor to manage selective demolition of existing building portions while maintaining owner occupancy in non-affected areas, with provisions for protecting existing utilities, equipment, and finishes to remain. Hazardous materials handling must comply with federal transportation regulations (49 CFR 172, 173, 263), EPA standards (40 CFR 261-268, 761), and state requirements, including proper classification, packaging, labeling, placarding, manifesting, and disposal at permitted facilities. A designated Transportation and Disposal Coordinator with five years of specialized experience and DOT certification must oversee all hazardous waste management. Asbestos remediation must follow OSHA (29 CFR 1926.1101), EPA NESHAP (40 CFR 61 Subpart M), and Maine DEP requirements, requiring a State-accredited Project Designer to prepare the Asbestos Hazard Abatement Plan and a Competent Person to supervise on-site work. The contractor must establish negative pressure enclosures, conduct air monitoring, implement medical surveillance programs, and ensure all personnel receive EPA Model Accreditation Plan training and current Maine asbestos worker licenses. Additional specifications address lead remediation, construction waste management, fire suppression systems, plumbing, HVAC, electrical systems with backup power generation, communications infrastructure, physical security systems, and site utilities—all with commissioning and compliance documentation requirements prior to project completion.

View the file

Other files

File Type Posted
S30 - SAM - Special Notice - Cancellation - 36C77626R0062_2 - EHRM Infra Upgrades - Togus.pdf PDF
S06 - Amend 0002 - Att 03 - Corrected Agenda - RFP - 07202026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0002 - 36C77626R0062 - 07202026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - Att 02 - SV - Attendance SHT - 06292026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - 36C77626R0062 - 07142026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - RFIs - 07132026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S06 - Amend 0001 - Att 01 - Rvd Structural Drwg - 06192026 - EHRM Infra - Togus.pdf PDF
S06 - Amend 0001 - Att 03 - SV - Agenda - RFP - 06292026 - EHRM Infra - Togus.pdf PDF
S02 - SOW - Att 05 - Drwg - Vol 3 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 13 - Const Sch - 02132026 - EHRM Infra Upgrades - Constr Togus.pdf PDF
S02 - SOW - Att 26 - Cut Sheet 04 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 03 -Prj Info Sheet for KTR - EHRM Infra Upgrade - Togus.docx DOCX document
S02 - SOW - Att 03 - Drwg - Vol 1C - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 22 - TS-000 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 07 - 852.219-75 - 06172026 - EHRM Infra Upgrade - Togus.pdf PDF
S02 - Att 04 - Memo - Brand Name - 04092026 - EHRM Infra Upgrade - Togus.pdf PDF
S02 - SOW - Att 35 - Cut Sheet 13 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 17 - Memo - Phy Sec Compliance - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 27 - Cut Sheet 05 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 09 - Specs - Vol 3- 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 30 - Cut Sheet 08 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 24 - Cut Sheet 02 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 05 - Division Cost Breakdown - EHRM Infra Upgrade - Togus.xlsx XLSX spreadsheet
S02 - SOW - Att 29 - Cut Sheet 07 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 37 - Cut Sheet 15 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 16 - Submittal Reg - 02182026 - EHRM Infra - Upgrades - Constr - Togus.xlsx XLSX spreadsheet
S02 - SOW - Att 14 - Design Calcs - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 18 - Memo - Prj Stnd Compliance - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 21 - PCRA 3 - MCR and Trench Work - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 40 - Cut Sheet 18 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 33 - Cut Sheet 11 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 01 - Drwg - Vol 1A - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 38 - Cut Sheet 16 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 06 - Drwg - Vol 4 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 11 - Haz Mat Report - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 12 - Geotechnical Report - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 32 - Cut Sheet 10 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 20 - PCRA 2 - Cabling and Data Outlets - EHRM Infra Upgrades - Constr - Togus.pdf PDF
RFP - EHRM Infra Upgrade - 36C77626R0062 - 06172026 - Togus.pdf PDF
S02 - SOW - Att 19 - PCRA 1 - TR Constr - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 07 - Specs - Vol 1 - Div 00-01 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 15 - Design Narrative - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 23 - Cut Sheet 01 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 31 - Cut Sheet 09 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 02 - PPQ - EHRM Infra Upgrade - Togus.docx DOCX document
S02 - SOW - Att 02 - Drwg - Vol 1B - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 34 - Cut Sheet 12 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - Att 01 - SOW - 05112026 - EHRM Infra Upgrades - Togus.pdf PDF
S02 - SOW - Att 10 - Specs - Vol 4 - 02182026 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
S02 - SOW - Att 36 - Cut Sheet 14 - EHRM Infra Upgrades - Constr - Togus.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construction Documents – 100% CD Submittal: Specifications

Volume 1 – Division 02-14 Reissued February 18th, 2026

Department of Veterans Health Administration

Electronic Health Record Modernization (EHRM) Infrastructure Upgrades – Togus, ME Project No. 402-22-700

Contract No. 36C77623C0002

Togus VA Medical Center

1 VA Center, Augusta, ME 04330

US Department of Veterans Affairs

Program Contracting Activity Central (PCAC)

6150 Oak Tree Blvd., Suite 490

Independence, OH 44131

Prepared by:

GDM-AE, Inc.

