This document is a Task Assignment Change Order (TACO) issued by the State of Florida Department of Environmental Protection (FDEP) for Contract Number HW682, Task Assignment Number DC021A. The contract involves the FDEP and the contractor Environmental Consulting and Technology, Inc. (ECT), with Karlee Fowler serving as the Department's Project Manager and Mark A. Culbreth as the contractor's representative. The work is located at Koretizing Cleaners II (D282) in Jacksonville, Duval County, Florida, under Project Number ERIC_4575.
This TACO authorizes a no-cost time extension for ECT to complete annual groundwater monitoring activities at the site. The task assignment maintains a fixed unit rate total value of $12,966.56 with 54 labor hours allocated across four subtasks: Project Management (Subtask 1), Well Installation/Abandonment (Subtask 2), Groundwater Sampling (Subtask 3), and Investigative Derived Waste (IDW) Management (Subtask 4). The completion date was extended from June 7, 2024, to August 30, 2024, representing an 84-day extension due to driller availability scheduling delays. Deliverables include well installation/abandonment field notes ($5,704.31), annual NAM report ($5,524.27), and IDW manifest/project management documentation ($1,737.98), with invoicing contingent upon FDEP approval of each deliverable. The change order was executed on February 13, 2024, and becomes effective upon the final authorized signature.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
DC021A 01 HW682
This Change Order authorizes a no cost time extension for ECT to perform annual groundwater monitoring at Koretizing Cleaners II (D282)
Karlee Fowler 850-245-8944 Contractor Environmental Consulting and Technology, Inc. (ECT) Contractor
Contractor Mark A. Culbreth Contractor 813-289-9338
ERIC_4575
Koretizing Cleaners II (D282)
✔ $ 12,966.56 $ 12,966.56
$ 12,966.56 $ 12,966.56 ✔ Completion ✔ Completion 06/07/2024 08/30/2024 84
✔ 1 1 1
Contractor Mark A. Culbreth
Contract Manager
2/13/2024
Digitally signed by Mark Culbreth Date: 2024.02.13 09:34:50-05'00'Mark Culbreth
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.02.13 09:19:42 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW682
DC021A
$ 12,966.56
Well Installation/Abandonment Field Notes (Subtask 2)
Annual NAM Report (Subtask 3)
IDW Manifest; Project Management (Subtask 1 & 4)
Upon submittal and FDEP approval of Well Installation/Abandonment Field Notes (Subtask 2)
Upon Submittal and FDEP approval of IDW Manifest; Project Management (Subtask 1 & 4)
Upon Submittal and FDEP approval of Annual NAM Report (Subtask 3)
05/03/2024
06/28/2024
07/29/2024
$ 5,704.31
$ 5,524.27
$ 1,737.98
FFLORIDAA DEPARTMENTT OF
EEnvironmentall Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ronn DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawnn Hamilton Secretary
To:
From:
Date:
HW68 Contract Negotiation File
County
ERIC_
Project Manager
Subject: Negotiation Summary
HW68
This Task Assignment
Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.
Subtask :
Subtask :
Fowler, Karlee
From: Fowler, Karlee Sent: Wednesday, January 31, 2024 9:56 AM To: Gregory Sattler Cc: Mark Culbreth; Courtney Wranosky Subject: RE: Koretizing Cleaners II (D282) ERIC_4545 TA DC021A Time Extensions
Thank you for le ng me know, Greg. I’ll go ahead and put together a me extension TACO.
Thanks!
Karlee
From: Gregory Sattler <gsattler@ectinc.com> Sent: Wednesday, January 31, 2024 9:49 AM To: Fowler, Karlee <Karlee.Fowler@FloridaDEP.gov> Cc: Mark Culbreth <mculbreth@ectinc.com>; Courtney Wranosky <cwranosky@ectinc.com> Subject: Koretizing Cleaners II (D282) ERIC_4545 TA DC021A Time Extensions
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Good morning Karlee, I am reques ng me extensions for all the Kore zing Cleaners II (D282), TA DC021A SubTasks. I cannot get the drilling scheduled as plan, and as a result, the first drilling date now is April 26th. I am reques ng the following date extensions.
SubTask 2 Well Install and Well Abandonment; changed from January 13, 2024, to May 3, 2024.
SubTask 3 Annual Report; changed from March 13, 2024, to June 28, 2024.
SubTask 4 IDW Manifest; changed from April 12, 2024, to July 29, 2024.
SubTask 1 PM; changed from May 12, 2024, to July 29, 2024.
A ached is the signed TA as a reference.
I am available any me to discuss the recommended change if needed.
Best Regards, Gregory Sattler, P.E.
Senior Remediation Engineer| Site Assessment & Remediation
Environmental Consulting & Technology, Inc.
3751 Maguire Boulevard | Suite 234 | Orlando, Florida 32803 C: 321.245.2124 | gsattler@ectinc.com
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW682
DC021A June 7, 2024
This Task Assignment authorizes ECT to perform annual groundwater monitoring in accordance with the attached Scope of Work and Cost Estimate.
Ginger Shirah 850-245-8899 Environmental Consulting and Technology, Inc. (ECT)
Mark A. Culbreth 813-289-9338
ERIC_4575
2261 Edgewood Avenue West, Jacksonville, Duval County
Koretizing Cleaners II (D282)
$ 12,966.56
$ 12,966.56
Scope of Work
Environmental Consulting and Technology, Inc. (ECT
Gregory L. Sattler
Contract Manager
Kelly Crain Digitally signed by Kelly Crain Date: 2023.09.08 15:27:38 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Invoice Schedule:
TOTAL COST