CN-370000-HW682-DC024A.pdf

PDF 4 MB Posted

Attached to
Master Agreement FL|HW682|8fccc28dda898687f0dd3c309f3a996b
Contract number
HW682
Issued by
Florida

About this file

This document is a Task Assignment (TA) issued by the Florida Department of Environmental Protection (FDEP) to Environmental Consulting and Technology, Inc. (ECT) for an initial soil and groundwater assessment at Classic Cleaners of Ocala, located at 2641 SW College Road, Ocala, Marion County, Florida (ERIC_4905). The TA is issued pursuant to Contract Number HW682 and is effective through November 21, 2025. ECT serves as the primary contractor with Mark A. Culbreth as the project manager, while FDEP's Karlee Fowler oversees the project as the Department Project Manager.

The contract authorizes ECT to perform an initial site assessment comprising eight subtasks with a total value of $142,659.27 on a fixed unit rate basis. The scope includes HASP preparation and utility clearance (Subtask 2), soil and direct push technology groundwater sampling with well installation (Subtask 3), monitoring well installation and sampling (Subtask 4), soil vapor assessment through Modified Active Gas Sampling (Subtask 5), professional land survey (Subtask 6), investigative derived waste management (Subtask 7), and site assessment report preparation (Subtask 8), with project management as Subtask 1. Deliverables are staged across multiple invoice milestones from October 2024 through July 2025, with specific FDEP approval requirements triggering each payment. Selected subcontractors include Site Lines LLC for utility location ($800), Groundwater Protection for initial DPT sampling ($16,383), Preferred Drilling Solutions for well installation ($37,425), SSMC for professional land survey ($3,911.75), and Erwin Remediation for IDW disposal at $150 per drum of soil and $125 per drum of water.

View the file

Other files

File Type Posted
CN-370000-HW682-DC001C.pdf PDF
CN-370000-HW682-DC003A.pdf PDF
CN-370000-HW682-DC003B.pdf PDF
CN-370000-HW682-DC006B.pdf PDF
CN-370000-HW682-DC007C.pdf PDF
CN-370000-HW682-DC007D.pdf PDF
CN-370000-HW682-DC008C.pdf PDF
CN-370000-HW682-DC010B.pdf PDF
CN-370000-HW682-DC010C.pdf PDF
CN-370000-HW682-DC015A.pdf PDF
CN-370000-HW682-DC016A.pdf PDF
CN-370000-HW682-DC016B.pdf PDF
CN-370000-HW682-DC021A.pdf PDF
CN-370000-HW682-DC027A.pdf PDF
CN-370000-HW682-DC03CCO2.pdf PDF
CN-370000-HW682-DC03CCO3.pdf PDF
CN-370000-HW682-DC04BCO2.pdf PDF
CN-370000-HW682-DC04BCO3.pdf PDF
CN-370000-HW682-DC04BCO5.pdf PDF
CN-370000-HW682-DC05BCO6.pdf PDF
CN-370000-HW682-DC05BCO8.pdf PDF
CN-370000-HW682-DC06BCO1.pdf PDF
CN-370000-HW682-DC06BCO2.pdf PDF
CN-370000-HW682-DC08DCO1.pdf PDF
CN-370000-HW682-DC09ACO2.pdf PDF
CN-370000-HW682-DC09ACO3.pdf PDF
CN-370000-HW682-DC10BCO1.pdf PDF
CN-370000-HW682-DC11ACO4.pdf PDF
CN-370000-HW682-DC11ACO6.pdf PDF
CN-370000-HW682-DC13ACO1.pdf PDF
CN-370000-HW682-DC13BCO1.pdf PDF
CN-370000-HW682-DC13BCO7.pdf PDF
CN-370000-HW682-DC16ACO2.pdf PDF
CN-370000-HW682-DC18ACO2.pdf PDF
CN-370000-HW682-DC18ACO3.pdf PDF
CN-370000-HW682-DC20ACO1.pdf PDF
CN-370000-HW682-DC21ACO1.pdf PDF
CN-370000-HW682-DC21BCO1.pdf PDF
CN-370000-HW682-DC22ACO2.pdf PDF
CN-370000-HW682-DC24ACO1.pdf PDF
CN-370000-HW682-DC26ACO3.pdf PDF
CN-370000-HW682-DC27ACO1.pdf PDF
CN-370000-HW682-DC28ACO1.pdf PDF
CN-370000-HW682-FIL2.pdf PDF
CN-370000-HW682-FIL6.pdf PDF
CN-370000-HW682-HW001A.pdf PDF
CN-370000-HW682-HW004A.pdf PDF
CN-370000-HW682-HW006A.pdf PDF
CN-370000-HW682-HW007A.pdf PDF
CN-370000-HW682-HW011A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW682

DC024A Completion November 21, 2025

This Task Assignment authorizes ECT to to perform an initial soil and groundwater assessment at Classic Cleaners of Ocala in accordance with the SAWP generated from

DC023A.

Karlee Fowler 850 245-8944 Contractor Environmental Consulting and Technology, Inc. (ECT) Contractor

Contractor Mark A. Culbreth Contractor 813-289-9338

ERIC_4905

2641 SW College Road Ocala, Florida 34471

Classic Cleaners of Ocala

Contractor Contractor

✔ $ 142,659.27

$ 142,659.27

Scope of Work

Environmental Consulting and Technology, Inc. (ECT Contractor Mark A. Culbreth

Contract Manager

10/11/2024

Digitally signed by Mark Culbreth Date: 2024.10.11 14:32:28-04'00'Mark Culbreth

Teresa Booeshaghi

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2024.10.08 20:04:59 -04'00'

10/8/2024

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Email Deliverable for HASP and Utility Clearance (Subtask 2) 11/15/2024

Email deliverable for DPT, Soil Field Notes (Subtask 3) 01/31/2025

Email deliverable for Well Install, Field Notes, & Well Permits (Subtask 4) 03/28/2025

Email deliverable for MAGS (Subtask 5) 05/30/2025

PLS and IDW Waste Manifest (Subtask 6 & 7) 06/27/2025

Project Management and Site Assessment Report (Subtask 1 & 8) 08/29/2025

FDEP Approval of Email Deliverable for HASP and Utility Clearance (Subtask 2) $ 4,135.96

FDEP Approval of Email deliverable for DTP, Soil Field Notes (Subtask 3) $ 47,120.42

FDEP Approval of Email deliverable for Well Install, Field Notes, & Well Permits (Subtask 4) $ 61,640.84

FDEP Approval of Email deliverable for MAGS (Subtask 5) $ 5,711.49

FDEP Approval of PLS and IDW Waste Manifest (Subtask 6 & 7) $ 10,433.15

FDEP Approval of Project Management and Site Assessment Report (Subtask 1 & 8) $ 13,617.41

$ 142,659.27

HW682

DC024A

Printed on recycled paper.

