ERRATA 3 SERM-507-22 VINDICATOR.pdf
PDF 193 KB Posted
- Attached to
- Conversion of an Offshore Support Vessel into a U. S. Navy Training Support Vessel, USNS VINDICATOR (TSV 5)
- Solicitation number
- N40027-22-R-0004
About this file
This document package contains an errata notice updating specifications for a federal contract solicitation to convert an offshore support vessel into a Navy training support vessel.
The errata notice revises three specifications dealing with 03 level and above modifications to the vessel, electrical installations, and fabrication and installation of an accommodation ladder. The solicitation seeks proposals for the fiscal year 2022 regular overhaul of USNS Vindicator (TSV 5) involving drydocking, pier-side maintenance and repairs, ABS certification, and potential upgrades to propulsion, power, command and control, and other systems. The NAICS code is 336611 and inquiries should be directed to the listed Navy contacts.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THIS PERMANENT CHANGE UPDATES THE SPECIFICATION BID PACKAGE.
SHIP: COMMANDER CARRIER STRIKE GROUP FOUR (CNRMC 9577)
SERM-507-22
ERRATA NUMBER:
SPECIFICATION NUMBER:
THE FOLLOWING ITEMS ARE REPLACED:
150-11-004
301-10-001
623-21-001
DATED: 7/28/2022 10:27:36AMPage 1 of 1
SHIP: COMMANDER CARRIER STRIKE GROUP
FOUR (CNRMC 9577)
ITEM NO: 150-11-004 (E3)
COAR: 12 PCN: TSV5-0044
TSV5-0047
BWST FILE NO: 000-001 CMP: NONE
REVISED: 05 APR 2019 PLANNER: BUNTING, ANTHONY
BENNETT, KEITH
BRIDGER, WRAY
DUNCAN, CHRISTOPHER
KRIMMER, DAVID
SSP: SERM-507-22 1 of 2 ITEM NO: 150-11-004
ERRATA NO. 3
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: 03 Level and Above Modification; accomplish
1.2 Location of Work:
1.2.1 Throughout the Ship
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 150-5113171, 87mNS1401 Vindicator (TSV 5) 03 & 05 Deck Modifications
2.2 171-5113172, 87mNS1401 Vindicator (TSV 5) Mast Arrangement and Details Modificaton
2.3 514-5113195, 87mNS1401 Vindicator (TSV 5) HVAC System Diagram
2.4 LAR 87mNS-2215, HVAC System Updates
2.5 LAR 87mNS-2212, 05 Deck HVAC Installation Details
2.6 LAR 87mNS-2205, HVAC Installation Details for the Training Operations Center (TOC)
2.7 LAR 87mNS-2204, HVAC Condensate Drains Installation
2.8 601-5113194, 87mNS1401 Vindicator (TSV 5) General Arrangement
2.9 074-5113191, 87mNS1401 Vindicator (TSV 5) Construction Weld Details and Notes
2.10 804-5773931 Rev A, Insulation for Ducts, Acoustic and Thermal Installation Details
2.11 American Bureau of Shipping (ABS), Part 2, Rules for Materials and Welding
2.12 American Bureau of Shipping (ABS), Part 7, Rules For Survey After Construction
2.13 PM 390-563,390-563 Rev A, SERMC, Exterior Vindicator TSV-5 Paint Schedule- "VINDICATOR (TSV 5)"
(E1)
3. REQUIREMENTS:
3.1 Provide the service of an American Bureau of Shipping (ABS) certified Surveyor.
3.2 Provide the service of an Original Equipment Manufacturer (OEM)
SSP: SERM-507-22 2 of 2 ITEM NO: 150-11-004
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
certified technical representative for the installation and testing of each refrigerant system.
3.3 Accomplish the requirements of 2.1 through 2.7, using 2.8 through
2.12 for guidance.
3.3.1 Chip and grind each surface flush in way of each repair.
3.4 Accomplish the requirements of Chapter 4 of 2.11 for welding, using
2.9 for guidance.
3.5 Perform an air hose test on each penetration, insert, closure patch and weld seam in accordance with Test Note T1 of 2.1 and 2.3. Allowable leakage: None.
3.5.1 Submit one legible copy, in approved transferrable media, reporting each result of the requirements of 3.5 to the SUPERVISOR.
(I)(G) "REFRIGERANT LEAK TEST"
3.6 Accomplish a leak test on new and disturbed refrigeration piping in accordance with manufacturer's instructions and Test Note T2 of 2.3.
Allowable leakage: None.
(V)(G) "OPERATIONAL TEST"
3.7 Accomplish an operational test of each new and disturbed ventilation system to ensure proper operation and joint tightness, using 2.3 for guidance. Allowable leakage: None.
