This is a Task Group Instruction (TGI) document for installing and removing scaffolding on the USS HOWARD (DDG-83). The work involves erecting and removing scaffolding at multiple locations throughout the ship, including areas between the 01 and 02 Level Weather (frames 105-115), 04 Level Weather (frames 125-130, 185-190, 217-225, and 235-245), and 02 Level Weather (frames 140-160 and 165-175). Each scaffolding installation requires temporary containment enclosures to prevent environmentally hazardous materials from entering surrounding waters.

The work is scheduled to be performed between April 7, 2025 and August 26, 2025 at Ship Repair Facility-Japan Regional Maintenance Center (SRF-JRMC). SRF-JRMC will provide support services including crane operations, rigging, electrical utilities, low pressure air, water supply, steam supply, safety inspections, gas free inspections, and QA inspections. The scaffolding will support Ship's Force maintenance work on various components including the CIWS MT 21 bulkhead, pilothouse windows, SLQ-32 platforms, life rafts, and multiple antenna platforms.

View the file

Other files

File Type Posted
2.03 Amendment 0011 25RA007.pdf PDF
2.01 Amendment 0010 25RA007.pdf PDF
2.01 Amendment 0009 25RA007.pdf PDF
2.01 Amendment 0008 25RA007.pdf PDF
2.01 Amendment 0007 25RA007.pdf PDF
TGI 38JC286401A01 rev1.pdf PDF
TGI 38JC258801A01 rev1.pdf PDF
TGI 38JC2123ANA01 rev1.pdf PDF
TGI 38JC252101A01 rev1.pdf PDF
TGI 38JC263401A01 rev1.pdf PDF
TGI 38JC258802A01 rev1.pdf PDF
TGI 38JC263402A01 rev1.pdf PDF
TGI 38JC212364A01 rev1.pdf PDF
TGI 38JC259301A01 rev1.pdf PDF
TGI 38JC286503A01 rev1.pdf PDF
TGI 38JC2123AMA01 rev2.pdf PDF
TGI 38JC212301A01 rev1.pdf PDF
2.01 Amendment 0006 25RA007.pdf PDF
TGI 38JC213601A01 rev1.pdf PDF
TGI 38JC212302A01 rev1.pdf PDF
2.01 Amendment 0005 25RA007.pdf PDF
Revised TGI 38JC263401A01.pdf PDF
2.01 Amendment 0004 25RA007.pdf PDF
2.01 Amendment 0003 25RA007.pdf PDF
2.01 Amendment 0002 25RA007.pdf PDF
2.01 Amendment 0001 25RA007.pdf PDF
TGI 38JC2123AMA01 rev1.pdf PDF
TGI 38JC2123ANA01.pdf PDF
TGI 38JC212364A01.pdf PDF
TGI 38JC213601A01.pdf PDF
TGI 38JC258802T01.pdf PDF
TGI 38JC259301T01.pdf PDF
TGI 38JC252101T01.pdf PDF
TGI 38JC258802A01.pdf PDF
TGI 38JC212302T01.pdf PDF
TGI 38JC263402A01.pdf PDF
TGI 38JC212302A01.pdf PDF
TGI 38JC212364T01.pdf PDF
2.03 Attachment IV N6264925RA007 Request for Information Form.doc DOC document
TGI 38JC259301A01.pdf PDF
TGI 38JC211001A01.pdf PDF
TGI 38JC212301T01.pdf PDF
TGI 38JC263401T02.pdf PDF
2.03 Attachment III N6264925RA007 Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
TGI 38JC212301A01.pdf PDF
TGI 38JC258801A01.pdf PDF
TGI 38JC263401T01.pdf PDF
N6264925RA007.pdf PDF
TGI 38JC2123AMA01.pdf PDF
TGI 38JC252101A01.pdf PDF
Show 40 more

Latest 50 of 54 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

FOUO: Public availability to be determined under 5 USC 552

TASK GROUP INSTRUCTION

AIM REV 20.11.4.0 (OCTOBER 2020)

TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:

NO.: TEMPORARY STAGING SF TST A 0 0

SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:

DDG-83 USS HOWARD 86512 JC2

CU PHASE TITLE:

*F/O - INSTALL AND REMOVE SCAFFOLDING TO/FROM VARIOUS LOCATION

PREPARING ACTIVITY:

PREPARED BY: CODE PHONE DATE

TAKAYUKI TAKEISHI 231B 315-243-6704 07-AUG-2024

APPROVED BY: CODE PHONE DATE

RYOUTA TAKAGI 231B 315-243-4502 07-AUG-2024

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

CONCURRED BY: CODE PHONE DATE

REASON FOR WORK/NEED FOR CHANGE:

CHANGE INSTRUCTIONS:

SPECIAL REQUIREMENTS:

WORK CERTIFICATION SIGNATURES

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

ACCEPTANCE OF COMPLETED WORK

PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:

REQUIRED:☐YES ☒NO

RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

TGI NO.: TEMPORARY STAGING SF TST A 0

FOUO

SHIP: DDG-83 CHG/VER: 0/0

LIST OF EFFECTIVE PAGES

SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.

1-4 J-1 M-1

1. SCOPE/PURPOSE:

1.1 Title: Scaffolding for Ship’s Force Work; install and remove

1.2 Location of work:

1.2.1 Between 01 Level and 02 Level Weather, Frames between 105 and 115, Port and Starboard (Stbd)

1.2.2 04 Level Weather, Frames between 125 and 130, Port and Stbd

1.2.3 02 Level Weather, Frames between 140 and 160, Port and Stbd

1.2.4 02 Level Weather, Frames between 165 and 175, Stbd

1.2.5 04 Level Weather, Frames between 185 and 190, Port and Stbd

1.2.6 04 Level Weather, Frames between 217 and 225, Port and Stbd

1.2.7 04 Level Weather, Frames between 235 and 245, Port and Stbd

1.3 Identification:

1.3.1 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.1 Remarks: Maintenance work of bulkhead of underneath CIWS MT 21 will be accomplished by Ship's Force.

1.3.2 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.2 Remarks: Maintenance work of pilothouse windows will be accomplished by Ship's Force.

1.3.3 Quantity (2 Lot), Scaffolding Assembly

Location: 1.2.3 Remarks: Maintenance work of SLQ-32 platforms will be accomplished by Ship's Force.

1.3.4 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.4 Remarks: Maintenance work of life raft will be accomplished by Ship's Force.

1.3.5 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.5 Remarks: Maintenance work of antenna numbers 3-21 and 3-10B platforms will be accomplished by Ship's

Force.

FOUO

SHIP: DDG-83 CHG/VER: 0/0

1.3.6 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.6 Remarks: Maintenance work of antenna number 2-3 platform will be accomplished by Ship's Force.

1.3.7 Quantity (One Lot), Scaffolding Assembly

Location: 1.2.7 Remarks: Maintenance work of antenna number 2-4 platform will be accomplished by Ship's Force.

1.3.8 Quantity (One Lot), Temporary Containment Enclosure

Location: 1.2.1 Remarks: Maintenance work of bulkhead of underneath CIWS MT 21 will be accomplished by Ship's Force.

1.3.9 Quantity (One Lot), Temporary Containment Enclosure

Location: 1.2.2 Remarks: Maintenance work of pilothouse windows will be accomplished by Ship's Force.

1.3.10 Quantity (2 Lot), Temporary Containment Enclosure

Location: 1.2.3 Remarks: Maintenance work of SLQ-32 platforms will be accomplished by Ship's Force.

1.3.11 Quantity (One Lot), Temporary Containment Enclosure

Location: 1.2.4 Remarks: Maintenance work of life raft will be accomplished by Ship's Force.

1.3.12 Quantity (One Lot), Temporary Containment Enclosure

Location: 1.2.5 Remarks: Maintenance work of antenna numbers 3-21 and 3-10B platforms will be accomplished by Ship's

Force.

1.3.13 Quantity (One Lot), Temporary Containment Enclosure

Location: 1.2.6 Remarks: Maintenance work of antenna number 2-3 platform will be accomplished by Ship's Force.