FFLORIDAA DEPARTMENTT OF

EEnvironmentall Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ronn DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawnn Hamilton Secretary

From:

Date:

To: HW Contract Negotiation File

ERIC_

, Project Manager

, 202 Subject: Negotiation Summary

HW

This Task Assignment is $ with labor hours.

FDEP COST ESTIMATEContractor: Environmental Consulting & Technology, Inc.

Date: 8/14/2024

Task #: SubTask 1 Project Management SubTask 6 Professional Land Survey

Site: Classic Cleaners of Ocala SubTask 2 HASP & Utility Clearance SubTask 7 IDW Management

Activity/Phase: Initial Site Assessment SubTask 3 Soil Sampling with DPT & Groundwater Sampling SubTask 8 SAR Preparation

Project Manager: Mark Culbreth SubTask 4 Well Installation & Groundwater Sampling SubTask 9

SubTask 5 MAGS SubTask 10

Totals 1 2 3 4 5 6 7 8 9 Labor Rate Category

$84.17 Project Manager 20.1 20.1 $84.17 Senior Principal Scientist (MC) 7.0 0.5 2.5 0 0 0 0 4 0 $54.08 Senior Engineer / Scientist (RP) 12.0 0.0 0.0 0.0 6 0 0 6 0 $55.00 Senior Engineer / Scientist (DP) 180.0 18.0 57.0 70.0 0 1 2 32 0 $28.44 GIS Analyst / Graphics (JV) 10.0 0 0 0.0 0 0 0 10 0 $24.18 Associate Engineer / Scientist (JP) 40.0 0 0 20.0 12 8 0 0 0 $23.00 Technician (MW) 13.0 0 0 0 13 0 0 0 0 $34.81 Administrative (BJ) 10.0 0 2 2 2 0 0 4 0

Total Hours 292.1 20.1 18.5 61.5 92.0 33.0 9 2 56 0

Direct Labor $14,731.65 $1,694.79 $1,032.09 $3,415.05 $4,403.22 $983.26 $248.44 $110.00 $2,844.80 #

Overhead 125.30% $18,458.75 $2,123.57 $1,293.21 $4,279.06 $5,517.23 $1,232.02 $311.30 $137.83 $3,564.53 # Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 # Fringe 47.40% $6,982.81 $803.33 $489.21 $1,618.73 $2,087.13 $466.07 $117.76 $52.14 $1,348.44 # Total Labor $40,173.21 $4,621.69 $2,814.51 $9,312.84 $12,007.58 $2,681.35 $677.50 $299.97 $7,757.77 #

Travel Vehicle Rental $1,8 .00 $120.00 $480.00 $840.00 $240.00 $12 .00 $0.00 $0.00 # Per diem + Hotel $2,226.00 $0.00 $780.00 $1,002.00 $444.00 $0.00 $0.00 $0.00 # Total Travel $4,0 .00 $120.00 $1,260.00 $1,842.00 $684.00 $12 .00 $0.00 $0.00 #

Subcontractor (Equipment Procurement) Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 # Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 # Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #

Subcontractor (Services Procurement) Drilling (Conventional) $53,808.00 $0.00 $16,383.00 $37,425.00 $0.00 $0.00 $0.00 $0.00 # Surveying $3,911.75 $0.00 $0.00 $0.00 $0.00 $3,911.75 $0.00 $0.00 #

IDW $4,450.00 $0.00 $0.00 $0.00 $0.00 $0.00 $4,450.00 $0.00 #

GPR $800.00 $800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #

Subcontractor Subtotal $62,969.75 $800.00 $16,383.00 $37,425.00 $0.00 $3,911.75 $4,450.00 $0.00 # Handling Fee $6,296.98 $80.00 $1,638.30 $3,742.50 $0.00 $391.18 $445.00 $0.00 # Total Subcontractor Cost $69,266.73 $880.00 $18,021.30 $41,167.50 $0.00 $4,302.93 $4,895.00 $0.00 #

Laboratory Analytical Costs $19,162.00 $0.00 $15,290.00 $2,672.00 $1,200.00 $0.00 $0.00 $0.00 # Sample Shipping $560.00 $0.00 $350.00 $70.00 $140.00 $0.00 $0.00 $0.00 # Total Laboratory $19,722.00 $0.00 $15,640.00 $2,742.00 $1,340.00 $0.00 $0.00 $0.00 #

Field Expenses Expendables $560.00 $40.00 $200.00 $240.00 $40.00 $40.00 $0.00 $0.00 # Soil Assessment Kit $700.00 $0.00 $700.00 $0.00 $0.00 $0.00 $0.00 $0.00 # Monitoring well Install Kit $1,950.00 $0.00 $650.00 $1,300.00 $0.00 $0.00 $0.00 $0.00 # Shallow Groundwater Sampling Kit $870.00 $0.00 $290.00 $580.00 $0.00 $0.00 $0.00 $0.00 # Ice $91.00 $0.00 $65.00 $26.00 $0.00 $0.00 $0.00 $0.00 # Total Survey Station $100.00 $0.00 $50.00 $50.00 $0.00 $0.00 $0.00 $0.00 # Deep Groundwater Sampling Kit $415.00 $0.00 $0.00 $415.00 $0.00 $0.00 $0.00 $0.00 # MAGS Kit $500.00 $0.00 $0.00 $0.00 $500.00 $0.00 $0.00 $0.00 # Air Sampling Canisters $268.00 $0.00 $0.00 $70.00 $198.00 $0.00 $0.00 $0.00 Total Field Expenses $5,454.00 $40.00 $1,955.00 $2,681.00 $738.00 $40.00 $0.00 $0.00 #