1308 NE 134th St Suite A Vancouver, WA 98685

REISSUED 02-18-2026

VA Togus Medical Center 100% CONSTRUCTION DOCUMENTS Augusta,ME 02/18/2026

Electronic Health Records Modernization 00 01 10 -1 (EHRM) Infrastructure Upgrades, Togus, ME TABLE OF CONTENTS VA Project No. 402-22-700

SECTION 00 01 00

TABLE OF CONTENTS – 100% CONSTRUCTION DOCUMENTS

The following listed documents comprise the Project Manual for Electronic Health Record Modernization (EHRM) Infrastructure Upgrades at the Togus VA Medical Center in Augusta, Maine. Numbering of Divisions conforms to CSI Format for Building Specifications; Divisions and Sections not appearing are not applicable.

The following listed documents comprise the Project Manual for Electronic Health Record Modernization (EHRM) Infrastructure Upgrades at the Togus VA Medical Center in Augusta, Maine. Numbering of Divisions conforms to CSI Format for Building Specifications; Divisions and Sections not appearing are not applicable.

VOLUME ONE

00 01 00 Table of Contents

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15 List of Drawing Sheets

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01 14 00 Project Phasing 01 32 16.15 Project Schedule 01 33 23 Shop Drawings, Product Data, and Samples 01 35 26 Safety Requirements 01 42 19 Reference Standards 01 45 00 Quality Control 01 45 29 Testing Laboratory Services 01 56 00 Temporary Barriers and Enclosures 01 57 19 Temporary Environmental Controls 01 74 19 Construction Waste Management 01 81 11 Sustainable Construction Requirements 01 91 00 General Commissioning Requirements

END VOLUME ONE

VOLUME TWO

00 01 00 Table of Contents

DIVISION 02 – EXISTING CONDITIONS

02 41 19 Selective Demolition 02 81 00 Transportation and Disposal of Hazardous Materials 02 82 00 Asbestos Remediation 02 83 00 Lead Remediation

DIVISION 03 – CONCRETE

03 30 00 Cast-In-Place Concrete

DIVISION 04 – MASONRY

04 20 00 Unit Masonry 04 26 13 Masonry Veneer 04 72 00 Cast Stone Masonry

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 05 21 00 Steel Joist Framing 05 31 00 Steel Decking 05 40 00 Cold-Formed Metal Framing

Electronic Health Records Modernization 00 01 10 -2

VA Project No. 402-22-700

05 50 00 Metal Fabrications

05 52 13 PIPE AND TUBE RAILINGS

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

06 10 53 Miscellaneous Rough Carpentry 06 16 00 Sheathing 06 41 16 Plastic-Laminate-Clad Architectural Cabinets 06 64 00 Plastic Paneling

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 13 26 Self-Adhering Sheet Waterproofing 07 19 00 Water Repellents 07 21 00 Thermal Insulation 07 21 19 Foamed-In-Place Insulation 07 26 50 Underslab Vapor Barrier 07 27 26 Fluid-Applied Membrane Air Barriers 07 42 93 Soffit Panels 07 52 00 Modified Bitumen Membrane Roofing 07 62 00 Sheet Metal Flashing And Trim 07 72 00 Roof Accessories 07 84 00 Firestopping General Requirements 07 84 43 Joint Firestopping 07 92 00 Joint Sealants 07 92 19 Acoustic Joint Sealants

DIVISION 08 – OPENINGS

08 11 13 Hollow Metal Doors And Frames 08 31 13 Access Doors And Frames 08 33 23 Overhead Coiling Doors 08 34 00 Hot Aisle Containment System 08 41 13 Aluminum-Framed Entrances And Storefronts 08 41 23 Fire-Rated Aluminum Framed Entrances And Storefronts 08 71 00 Door Hardware 08 71 00A Door Hardware Groups 08 80 00 Glazing 08 88 13 Fire-Rated Glass 08 90 00 Louvers And Vents

DIVISION 09 – FINISHES

09 22 16 Non-Structural Metal Framing 09 29 00 Gypsum Board 09 30 13 Ceramic Tiling 09 51 13 Acoustic Panel Ceilings 09 65 13 Resilient Base And Accessories 09 65 36 Static-Control Resilient Flooring 09 68 13 Tile Carpeting 09 91 14 Exterior Painting 09 91 24 Interior Painting

DIVISION 10 – SPECIALTIES

10 26 00 Wall And Door Protection 10 28 00 Toilet, Bath And Laundry Accessories 10 44 13 Fire Protection Cabinets 10 44 19 Fire Extinguishers

DIVISION 11 – EQUIPMENT

11 13 19 Stationary Loading Dock Equipment

DIVISION 12 – FURNISHINGS

12 36 23.13 Plastic-Laminate-Clad Countertops

DIVISION 13 – SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements For Non-Structural Components

Electronic Health Records Modernization 00 01 10 -3

VA Project No. 402-22-700

DIVISION 14 – CONVEYING EQUIPMENT - NA

END OF VOLUME TWO

VOLUME THREE

00 01 00 Table Of Contents

DIVISION 21 – FIRE SUPPRESSION

21 08 00 Commissioning Of Fire Suppression Systems 21 13 13 Wet-Pipe Sprinkler Systems 21 13 45 Sprinkler Guards 21 22 00 Clean Agent Fire Suppression Systems

