This document is a Task Assignment Change Order (TACO #1) issued by the State of Florida Department of Environmental Protection (FDEP) to Environmental Consulting and Technology, Inc. (ECT). The change order amends the original Task Assignment DC006B under Contract HW682 and extends the project completion timeline. Key parties include FDEP Project Manager Karlee Fowler and ECT Project Manager Mark A. Culbreth. The project addresses work at Crossroads Square Shopping Center (ERIC_4625) located at 8102 Blanding Boulevard, Jacksonville, Duval County, Florida.

The Task Assignment authorizes ECT to perform annual groundwater monitoring in accordance with an attached Scope of Work and Cost Estimate. The total contract value remains $6,845.07 on a fixed unit rate basis with no changes to compensation. The original completion date of May 17, 2024 was extended to September 13, 2024 (a 119-day extension) to allow additional time to complete and review the Natural Attenuation Monitoring report and IDW deliverable. The invoice schedule specifies two deliverables: an Annual NAM Report due July 26, 2024 ($5,979.53) and an IDW Manifest; Project Management due August 16, 2024 ($865.54). The change order was executed on May 16, 2024.

View the file

Other files

File Type Posted
CN-370000-HW682-DC001C.pdf PDF
CN-370000-HW682-DC003A.pdf PDF
CN-370000-HW682-DC003B.pdf PDF
CN-370000-HW682-DC006B.pdf PDF
CN-370000-HW682-DC007C.pdf PDF
CN-370000-HW682-DC007D.pdf PDF
CN-370000-HW682-DC008C.pdf PDF
CN-370000-HW682-DC010B.pdf PDF
CN-370000-HW682-DC010C.pdf PDF
CN-370000-HW682-DC015A.pdf PDF
CN-370000-HW682-DC016A.pdf PDF
CN-370000-HW682-DC016B.pdf PDF
CN-370000-HW682-DC021A.pdf PDF
CN-370000-HW682-DC027A.pdf PDF
CN-370000-HW682-DC03CCO2.pdf PDF
CN-370000-HW682-DC03CCO3.pdf PDF
CN-370000-HW682-DC04BCO2.pdf PDF
CN-370000-HW682-DC04BCO3.pdf PDF
CN-370000-HW682-DC04BCO5.pdf PDF
CN-370000-HW682-DC05BCO6.pdf PDF
CN-370000-HW682-DC05BCO8.pdf PDF
CN-370000-HW682-DC06BCO2.pdf PDF
CN-370000-HW682-DC08DCO1.pdf PDF
CN-370000-HW682-DC09ACO2.pdf PDF
CN-370000-HW682-DC09ACO3.pdf PDF
CN-370000-HW682-DC10BCO1.pdf PDF
CN-370000-HW682-DC11ACO4.pdf PDF
CN-370000-HW682-DC11ACO6.pdf PDF
CN-370000-HW682-DC13ACO1.pdf PDF
CN-370000-HW682-DC13BCO1.pdf PDF
CN-370000-HW682-DC13BCO7.pdf PDF
CN-370000-HW682-DC16ACO2.pdf PDF
CN-370000-HW682-DC18ACO2.pdf PDF
CN-370000-HW682-DC18ACO3.pdf PDF
CN-370000-HW682-DC20ACO1.pdf PDF
CN-370000-HW682-DC21ACO1.pdf PDF
CN-370000-HW682-DC21BCO1.pdf PDF
CN-370000-HW682-DC22ACO2.pdf PDF
CN-370000-HW682-DC24ACO1.pdf PDF
CN-370000-HW682-DC26ACO3.pdf PDF
CN-370000-HW682-DC27ACO1.pdf PDF
CN-370000-HW682-DC28ACO1.pdf PDF
CN-370000-HW682-FIL2.pdf PDF
CN-370000-HW682-FIL6.pdf PDF
CN-370000-HW682-HW001A.pdf PDF
CN-370000-HW682-HW004A.pdf PDF
CN-370000-HW682-HW006A.pdf PDF
CN-370000-HW682-HW007A.pdf PDF
CN-370000-HW682-HW011A.pdf PDF
CN-370000-HW682-HW016A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

DC006B 1 HW682

Karlee Fowler 850-245-8944 Environmental Consulting and Technology, Inc. (ECT)

Mark A. Culbreth 813-289-9338

ERIC_4625

Crossroads Square Shopping Center

$ 6,845.07 $ 6,845.07

$ 6,845.07 $ 6,845.07

05/17/2024 09/13/2024 119

1 1 1

Environmental Consulting & Technology, Inc.

Mark A. Culbreth

Contract Manager

May 16, 2024

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2024.05.16 14:14:41 -04'00'

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO:

FROM:

SUBJECT:

DATE:

HW682 Contract File

ERIC_4

K , Project Manager Negotiation Summary Task Assignment DC

This Task Assignment authorizes

The Task Assignment total $ , The project manager agrees to the scope of work and associated costs.