Subtotal $138,6 .94 $4,621.69 $3,854.51 $46,189.14 $60,440.08 $5,443.35 $5,1 .43 $5,194.97 $7,757.77 # Completion Fee $4,017.33 $462.17 $281.45 $931.28 $1,200.76 $268.14 $67.75 $30.00 $775.78 #

Total Estimated Cost $142,6 .27 $5,083.86 $4,135.96 $47,120.42 $61,640.84 $5,711.49 $5,2 .18 $5,224.97 $8,533.55 #

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Classic Cleaners of Ocala SUBTASK 2: HASP & Utility Clearance

DATE: 8/14/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

M. Culbreth Senior Principal Review Health and Safety Plan 0.5 Scientist

Total Hours 0.5 D Phillips Senior Scientist Prepare Health and Safety Plan 2

Verification of property ownership, notify RPO of field activities 1 Obtain off-site access - 2 properties 6 Round trip Mobilization between Orlando and the site in Ocala 5 Utility clearance 4

Total Hours 18

TOTAL LABOR 18.5

VEHICLE TYPE RATE UNIT USAGE

Rental Truck $120.00 day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNITS

Site Lines LLC Private Utility Location $800.00 1 $800.00

TOTAL $800.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Expendables $40.00 Event 1 $40.00

TOTAL EQUIPMENT $40.00

FINAL --7/24/96

SUBTASK 3: Soil Sampling with DPT & Groundwater Sampling

DATE: 8/14/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

M. Culbreth Senior Principal Determine which samples to run SPLP, confer with FDEP. 1

Scientist Evaluate geologic conditions based on boring logs and DPT sampling. 1.5 Total Hours 2.5

D Phillips Senior Scientist Round trip Mobilization from Orlando to the site in Ocala 5 Soil Borings and DPT Sampling 50 DTW measurements & grab groundwater sampling at 4 wells 2

Total Hours 57 B. Jarvis Administrative Create tables and data entry 2

Total Hours 2

TOTAL LABOR 61.5

VEHICLE TYPE RATE UNIT USAGE

Rental Truck $480.00 week 1 $480.00

TOTAL VEHICLE $480.00

PER DIEM STAFF RATE UNIT USAGE

Hotel D Phillips $150.00 day 4 $600.00 Per Diem D Phillips $36.00 day 5 $180.00

TOTAL PER DIEM $780.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Groundwater Protection DPT Soil & Groundwater Sampling $16,383.00 1 $16,383.00

TOTAL $16,383.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC UNITS

Method 8260 for Full list Soil $110.00 62 $6,820.00 SPLP Extractions $45.00 24 $1,080.00 Method 8260 for Full list Groundwater DPT $110.00 27 $2,970.00 Method 8260 Full list Grab samples from 4 MW's $110.00 4 $440.00 Method 8260 for SPLP $110.00 24 $2,640.00 IDW Method 8260 for Full List Soil $110.00 1 $110.00 IDW Encore Samplers $16.00 1 $16.00 IDW Method 6020 or 6010 for RCRA 4 Metals Soil $56.00 1 $56.00 IDW Method 8260 for Full List Purge water $110.00 1 $110.00 IDW Method 6020 or 6010 for RCRA 4 Metals Water $56.00 1 $56.00 Encore Samplers $16.00 62 $992.00 Shipping Samples $70.00 5 $350.00

TOTAL LAB $15,640.00

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Expendables $40.00 Day 5 $200.00 Soil Assessment Kit $700.00 Week 1 $700.00 Monitoring well Install Kit $325.00 Day 2 $650.00 Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00 Ice $6.50 each 10 $65.00 Total Survey Station $50.00 day 1 $50.00

TOTAL EQUIPMENT $1,955.00

SUBTASK 4: Well Installation & Groundwater Sampling

DATE: 8/14/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

D Phillips Senior Scientist Round trip Mobilization from Orlando to the site in Ocala (2 trips) 10 Oversight of well installations 60

Total Hours 70 J. Penia 4

DTW measurement & Sampling Wells (8 shallow, 4 intermediate & 1 deep), containerize water 16 Total Hours 20

B. Jarvis Administrative Create tables and data entry 2

Total Hours 2

TOTAL LABOR 92

VEHICLE TYPE RATE UNIT USAGE

Rental Truck DP $480.00 week 1 $480.00 Rental Truck JP + DP $120.00 day 3 $360.00

TOTAL VEHICLE $840.00

PER DIEM STAFF RATE UNIT USAGE

Hotel D Phillips $150.00 day 4 $600.00 Per Diem D Phillips $36.00 day 5 $180.00

Hotel J. Penia $150.00 day 1 $150.00 Per Diem J. Penia $36.00 day 2 $72.00

TOTAL PER DIEM $1,002.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST UNITS

Preferred Drilling Solutions Well install 1 $37,425.00

TOTAL $37,425.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC Units Method 8260 Full list samples from MW's $110.00 13 $1,430.00 IDW Method 8260 for Full List Soil $110.00 5 $550.00 IDW Encore Samplers $16.00 5 $80.00 IDW Method 6020 or 6010 for RCRA 4 Metals Soil $56.00 5 $280.00 IDW Method 8260 for Full List Purge water $110.00 2 $220.00 IDW Method 6020 or 6010 for RCRA 4 Metals Water $56.00 2 $112.00 Shipping Samples $70.00 1 $70.00

TOTAL LAB $2,742.00

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Expendables $40.00 Day 6 $240.00 Monitoring well Install Kit $1,300.00 Week 1 $1,300.00 Shallow Groundwater Sampling Kit $290.00 Day 2 $580.00 Ice $6.50 each 4 $26.00 Total Survey Station $50.00 day 1 $50.00 Deep Groundwater Sampling Kit $415.00 Day 1 $415.00 Generator $70.00 Day 1 $70.00

TOTAL EQUIPMENT $2,681.00

$37,425.00

Associate Scientist

Round trip Mobilization from Tampa to the site in Ocala

SUBTASK 5: MAGS

DATE: 8/14/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

R. Powell Senior Engineer P.E. oversight of MGAS events (Provide SOW, guidance, and answer field question) 3 Analyze MAGS data. 3