DIVISION 22 – PLUMBING

22 05 11 Common Work Results For Plumbing 22 05 12 General Motor Requirements For Plumbing Equipment 22 05 19 Meters And Gages For Plumbing Piping 22 05 23 General-Duty Valves For Plumbing Piping 22 05 33 Heat Tracing For Plumbing Piping 22 07 11 Plumbing Insulation 22 08 00 Commissioning Of Plumbing Systems 22 11 00 Facility Water Distribution 22 11 23 Domestic Water Pumps 22 13 00 Facility Sanitary And Vent Piping 22 14 00 Facility Storm Drainage 22 40 00 Plumbing Fixtures 22 62 00 Vacuum Systems For Laboratory And Healthcare Facilities 22 63 00 Gas Systems For Laboratory And Healthcare Facilities

DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 05 11 Common Work Results For Hvac 23 05 12 General Motor Requirements For Hvac And Steam Generation Equipment 23 05 41 Noise And Vibration Control For Hvac Piping And Equipment 23 05 93 Testing, Adjusting, And Balancing For Hvac 23 07 11 Hvac And Boiler Plant Insulation 23 08 00 Commissioning Of Hvac Systems 23 09 23 Direct-Digital Control System For Hvac 23 09 27 Data Center Cooling Optimization System 23 10 00 Facility Fuel Oil Systems 23 21 13 Hydronic Piping 23 22 13 Steam And Condensate Heating Piping 23 23 00 Refrigerant Piping 23 25 00 Hvac Water Treatment 23 31 00 Hvac Ducts And Casings 23 34 00 Hvac Fans 23 37 00 Air Outlets And Inlets 23 81 00 Decentralized Unitary Hvac Equipment 23 81 23 Computer-Room Air-Conditioners 23 81 45 Variable Refrigerant Flow Systems 23 82 00 Convection Heating And Cooling Units 23 85 00 Radon Mitigation Systems

DIVISION 26 – ELECTRICAL

26 05 11 - Requirements for Electrical Installations 26 05 13 - Medium-Voltage Cables 26 05 19 - Low-Voltage Electrical Power Conductors and Cables 26 05 26 - Grounding and Bonding for Electrical Systems 26 05 33 - Raceways and Boxes for Electrical Systems 26 05 41 - Underground Electrical Construction 26 05 73 - Overcurrent Protective Device Coordination Study 26 08 00 - Commissioning of Electrical Systems

Electronic Health Records Modernization 00 01 10 -4

VA Project No. 402-22-700

26 09 23 - Lighting Controls 26 12 19 - Pad-Mounted Liquid-Filled Medium-Voltage Transformers 26 13 16 - Medium-Voltage Fusible Interrupter Switches 26 22 00 - Low-Voltage Transformers 26 24 13 - Distribution Switchboards 26 24 16 - Panelboards 26 27 26 - Wiring Devices 26 29 21 - Enclosed Switches and Circuit Breakers 26 32 13 - Engine Generators 26 33 53 - Static Uninterruptible Power Supply 26 36 23 - Automatic Transfer Switches 26 41 00 - Facility Lightning Protection 26 43 13 - Surge Protective Devices 26 51 00 - Interior Lighting 26 56 00 - Exterior Lighting

VOLUME FOUR

DIVISION 27 – COMMUNICATIONS

270511 - Requirements for Communications Installations 270526 - Grounding and Bonding for Communications Systems 270533 - Conduits and Backboxes for Communications Systems 270536 - Cable Trays for Communications Systems 270553 - Identification for Communications Systems 270800 - Commissioning of Communications Systems 271000 - Structured Cabling 271116 - Communications Cabinets, Racks, Frames, and Enclosures 271119 - Communications Termination Blocks and Patch Panels 271126 - Communications Rack Mounted Power Protection and Power Strips 271313 - Communications Copper Backbone Cabling

271313.13 - Communications Copper Cable Splicing and Terminations 271323 - Communications Optical Fiber Backbone Cabling

271323.13 - Communications Optical Fiber Cable Splicing and Terminations 271513 - Communications Copper Horizontal Cabling 271619 - Communications Patch Cords, Station Cords, and Cross Connect Wire 275116 - Public Address and Mass Notification Systems

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

280500 - Common Work Results for Electronic Safety and Security 280513 - Conductors and Cables for Electronic Safety and Security 280526 - Grounding and Bonding for Electronic Safety and Security

280528.33 - Conduits and Backboxes for Electronic Safety and Security 280800 - Commissioning of Electronic Safety and Security Systems 281300 - Physical Access Control System 281353 - Security Access Detection 281600 - Intrusion Detection System 282300 - Video Surveillance 28 31 00 - Fire Detection And Alarm

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 31 23 19 Dewatering 31 32 19 Mechanically Stabilized Earth (MSE) Segmental Retaining Wall

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement And Concrete For Exterior Improvements 32 12 16 Asphalt Paving 32 17 13 Pavement Markings 32 90 00 Planting

DIVISION 33 – SITE UTILITIES

33 08 00 Commissioning Of Site Utilities 33 10 00 Water Utilities 33 30 00 Sanitary Sewer Utilities

Electronic Health Records Modernization 00 01 10 -5

VA Project No. 402-22-700

33 40 00 Storm Sewer Utilities

APPENDIX

40 00 00 Geotechnical Engineering Report

VA Togus Medical Center Augusta, ME

100% CONSTRUCTION DOCUMENTS

11/10/2025

Electronic Health Records Moderniza-tion EHRM Infrastructure Upgrades, Togus, ME

VA Project No. 402-22-700

02 41 19 - 1

SELECTIVE DEMOLITION

Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties. It was created by "A&E Architects - Billings - Main" for "Electronic Health Records Modernization EHRM Infrastructure Upgrades". A valid, current MasterSpec license is required for editing and use of this document for any other project.(22683)

SECTION 02 41 19 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure.

