About this file

This document is an electrical lighting plan drawing (E-103) for the Design Wing Relocation in Building 1005 at Marine Corps Base Camp Lejeune. The lighting plan provides detailed specifications for a renovation project, including several key requirements:

The drawing outlines new work requirements for electrical and lighting systems, specifically to: provide a new lighting plan, install new luminaires and lighting circuits, add occupancy and vacancy sensors, install new lighting control panels, provide emergency lighting and exit signs, and ensure branch circuits meet minimum specifications. The plan includes general notes emphasizing contractor responsibilities such as reviewing electrical drawings, surveying existing conditions, coordinating power outages with the government, field verifying all circuits and dimensions, and routing conduit and circuits to avoid interference with existing systems. The document is part of a project with contract number 60036663 and revision 1.2, prepared for the Marine Corps Base Design Wing Relocation project.

View the file

Other files

File Type Posted
N4008524R2785 Amendment 0007.pdf PDF
N4008524R2785 Amendment 0006.pdf PDF
VMR- uncapped.jpg JPG image
E-101.pdf PDF
E-105.pdf PDF
M103.pdf PDF
M104.pdf PDF
M602.pdf PDF
23 73 33_Amendment 2.pdf PDF
E-104.pdf PDF
E-107.pdf PDF
M601.pdf PDF
A-202.pdf PDF
E-106.pdf PDF
M802.pdf PDF
VMR- capped.jpg JPG image
T-1.pdf PDF
N4008524R2785 Amendment 0005.pdf PDF
23 09 00.pdf PDF
23 09 23.13 20 Attachment 4.pdf PDF
01 32 16.00 20.pdf PDF
22 00 00.pdf PDF
23 09 23.13 20 Attachment 2.pdf PDF
N4008524R2785 Amendment 0004.pdf PDF
Attachment Q - Revised Drawings.pdf PDF
23 09 23.13 20 Attachment 5.pdf PDF
23 09 13.pdf PDF
23 09 23.02.pdf PDF
Attachment N - Revised Eletrical-Telecomm Sheets.pdf PDF
Attachment O - Revised Specs pg3.pdf PDF
Attachment M - Specifications TOC.pdf PDF
N4008524R2785 Amendment 0003.pdf PDF
Attachment P - Site Visit Log.pdf PDF
N4008524R2785 Amendment 0002.pdf PDF
Attachment I - Site Visit Information REVISED.pdf PDF
Attachment I - Site Visit Information.pdf PDF
Attachment J - Site Visit Participant Log.xlsx XLSX spreadsheet
Attachment L - Electrical Room.pdf PDF
N4008524R2785 Amendment 0001.pdf PDF
Attachment K - Asbestos Inspection Report.pdf PDF
N4008524R2785 Small Business Marine Corps MACC for General Construction.pdf PDF
Attachment A - PPI LOG TEMPLATE.xlsx XLSX spreadsheet
Attachment B - CONSTRUCTION AND DESIGN EXPERIENCE PROJECT DATA.docx DOCX document
Attachment E - B1005 Drawings.pdf PDF
Attachment F - B1005 Specifications.pdf PDF
Attachment H - PIEE VENDOR ACCESS INSTRUCTIONS.pdf PDF
N4008524R2785 Small Business Marine Corps MACC for General Construction.pdf PDF
Attachment C- PAST PERFORMANCE QUESTIONNAIRE.docx DOCX document
Attachment D - B1005 Price Proposal Form.docx DOCX document
Attachment G - B1005 Statement of Work.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

X X

X X

318 320

321319

327 328

F

S LV43

S LV43

S LV43

S LV43

S LV43

S LV3 S LV3 S LV43

S LV3

S LV3

S LV4

SLV4

S LV43 SLV4 SLV

SLV4

SLV4

SLV4 SLV4

SLV4

SLV4

SLV4

SLV4

SLV4

SLV4

SLV4

SLV4SLV4

SLV4

SLV4

SLV4

SLV4

SLV4

SLV4

SLV4

SLV4

SLV4

SLV4

SLV4

SLV

S LV3

LA-1

LA-2

LA-3

LA-5

LA-4

LC-1

LC-2

LC-3

LCP

LA LB

LC

LBCR

SLV

CONST. CONTR. NO.

REVISION 1.2 E-103

K. BROWN

K. BROWN

K. BROWN

K. ROOT

F. ORR

DESIGN WING RELOCATION

BUILDING 1005

LIGHTING PLAN

60036663 21-0019

NOTED NA 16 36

0 10' 20' 40'5'

GENERAL NOTES

1. THE CONTRACTOR MUST REVIEW THE ELECTRICAL DRAWINGS AND SPECIFICATIONS AND CARRY OUT HIS WORK IN A COMPATIBLE AND

COMPLEMENTARY MANNER. SURVEY THE AFFECTED AREAS AS ALL EXISTING CONDITIONS ARE NOT COMPLETELY DEPICTED ON THE

DRAWINGS AND SOME UNUSUAL CONDITIONS EXIST.

