Document Summary

This document is a Task Assignment Change Order (TACO #1) issued by the State of Florida Department of Environmental Protection (FDEP) to CDM Smith Inc., a contractor under Contract Number HW681. The change order modifies a Task Assignment (DC020B) related to environmental monitoring services at Touch of Class Cleaners located at 8420 Lockwood Ridge Road in Sarasota, Florida. The Department's Project Manager is Kyle McMurray, and the Contractor's Project Manager is Shayne Wood. This TACO tasks CDM with reinstalling two MAGS (Mobile Air Sampling Grab System) wells and extends the project timeline.

The amended Task Assignment value increases from $18,086.60 to $29,869.85, representing a cost increase of $11,783.25 attributed to increased vehicle, subcontractor, lab, equipment, and CDM labor costs for the MAGS reinstall and testing subtask. The deliverables include field notes and air sample data due August 15, 2023; an Annual Groundwater Monitoring Report due December 15, 2023; and MAGS reinstall and sampling data due February 14, 2024. The project completion date was extended from January 15, 2024, to April 17, 2024, providing an additional 93 days. Invoice payments are structured as $2,928.01 for field notes and sampling data and $26,941.84 for the monitoring report and reinstall work. The FDEP Project Manager approved the scope and cost of this change order on November 2, 2023.

View the file

Other files

File Type Posted
CN-370000-HW681-DC001B.pdf PDF
CN-370000-HW681-DC001E.pdf PDF
CN-370000-HW681-DC002E.pdf PDF
CN-370000-HW681-DC002F.pdf PDF
CN-370000-HW681-DC003B.pdf PDF
CN-370000-HW681-DC005D.pdf PDF
CN-370000-HW681-DC005E.pdf PDF
CN-370000-HW681-DC008B.pdf PDF
CN-370000-HW681-DC008E.pdf PDF
CN-370000-HW681-DC009A.pdf PDF
CN-370000-HW681-DC010A.pdf PDF
CN-370000-HW681-DC010C.pdf PDF
CN-370000-HW681-DC011C.pdf PDF
CN-370000-HW681-DC012D.pdf PDF
CN-370000-HW681-DC013A.pdf PDF
CN-370000-HW681-DC013B.pdf PDF
CN-370000-HW681-DC013C.pdf PDF
CN-370000-HW681-DC013D.pdf PDF
CN-370000-HW681-DC015A.pdf PDF
CN-370000-HW681-DC016C.pdf PDF
CN-370000-HW681-DC017B.pdf PDF
CN-370000-HW681-DC018C.pdf PDF
CN-370000-HW681-DC019B.pdf PDF
CN-370000-HW681-DC01ACO5.pdf PDF
CN-370000-HW681-DC021A.pdf PDF
CN-370000-HW681-DC021B.pdf PDF
CN-370000-HW681-DC021C.pdf PDF
CN-370000-HW681-DC025A.pdf PDF
CN-370000-HW681-DC02BCO2.pdf PDF
CN-370000-HW681-DC02DCO1.pdf PDF
CN-370000-HW681-DC031C.pdf PDF
CN-370000-HW681-DC032D.pdf PDF
CN-370000-HW681-DC033C.pdf PDF
CN-370000-HW681-DC037B.pdf PDF
CN-370000-HW681-DC038B.pdf PDF
CN-370000-HW681-DC038C.pdf PDF
CN-370000-HW681-DC03A.pdf PDF
CN-370000-HW681-DC03CCO1.pdf PDF
CN-370000-HW681-DC03CCO2.pdf PDF
CN-370000-HW681-DC041C.pdf PDF
CN-370000-HW681-DC042B.pdf PDF
CN-370000-HW681-DC042C.pdf PDF
CN-370000-HW681-DC043A.pdf PDF
CN-370000-HW681-DC043B.pdf PDF
CN-370000-HW681-DC04BCO1.pdf PDF
CN-370000-HW681-DC05CCO3.pdf PDF
CN-370000-HW681-DC06BCO4.pdf PDF
CN-370000-HW681-DC07ACO1.pdf PDF
CN-370000-HW681-DC07CCO1.pdf PDF
CN-370000-HW681-DC08CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

DC020B 1 HW681

This Task Assignment Change Order tasks CDM with reinstalling two MAGS wells and a time extension

Kyle McMurray 850-245-8973 CDM Smith Inc.