Total Hours 6 J. Penia Round trip Mobilization from Tampa to the site in Ocala 4

Perform MAGS Testing 8 Total Hours 12

M. Wiss Technician Round trip Mobilization from Orlando to the site in Ocala 5 Perform MAGS Testing 8

Total Hours 13 B. Jarvis Administrative Update tables 2

Total 2

TOTAL LABOR 33

VEHICLE TYPE RATE UNIT USAGE

Rental Truck J. Penia $120.00 day 2 $240.00 Rental Truck M. Wiss $120.00 day 2 $240.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USAGE

Hotel J. Penia $150.00 day 1 $150.00 Per Diem J. Penia $36.00 day 2 $72.00

Hotel M. Wiss $150.00 day 1 $150.00 Per Diem M. Wiss $36.00 day 2 $72.00

TOTAL PER DIEM $444.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC Units

USEPA Method TO-15 for VOHs $200.00 6 $1,200.00 Sampling Shipping Overnight $70.00 2 $140.00

TOTAL LAB $1,340.00

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Expendables $40.00 Day 1 $40.00 MAGS Kit $500.00 Day 1 $500.00 Air Sampling Canisters $33.00 Day 6 $198.00

TOTAL EQUIPMENT $738.00

Associate Scientist

SUBTASK 6: Professional Land Survey

DATE: 8/14/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

D. Phillips Senior Scientist Coordinate and schedule with Surveyor 1 Total Hours 1

J. Penia Technician Round trip Mobilize from Tampa to the site in Ocala 4 PLS Oversight and aid in location of wells 4

Total Hours 8

TOTAL LABOR 9

VEHICLE TYPE RATE UNIT USAGE

Rental Truck J. Penia $1 .00 day 1 $1 .00

TOTAL VEHICLE $12 .00

PER DIEM STAFF RATE UNIT USAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

SSMC Professional Land Survey $3,911.75 1 $3,911.75

TOTAL $3,911.75

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

Expendables $40.00 Event 1 $40.00

TOTAL EQUIPMENT $40.00

SUBTASK 7: IDW Management

DATE: 8/14/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

D. Phillips Senior Scientist Characterization of waste to profile soil & water IDW drums for transportation and disposal 1 Schedule IDW transport and disposal 1

Total 2

TOTAL LABOR 2

VEHICLE TYPE RATE UNIT USAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin Remediation IDW T&D Soil $150.00 23 $3,450.00 Erwin Remediation IDW T&D Water $125.00 8 $1,000.00

TOTAL $4,450.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

TOTAL EQUIPMENT $0.00

SUBTASK 8: SAR Preparation

DATE: 8/14/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

M. Culbreth Senior Principal Develop conclusions, recommendations, and prepare final Assessment Report 4

Scientist Total 4 R. Powell Senior Engineer Prepare the draft SAR MAGS section 6

Total 6 D. Phillips Senior Scientist Prepare draft SAR lithological section, create draft figures to be submitted for AutoCAD generatio 30

QA/QC of analytical data 2 Total 32

J. Von Borstel GIS Analyst Revise and Update Figures 10 Total 10

B. Jarvis Administrative Update tables, Document Preparation & Publishing 4 Total 4

TOTAL LABOR 56

VEHICLE TYPE RATE UNIT USAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

TOTAL EQUIPMENT $0.00

ectinc.com

ATTACHMENT 2: SUBCONTRACTOR QUOTES

SITE LINES LLC

Utility Locating 1143 59th Avenue North (727) 432-9482 St. Petersburg, FL 33703 bhardy@sitelinesllc.com

Mr. Daniel S. Phillips, P.G.

Environmental Consulting &Technology, Inc.

3751 Maguire Boulevard, Suite 234 Orlando, FL 32803

June 18, 2024

SITE: Classic Cleaners Site – Ocala, Florida PROPOSAL: 01490p

Dear Mr. Phillips:

Thank you for contacting Site Lines LLC regarding the private utility locate at your project site. Attached is our proposal in response to your inquiry.

Please review the proposal to ensure I have accurately captured the project details.

If you agree to the proposal, including the terms and conditions, and the statement of work, please sign, initial and date where indicated. Upon signing, the proposal will serve as the Agreement of the parties as to the above-referenced Project.

If you have any questions, please feel free to contact me. I look forward to working with you.

Sincerely, Site Lines LLC

William L. Hardy II Geophysicist President

Enclosure

SITE LINES LLC PROPOSAL

SITE LOCATION

Classic Cleaners Site – 2641 SW College Road, Ocala, FL

PROPOSED SCOPE OF WORK

Site Lines (“Company”) will use Ground Penetrating Radar (GPR) and conventional electromagnetic (EM) pipe and cable locators to determine the location of underground utilities at the site identified by Environmental Consulting & Technology, Inc. (“Client”).

RESULTS OF THE INVESTIGATION

The estimated depth and location of utilities identified during the investigation will be marked on the ground surface using spray paint or other method to be agreed upon by the parties. The American Public Works Association Uniform Color Codes for the marking of underground utilities will be used.

PROJECT FEE

The fee to complete the project as described within this proposal is:

$800.00

Client shall pay Company in full within thirty (30) days of the invoice date, unless the parties have agreed to another payment arrangement in writing. If during the investigation, Company determines that the goals of the project cannot be achieved with the resources available to Company, Company will notify Client as soon as reasonably possible. Under such circumstances, Company will charge Client only for time expended and materials used to date.

CLIENT REQUIREMENTS

Client is responsible for all site access, maintenance of traffic (MOT), site clearing and/or any other logistical considerations necessary to conduct the utility locate.

Client will also provide all pertinent maps of the project site, including those that show the boundaries of the utility locate, pertinent landmarks, and known utilities (if available). Company is not a substitute for Chapter 556, Florida Statutes.

Accordingly, Client is responsible for calling Sunshine State One Call of Florida

(811) before undertaking any invasive activities, whether through Company, any other entity, or on its own.

