This is a Task Group Instruction (TGI) document for inspection and preservation work on the deck plating in compartment 1-399-0-J (Helicopter Fueling Station) aboard the USS HOWARD (DDG-83). The work involves ultrasonic thickness measurement (UTM) of 100 SF of structural plating and preservation of 105 SF of deck plating, including vertical surfaces up to 12 inches from deck level, arranged in a 12-inch x 12-inch grid pattern.
The contractor work period is scheduled from April 15, 2024 to October 2, 2024. The procedure requires UTM measurements according to specified technical references, with results to be submitted to the supervisor. Additional preservation work must comply with reference 009-32, Table 3, Line 6 requirements. SRF-JRMC will provide support services including crane operations, utilities (electrical, air, water, and steam), safety inspections, gas-free inspections, and QA inspections. The work stems from inspection report CCIMS-G1N6-DDG83-038-24 and is associated with JCN ES01-NP4E.
View the file
Other files
Show 40 more
Latest 50 of 54 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
22-JUL-2024 0938
20.14.12.0.8874 (April 2024) ICN: 38JC263402 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 1-399-0-J MS A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-83 USS HOWARD JC2 13111
CU PHASE TITLE: F/O - INSPECT AND PRESERVE DECK PLATING IN 1-399-0-J
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 4
ES01NP4E
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
NAKANO, SEIICHI 231B 3152434519 19-JUL-2024
APPROVED BY: CODE: PHONE: DATE:
TAKAGI, RYOUTA 231B 3152434502 19-JUL-2024
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
ES01-NP4E
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE 1-399-0-J 1 U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
634A2102
1 SCOPE/PURPOSE:
1.1 Title: Deck Plating in 1-399-0-J; inspect and preserve
1.2 Location of Work:
1.2.1 Helicopter Fueling Station (1-399-0-J)
1.3 Identification:
1.3.1 Quantity (100 SF), Structural Plating in 1-399-0-J, including vertical surface up to height of 12 inches from deck
Reading Point: 12 Inches x 12 Inches Grid Pattern Remarks:
See Ref. No. 5 for base material.
The area excepts structural shapes.
TGI Short Form
22-JUL-2024 0938
20.14.12.0.8874 (April 2024) (Continued) ICN: 38JC263402 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 1-399-0-J MS A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-83 USS HOWARD JC2 13111
CU PHASE TITLE: F/O - INSPECT AND PRESERVE DECK PLATING IN 1-399-0-J
FOUO Pg 2 of 4
CU PHASE DESCRIPTION (Cont.)
1.3.2 Quantity (105 SF), Entire Deck Plating in 1-399-0-J, including vertical surface up to height of 12 inches from deck
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor work start date: 4/15/2024
1.7 Contractor work completion date: 10/2/2024
2. PROCEDURE:
2.1 Accomplish ultrasonic thickness measurement (UTM) on each area listed in 1.3.1 in accordance with Paragraph 6.7 of Ref. No. 3, and Ref. No. 4, using Ref. No. 5 for guidance.
2.1.1 Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 2.1 to the SUPERVISOR.
2.2 Accomplish the requirements of 009-32 of Ref. No. One, including Table 3, Line(s) 6, for each area listed in 1.3.2.
2.3 Notes:
2.3.1 Planner: Code 231B S. Nakano, 243-4519
Planner: Code 234 S. Yamashita, 243-8308
2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.3.3 This TGI is in response to inspection report No. CCIMS-G1N6-DDG83-038-24 from TGI No. 38JCA11006I04.
2.3.4 JCN ES01-NP4E is related to this TGI.
2.4 Government Furnished Material (GFM): None.
2.5 SRF-JRMC will provide the following service work: (TGI No. 38JC263402S02)
2.5.1 [C740] Crane and crane rigging service.
2.5.2 [X99E] Utility service, electrical.
2.5.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.5.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.5.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.5.6 [C133] QA inspection for (G) symbol(s).
22-JUL-2024 0938
20.14.12.0.8874 (April 2024) (Continued) ICN: 38JC263402 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 1-399-0-J MS A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-83 USS HOWARD JC2 13111
CU PHASE TITLE: F/O - INSPECT AND PRESERVE DECK PLATING IN 1-399-0-J
FOUO Pg 3 of 4
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
22-JUL-2024 0938
20.14.12.0.8874 (April 2024) (Continued) ICN: 38JC263402 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 1-399-0-J MS A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-83 USS HOWARD JC2 13111
CU PHASE TITLE: F/O - INSPECT AND PRESERVE DECK PLATING IN 1-399-0-J
FOUO Pg 4 of 4
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 TM T9074-AS-GIB-
010/271 Requirements for Nondestructive Testing Methods
1 N
4 TM S9086-DA-STM-
010/CH-100
Hull Structures 4 N
5 DWG 100-7026705 UNIT STRL ARR DWG - ASSY
UNIT 3340
H Y 3
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 38JC263402 KEY OP: A01