Shayne Wood 904-527-6703

ERIC_4897

Touch of Class Cleaners - Sarasota

$ 29,869.85 $ 18,086.60

$ 29,869.85 $ 18,086.60

01/15/2024 04/17/2024 93

1 1 1

CDM Smith Inc.

Shayne Wood

CDM Contract Manager

11/16/2023

Kelly Crain

Kelly Crain Digitally signed by Kelly Crain Date: 2023.11.09 12:27:04 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

TO: HW681 Contract File

FROM: Kyle McMurray, Contract Manager

DATE: November 2, 2023

SUBJECT: Negotiation Summary Task Assignment DC020B

TACO #1

This Task Assignment Change Order tasks CDM with reinstalling two MAGS wells and a time extension. In accordance with the CDM Smith (CDM) Change Order request received on October 16th, 2023.

Changes to the original CDM scope of work include the following:

Subtask 5: MAGS Reinstall + Test Subtask 5 has an overall price increase due to increased vehicle, subcontractor, lab, equipment, and CDM labor costs.

The overall cost increase related to this Change Order is $11,783.25

The FDEP project manager agrees to the scope of work and final cost associated with this Task Assignment Change Order. The final cost total for Task Assignment DC020B is $29,869.85.

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Touch of Class Cleaners - Sarasota SUBTASK: MAGS Reinstall + MAGS Test

DATE: 10/9/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager K. Fincham Prepare Field Scope of Work 1

Review/submittal of Data Summary 1

Professional II K. Turner Mobilization/Demobilization (1 mob) 2

Field Preparation 1

Update HASP 1

Prepare Sample Kit 1

Perform MAGS Test 5

Preparation of Data Summary 1

Professional I L. Weber Data Tabulation/Data Package Preparation 1

Total Hours

K.Fincham 2

K. Turner 11

L. Weber 1

TOTAL LABOR 14

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 1 $120.00

TOTAL VEHICLE $120.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOCs by TO-15 $200.00 1 0 $200.00

Shipping Cooler $150.00 1 $150.00

Ice $6.50 2 $13.00

TOTAL LAB $363.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

MAGS Investigation Kit $500.00 1 day $500.00

Expendables $40.00 1 day $40.00

Summa Canister $33.00 1 each $33.00

TOTAL EQUIPMENT $573.00

FINAL --7/24/96

SUBTASK: Annual Groundwater Sampling

DATE: 10/9/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager K. Fincham Prepare Field Scope of Work 1

Review/submittal of Data Summary 1

Professional II K. Turner Mobilization/Demobilization (4 mob - sampling -IDW) 8

Field Preparation 1

Update HASP 1

Prepare Sample Kit 1

Sample Monitoring Wells 24

Preparation of Data Summary 2

IDW Managment 2

Professional I L. Weber Data Tabulation/Data Package Preparation 2

Total Hours

K.Fincham 2

K. Turner 39

L. Weber 2

TOTAL LABOR 43

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 4 $480.00

TOTAL VEHICLE $480.00

SUBCONTRACTOR COSTS

NAME PURPOSE Unit COST

Erwin Remediation IDW 1 $125.00 $125.00

TOTAL $125.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOH - EPA Method 8260 $73.00 16 0 $1,168.00

Shipping Coolers (Large) $150.00 2 $300.00

Ice $6.50 4 $26.00

TOTAL LAB $1,494.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Groundwater Sampling Kit $290.00 3 day $870.00

Expendables $40.00 3 day $120.00

HDPE Tubing $0.30 160 foot $48.00

Silicon Tubing (1/4") $3.00 6 foot $18.00

Drum $100.00 1 each $100.00

TOTAL EQUIPMENT $1,156.00

SUBTASK: Annual Groundwater Monitoring Report

DATE: 10/9/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Leader S. Cobert PE review/Seal 2

Project Manager K. Fincham GWMR Conclusions/Recommendations 2

Profesisonal II K. Turner Preparation of GWMR - body of report 24

Professional I L. Weber Preparation of GWMR Data Tables, Summaries 12

Total Hours

S. Cobert 2

K.Fincham 2

K. Turner 24

L. Weber 12

TOTAL LABOR 40

SUBTASK: MAGS Reinstall + Test TACO 1

DATE: ########

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical LeadS. Cobert Predrill Planning/Technical Field Support/Review of Data Summary 3