2. EXISTING ELECTRICAL EQUIPMENT AND DEVICES MUST REMAIN UNLESS SPECIFICALLY NOTED TO BE REMOVED.

3. COORDINATE POWER OUTAGES WITH THE GOVERNMENT. MAINTAIN EXISTING ELECTRICAL SYSTEMS IN SERVICE. DISABLE SYSTEMS ONLY

TO MAKE SWITCHOVERS AND CONNECTIONS. OBTAIN PERMISSION FROM THE CONTRACTING OFFICER AT LEAST 5 DAYS BEFORE PARTIALLY

OR COMPLETELY DISABLING SYSTEM. MINIMIZE OUTAGE DURATION.

4. WHERE THE DURATION OF A PROPOSED OUTAGE CANNOT BE TOLERATED BY THE GOVERNMENT, PROVIDE TEMPORARY CONNECTIONS AS

REQUIRED TO MAINTAIN SERVICE.

5. THE CONTRACTOR MUST FIELD VERIFY ALL CIRCUITS, WIRING, CONDUIT, DIMENSIONS, POINTS OF ACCESS AND ALL FIELD CONDITIONS AFFECTING HIS WORK. BEGINNING WORK MEANS THE CONTRACTOR ACCEPTS EXISTING CONDITIONS.

6. PLAN IS A GENERAL REPRESENTATION OF EXISTING CONDITIONS. PLAN DOES NOT REFLECT ALL COMPONENTS OR CONFIGURATIONS. WORK DESCRIBED HERE-IN SHALL BE APPLIED TO ACTUAL FIELD CONDITIONS. DRAWINGS, AS A REPRESENTATION FOR EXISTING CONDITIONS, HAVE

BEEN SIMPLIFIED FOR CLARITY.

7. ROUTING OF CONDUIT AND CIRCUITS ARE AT THE DISCRETION OF THE CONTRACTOR. ROUTING SHALL ALIGN WITH GENERALLY ACCEPTED

GOOD PRACTICE AND INDUSTRY STANDARDS.

8. CONDUIT AND CIRCUITS ROUTING SHALL BE PROVIDED TO AVOID INTERFERENCE WITH EXISTING SYSTEMS.

9. DO NOT SCALE ELECTRICAL DRAWINGS.

10. LOW VOLTAGE WIRING IS NOT SHOWN FOR CLARITY. LUMINAIRE CIRCUITS ARE SHOWN AS DIAGRAMMATIC ONLY INDICATING CIRCUITS AND

SWITCHED/NON-SWITCHED LEGS.

LIGHTING PLAN

A

A

G

A

A

A

A

A

F

A

A

A A

AA

A

A

A

A A

A

A

A

A

A

A

A

A

A A

A

A

A

A

B

B B

D

D

D

D

D

D

C

C

C

NEW WORK NOTES

1. PROVIDE LIGHTING PLAN.

2. PROVIDE NEW LUMINAIRES AND LIGHTING CIRCUITS. SEE LUMINAIRE SCHEDULE FOR DETAILS.

3. PROVIDE NEW OCCUPANCY & VACANCY SENSORS, POWER PACKS, AND SWITCHES. SEE OCCUPANCY SENSOR DIAGRAM FOR DETAILS.

4. PROVIDE NEW LIGHTING CONTROL PANEL(S) TO CONTROL LIGHTING IN THE AREA OF WORK.

5. LIGHTING CONTROL WIRING IS NOT SHOWN FOR CLARITY. LUMINAIRE CIRCUITS SHOWN ARE DIAGRAMMATIC ONLY INDICATING CIRCUITS AND

SWITCHED/NON-SWITCHED LEGS. BRANCH CIRCUITS ARE MINIMUM 2-#12, 1-#12 EGC IN 12"C.

6. PROVIDE EMERGENCY LIGHTING & EXIT SIGNS. THESE LIGHTS AND SIGNS MUST BE DIRECT WIRED AND NOT SUPPLIED BY A SWITCH. SEE

LIGHTING PLATES & DETAILS.

B

AutoCAD SHX Text E

AutoCAD SHX Text

SHEET:

AutoCAD SHX Text 80091

AutoCAD SHX Text E1

AutoCAD SHX Text

MARINE CORPS BASE

AutoCAD SHX Text

DEPARTMENT OF THE NAVY NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND

AutoCAD SHX Text

CAMP LEJEUNE, NORTH CAROLINA

AutoCAD SHX Text

DESIGN DIR.

AutoCAD SHX Text

SUBMITTED BY:

AutoCAD SHX Text

NAVFAC DRAWING NO.

AutoCAD SHX Text

CODE IDENT. NO

AutoCAD SHX Text

SIZE

AutoCAD SHX Text

SPEC.

AutoCAD SHX Text

SCALE:

AutoCAD SHX Text

SATISFACTORY TO:

AutoCAD SHX Text

APPROVED: PWO OR OICC:

AutoCAD SHX Text

DR.

AutoCAD SHX Text

DES.

AutoCAD SHX Text

CHK.

AutoCAD SHX Text

DATE:

AutoCAD SHX Text

DATE:

AutoCAD SHX Text

OF