DESCRIPTION OF COMPANY INVESTIGATION AND LIMITATIONS

A GSSI SIR-4000 GPR system will be used with a 900, 400, or 270 megahertz antenna configuration depending on site conditions and desired targets. The GPR will assist in locating nonmetallic and metallic utilities. Physical surface conditions, subsurface conditions and technical limitations effect the ability of GPR to resolve targeted utilities and/or subsurface structures. Depth and/or diameter of the utility, soil type, moisture/ionic content of the soil, and electrical properties of the soil compared to that of the utility can prevent the GPR from identifying utilities at the site. The diameter of a utility cannot be determined by GPR data. Estimated depths of utilities are directly affected by soil conditions and the material of the utility. A margin of error of +/- 20-25% in depth should be expected when performing invasive activities.

A Fisher TW-6 split box will be used for the EM survey. The EM survey will assist in finding only metallic utilities.

Due to the limitations described above, when Client is working around indicated utilities, a minimum of two (2)-feet clearance from either side of the marked utility will be maintained. For absolute confirmation, Client is responsible for exposing any indicated underground utility.

Company will conduct utility investigations in accordance with the level of care and generally accepted professional practices as ordinarily exercised by members of the same profession practicing in the same locality under similar conditions.

REPRESENTATIONS AND WARRANTIES

Neither Company nor its employees or agents are licensed surveyors under Florida law, nor do they represent themselves as such. Accordingly, the work Company is to perform is not a substitute for work typically completed by a licensed surveyor.

Company specifically and expressly disclaims any liability for any type of property damage or personal injury, including but not limited to death, arising from client’s failure to determine that the services of a licensed surveyor are necessary or to retain a licensed surveyor to perform necessary services.

Limitations in technology, complexity of the physical characteristics of the subsurface conditions, and circumstances beyond Company’s control may limit the performance of Company’s utility investigation. For these reasons, Company expresses no guarantee that all utilities and underground structures will be identified and located during this project.

Company is responsible only for locating underground utilities, the presence of which is both known and indicated on site maps to be provided by Client to Company before Company performs the utility locate. Company will use its best efforts to locate both known and unknown utilities within the project boundaries. However, Company will only be responsible for locating utilities, the presence of which is known before Company undertakes its investigation.

Company expressly disclaims any and all warranties regarding specific or desired results.

TERMS AND CONDITIONS

Additional Insured: If requested, Company will name Client as an additional insured with respect to the services to be performed under this agreement.

Indemnity: Company agrees to indemnify, protect and hold harmless Client from and against all liabilities, claims or demands of every kind of injury, including death, or damages to any person or property related in any way to Company’s performance of this Agreement, except to the extent such liabilities, claims or demands are caused by the negligence or willful misconduct of Client.

Client agrees to indemnify, protect and hold harmless Company from and against all liabilities, claims or demands of every kind of injury, including death, or damages to any person or property related in any way to Client’s performance of this Agreement, except to the extent such liabilities, claims or demands are caused by the negligence or willful misconduct of Company.

Release of Information. Client authorizes Company to release any information regarding Client and this Agreement as may be permitted by Company's privacy policy or as may be required by law or requested by governmental authorities or agencies, law enforcement agencies or courts including, but not limited to, officials from local and state code enforcement agencies.

Governing Law; Jurisdiction; Severability; Waiver of Jury Trial. This Agreement shall be governed and construed in accordance with the laws of the State of Florida. Whenever possible, each provision of this Agreement shall be interpreted in such manner as to be effective and valid under Florida law, but if any provision of this Agreement shall be invalid or prohibited under Florida law, such provision shall be ineffective only as to the invalid portion of the provision without invalidating the remainder of such provision or the remaining provisions of this Agreement.

Client agrees to waive his or her rights to a jury trial for any and all claims made against or through Company. Client further agrees that Company will be notified of all claims no later than the earlier of thirty (30) days from the initial discovery of the claim or default or thirty (30) days following the expiration or termination of this Agreement. Client also agrees that failure to notify Company of any and all claims within this time period will result in the forfeiture of said claim.

Any claims by Client arising under this Agreement must be brought in a state or federal court of competent jurisdiction located in Pinellas County, Florida or in the

United States District Court for the Middle District of Florida in Tampa, Florida.

Client waives any objection to the jurisdiction and venue of such courts. This exclusive choice of jurisdiction and venue does not preclude Client or Company from bringing an action to enforce any judgment or judicial order in any other jurisdiction. The prevailing party in any dispute will be entitled to recover from the losing party its costs, including, but not limited to, costs of collection, reasonable attorney’s fees, and investigative fees.

Assignment; Succession; Third-Party Beneficiaries. Client shall not assign this Agreement or the rights thereto to any other person or entity without the express written consent of the Company. Company may assign or transfer this Agreement without the consent of Client and, after such assignment or transfer, Company shall be released from all obligations under this Agreement occurring after such assignment or transfer. All of the provisions of this Agreement shall apply to, bind and be obligatory upon the heirs, executors, administrators, representatives, successors and assigns of the parties hereto. This Agreement is for the sole benefit of the parties to this Agreement and their respective successors and permitted assigns. Nothing in this Agreement, express or implied, is intended to or shall confer on any other person or entity any legal or equitable right benefit or remedy of any nature whatsoever under or by reason of this Agreement. Notwithstanding the foregoing, any Company Agent is a third-party beneficiary of this Agreement and has the right to enforce the provisions of this Agreement directly against the Client.

Modification of Agreement. No term of this Agreement can be waived or modified except by a writing signed by both parties. If any provision of this Agreement is deemed not to apply, is illegal, or is against public policy, the remainder of the Agreement’s provisions shall retain their full force and effect.

Entire Agreement. This Agreement, including any addenda or schedules specifically incorporated by reference herein, constitutes the entire agreement between Client and Company. This Agreement contains all representations and agreements between Client and Company. Client agrees that Company has not promised Client anything that is not written on the face of this Agreement.

Disclosure Statement. These terms and conditions apply to Projects to which the Company agrees to engage, whether such agreement is made via the Company’s online website, by email, by telephone, or in person. Be advised that the terms and conditions are subject to change without notice. The extent of Site Lines LLC exposure is the limit of this contract.

SITE LINES PROPOSAL ACCEPTANCE

SIGNATURE PAGE

Site Lines Proposal Number: 01490p Proposal Date: June 18, 2024

Project Site: Classic Cleaners Site – 2641 SW College Rd, Ocala, FL

Project Fee: $800.00

Payment Terms: [PAYABLE WITHIN 30-DAYS OF INVOICE]

INVOICE TO:

Client: ECT Address: 3751 Maguire Blvd, Ste 234, Orlando, FL 32803 Attention: Daniel S. Phillips, P.G.