Project Manager K. Fincham Prepare Field Scope of Work & predrilling planning 3 Review/submittal of Data Summary 2

Professional II K. Turner Mobilization/Demobilization (1 mob) Drilling 2 Field Preparation & Predrilling planning 3 MAGS Well Reinstall 10 Preparation of Data Summary 1 Mobilization/Demobilization (1 mob) MAGS Test 2 Field Preparation 1 Prepare Sample Kit 1

Perform MAGS Test 8 Preparation of Data Summary 2

Professional I M. Ivers IDW Management 2 Professional I L. Mueller Data Tabulation/Data Package Preparation 2

Total Hours S. Cobert 3 K. Fincham 5 K. Turner 30 M. Ivers 2 L. Weber 2

TOTAL LABOR 42

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 2 $240.00

TOTAL VEHICLE $240.00

SUBCONTRACTOR COSTS

NAME PURPOSE Unit COST

Groundwater Protection Drilling 1 $2,855.00 $2,855.00 Erwin Remediation IDW 1 $125.00 $125.00

TOTAL $2,980.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOCs by TO-15 $200.00 1 0 $200.00 IDW- TCLP Soil VOCs $210.00 1 0 $210.00 Shipping Cooler $150.00 2 $300.00 Ice $6.50 4 $26.00

TOTAL LAB $736.00

EQUIPMENT ITEM RATE COSTING UNITUSEAGE TOTALS

Well Install Kit $325.00 1 day $325.00 MAGS Investigation Kit $500.00 1 day $500.00 Expendables $40.00 2 day $80.00 Summa Canister $33.00 1 each $33.00

TOTAL EQUIPMENT $938.00

SUBTASK: MAGS Rein 0

DATE: ########

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical LeadeS. Cobert Predrill Planning/Technical Field Support/Review of Data Summary 3

Project Manager K. Fincham Prepare Field Scope of Work & predrilling planning 3 Review/submittal of Data Summary 2

Professional II K. Turner Mobilization/Demobilization (1 mob) Drilling 2 Field Preparation & Predrilling planning 3 MAGS Well Reinstall 10 Preparation of Data Summary 1 Mobilization/Demobilization (1 mob) MAGS Test 2 Field Preparation 1 Prepare Sample Kit 1

Perform MAGS Test 8 Preparation of Data Summary 2

Professional I M. Ivers IDW Management 2 Professional I L. Mueller Data Tabulation/Data Package Preparation 2

Total Hours S. Cobert 3 K. Fincham 5 K. Turner 30 M. Ivers 2 L. Weber 2

TOTAL LABOR 42

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 2 $240.00

TOTAL VEHICLE $240.00

SUBCONTRACTOR COSTS

NAME PURPOSE Unit COST

Groundwater Protection Drilling 1 $2,855.00 $2,855.00 Erwin Remediation IDW 1 $125.00 $125.00

TOTAL $2,980.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOCs by TO-15 $200.00 1 0 $200.00 IDW- TCLP Soil VOCs $210.00 1 0 $210.00 Shipping Cooler $150.00 2 $300.00 Ice $6.50 4 $26.00

TOTAL LAB $736.00

EQUIPMENT ITEM RATE COSTING UNITUSEAGE TOTALS

Well Install Kit $325.00 1 day $325.00 MAGS Investigation Kit $500.00 1 day $500.00 Expendables $40.00 2 day $80.00 Summa Canister $33.00 1 each $33.00

TOTAL EQUIPMENT $938.00

UNIT COST TOTAL

EA $ 3,405.00 $ 3,405.00

Feet $ 30.00 $ 300.00

Drums $ 70.00 $ 70.00

$ 3,775.00 days

BID FORM - DRILLER

Touch of Class Cleaners - Sarasota

8420 Lockwood Ridge Road Sarasota, Sarasota County, Florida FDEP Facility ID No. ERIC_4897

*Please reference the Bid Specifications for a complete description of the items listed below

ITEM QUANTITY

Preconstruction Activities: Includes health and safety, pre-drill meeting, mobilization of equipment and manpower to the site, and utility locate 1

MAGS Well Installation: Using hand bucket auger methodologies, install two MAGS wells inside the current building. The MAGS wells will be installed to a terminal depth of 5 feet below land surface (bls). The MAGS wells will be constructed using 4 feet of 2-inch diameter, 0.010-inch, factory-slotted polyvinyl chloride (PVC) well screen, coupled with 1 foot of solid 2-inch diameter PVC riser. Approximately 4.5 feet of 20/30 graded silica sand seal will be placed from the bottom of the well screen to approximately 6 inches bls. The remaining annular space will be filled with neat cement grout. The MAGS wells will be finished inside a flush-mount 6- inch well vault, installed within the concrete slab.