2. Demolition and removal of selected site elements.

3. Salvage of existing items to be reused or recycled.

B. Related Requirements:

1. Section 01 10 00 "Summary" for restrictions on use of the premises, Owner-occupancy requirements, and phasing requirements.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled.

B. Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and deliver to Owner ready for reuse or store as indicated in drawings.

C. Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage, prepare for reuse, and reinstall where indicated.

D. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.

E. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

1.3 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

EHRM Infrastructure Upgrades, Togus, ME

VA Project No. 402-22-700

02 41 19 - 2

Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties. It was created by "A&E Architects - Billings - Main" for "Electronic Health Records Modernization EHRM Infrastructure Upgrades". A valid, current MasterSpec license is required for editing and use of this document for any other project.(22683)

1. Carefully salvage in a manner to prevent damage and promptly return to Owner.

1.4 PREINSTALLATION MEETINGS

A. Predemolition Conference: Conduct conference at Project site .

1. Inspect and discuss condition of construction to be selectively demolished.

2. Review structural load limitations of existing structure.

3. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.

4. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.

5. Review areas where existing construction is to remain and requires protection.

1.5 INFORMATIONAL SUBMITTALS

A. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property , for environmental protection , for dust control and , for noise control. Indicate proposed locations and construction of barriers.

B. Schedule of Selective Demolition Activities: Indicate the following:

1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's on-site operations are uninterrupted.

2. Interruption of utility services. Indicate how long utility services will be interrupted.

3. Coordination for shutoff, capping, and continuation of utility services.

4. Coordination of Owner's continuing occupancy of portions of existing building and of Owner's partial occupancy of completed Work.

C. Predemolition Photographs or Video: Show existing conditions of adjoining construction, including finish surfaces, that might be misconstrued as damage caused by salvage and demolition operations.

1.6 CLOSEOUT SUBMITTALS

A. Inventory: Submit a list of items that have been removed and salvaged.

EHRM Infrastructure Upgrades, Togus, ME

VA Project No. 402-22-700

02 41 19 - 3

Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties. It was created by "A&E Architects - Billings - Main" for "Electronic Health Records Modernization EHRM Infrastructure Upgrades". A valid, current MasterSpec license is required for editing and use of this document for any other project.(22683)

1.7 FIELD CONDITIONS

A. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

1. Before selective demolition, Owner will remove the following items:

a. Existing furniture, furnishings, and equipment .

B. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

C. Hazardous Materials: Reference and/or request owner provided hazardous material report.

1. If suspected hazardous materials are encountered, do not disturb;

immediately notify Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.

D. Storage or sale of removed items or materials on-site is not permitted.

E. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

1.8 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties. Notify warrantor before proceeding. Existing warranties include the following:

1. Obtain list of existing products under warranty from owner.

1.9 COORDINATION

A. Arrange selective demolition schedule so as not to interfere with Owner's operations.

EHRM Infrastructure Upgrades, Togus, ME

VA Project No. 402-22-700

02 41 19 - 4

Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties. It was created by "A&E Architects - Billings - Main" for "Electronic Health Records Modernization EHRM Infrastructure Upgrades". A valid, current MasterSpec license is required for editing and use of this document for any other project.(22683)

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI/ASSP A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Review Project Record Documents of existing construction or other existing condition and hazardous material information provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents.

C. Perform an engineering survey of condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective building demolition operations.

1. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.

D. Verify that hazardous materials have been remediated before proceeding with building demolition operations.

E. Survey of Existing Conditions: Record existing conditions by use of measured drawings .

1. Before selective demolition or removal of existing building elements that will be reproduced or duplicated in final Work, make permanent record of measurements, materials, and construction details required to make exact reproduction.

3.2 PREPARATION

A. Refrigerant: Before starting demolition, remove refrigerant from mechanical equipment according to 40 CFR 82 and regulations of authorities having jurisdiction.

EHRM Infrastructure Upgrades, Togus, ME

VA Project No. 402-22-700

02 41 19 - 5

Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties. It was created by "A&E Architects - Billings - Main" for "Electronic Health Records Modernization EHRM Infrastructure Upgrades". A valid, current MasterSpec license is required for editing and use of this document for any other project.(22683)

3.3 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned:

Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Owner will arrange to shut off indicated services/systems when requested by Contractor.

2. Arrange to shut off utilities with utility companies.

3. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

4. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment.

d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.

f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.

g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material and leave in place.

3.4 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.

2. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.

EHRM Infrastructure Upgrades, Togus, ME

VA Project No. 402-22-700

02 41 19 - 6

Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties. It was created by "A&E Architects - Billings - Main" for "Electronic Health Records Modernization EHRM Infrastructure Upgrades". A valid, current MasterSpec license is required for editing and use of this document for any other project.(22683)

3. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.