3.8 Accomplish painting requirements for each new and disturbed surface in accordance with 2.13, as approved by Operator, Owner's Specifications, ABS certified Surveyor and in accordance with the paint manufacturer's recommendation.
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 1 EA
DOOR,STL,WT,36X6
6,RH,INDV 10
DOG,13PSI
805- 1400066-
309-MOD (E3)
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
ITEM NO: 301-10-001 (E3)
COAR: 12 PCN: TSV5-0045
TSV5-0048
TSV5-0051
TSV5-0046
TSV5-0043
CSWT FILE NO: 301-001 (PC 1) CMP: NONE
REVISED: 13 OCT 2021 PLANNER: MAYNARD, JAMES
BENNETT, KEITH
BRIDGER, WRAY
DUNCAN, CHRISTOPHER
SSP: SERM-507-22 1 of 3 ITEM NO: 301-10-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: BoatAlt-87mNS/10B, Electrical Installation; accomplish
(OPTION ITEM)
1.2 Location of Work:
1.2.1 Throughout the Ship
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 301-5113175, BoatAlt 87mNS1401 Vindicator (TVS 5), Electrical Single Line Diagrams
2.2 LAR 87mNS-2208, 440 VAC Distribution Modification
2.3 LAR 87mNS-2213, Electrical Single Line Modifications
2.4 LAR 87mNS-2214, Portable Accommodation Module (PAM) Power Supply Modifications
2.5 LAR 87mNS-2216, HVAC Power Supply Updates
2.6 544-5113176, BoatAlt 87mNS1401 Vindicator (TVS 5), Bulk Mud Valve Control Mods
2.7 544-5113177, BoatAlt 87mNS1401 Vindicator (TVS 5), Fuel Oil Transfer System Valve Control Modifications
2.8 LAR 87mNS-2210, ATMO Fuel System Electrical Supply
2.9 301-5113177,301-5113175, BoatAlt 87mNS1401 Vindicator (TVS 5), Fuel Electrical Oil Single Transfer Line System DiagramValve Control Modifications
(E1)
2.10 324-5113178, BoatAlt 87mNS1401 Vindicator (TVS 5), TOC Electrical Panel Schematic
2.11 331-5113179, BoatAlt 87mNS1401 Vindicator (TVS 5), TOC Electrical General Arrangement
2.12 324-5113180, BoatAlt 87mNS1401 Vindicator (TVS 5), Transmitter Room Electrical Panel Schematics
2.13 331-5113181, BoatAlt 87mNS1401 Vindicator (TVS 5), Transmitter and
SSP: SERM-507-22 2 of 3 ITEM NO: 301-10-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
Mechanical Room Electrical General Arrangement
2.14 331-5113182, BoatAlt 87mNS1401 Vindicator (TVS 5), External Lighting Diagram
2.15 331-5113183, BoatAlt 87mNS1401 Vindicator (TVS 5), Miscellaneous Electrical Systems Arrangement and Details
2.16 LAR 87mNS-2211, SLAD Motor Controller Mounting and Electrical Hook Up
2.17 PM 390-568 Rev A, BoatAlt-mNS/10B, Electrical Equipment List (Additional)
2.18 302-7512881 Rev A, Standard Drawing Typical for Non-Standard Power Distribution System 120/208 VAC, W/Grounded Neut
2.19 302-7598285 Rev A, Standard Drawing Typical for Non-Standard Power Distribution System 240/120 VAC
2.20 583-6743682 Rev B, Davit, Boat, Slewing Elec. Items and Requirements
2.21 583-6743684 Rev D, Davit, Boat, Slewing Operator Control Station Assy and Dets
2.22 601-5113194, BoatAlt 87mNS1401 Vindicator (TVS 5), General Arrangement
2.23 074-5113191, BoatAlt 87mNS1401 Vindicator (TVS 5), Construction Weld Details and Notes
2.24 American Bureau of Shipping, ABS Rules for Material and Welding, Part 2
2.25 IEEE STD 45TM/2002, Recommended Practice for Electrical
Installations on Shipboard
2.26 PM 390-563 Rev A, SERMC, Vindicator TSV-5 Paint Schedule (E1)
3. REQUIREMENTS:
3.1 Accomplish electrical removals, modifications, and installations of BoatAlt 87mNS1401, in accordance with 2.1 through 2.17, using 2.18 through 2.22 for guidance.
3.1.1 Chip and grind each surface flush in way of each installation and removal.
3.1.2 Install new studs, hangers, foundations, brackets and stuffing tubes to support electrical cable and equipment installations affected by this BoatAlt.
3.1.3 Provide 5 mandays of labor and 500 dollars of material to install light brackets and foundations, as directed by the SUPERVISOR. If the total cost is less than the authorized manday and dollar amount, remaining funding will be subject to recoupment. The contractor is not authorized to exceed this limit.