IDW: Includes FDOT-approved 55-gallon drums and movement of drums to on-site staging area determined by CDM1.

TOTAL:

COMPANY NAME

PRINT NAME TITLE

SIGNATURE DATE

QUOTE IS VALID FOR DAYS

TIME ESTIMATE

Days required for well installation 1

Notes:

1. Number of drums required to be specified by drilling contractor.

Preferred Drilling Solutions, Inc.

Austin Bonacum Project Estimator

9/26/2023

McMurray, Kyle

From: Leggoe, Kathy R. <leggoekr@cdmsmith.com> Sent: Monday, October 16, 2023 12:41 PM To: McMurray, Kyle Cc: Cobert, Steven C.; Blanton, Melanie E.

Subject: TOC Sarasota TACO DC020B Attachments: ERIC_4897_TOC-Sarasota_TA DC020B.TACO 1 original.xlsx; ERIC_4897_TOC-Sarasota_TA

DC020B.TACO 1 Delta.xlsx; ERIC_4897_TOC-Sarasota_TA DC020B.TACO 1 Final.xlsx; Attachment A.pdf

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Good morning, Kyle. I am pleased to submit the TACO for TOC Sarasota.

In August when we were trying to schedule work at this site, we initially ran into issues with gaining access to the restaurant by the site tenant. FDEP assisted and CDM attempted to perform MAGS testing on 8/17, not all wells were present, this was discussed with FDEP, and the team determined new wells need to be installed. This TACO is to add in Subtask 5 to reinstall two MAGS wells inside the restaurant and perform MAGS testing.

Initial payment of Subtask 2 (invoiced 9/18/23) included 1 air sample and 1 summa canister, and only 1 additional of each are requested in this TACO.

The TA currently includes Subtask 1,3,4 Annual Groundwater Monitoring Report due 12/15/2023 - groundwater last sampled 10/26/22, CDM sampling in late October, no change to this deliverable.

CDM is currently scheduling the work Subtask 5 MAGS reinstall & sampling for November and December 2023.

Subtask 5 MAGS Install & Sample, the requested due date is 2/14/2024.

The end of the TA is 1/15/2024, please extend to 4/17/2024 to accommodate the schedule and allow review and final billing.

Very Respectfully, Kathy R. Leggoe, PG, PMP Geologist Project Manager CDM Smith 4651 Salisbury Road, Suite 420 Jacksonville, Florida 32256 (office) 904.527.6727, (cell) 904.651.0740 cdmsmith.com

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor�st �s Project Manager: ontractor�s t�s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW681

DC020B Completion January 15, 2024

CDM Smith Inc. will conduct Annual Groundwater Monitoring in accordance with the approved June 1st, 2023 Scope of Work and Cost Proposal.

Kyle McMurray 850-245-8973 Contractor CDM Smith Inc. Contractor

Contractor Shayne Wood Contractor 904-527-6703

ERIC_4897

8420 Lockwood Ridge Road, Sarasota, Manatee County, Florida

Touch of Class Cleaners - Sarasota

Contractor Contractor

$ 18,086.60

$ 18,086.60

Scope of Work

CDM Smith Inc.

Contractor

Shayne Wood

Project Manager

6/23/2023

Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2023.06.23 08:19:19-04'00'

Kelly Crain

Kelly Crain Digitally signed by Kelly Crain Date: 2023.06.22 08:56:10 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Field notes, air sample data and updated table 08/15/2023

Annual Groundwater Monitoring Report including tabulated data, conclusions, and recommendations 12/15/2023

Field notes, air sample data and updated table - Subtask 2 $ 2,928.01

Annual Groundwater Monitoring Report including tabulated data, conclusions, and recommendations + Project Management - Subtask 1, 3, and 4. $ 15,158.59

$ 18,086.60