Phone: 407-509-7684 Email: dphillips@ectinc.com

Special Instructions:

In witness thereof, the parties hereto have made and executed this agreement

FOR [CLIENT] FOR SITE LINES LLC

Signature: Signature:

By: By: William L. Hardy II

Title: Title: President

Date Signed: Date Signed: June 18, 2024

A Geophysical Services Company

5709 First Avenue South Tel.: (727) 209-2334 St. Petersburg, FL 33707 Fax: (727) 328-2477

June 14, 2024

Mr. Daniel S. Phillips, P.G.

Environmental Consulting & Technology, Inc.

3751 Maguire Blvd., Suite 234 Orlando, FL 32803

Subject: Proposal to Perform a Utility Designation Study

Classic Cleaners of Ocala Site Ocala, Florida GeoView Proposal Number: 11207p

Mr. Phillips, P

The purpose of this letter is to transmit a proposal to complete a geophysical investigation at the subject site. This proposal is in response to your request for a proposal made during our recent conversations. GeoView Associates, Inc.

(GeoView) appreciates the opportunity to provide our services on this project. We look forward to hearing from you soon.

GEOVIEW ASSOCIATES, INC.

Michael J. Wightman, P.G.

President Florida Professional Geologist Number 1423

Enclosure

Proposal

This document shall serve as a proposal for work to be performed by GeoView Associates, Inc. (GeoView) for Environmental Consulting & Technology, Inc. (ECT).

Description of Site

The project site is referred to as the Classic Cleaners of Ocala Site and is located at 2641 SW College Road in Ocala, Florida. The purpose of the geophysical survey will be to determine the location of underground utilities within a 5-to-10-foot radius of planned boring locations. The location of the planned borings are provided on Figure 1 (page 6).

Scope of Work

GeoView will provide geophysical surveying services at the project site. The purpose of the geophysical survey will be to determine the location of underground utilities or other underground structures within the designated area of the project site. The fieldwork is estimated to take less than 1 day to complete. This estimate is based upon the site conditions as described by ECT.

The geophysical survey will be completed using ground penetrating radar (GPR) and conventional electromagnetic (EM) pipe and cable locators. The GPR survey will be conducted using either a Mala and/or a GSSI GPR system. The appropriate GPR antenna configuration and time range and processing parameters will be determined in the field by the project manager.

The EM survey will be performed using a Subsite 95R and/or a Radiodetection RD (8000, 8100 or 8200) system. As appropriate, the EM survey will be conducted using both passive and active modes. The passive mode is used to find cables and conduits carrying live power (50-60 Hz) and communication (29-33Hz) signals. For the active mode survey, a current is transmitted directly or broadcast into using electromagnetic induction a metal pipe or conduit and the path of the pipe/conduit is identified by following the signal with a portable receiver.

The active mode is used to trace out cast iron pipes, metal water and sewer lines, utilities that have trace wires, and inactive power and communication lines.

GeoView’s utility locating personnel are all certified GPR and conventional pipe and cable locator operators with extensive in-house training.

Based on information provided by ECT, it does not appear that the work at any of the sites will require MOT (traffic calming efforts). This proposal does not include the costs for the design or implementation of an MOT program.

If requested GeoView can provide vacuum excavation services to determine the exact horizontal location, top elevation, outside diameters and material type of specific underground utilities of any utilities identified at the project site. The vacuum excavation will be performed using the Vermeer CV573GT vacuum excavation system. It is noted that the vacuum excavation equipment used by GeoView can only identify utilities above the water table or to a maximum depth of 7 to 8 ft in unconsolidated soils. It will not be possible to confirm (using vacuum excavation) the presence, location or depth of utilities that are located below these depths or in consolidated soil/rock. The cost for vacuum excavation will range in general from $450 to $550 per hole, with a $1,800 minimum. A full proposal for vacuum excavation services can be provided upon request.

Presentation of Results

The location and estimated depths of underground utilities or any other identified structures shall be indicated on the ground surface using spray paint or other methods as specified by ECT. Designated utilities will also be documented on a scaled AutoCAD site map. The site map will provide the location, depth and purpose of any underground utilities or other structures identified by the survey.

GeoView will use a Trimble Geo7X GPS system to determine the location of any identified underground features. In most site settings the documented positions will be accurate within +/- 1-2 feet.

Compensation

Cost to complete the survey will be as follows:

• Field Investigation and Utility Markout: $1,350

• Preparation of AutoCAD Site Figure: $150

This price is inclusive of all charges associated with the project. Unless otherwise agreed upon, GeoView shall be compensated for all services within 30 days of the invoice date. GeoView shall be paid in full regardless of whether the results of the geophysical survey are what ECT anticipated. If it is determined during the survey that the geophysical survey will not achieve the objectives of the project, ECT will immediately be notified. If a decision is made to discontinue the survey, only charges for time and materials costs to that point will be submitted.

These prices are based upon GeoView being able to access the site during normal business hours, Monday through Friday. It is also based upon the assumption that no site-specific training or drug testing will be required. If there are any such requirements, additional costs will be incurred.

Requirements of Client

ECT will provide a scaled map and digital file, if available, of the project site showing the boundaries of the project site, areas of specific concern and pertinent landmarks. ECT will also supply all available information regarding the presence and history of underground utilities at the project site (see limitations for further discussion). Unless otherwise requested, ECT will be responsible for the coordination of site access, traffic control, clearing of onsite obstructions or any other logistical consideration necessary to conduct the survey. If any test drilling, monitor well installation or other excavation activities are planned it will be the responsibility of ECT to submit a notification (dig ticket) to the appropriate 811 One-Call agency. It is recommended that such notification be filed sufficiently in advance so that GeoView will have the opportunity incorporate the 811 findings into their results.

Limitations

The objective of the geophysical survey is to determine the presence and configuration of underground utilities. However, the geophysical response of these features may be highly complex depending upon on the physical characteristics of the underground utilities, the electrical properties of the surrounding soils, the depth of burial of the utilities, and the proximity of the utilities to each other.