4. Cover and protect furniture, furnishings, and equipment that have not been removed.

5. Comply with requirements for temporary enclosures, dust control, heating, and cooling specified in Section 01 50 00 "Temporary Facilities and Controls."

B. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

1. Strengthen or add new supports when required during progress of selective demolition.

C. Remove temporary barricades and protections where hazards no longer exist.

3.5 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.

2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

5. Maintain fire watch during and for at least one hours after flame-cutting operations.

6. Maintain adequate ventilation when using cutting torches.

7. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.

8. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.

EHRM Infrastructure Upgrades, Togus, ME

VA Project No. 402-22-700

02 41 19 - 7

Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties. It was created by "A&E Architects - Billings - Main" for "Electronic Health Records Modernization EHRM Infrastructure Upgrades". A valid, current MasterSpec license is required for editing and use of this document for any other project.(22683)

9. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

10. Dispose of demolished items and materials. Comply with Section 01 74 19 VA Construction Waste Management.

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

C. Removed and Salvaged Items:

1. Clean salvaged items.

2. Pack or crate items after cleaning. Identify contents of containers.

3. Store items in a secure area until delivery to Owner.

4. Transport items to Owner's storage area on-site .

5. Protect items from damage during transport and storage.

D. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

3.6 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS

A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.

B. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power-driven saw, and then remove concrete between saw cuts.

C. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, and then break up and remove.

EHRM Infrastructure Upgrades, Togus, ME

VA Project No. 402-22-700

02 41 19 - 8

Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties. It was created by "A&E Architects - Billings - Main" for "Electronic Health Records Modernization EHRM Infrastructure Upgrades". A valid, current MasterSpec license is required for editing and use of this document for any other project.(22683)

D. Resilient Floor Coverings: Remove floor coverings and adhesive according to recommendations in RFCI's "Recommended Work Practices for the Removal of Resilient Floor Coverings." Do not use methods requiring solvent-based adhesive strippers.

3.7 DISPOSAL OF DEMOLISHED MATERIALS

A. Remove demolition waste materials from Project site and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction. and recycle or dispose of them according to Section 01 74 19 "Construction Waste Management and Disposal."

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

4. Comply with requirements specified in Section 01 74 19 "Construction Waste Management."

B. Burning: Do not burn demolished materials.

3.8 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 02 41 19

Augusta, ME 11/10/2025

Electronic Health Records Modernization 02 81 00 - 1 of 15 (EHRM) Infrastructure Upgrades, Togus, ME TRANSPORTATION AND DISPOSAL OF Project No. 402-22-700 HAZARDOUS MATERIALS

SECTION 02 81 00

TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

PART 1 - GENERAL

1.1. CONTRACT DOCUMENTS AND RELATED REQUIREMENTS

A. Drawings, general provisions of the contract, including general and supplementary conditions and other Division 01 specifications, shall apply to the work of this section. The contract documents show or describe the work to be done under the contract and related requirements and conditions impacting the project. Related requirements and conditions include applicable codes and regulations, notices and permits, existing site conditions and restrictions on use of the site, requirements for partial owner occupancy during the work, coordination with other work and the phasing of the work. In the event the Contractor/Sub-Contractor discovers a conflict in the contract documents and/or requirements or codes, the conflict must be brought to the immediate attention of the COR for resolution. Whenever there is a conflict or overlap in the requirements, the most stringent shall apply. Any actions taken by the Contractor/Sub-Contractor without obtaining guidance from the COR shall become the sole risk and responsibility of the Contractor/Sub-Contractor. All costs incurred due to such action are also the responsibility of the Contractor/Sub-

Contractor.

1.2. RELATED WORK

A. 01 35 26 SAFETY REQUIREMENTS

B. 02 41 00 SELECTIVE DEMOLITION

C. 02 82 00 ASBESTOS REMEDIATION

D. 02 83 00 LEAD REMEDIATION

E. 07 84 00 FIRESTOPPING

F. Division 09 FINISHES

Electronic Health Records Modernization 02 81 00 - 2 of 15

1.3. REFERENCES

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

B. All work under this contract shall be done in strict accordance with all applicable federal, state, and local regulations, standards and codes governing hazardous materials-related work, and any other trade work done in conjunction with the project. All applicable codes, regulations and standards are adopted into this specification and will have the same force and effect as this specification.

C. The most recent edition of any relevant regulation, standard, document, or code shall be in effect. Where conflict among the requirements or with these specifications exists, the most stringent requirement(s) shall be utilized.

