This document is an Amendment of Solicitation for an Indefinite-Delivery Indefinite-Quantity (IDIQ) Small Business Multiple Award Construction Contract issued by the Naval Facilities Engineering Command (NAVFAC) for general construction projects at Marine Corps Base Camp Lejeune and Marine Corps Air Station Cherry Point. The procurement is a total small business set-aside, with all correspondence to be directed to Jonathan Durham via email.
Amendment 0009 clarifies responses to previous Potential Pricing Inquiries (PPIs), specifically addressing schedule requirements for the technical proposal and seed project. Key clarifications include: a schedule is not required as part of the technical proposal submission, Specification Section 01 32 17 (Cost-Loaded Network Analysis Schedules) can be deleted entirely, and the firm awarded the seed project will be required to provide a schedule as part of pre-construction submittals. The amendment was issued on 08-Apr-2025 and does not extend the solicitation's receipt of offer date.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Indefinite-Delivery Indefinite-Quantity Small Business Multiple Aw ard Construction Contract for General Construction Projects Primarily aboard Marine Corps Base Camp Lejeune and Marine Corps Air Station Cherry Point in the NAVFAC MIDLANT Marine Corps Installation East Area of Responsibility
This procurement is being solicited as a total small business set-aside.
All correspondence regarding this solicitation shall be directed via email to Jonathan Durham at jonathan.m.durham.civ@us.navy.mil
See Continuation Page
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 08-Apr-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008524R2785
X 9B. DATED (SEE ITEM 11)
11-Feb-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Apr-2025
CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008524R2785
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0009
The purpose of this amendment is to:
1. Clarify the Responses to PPI #153
1. Clarify the Responses to PPI #2, #34, and #153
No Date
Submitted
Reference Question Response
Page Section Para
2 This section states that the Evaluation Factors for Award under Factor 3 include a Management Approach and Schedule, however, detailed instructions for Factor 3 on page 14 of 87 do not mention any requirement for a Schedule. Please confirm that a schedule IS NOT required for the Technical Proposal.
Schedule is not required as part of the technical proposal.
34 Spec Section 01 32 17 (COSTLOADED NETWORK ANALYSIS SCHEDULES) is in conflict with the requirements of Spec Section 01 32 16
(CONSTRUCTION PROGRESS
DOCUMENTATION). Currently, the specified requirement for all MACC Task Orders performed at MCB Camp Lejeune only requires schedules to be submitted in accordance with Spec Section 01 32 16.
Also, Cost-Loaded are extremely expensive to build & maintain. Can Spec Section 01 32 17 be deleted be Amendment?
Spec Section 01 32 17 can be deleted in its entirety. See attached revised specifications.
153 04/03/2025 Does this solicitation require a baseline schedule for the seed project? Page 6 of the solicitation under "Evaluation Factors for Award" it states the following:
The solicitation requires the evaluation of price and the following non-cost/price factors. Factor 1 - Corporate Experience. Factor 2 - Safety. Factor 3 - Management Approach and Schedule. Factor 4 - Past Performance.
Amendment 0004 provided a revised specification for such but does not identify a schedule as being required for the seed. Please advise.
Yes, the solicitation requires a baseline schedule be provided for the seed project in accordance with specification section 01 32 16.00 20.
To confirm, per PPI Response #2 a schedule is not required to be submitted for the technical proposal.
- SEE BELOW THE TABLE
N4008524R2785
To clarify, the firm that is awarded the seed project will be required to provide a schedule, per the specifications referenced in PPI Responses #34 and #153, as part of the pre-construction submittals.