GeoView shall conduct the geophysical survey using the most “up-to-date” geophysical equipment in a manner consistent with the level of care and skill ordinarily exercised by members of the geophysical profession practicing in the same locality under similar conditions. GeoView’s utility locating personnel are all certified GPR and conventional pipe and cable locator operators with extensive in-house training.

It is acknowledged that GeoView is not an 811 Sunshine One-Call or equivalent utility mark-out service. GeoView does not have access to any utility-related records for either public or private properties. It is the responsibility of ECT to obtain such records and provide them to GeoView prior to the site investigation.

GeoView will use these records during the site investigation and report to ECT any utilities that are shown on the site records but cannot be confirmed by GeoView.

GeoView will not mark on the ground surface any utilities which it cannot confirm.

GeoView shall only be liable for the successful locating of underground utilities or any other underground structures whose presence is both known and indicated on site maps to be provided prior to the performance of the geophysical survey. Every attempt will be made to locate both known and unknown utilities within the survey area. However, GeoView will only be liable for utilities whose presence is known prior to the survey. ECT accepts that due to the inherent limitations of non-intrusive geophysical technologies GeoView cannot be held liable for damages to utilities that cannot be identified using non-intrusive technologies.

ECT accepts that a non-intrusive utility designation study does not replace the need to employ widely accepted industry safety standards for subsurface work.

Concerning the installation of well or test borings this standard of care includes post-holing or hand auguring at the planned test locations to the minimum depth at which underground utilities are anticipated at the project site. If absolute confirmation is needed to a specified depth that underground utilities are not present at a planned work location GeoView can provide vacuum excavation services. Pricing for such services is available on request.

When ECT is working around indicated utilities, a minimum of 2 ft clearance from either side of the marked utility will be maintained. Unless otherwise indicated, a minimum vertical clearance of +/- 20 percent of the indicated depth shall also be maintained. ECT maintains the responsibility for manually exposing any indicated underground utility for absolute confirmation.

Authorization and scheduling of the project is considered acceptance of these terms and conditions.

Other Terms and Conditions

Additional Insured: If requested, ECT will be named as an additional insured with respect to the services to be performed under this agreement.

Confidentiality: GeoView shall not directly or indirectly disclose to any third person information regarding the results of the geophysical investigation prior to obtaining written permission from ECT.

Agreement: This agreement represents the entire agreement between the parties and may only be modified in writing signed by both parties.

Governing Law: This agreement shall be deemed to have been made in the place of performance of the Geophysical Services and shall be governed by, and construed in accordance with the laws of the state in which the geophysical services were provided. Any controversy or claim arising out of this agreement, or breach thereof, shall be settled by binding arbitration administered by the American Arbitration Association under its Construction Industry Arbitration rules. Judgment on the award rendered by the arbitrator(s) may be entered in any court having jurisdiction thereof.

Indemnity: GeoView agrees to indemnify, protect and hold harmless ECT from and against all liabilities, claims or demands of every kind of injury, including death, or damages to any person or property related in any way to GeoView’s performance of this agreement, except to the extent such liabilities, claims or demands are caused by the negligence or willful misconduct of ECT.

Figure 1 – Site Location

Experience

GeoView has completed over 10,000 utility designating projects. These projects include:

United States Air Force Bases: GeoView successfully located and mapped the exact location of approximately 250,000 linear feet of petroleum oil and lubrications at 12 Air Force Bases throughout the continental United States.

Hospitals: GeoView successfully located and mapped the precise location of utilities at multiple hospitals prior to demolition and construction activity.

School Buildings: GeoView has successfully located and mapped the location of utilities at more than 250 schools throughout the eastern United States as part of a design-build or construction projects.

Utility Mapping at Multiple Federal Penitentiaries: GeoView has successfully located and mapped the location of utilities around the perimeter of multiple federal penitentiaries as part of construction projects. The penitentiaries were located in Florida, Louisiana, West Virginia, and Kentucky.

Gasoline Service Stations: GeoView has successfully designated underground utilities at over 2500 gasoline service stations. Designated utilities have included product pipelines along with all other underground utilities typically encountered at such facilities.

GPR data collected by GeoView as part of a Design Build Survey

Buried Utilities

Trench

Marking fiberglass fuel lines with GPR

GEOVIEW ASSOCIATES, INC.

PROPOSAL ACCEPTANCE SHEET

Project Name: Custom Care Cleaners Site Project Location Ocala, Florida GeoView Proposal #: 11207p Proposal Date: June 14, 2024 Description of Services Provide Utility Designating and Mapping Services Project Cost: $1,350 or $1,500– see compensation, page 3 Payment Terms: Payable within 30 days of receipt of invoice

CHARGE INVOICE TO THE ACCOUNT OF:

Client: Environmental Consulting & Technology, Inc.

Address: 3751 Maguire Blvd., Suite 234

Orlando, FL 32803 Attention: Daniel S. Phillips, P.G.

Phone (Office): (407) 903-0005 Phone (Cell): (407) 509-7684 Email: dphillips@ectinc.com

FOR APPROVAL OF CHARGES:

Firm:

Address:

Phone No.: Fax No:

Attention:

Special Instructions and/or Mutually Agreed Upon Changes to the Proposal:

In witness thereof, the parties hereto have made and executed this Agreement

Client: GeoView Associates, Inc.

Signature

By: By: Mike Wightman, P.G.

Title: Title: President

Date Signed: Date Signed: June 14, 2024

General Description of Geophysical Methods

Ground Penetrating Radar (GPR)

The GPR survey will be conducted using a Mala or GSSI GPR system. The survey will be conducted with either a 500, 400 or 250 mega-Hertz antenna. The appropriate antenna will be determined in the field by the project manager. GPR will be able to provide both the position and estimated depth of both metallic and non-metallic underground utilities.

The ability of GPR to resolve a particular utility will be controlled by the following factors: 1) Depth of penetration of the GPR signal, 2) Depth of burial and diameter of the underground utility and 3) Electrical contract between the underground utility and the surrounding soils and 4) The complexity of the utility layout at the site. Due to one or a combination of these factors the GPR may not be able to identify all the utilities at the site. The diameter or composition of utilities cannot be accurately determined using GPR, though can be estimated. Estimates of burial depth are typically accurate to within +/- 20 percent, more accurate depths are possible if invert elevations for some on-site utilities are known.