D. All related regulations, statutes, public laws, registers, and regulatory guidance are incorporated by reference.

INTERNATIONAL AIR TRANSPORT ASSOCIATION (IATA)

IATA DGR (2018) Dangerous Goods Regulations

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1926.59 Hazard Communication

29 CFR 1926.65 Hazardous Waste Operations and Emergency Response

40 CFR 61 National Emission Standards for Hazardous Air

Pollutants

40 CFR 261 Identification and Listing of Hazardous Waste

40 CFR 262 Standards Applicable to Generators of Hazardous Waste

40 CFR 263 Standards Applicable to Transporters of Hazardous

Waste

40 CFR 264 Standards for Owners and Operators of Hazardous Waste

Treatment, Storage, and Disposal Facilities

Electronic Health Records Modernization 02 81 00 - 3 of 15

40 CFR 265 Interim Status Standards for Owners and Operators of

Hazardous Waste Treatment, Storage, and Disposal

Facilities

40 CFR 266 Standards for the Management of Specific Hazardous

Wastes and Specific Types of Hazardous Waste

Management Facilities

40 CFR 268 Land Disposal Restrictions

40 CFR 270 EPA Administered Permit Programs: The Hazardous

Waste Permit Program

40 CFR 300 National Oil and Hazardous Substances Pollution

Contingency Plan

40 CFR 302 Designation, Reportable Quantities, and Notification

40 CFR 761 Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in Commerce, and Use

Prohibitions

49 CFR 107 Hazardous Materials Program Procedures

49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency

Response Information, and Training Requirements

49 CFR 173 Shippers - General Requirements for Shipments and

Packagings

49 CFR 178 Specifications for Packagings

1.4. DEFINITIONS

A. Contracting Officer Representative (COR)

1. The VA official responsible for monitoring on-going project work.

B. Hazardous Material

1. A substance or material which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce, and

Electronic Health Records Modernization 02 81 00 - 4 of 15 which has been so designated pursuant to the Hazardous Materials

Transportation Act, 49 U.S.C. Appendix Section 1801 et seq. The term includes materials designated as hazardous materials under the provisions of 49 CFR 172, Sections .101 and .102 and materials which meet the defining criteria for hazard classes and divisions in 49 CFR 173. EPA designated hazardous wastes are also hazardous materials.

C. Hazardous Waste

1. A waste which meets criteria established in RCRA or specified by the EPA in 40 CFR 261, or the criteria established by the applicable state of Maine Administrative Rules; or the criteria established by the applicable sections of the Maine Codified Laws.

1.5. SUBMITTALS

A. Submit the following in accordance with Section 01 33 23, SHOP

DRAWINGS, PRODUCT DATA, AND SAMPLES:

1. Preconstruction Submittals

a. Asbestos Abatement Plan, prepared in accordance with the requirements of Maine Department of Environmental Protection

(DEP)

b. Lead Based Paint Abatement Plan, prepared in accordance with the requirements of Maine Department of Environmental

Protection (DEP)

c. Packaging Notifications

d. Hazardous Waste Management Plan

e. Onsite Hazardous Waste Management

f. Notices of Non-Compliance and Notices of Violation

g. Transportation and Disposal Coordinator

h. Organization Chart, Qualifications, Training, Licenses

Certification

i. Security Plan

Electronic Health Records Modernization 02 81 00 - 5 of 15

j. Spill Response Plan

k. Waste Minimization Plan

2. Periodic Submittals

a. Updates to any of the preconstruction submittals

3. Closeout Submittals

a. Recordkeeping

b. Exception Report

c. Shipping Documents and Packagings Certification

d. Certificates of Disposal

e. In addition to these submittals, the closeout submittals shall include all updates to previously submitted information as necessary to ensure the documentation requirements of this section are fulfilled.

1.6. QUALITY ASSURANCE

A. Transportation and Disposal Coordinator

1. Designate, by position and title, one person to act as the

Transportation and Disposal Coordinator (TDC) for this contract.

The TDC must serve as the single point of contact for all environmental regulatory matters and have overall responsibility for total environmental compliance at the site including, but not limited to, accurate identification and classification of hazardous waste and hazardous materials; determination of proper shipping names; identification of marking, labeling, packaging and placarding requirements; completion of waste profiles, hazardous waste manifests, asbestos waste shipment records, PCB manifests, bill of ladings, exception and discrepancy reports; and all other environmental documentation. The TDC must have, at a minimum, five years of specialized experience in the management and transportation of hazardous waste and have been Department of

Transportation certified under 49 CFR 172, Subpart H.

B. Training

Electronic Health Records Modernization 02 81 00 - 6 of 15

1. Hazardous materials employees must be trained, tested, and certified to safely and effectively carry out their assigned duties in accordance with 29 CFR 1926.59, 29 CFR 1926.65, and 49

CFR 172, Subpart H. Employees transporting hazardous materials or preparing hazardous materials for transportation, including samples, must be trained, tested, and certified in accordance with

49 CFR 172, Subpart H, including security awareness and any applicable security plans. Hazardous material employees must also be trained in accordance with IATA DGR when shipping hazardous materials by air.

C. Certification

1. The hazardous materials transporter must possess a current certificate of registration issued by the Research and Special

Programs Administration (RSPA), U.S. Department of Transportation, when required by 49 CFR 107, Subpart G. Submit copies of the certificates or written statements certifying exemption from these requirements.

1.7. LAWS AND REGULATIONS REQUIREMENTS

A. Comply with Federal, state, and local laws and regulations which are applicable. These requirements are amended frequently and compliance with amendments is required as they become effective. Notify the

Contracting Officer immediately if compliance exceeds the scope of work or conflicts with specific requirements of the contract.

PART 2 - PRODUCTS

2.1. MATERIALS

A. Provide all the materials required for the packaging, labeling, marking, placarding and transportation of hazardous wastes and hazardous materials in conformance with Department of Transportation standards and IATA DGR. Details in this specification must not be construed as establishing the limits of the Contractor's responsibility.

