TGI 38JC252101A01 rev1.pdf
PDF 2 MB Posted
- Solicitation number
- N6264925RA007
About this file
This is a Task Group Instruction (TGI) for replacing overboard discharge piping on the USS HOWARD (DDG-83). The work involves replacing fireman overboard discharge piping assembly in Auxiliary Machinery Room No. One, including a 2-1/2 inch IPS steel pipe assembly, 3-1/2 inch nozzle assembly with flange, and waster sleeve components. The work affects frames between 131-137 on the port side and requires Class P-2 piping with Level III cleanliness standards.
The work is scheduled to begin April 14, 2025 and complete by September 3, 2025. Special requirements include fabricating/staging a non-flammable closure since the work affects a fire zone boundary. The work will be performed as part of Job Order 38JC252101 with PROJ/WO No. JC2. The file includes detailed material specifications, referenced technical documents, and quality assurance requirements including hydrostatic testing at 50 PSIG. SRF-JRMC will provide various support services including crane operations, utilities, and safety/QA inspections.
View the file
Other files
Show 40 more
Latest 50 of 54 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
4/14/2025
9/3/2025
C1209.3 Shimizu, 11120180, SS, 9/7/2024