3.1.4 Accomplish the requirements of 2.23 and Chapter 4 of 2.24 for welding.
SSP: SERM-507-22 3 of 3 ITEM NO: 301-10-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.1.5 Ensure electrical cable and equipment removals, installations, and modifications conform to the requirements of 2.25.
(V)(G) "LOCAL AIR HOSE TEST"
3.1.6 Accomplish a local air hose test of each new and disturbed cable penetration. Allowable leakage: None.
(V)(G) "FUNCTIONAL TEST"
3.2 Accomplish a functional test of each new and disturbed electrical circuit and equipment in accordance with Chapter 34 of 2.25.
3.3 Accomplish painting requirements for each new and disturbed surface,surface in accordance with 2.26, as approved by Operator, Owner's Specifications, American ABS Bureau of Shipping (ABS) certified Surveyor and in accordance with the paint manufacturer's recommendation.
(E1)
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 1 EA
CABLE, UNARM,
WT,1000V,0 AWG,
4 COND, 1.358”
OD (1.820#/FT)
LSFSGU-
100 (E3)
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 1 KT SLAD Assembly N/A 2.15 N/A 3.1
2. 1 EA
SERIES 25M
MINIATURE
VANEAXIAL BLOWER
A25-M--
85TA---
STFIF2 2.5 N/A 3.1
3. 1 EA
SERIES 25M
MINIATURE
VANEAXIAL BLOWER
A25-M--
85TA---
STFID3 2.5 N/A 3.1
ITEM NO: 623-21-001 (E3)
COAR: 12 PCN: TSV5-0025
CSWT FILE NO: 623-012 (CG 47) CMP: NONE
REVISED: 12 OCT 2021 PLANNER: CORNWELL, RICHARD
BENNETT, KEITH
BRIDGER, WRAY
BROWN, DERRICK
DUNCAN, CHRISTOPHER
SSP: SERM-507-22 1 of 2 ITEM NO: 623-21-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Accommodation Ladder, Fabricate, Fit, and Install; accomplish
(OPTION ITEM)
1.2 Location of Work:
1.2.1 01 Level, Weather, Frame 65, Port
1.3 Identification:
1.3.1 Quantity (One AY), Accommodation Ladder
2. REFERENCES:
2.1 805-1749049 Rev J, Gangway Aluminum
2.2 804-2255404, Accommodation Ladder Upper Platform Types A, B, and C
2.3 805-1749040, Accommodation Ladder Arrangement Handling and Stowage Fixed or Feathering Thread
2.4 601-5113194, 87mNS1401 Vindicator (TSV 5) General Arrangement
2.5 American Bureau of Shipping (ABS), Part 7, Rules For Survey After Construction
2.6 American Bureau of Shipping (ABS), Part 2, Rules for Materials and Welding
2.7 PM 390-563,390-563 Rev A, SERMC, Exterior Vindicator TSV-5 Paint Schedule- "VINDICATOR (TSV 5)"
(E1)
3. REQUIREMENTS:
3.1 Provide the service of an American Bureau of Shipping (ABS) certified Surveyor.
3.2 Accomplish the requirements of 2.1 through 2.3, using 2.4 through
2.6 for guidance.
3.2.1 Fabricate, fit and install new accommodation ladder, including the upper and lower platform and fender assembly. The yoke guide will be mounted onto a Type 316L corrosion resistant steel reinforcement plate welded to ships support structure, listed in 1.3, and located in 1.2.
3.2.2 Remove existing and install new a total of 10 square feet of damaged or deteriorated plating and associated support structure.
3.2.3 Accomplish the requirements of Chapter 4 of 2.6 for welding.
(I)(G) "STATIC LOAD TEST"
SSP: SERM-507-22 2 of 2 ITEM NO: 623-21-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.3 Accomplish a static load test of each accommodation ladder assembly in accordance with General Note 3 of 2.1. Accept/Reject Criteria: No visible evidence of damage or permanent deformation. None.
(V)(G) "PROPER FIT"
3.4 Verify proper fit of the accommodation ladder, with no binding between equipment and each stowage rack. Ensure each quick release pin and toggle pin with lanyard are secured to stowage structure and equipment, using 2.1 and 2.3 for guidance.
3.5 Accomplish painting requirements for each new and disturbed surface,surface in accordance with 2.7, as approved by Operator, Owner's Specifications, American ABS Bureau of Shipping (ABS) certified Surveyor and in accordance with the paint manufacturer's recommendation recommendation.and using 2.7 for guidance.
(E1)
4. NOTES:
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 1 KT Vang Staples 2.3 (E3)
2. 1 KT
Rigging Hardware
ACCOM 2.3 (E3)
3. 1 EA
Rotating Upper Platform N/A 2.5 N/A 3.3 (E3)
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
File details come from the government source that posted it. Updated .