Electronic Health Records Modernization 02 81 00 - 7 of 15

2.2. PACKAGINGS

A. Provide bulk and non-bulk containers for packaging hazardous materials/wastes consistent with the authorizations referenced in the

Hazardous Materials Table in 49 CFR 172, Section .101, Column 8. Bulk and non-bulk packaging must meet the corresponding specifications in

49 CFR 173 referenced in the Hazardous Materials Table, 49 CFR 172, Section .101. Packaging must conform to the general packaging requirements of Subpart B of 49 CFR 173, to the requirements of 49 CFR

178 at the specified packing group performance level, to the requirements of special provisions of column 7 of the Hazardous

Materials Table in 49 CFR 172, Section .101, and be compatible with the material to be packaged as required by 40 CFR 262. Also provide other packaging related materials such as materials used to cushion or fill voids in overpacked containers. The hazardous materials being packaged must not react dangerously with, decompose, or ignite the sorbent packaging materials. Additionally, sorbents used to treat free liquids to be disposed of in landfills must be non-biodegradable as specified in 40 CFR 264, Section .314. In addition, packaging notifications will be provided to the Government in accordance with 49

CFR 172, Section .178.2(c) regarding type and dimensions of closures, including gaskets, needed to satisfy performance test requirements.

2.3. MARKINGS

A. Provide markings for each hazardous material/waste package, freight container, and transport vehicle consistent with the requirements of

49 CFR 172, Subpart D; 40 CFR 262, Section .32 (for hazardous waste);

40 CFR 761, Section .45 (for PCBs); and 40 CFR 61, Section .149(d)

(for asbestos). Markings must withstand a 180-day exposure to conditions reasonably expected to be encountered during container storage and transportation, without deterioration or substantial color change.

2.4. LABELING

A. Provide primary and subsidiary labels for hazardous materials/wastes consistent with the requirements in the Hazardous Materials Table in

49 CFR 172, Section .101, Column 6. Labels must meet design specifications required by 49 CFR 172, Subpart E including size, Electronic Health Records Modernization 02 81 00 - 8 of 15 shape, color, printing, and symbol requirements. Labels must be durable weather resistant and withstanding a 180-day exposure to conditions reasonably expected to be encountered during container storage and transportation, without deterioration or substantial color change.

2.5. PLACARDS

A. For each offsite shipment of hazardous material/waste, provide primary and subsidiary placards consistent with the requirements of 49 CFR

172, Subpart F. Provide placards for each side and each end of bulk packaging, freight containers, transport vehicles, and rail cars requiring such placarding. Placards may be plastic, metal, or other material capable of withstanding, without deterioration, a 30-day exposure to open weather conditions and must meet design requirements specified in 49 CFR 172, Subpart F.

2.6. SPILL RESPONSE MATERIALS

A. Provide spill response materials including, but not limited to, containers, adsorbent, shovels, and personal protective equipment.

Spill response materials must be available at all times when hazardous materials/wastes are being handled or transported. Spill response materials must be compatible with the type of material being handled.

2.7. EQUIPMENT AND TOOLS

A. Provide miscellaneous equipment and tools necessary to handle hazardous materials and hazardous wastes in a safe and environmentally sound manner.

PART 3 - EXECUTION

3.1. HAZARDOUS WASTE MANAGEMENT PLAN

A. Prepare a Hazardous Waste Management Plan detailing the manner in which hazardous wastes will be managed and describing the types and volumes of hazardous wastes anticipated to be managed. The plan must address both onsite and offsite hazardous waste management. Describe the methods to be used to ensure accurate piece counts or weights of shipments; describe waste minimization methods; identify and describe

Electronic Health Records Modernization 02 81 00 - 9 of 15 facilities to be used for treatment, storage, and disposal (TSD);

identify areas onsite where hazardous wastes are to be handled; and identify whether transfer facilities are to be used; and if so, how the wastes will be tracked to ultimate disposal. Submit the plan to the Contracting Officer for approval prior to start of work. Submit written documentation of weekly hazardous waste inspections on a monthly basis.

3.2. ONSITE HAZARDOUS WASTE MANAGEMENT

A. Coordinate the onsite management of all hazardous materials and waste with the COR. These paragraphs apply to Government owned waste only.

The Contractor is responsible for ensuring compliance with federal, state, and local hazardous waste laws and regulations and verifying those requirements when preparing reports, waste shipment records, hazardous waste manifests, or other documents. Identify hazardous wastes using criteria set forth in 40 CFR 261 or applicable state and local laws, regulations, and ordinances. Comply with generator requirements in 40 CFR 262 when accumulating hazardous waste onsite.

Onsite accumulation times must be restricted to applicable time frames referenced in 40 CFR 262, Section .34 or as otherwise directed by the

COR. Accumulation start dates commence when waste container is transferred into a 90 day accumulation site or permitted storage facility. Only use containers in good condition and compatible with the waste to be stored. Ensure containers are closed except when adding or removing waste, and immediately mark all hazardous waste containers with the words "hazardous waste" and other information required by 40 CFR 262, Section .32 as soon as the waste is containerized. An additional marking must be placed on containers of

"unknowns" designating the date sampled, and the suspected hazard.

Inspect containers for signs of deterioration and for responding to any spills or leaks. Inspect all hazardous waste areas weekly and provide written documentation of the inspection. Include date and time of inspection, name of individual conducting the inspection, problems noted, and corrective actions taken on the inspection logs.

Electronic Health Records Modernization 02 81 00 - 10 of 15

3.3. HAZARDOUS WASTE CLASSIFICATION

A. Identify all waste codes applicable to each hazardous waste stream based on requirements in 40 CFR 261 or applicable state or local law or regulation. Also identify applicable treatment standards in 40 CFR

268 and state land disposal restrictions and make a determination as to whether or not the waste meets or exceeds the standards. Submit waste profiles, analyses, classification, and treatment standards information to COR for review and approval.

3.4. OFFSITE HAZARDOUS WASTE MANAGEMENT

A. Coordinate the offsite transfer of all hazardous materials and waste with the COR. Use RCRA Subtitle C permitted facilities which meet the requirements of 40 CFR 264 or facilities operating under interim status which meet the requirements of 40 CFR 265. Do not use offsite treatment, storage, and disposal facilities with significant RCRA violations or compliance problems (such as facilities known to be releasing hazardous constituents into ground water, surface water, soil, or air). Submit Notices of Non-Compliance and Notices of

Violation by a federal, state, or local regulatory agency issued to the Contractor in relation to any work performed under this contract.

Immediately provide copies of such notices to the Contracting Officer.

Also furnish relevant documents regarding the incident and any information requested by the COR and coordinate its response to the notice with the COR prior to submission to the notifying authority.

Also furnish a copy to the COR of all documents submitted to the regulatory authority, including the final reply to the notice, and all other materials, until the matter is resolved.

3.5. TREATMENT, STORAGE, AND DISPOSAL FACILITY AND TRANSPORTER

A. Provide the COR with EPA ID numbers, names, locations, and telephone numbers of TSD facilities and transporters. This information must be contained in the Hazardous Waste Management Plan and be approved by the COR prior to waste disposal.

3.6. FACILITY STATUS INFORMATION

A. Facilities receiving hazardous waste must be permitted in accordance with 40 CFR 270 or operating under interim status in accordance with

Electronic Health Records Modernization 02 81 00 - 11 of 15

40 CFR 265 requirements or permitted by a state authorized by the

Environmental Protection Agency to administer the RCRA permit program.

Additionally, prior to using a TSD Facility, contact the EPA Regional

Offsite Coordinator specified in 40 CFR 300, Section .440, to determine the facility's status, and document all information necessary to satisfy the requirements of the EPA Offsite policy and submit this information to the COR in the Hazardous Waste Management

Plan.

3.7. SHIPPING DOCUMENTS AND PACKAGINGS CERTIFICATION

A. Prior to shipment of any hazardous material offsite, and a minimum of

5 days prior to anticipated pickup, provide for review written certification to the COR that hazardous materials have been properly packaged, labeled, and marked in accordance with Department of

Transportation and EPA requirements. Furnish designated disposal facility packaging assurances not later than 35 days after acceptance of the shipment. The Contractor's TDC must also provide written certification regarding waste minimization efforts documenting that efforts have been taken to reduce the volume and toxicity of waste to the degree economically practicable and that the method of treatment, storage, or disposal selected minimizes threats to human health and the environment.

3.8. TRANSPORTATION

A. Prior to conducting hazardous materials activities, the Contractor responsible for pre-transportation activities must either certify to the Government that a Security Plan is in place which meets the requirements of 49 CFR 172, Subpart I or in the event that the types or amounts of hazardous materials are excluded from the security planning requirements, a written statement to that effect detailing the basis for the exception. Use manifests for transporting hazardous wastes as required by 40 CFR 263 or applicable state or local law or regulation. Transportation must comply with all requirements in the

Department of Transportation referenced regulations in the 49 CFR series. Prepare hazardous waste manifests for each shipment of hazardous waste shipped offsite. Complete manifests using instructions in 40 CFR 262, Subpart B and applicable state or local

Electronic Health Records Modernization 02 81 00 - 12 of 15 law or regulation. Submit manifests and waste profiles to the COR for review and approval. Prepare land disposal restriction notifications as required by 40 CFR 268 or applicable state or local law or regulation for each shipment of hazardous waste. Submit notifications with the manifest to the COR for review and approval.

3.9. TREATMENT AND DISPOSAL OF HAZARDOUS WASTES

A. Coordinate any offsite shipments of hazardous materials or hazardous wastes with the COR. Initial, or satellite hazardous waste accumulation is limited to 55 gallons (or 1 quart of acutely hazardous waste). Once a waste stream exceeds 55 gallons, it must be transferred to an on-site 90-day (180-day small quantity generator) accumulation area, or a permitted hazardous waste treatment, storage, or disposal facility within three days. Ship hazardous wastes only to facilities which are properly permitted to accept the hazardous waste or operating under interim status. Ensure wastes are treated to meet land disposal treatment standards in 40 CFR 268 prior to land disposal. Propose TSD facilities via submission of the Hazardous

Waste Management Plan, subject to the approval of the COR. Submit

Certificates of Disposal documenting the ultimate disposal, destruction or placement of hazardous wastes, polychlorinated biphenyls (PCBs), and asbestos within 90 days of initial shipment.

Receipt of these certificates will be required for final payment.

3.10. IDENTIFICATION OF PROPER SHIPPING NAMES

A. Use 49 CFR 172, Section .101 to identify…