About this file

This is Amendment 0002 to solicitation N4008524R2785 for an Indefinite-Delivery Indefinite-Quantity (IDIQ) Small Business Multiple Award Construction Contract for general construction projects at Marine Corps Base Camp Lejeune and Marine Corps Air Station Cherry Point in the NAVFAC MIDLANT Marine Corps Installation East Area of Responsibility.

The amendment makes two key changes: 1) Revises the site visit requirements to reduce the advance notice needed for obtaining visitor passes from 24 hours to 2-3 hours prior to scheduled visit time, and 2) Provides responses to questions about project experience requirements, confirming that the minimum requirements remain unchanged ($5M for at least 3 projects with one being $10M+), proposal submission requirements (one electronic copy each of price and non-price proposals), teaming arrangements (first-tier subcontractors used for corporate experience must be small businesses), and other administrative clarifications. The amendment maintains this as a total small business set-aside with plans to award approximately five contracts, though more or fewer awards may be made based on best value to the government.

View the file

Other files

File Type Posted
N4008524R2785 Amendment 0007.pdf PDF
N4008524R2785 Amendment 0006.pdf PDF
VMR- uncapped.jpg JPG image
E-101.pdf PDF
E-105.pdf PDF
M103.pdf PDF
M104.pdf PDF
M602.pdf PDF
A-202.pdf PDF
E-106.pdf PDF
M802.pdf PDF
23 73 33_Amendment 2.pdf PDF
E-103.pdf PDF
E-104.pdf PDF
E-107.pdf PDF
M601.pdf PDF
VMR- capped.jpg JPG image
T-1.pdf PDF
N4008524R2785 Amendment 0005.pdf PDF
23 09 00.pdf PDF
23 09 23.13 20 Attachment 4.pdf PDF
N4008524R2785 Amendment 0004.pdf PDF
Attachment Q - Revised Drawings.pdf PDF
23 09 23.13 20 Attachment 5.pdf PDF
01 32 16.00 20.pdf PDF
22 00 00.pdf PDF
23 09 23.13 20 Attachment 2.pdf PDF
23 09 13.pdf PDF
23 09 23.02.pdf PDF
Attachment N - Revised Eletrical-Telecomm Sheets.pdf PDF
Attachment O - Revised Specs pg3.pdf PDF
Attachment M - Specifications TOC.pdf PDF
N4008524R2785 Amendment 0003.pdf PDF
Attachment P - Site Visit Log.pdf PDF
Attachment I - Site Visit Information REVISED.pdf PDF
Attachment I - Site Visit Information.pdf PDF
Attachment J - Site Visit Participant Log.xlsx XLSX spreadsheet
Attachment L - Electrical Room.pdf PDF
N4008524R2785 Amendment 0001.pdf PDF
Attachment K - Asbestos Inspection Report.pdf PDF
N4008524R2785 Small Business Marine Corps MACC for General Construction.pdf PDF
Attachment A - PPI LOG TEMPLATE.xlsx XLSX spreadsheet
Attachment B - CONSTRUCTION AND DESIGN EXPERIENCE PROJECT DATA.docx DOCX document
Attachment E - B1005 Drawings.pdf PDF
Attachment F - B1005 Specifications.pdf PDF
Attachment H - PIEE VENDOR ACCESS INSTRUCTIONS.pdf PDF
N4008524R2785 Small Business Marine Corps MACC for General Construction.pdf PDF
Attachment C- PAST PERFORMANCE QUESTIONNAIRE.docx DOCX document
Attachment D - B1005 Price Proposal Form.docx DOCX document
Attachment G - B1005 Statement of Work.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Indefinite-Delivery Indefinite-Quantity Small Business Multiple Aw ard Construction Contract for General Construction Projects Primarily aboard Marine Corps Base Camp Lejeune and Marine Corps Air Station Cherry Point in the NAVFAC MIDLANT Marine Corps Installation East Area of Responsibility

This procurement is being solicited as a total small business set-aside.

All correspondence regarding this solicitation shall be directed via email to Jonathan Durham at jonathan.m.durham.civ@us.navy.mil

See Continuation Page

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 28-Feb-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008524R2785

X 9B. DATED (SEE ITEM 11)

11-Feb-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

28-Feb-2025

CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008524R2785

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0002

The purpose of this amendment is to:

1. Incorporate Attachment I – Site Visit Information REVISED (attached separately)

2. Incorporate PPI Responses

1. Incorporate Attachment I – Site Visit Information REVISED (attached separately)

Please see the attachment for the full document. The following changes have been made:

From:

• Participants without DBIDS access are required to obtain a visitor’s pass from either the MCB Camp

Lejeune Visitors Center or the MCAS New River Visitors Center minimum 24 hours prior to the scheduled site visit date.

To:

• Participants without DBIDS access are required to obtain a visitor’s pass from either the MCB Camp

Lejeune Visitors Center or the MCAS New River Visitors Center minimum of 2-3 hours prior to the scheduled site visit time.