1.3.14 Quantity (One Lot), Temporary Containment Enclosure

Location: 1.2.7 Remarks: Maintenance work of antenna number 2-4 platform will be accomplished by Ship's Force.

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date:

1.7 Contractor work completion date:

2. REFERENCES:

4/7/2025

8/26/2025

FOUO

SHIP: DDG-83 CHG/VER: 0/0

REF.

NO.

DOCUMENT

/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV CHG

NO.

COPY

REQ’D

(Y/N)

SOURCE

DOC

(Y/N)

PARA SEC PG CHP

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

3 TM 29 CFR

PART

1915.71

Scaffolding or Staging - N

3. APPENDICES:

3.1 Appendix “J” TGI Job Summary Information Sheet

3.2 Appendix "M" TGI Material List

3.3 Appendix “D” Deficiency Form

4. GENERAL REQUIREMENTS:

4.1 Not Applicable.

5. PROCEDURE:

5.1 Erect/hang scaffolding listed in 1.3.1 through 1.3.7 in accordance with 2.3.

5.2 Install each temporary containment enclosure listed in 1.3.8 through 1.3.14 to each scaffolding listed in 1.3.1 through 1.3.7 to prevent environmentally hazardous material from entering surrounding waters.

5.3 Remove each temporary containment enclosure listed in 1.3.8 through 1.3.14 upon completion of the work from each scaffolding listed in 1.3.1 through 1.3.7 when requested by Ship’s Force via Code 333.

5.4 Remove scaffolding listed in 1.3.1 through 1.3.7 upon completion of the work in accordance with 2.3 when requested by Ship’s Force via Code 333.

5.5 Notes:

5.5.1 Planner: Code 231B T. Takeishi, 243-6704

5.5.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

5.5.3 JCN EXSY-ZAC2 is related to this TGI.

5.6 Government Furnished Material (GFM): None.

5.7 SRF-JRMC will provide the following service work: (TGI No. 38JC286503S02)

5.7.1 [C740] Provide Crane and crane rigging service.

5.7.2 [X99E] Provide utility service, electrical.

5.7.3 [X99M] Provide utility service, including low pressure air, water supply, and steam supply.

5.7.4 [C106.1] Provide Safety inspection for SRF-JRMC employees.

5.7.5 [C106.2] Provide gas free inspection for SRF-JRMC employees.

5.7.6 [C133] Provide QA inspection for (G) symbol(s).

C1209.3 Shimizu, 11120180, SS, 8/30/2024

Shinya.Shimizu.ja Line

TGI NO.: TEMPORARY STAGING

SF

TST A 0

FOUO

M-1

SHIP: DDG-83 CHG/VER: 0/0

APPENDIX “M”

TGI MATERIAL LIST

SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH

VERSION:

CASREP

CAT:

86512 TEMPORARY STAGING SF TST A 0 0

CU PHASE TITLE:

*F/O - INSTALL AND REMOVE SCAFFOLDING TO/FROM VARIOUS LOCATION

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING

NUMBER

DOCUMENT/DRAWING TITLE REV

JOB ORDER: KEY OP:

38JC286503 A01

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

NOTES:

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR APPENDIX "D"

DEFICIENCY FORM

☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One)

2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

DDG-83 TEMPORARY STAGING SF TST A 0

4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:

38JC286503 A01

7. DESCRIPTION:

8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

9. CORRECTIVE ACTION:

10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:

FOR NON-NUCLEAR USE ONLY

11. RFD/RFW REQ’D ☐ LAR REQ'D ☐

ILS MOD REQ’D ☐

SRD/PLAN REV REQ'D ☐

DWG NO.: _____________________ S/A NO.: ___________________

12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:

SATISFACTORY:

13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

YES ☐ NO ☐

14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE:

15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

_________:YES ☐ NO ☐

16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.

COMPLETE (DR ONLY)

DL’s ISSUED

(DR ONLY)

FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____

☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR

1. SHIP/HULL NO.: 2a. DL or DR No.

(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:

DDG-83 TEMPORARY STAGING SF TST A 0