J-2 EXECUTION MILESTONES AND KEY EVENTS.xlsx

XLSX spreadsheet 11 KB Posted

Attached to
Conversion of an Offshore Support Vessel into a U. S. Navy Training Support Vessel, USNS VINDICATOR (TSV 5)
Solicitation number
N40027-22-R-0004
Issued by

About this file

This document contains details regarding a federal solicitation for the regular overhaul of a U.S. Navy training support vessel. The solicitation seeks proposals for the dry-docking, pier-side overhaul, maintenance, repairs and alterations of USNS VINDICATOR (TSV 5) to meet ABS certification. Key systems targeted for potential repair or upgrade include propulsion, power, command and control, steering, fuel, electrical, communication, hull and structural components. The work also involves equipment upgrades, alterations and modernization. The solicitation was issued as full and open competition under NAICS code 336611. The performance period is from September 28, 2022 through June 5, 2023. Key milestones include 25% completion by November 17, 2022, 50% by November 29, 2022, 75% by January 30, 2023, dock trials by April 4, 2023 and availability completion by June 5, 2023. The points of contact for proposal submission and questions are Bethjoven de los Reyes and Andres Walsh via email.

View the file

Other files

File Type Posted
N4002722R00040010 CONFORMED.pdf PDF
ERRATA 6 SERM-507-22 VINDICATOR.pdf PDF
ERRATA 7 SERM-507-22 VINDICATOR.pdf PDF
N40027-22-R-0004-0010.pdf PDF
N40027-22-R-0004-0009.pdf PDF
S-2 Price Data Breakdown SERM-507-22(Rev 4).xlsx XLSX spreadsheet
N4002722R00040008.pdf PDF
N4002722R00040008 CONFORMED.pdf PDF
ERRATA 5 SERM-507-22 VINDICATOR.pdf PDF
ERRATA 4 SERM-507-22 VINDICATOR.pdf PDF
N4002722R00040008.pdf PDF
N4002722R00040008 CONFORMED.pdf PDF
J-2 EXECUTION MILESTONES AND KEY EVENTS (Rev 1).xlsx XLSX spreadsheet
S-2 Price Data Breakdown SERM-507-22(Rev 3).xlsx XLSX spreadsheet
J-7 Vindicator Tank Soundings 7-26-22.xlsx XLSX spreadsheet
ADDENDUM 1 SERM-507-22 VINDICATOR.pdf PDF
N4002722R00040007.pdf PDF
N4002722R00040006.pdf PDF
S-2 Price Data Breakdown SERM-507-22(Rev 2).xlsx XLSX spreadsheet
J-2 EXECUTION MILESTONES AND KEY EVENTS (Rev 1).xlsx XLSX spreadsheet
ERRATA 3 SERM-507-22 VINDICATOR.pdf PDF
Attachment J-6 RMC Office Space.docx DOCX document
N4002722R00040005.pdf PDF
ERRATA 2 SERM-507-22 VINDICATOR.pdf PDF
N4002722R00040004.pdf PDF
N4002722R00040003.pdf PDF
S-2 Price Data Breakdown SERM-507-22(Rev 1).xlsx XLSX spreadsheet
N4002722R00040002.pdf PDF
J-5 Past Performance Questionnaire.docx DOCX document
ERRATA 1 SERM-507-22 VINDICATOR.pdf PDF
N4002722R00040001.pdf PDF
J-4 HEAVY WEATHER PLAN.docx DOCX document
Exhibits A and B Contract Data Requirements List (CDRL) DD Form 1423.pdf PDF
S-1 Request for Specification Clarification.docx DOCX document
S-2 Cost Data Break Down Vindicator SERM-507-22.xlsx XLSX spreadsheet
J-3 Small Business Subcontracting Plan.doc DOC document
N40027-22-R-0004.pdf PDF
J-1 SERM-507-22 COMPOSITE WORK PACKAGE.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

VINDICATOR (TSV 5) ROH MILESTONE CHART PERIOD OF PERFORMANCE 28 SEPTEMBER 2022 - 05 JUNE 2022
(AS) AVAILABILITY STARTKey Event9/28/22A + 0WED
20% OPEN/INSPECT COMPLETE (All)Execution Milestone11/17/22A + 50THUR
25% CONFERENCEExecution Milestone11/29/22A + 62TUE
50% CONFERENCEExecution Milestone1/30/23A+125MON
75% CONFERENCEExecution Milestone4/4/23A+187TUE
(DT) - DOCK TRIALSKey Event5/29/23A+243MON
(ST) - SEA TRIALSKey Event5/30/23A+244TUE
(AC) - AVAILABILITY COMPLETIONKey Event6/5/23A+251MON

File details come from the government source that posted it. Updated .