2. Incorporate PPI Responses

Number

LEAVE

BLANK

Reference Question Response

Page Section Paragraph

Will you be providing asbestos and lead reports?

Asbetos report was included in Amendment 0001 as Attachment K. The building has already been abated for lead, so there is no report.

13 9 00 21 00 Factor 1

For the proposals, Corporate Experience we are to submit a minimum of 3 projects with "A final construction cost of at least $5,000,000. (At least one project must demonstrate with a final construction cost of at least $10,000,000.)". Would the Govt consider reducing these amounts to a minimum of $1M and at least one over $4M. The current range of $5M/$10M is very hard for a small businesses to meet and will severely limit competition. We are able to bond projects up to $18M single project value.

Bid per RFP

14 9 of 87 4 Factor 1

Increased Competition: You state that the final construction cost must be at least $5,000,000, and at least one project must demonstrate a final construction cost of at least $10,000,000. As the historical contract data indicates there were 59 TO < $1M (33 of these < $500K), 28 TO between $1M and $3M, 9 TO between $3M and $5M, 10 TO between $5M and $10M, and 16 TO > $10M, would you lower the project size requirements to align with the types of previously awarded projects (i.e., final construction above $3M, and at least one project above $5M)?

Bid per RFP

15 5 of 87 1 1.3.5

Limiting Costs for Small Businesses:

The solicitation states, “The Government intends to award approximately five (5) contracts resulting from this solicitation to the responsible Offerors whose proposals represent the best values after evaluation in accordance with the factors and their relative importance, unless more or less than five (5) is determined to be the best value to the government by the Source Selection Authority”, but on the prior contract there were 10 awardees. In addition, you state, “a MACC awardee can only elect to withdraw from submitting a proposal on three (3) task order RFPs during the course of each year of the contract (base plus four options).”

Based on the historical task data of the existing contract, an awardee is expected to submit 20-30 bids each year. Would you increase this restriction to withdraw from up to seven (7) per year? And increase it further or remove it altogether if you select more than five (5) awardees?

No changes will be made

16 Page 1 of 87

SF1442 Block 13

SF1442 Block 13, item A indicated submission of original and 1 copies.

Since the proposal response will be submitted electronically, please confirm one electronic original will be sufficient to meet submission requirements.

One electronic copy of the price and one electronic copy of the non-price proposal will be sufficient.

17 Page 9 of 87

00 21 00 Factor 1

Would the government respectfully consider lowering the minimum project size value stated in Section 00 21 00 - Factor 1, Corporate Experience

(1) Solicitation Submittal Requirements, Subfactor Size. “A final construction cost of at least $5,000,000” to $3,000,000 in alignment with the task order range noted on page 5 of 87, paragraph 1.3.3 “$250,000 and $15,000,000” and on page 80 of 87, paragraph Estimated Budget Amount or Price Range "...of $1,000,000 to $5,000,000."

Bid per RFP

18 14 of 87 RFP NCP Factor

Can the reference to PPQs or CPARS previously submitted for other RFPs indicated in Factor 4 of the Non-Cost Proposal requirements for Offerors be deleted by Amendment?

No. Incorporating by reference PPQs or CPARS submitted as part of other proposals will not be accepted. PPQs and/or CPARS are required to be submitted per the submittal requirements in Factor 4

19 9 of 87 RFP NCP Factor

As the estimated construction cost range for the upcoming MACC Task Orders will be between $250,000 and $15,000,000, may one or two projects with a final construction cost between $2,000,000 and $5,000,000 be included in an offeror's proposal if the requirement for a minimum size of $5,000,000,with one project over $10,000,000, is maintained for at least

(3) projects?

Bid per RFP

N/A Solicitation N/A

Are Offerors permitted to include proposal covers, title pages, and tables of contents for each volume outside of the page count?

Yes, that is allowed

Pages 11 and 12

Solicitation

Page 11 (last paragraph and page 12 (first paragraph)

Does the agency expect teaming affiliates to mean all non-related small business companies that are team subcontractors under the contract must be considered small collectively?

If prime contractor desires to satisfy the Corporate Experience factor through providing experience of a first-tier subcontractor that first-tier subcontractor must be a small business in accordance with Factor 1. A team member identified in the proposal, but not being utilized to satisfy the Corporate Experience requirement, can be either large or small businesses.

However, the offeror must comply with the self-performance requirements as set forth in the solicitation.

N/A Attachment

B N/A

Are Offerors permitted to recreate Attachment B for inclusion in proposals as long as all information is included in the recreated document?

Submit data using the provided attachment.

N/A Attachment

G N/A

This attachment is labeled as a Statement of Work; however, it is only half a page long. Should there be additional information located in this document as it appears to inculde only the second page of the Attachment H?

Attachment G - Statement of Work was included to provide a 1 page summary of the project. Attachment F provides the full set of specifications.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .