This document consists of two Task Assignment Change Orders (TACO #3 and TACO #4) issued by the State of Florida Department of Environmental Protection (FDEP) to CDM Smith Inc. under Contract HW681 for environmental remediation work at the Jasper Laundry & Cleaners site (Project ERIC_4671). The primary parties involved are the FDEP, represented by Contract Managers Mubeen Darji and Aaron Cohen, and CDM Smith Inc., represented by Project Managers Leslie Samel and Shayne Wood. The contract file pertains to environmental investigation and remediation activities in Florida.
TACO #3, executed on November 27, 2023, authorizes a time extension of 120 days, extending the completion date from November 30, 2023 to March 29, 2024, with no additional cost ($0.00). This change order allows time for FDEP to review the Supplemental Soil Assessment Report (SSAR) while CDM Smith prepares the Interim Source Removal Plan (ISRP). TACO #4, executed on March 12, 2024, grants a further no-cost time extension of 216 days, extending the completion date from March 29, 2024 to October 31, 2024. The total contract value for Task Assignment DC006B is $157,367.97 with 540 labor hours. Deliverables include the SSAR (due 08/30/2023), Groundwater Sampling Updated Tables and Laboratory Report (due 08/30/2023), and Revised ISRP (due 07/31/2024), with invoicing contingent upon FDEP review and approval of each subtask deliverable.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
DC006B 4 HW681
Mubeen Darji 850-245-8965 CDM Smith Inc.
Leslie Samel 904-527-6727
ERIC_4671
Jasper Laundry & Cleaners
$ 157,367.97 $ 157,367.97
$ 157,367.97 $ 157,367.97
03/29/2024 10/31/2024 216
1 1 3
CDM Smith Inc.
Leslie Samel
Contract Manager
Teresa Booeshaghi
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2024.03.12 13:03:35 -04'00'
3/12/2024
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
TO: HW681 Contract File
FROM: Mubeen Darji, P.E., Contract Manager
DATE: October 12, 2023
SUBJECT: Negotiation Summary Task Assignment DC006B
TACO #4
This Task Assignment Change Order authorizes a no cost time extension to the CDM Smith Inc.
scope of work. The TA completion date has been extended by 216 days. The new TA completion date is now October 31, 2024.
CDM Smith Inc. requested a 6-month extension to the TA for FDEP to complete review of the SSAR while CDM Smith is preparing the ISRP.
The FDEP project manager agrees to the scope of work and final cost associated with this Task Assignment Change Order. The final cost total for Task Assignment DC006B is $157,367.97 with 540 labor hours.
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department�s Project Manager: Department�s Project Manager Phone:
Contractor Name: (Contractor ) ntractor�st �s Project Manager: ontractor�s t�s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
DC006B 3 HW681
This Task Assignment Change Order is for a time extension to complete the Interim Source Removal Plan (ISRP) pending DEP comments on the Supplemental Soil Assessment Report (SSAR) that are needed to inform the ISRP.
Aaron Cohen 850-245-8974 Contractor CDM Smith Inc. Contractor
Contractor Shayne Wood Contractor 904-527-6703
ERIC_4671
Jasper Laundry & Cleaners
$ 0.00 $ 0.00
$ 0.00 $ 0.00
Completion Completion 11/30/2023 03/29/2024 120
1 1 2
CDM Smith Inc.
Contractor
Shayne Wood
Vice President
11/27/2023
Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, O=CDM Smith, OU=NAU, CN=Shayne Wood Date: 2023.11.27 17:21:32-05'00'
Teresa Booeshaghi
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.11.27 15:15:30 -05'00'
11/27/2023
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW681
DC006B
$ 157,367.97
Supplemental Soil Assessment Report (SSAR)
Groundwater Sampling - Updated Tables, Field Notes, and Laboratory Analytical Report
Revised ISRP
Subtasks 1 and 2: FDEP Review and approval of Supplemental Soil Assessment Report, and Project Management
Subtask 4: FDEP Review and approval of Revised ISRP
Subtask 3: FDEP Review and approval of Groundwater Sampling - Updated Tables, Field Notes, and Laboratory Analytical Report
08/30/2023
08/30/2023
01/31/2024
$ 35,293.91
$ 104,658.16
$ 17,415.90