Conventional Electromagnetic Pipe and Cable Locators

A Radiodetection System is used to locate underground utilities using conventional means. The system consists of a dual-function receiver and transmitter. The receiver can be operated in two modes: active and passive. In the passive mode the receiver detects the presence of underground utilities that are energized by a 60-Hertz or other known frequency. These utilities can either be those actually carrying electrical power or those utilities that are both metallic and sufficiently close to the electrical lines to have an electrical field induced within them.

In the active mode, the transmitter deliberately induces an electrical current into the utility. The frequency of this field can be varied from 512 Hertz to 200 kilohertz. The electrical field is induced using a transmitter which is either directly attached to the utility, placed on or above the utility or attached to an induction coil which is placed around the utility. Depths of underground utilities can be determined when the EM equipment is being used in the active mode. Depths are typically accurate to within 10-15 percent of the total utility depth.

SurvTech Solutions, Inc.

10220 U.S. Highway 92 East Phone: 813-621-4929 Tampa, Florida 33610 Fax: 813-621-7194 Web: www.survtechsolutions.com Email: Sales@survtechsolutions.com

Tuesday, July 2, 2024

Daniel Phillips Environmental Consulting & Technology, Inc.

3751 Maguire Blvd, Suite 234 Orlando, FL 32803

RE: Proposal for Services for 241117 - Classic Cleaners of Ocala SUE located at 2641 SW College Rd, Ocala, FL, 34471; Folio No.: N/A; Estimate No.: 241217; Project No.: N/A

Dear Daniel;

SurvTech Solutions, Inc. is pleased to submit the following information for your consideration in selecting a firm to perform the necessary services, as noted above. We feel that you will find SurvTech Solutions, Inc. is well qualified to accomplish all services set forth in the request for proposal. Our outstanding staff of professional, technical, and support personnel has extensive and varied qualifications.

The lump-sum cost for the project will be $3,932.50, with an estimated time frame of 30 days from notice to proceed. Please see attached scope of work for a detailed breakdown of costs and services. If a quicker schedule is needed, please contact us, and we will try to accommodate your schedule.

If this proposal is acceptable, please sign the attached contract and send it to SurvTech Solutions via fax, email, or U.S. Mail. SurvTech cannot start said project without having a signed contract in place. If your firm wishes to use its own in-house contract or purchase order, then please forward them to SurvTech for review and signatures. SurvTech Solutions, Inc. appreciates this opportunity to submit this proposal for services. We look forward to serving Environmental Consulting & Technology, Inc.

on this project.

Respectfully submitted, SurvTech Solutions, Inc.

Florida Licensed Business No. 7340

Raymondjames Hicks SUE Division Leader

PROPOSAL 241217

PM, QA/QC, Clerical, Field Checks $786.50 Subsurface Utility Designation (SUE QL-B) $2,112.00 Utility Survey Collection $1,034.00

TOTAL $3,932.50

SUE Scope of Services

Standards of Practice:

1. All Utility Mapping Services will use the standards set forth by ASCE under CI/ASCE 38-22 as a guide.

Subsurface Utility Designation

1. By use of Ground Penetrating Radar (GPR) and Electromagnetic Induction (EM), Attempt to horizontally locate and field mark (paint & flags) all public subsurface utilities found excluding service lines, gravity sewer lines and irrigation within the area outlined in red on the attached exhibit.

Subsurface Utility Survey Collection

1. Survey collect all utility data using GPS or conventional surveying equipment.

2. SurvTech shall only locate and map found utilities. No other mapping is included in this proposal unless specifically noted below.

3. Elevation and depth data is NOT included in this proposal.

Deliverables

1. The following deliverables are included in this proposal:

Deliverables shall be surface marking (paint and/or flags) of horizontal location of found subsurface utilities and a utility designation field sketch(s) of the project area reflecting all obtained relevant data for your use.

Survey drawing at a standard scale on a standard 24" x 36"size title block, unless specifically requested otherwise by client. Final drawings shall be submitted as full-size copies, certified, and sealed, dated, and signed by a Florida Professional Surveyor and Mapper. Final survey shall be made available to client in electronic format, AutoCAD (.dwg format), and Adobe PDF format. File will be sent by email unless the client specifically requests a CD of the drawing file.

Utilities will be overlaid on a rectified ortho-photo from the State of Florida’s LABINS orthoimagery database.

2. The following deliverables are also included in this proposal:

a. Copies of all Site Photos Requested by Client

b. Copies of all Field Notes Requested by Client

c. Other ________________________________

Terms and Conditions

It is understood that the Client is responsible to abide by Sunshine 811, Florida State Statutes Chapter

556.106 and all applicable laws, and regulations that pertain to the services provided.

SurvTech expects Client to supply any existing information pertaining to the location of underground utilities in the project area. In addition to any information provided by Client, SurvTech will proceed with retrieving records from regulatory agencies including but not limited to: Sunshine One Call, local and state utility departments, and private utility providers.

SurvTech will ensure that all reasonable efforts are made to identify the location of each underground utility and provide the best available information within the project area but makes no guarantees that all utilities and structures will be found. Limitations including but not limited to the lack of or inaccuracy of prints, and restrictions with GPR technology exist due to the complexity of site conditions and circumstances beyond the control of SurvTech.

SurvTech expects that the proposed work area to be free and clear of objects or obstacles that might prohibit access in and around the proposed work area. This would include clearing vegetation, machinery, debris, or any other object that would prevent access to the proposed work area. Failure to do so could result in time delay or incomplete coverage of the proposed work area.

Client will be responsible for verifying any information provided by SurvTech that is obtained via contact with utility providers as per the Underground Facility Damage Prevention and Safety Act.

The surface designation provided by SurvTech is certified to be within two (2) feet of the true underground position of the utility relative to the mark as shown on the surface.

SurvTech shall not be held liable for any latent or unreasonably discoverable utilities or structures in the project area. Furthermore, in the event of a claim regarding the services provided in the proposal, SurvTech shall have liability for reasonable and necessary defense costs to the extent caused by SurvTech’s negligence.

SurvTech shall NOT obtain depths while designating utilities.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .