This document is a Task Assignment (TA) under Contract Number HW681 between the State of Florida Department of Environmental Protection (FDEP) and CDM Smith Inc., a contractor based in Jacksonville, Florida. The task assignment pertains to Operation & Maintenance (O&M) and Annual Groundwater Monitoring services at Merlin's Custom Cleaners, located at 26936 US Highway 19 North in Clearwater, Pinellas County, Florida (ERIC_5345). The agreement is effective from June 7, 2023, with a completion date of October 15, 2024. Kyle McMurray serves as the FDEP Project Manager, while Shayne Wood represents CDM Smith Inc. as the contractor's project manager.
The scope of work encompasses nine subtasks: Project Management (13% of direct labor); Semi-Annual Groundwater Monitoring (sampling, analysis, and reporting); SVE System Operation & Maintenance and Optimization for two periods; Annual Groundwater Monitoring; and Utilities provision at $700 per month. The total task assignment value is $62,437.64, comprised of a fixed unit rate of $54,037.64 and cost reimbursement of $8,400.00 for utilities. Payment is structured through nine invoicing milestones corresponding to specific deliverables, including groundwater monitoring laboratory reports due August 31, 2023, Semi-Annual Remedial Action Status Reports due March 15, 2024, Annual Groundwater Monitoring reports due March 31, 2024, and Annual Remedial Action Status Reports due September 15, 2024. Investigation-derived waste disposal is subcontracted to Erwin Remediation at $125 per drum, selected as the lowest-cost bidder among three competing firms. The detailed cost estimate reflects labor costs of $36,716.03, with overhead at 135%, fringe benefits at 37.7%, travel costs of $1,800.00, laboratory services totaling $3,970.00, field equipment expenses of $7,090.00, and a completion fee of $3,671.61.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW681
DC013B Completion October 15, 2024
CDM Smith Inc. will conduct Operation & Maintenance and Annual Groundwater Monitoring in accordance with the approved May 18th, 2023 Scope of Work and Cost Proposal.
Kyle McMurray 850-245-8973 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
CDM Smith Inc.
CDM Smith Inc.
Shayne Wood 904-527-6703
ERIC_5345
26936 US Highway 19 North, Clearwater, Pinellas County, Florida
Merlin's Custom Cleaners
✔ $ 54,037.64 ✔ $ 8,400.00
$ 62,437.64
Scope of Work
Shayne Wood
Vice President
6/7/2023
Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2023.06.07 16:43:26-04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2023.06.07 14:29:34 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Semi-Annual Groundwater Monitoring - Laboratory Reports, Field notes.
08/31/2023
Semi-Annual Remedial Action Status Report, including Groundwater Monitoring.
03/15/2024
Annual Groundwater Monitoring - Laboratory Reports, Field notes 03/31/2024
Annual Remedial Action Status Report, including Groundwater Monitoring.
09/15/2024
Utilities - Paid Utility Invoices for 6 months.
02/12/2024
Utilities - Paid Utility Invoices for 6 months.
08/30/2024
Subtask 2: Semi-Annual Groundwater Monitoring - Laboratory Reports, Field notes.
$ 3,838.01
Subtasks 3 and 4: SVE System O&M and Optimization – Quarters 9 and 10 (August 2023-January 2024) - Semi-Annual Remedial Action Status Report, including Groundwater Monitoring.
$ 18,584.73
Subtask 5: Annual Groundwater Monitoring - Laboratory Reports, Field notes $ 6,110.71
Subtasks 1, 6, and 7: SVE System O&M and Optimization + Project Management – Quarters 11 and 12(February 2024–July 2024) - Annual Remedial Action Status Report, including Groundwater Monitoring.
$ 25,264.19
Subtask 8: Utilities - Paid Utility Invoices for 6 months. Not to exceed $4,200.00;
Utilities Handling Fee = $120.00 $ 4,320.00
Subtask 9: Utilities - Paid Utility Invoices for 6 months. Not to exceed $4,200.00;
Utilities Handling Fee = $120.00 $ 4,320.00
$ 62,437.64
HW681
DC013B
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
TO:
FROM:
DATE:
SUBJECT:
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
HW681 Contract File
Kyle McMurray, Contract Manager
May 30, 2023
Negotiation Summary Task Assignment DC013B Merlin’s Custom Cleaners
ERIC_5345
Operation & Maintenance and Annual Groundwater Monitoring
CDM Smith Inc. (CDM) will conduct Operation & Maintenance and Annual Groundwater Monitoring. Specific subtasks are detailed below:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2: Semi-Annual Groundwater Sampling The semi-annual groundwater monitoring requirements for the site were identified in the 2018 ISRP. CDM Smith will complete the semi-annual groundwater sampling event in August 2023.
CDM Smith will collect water levels from all sampled monitoring wells during the sampling event.
Purging and sampling will be in accordance with FDEP’s Standard Operating Procedures for Groundwater Sampling, FS 2200, and will be collected using low-flow techniques with a peristaltic pump and dedicated polyethylene tubing. A YSI-556 multi-parameter probe and a turbidimeter will be used to collect well purge parameters including dissolved oxygen, pH, conductivity, oxidation reduction potential, temperature, turbidity.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Erwin Remediation for IDW disposal was chosen on a lowest-cost basis.
Subtask 3 and 4: SVE System Operation & Maintenance, Optimization O&M site visits will be completed monthly. SVE system influent samples will be collected quarterly for laboratory analyses by Method TO-15. Following the completion of Subtask 3 and 4 O&M activities, CDM Smith will prepare a Semi-annual RASR. The report will summarize the history of the Site, all field work completed by CDM Smith, field and laboratory data, conclusions, and recommendations.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Erwin Remediation for IDW disposal was chosen on a lowest-cost basis.
Subtask 5: Annual Groundwater Monitoring The annual groundwater monitoring requirements for the site were identified in the 2018 ISRP.
CDM Smith will complete the annual groundwater sampling event in February 2024. CDM Smith will collect water levels from all sampled monitoring wells during the sampling event. Purging and sampling will be in accordance with FDEP’s Standard Operating Procedures for Groundwater
Sampling, FS 2200, and will be collected using low-flow techniques with a peristaltic pump and dedicated polyethylene tubing. A YSI-556 multi-parameter probe and a turbidimeter will be used to collect well purge parameters including dissolved oxygen, pH, conductivity, oxidation reduction potential, temperature, turbidity.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Erwin Remediation for IDW disposal was chosen on a lowest-cost basis.
Subtask 6 and 7: SVE System Operation & Maintenance, Optimization O&M site visits will be completed monthly. SVE system influent samples will be collected quarterly for laboratory analyses by Method TO-15. Following the completion of Subtask 6 and 7 O&M activities, CDM Smith will prepare an Annual RASR. The report will summarize the history of the Site, all field work completed by CDM Smith, field and laboratory data, conclusions, and recommendations.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Erwin Remediation for IDW disposal was chosen on a lowest-cost basis.
Subtask 8 and 9: Utilities CDM Smith will provide utilities for the SVE system and assume $700 per month. Administrative costs are covered under Handling Fees.
CDM and the FDEP confirmed on May 30th, 2023, that an Access Agreement with the current real property owner of the site has been executed.
The final cost total for Task Assignment DC013B is $62,437.64
FDEP COST ESTI MATEContractor: CDM Smith, Inc.
Date: 6/6/2023
Task #: SubTask 1 Project Management SubTask 6 SVE System O&M and Optimization
Site: SubTask 2 Semi-Annual Groundwater Monitoring SubTask 7 SVE System O&M and Optimization
Activity/Phase: O&M SubTask 3 SVE System O&M and Optimization SubTask 8 Utilities
Project Manager: Kara Fincham SubTask 4 SVE System O&M and Optimization SubTask 9 Utilities
SubTask 5 Annual Groundwater Monitoring SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$63.58 Project Manager 24.4 24.4 $0.00 Senior Officer 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0
$71.37 Senior Technical Expert SC 22.0 4.0 3.0 5.0 2.0 3.0 5.0 0.0 0 0 $63.58 Project Technical Leader KF 8.0 0.0 0.0 4.0 0.0 0.0 4.0 0.0 0 0
$0.00 Senior Professional 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $43.05 Professional II KT 121.0 11.0 8.0 36.0 14.0 8.0 44.0 0.0 0 0 $28.17 Professional I JL 156.0 0.0 32.0 39.0 14.0 32.0 39.0 0.0 0 0
$0.00 Professional I 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $23.26 Professional I LW 10.0 6.0 0.0 0.0 4.0 0.0 0.0 0.0 0 0
$0.00 Professional II 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 Senior Support Services 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 Staff Support Services 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0
$0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0
Total Hours 341.4 24.4 21.0 43.0 84.0 34.0 43.0 92.0 0.0 0 0
Direct Labor $13,463.89 $1,548.94 $898.59 $1,459.95 $3,259.60 $1,232.86 $1,459.95 $3,604.00 $0.00 $0.00 $0.00
Overhead 135.00% $18,176.25 $2,091.07 $1,213.10 $1,970.93 $4,400.46 $1,664.36 $1,970.93 $4,865.40 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $5,075.89 $583.95 $338.77 $550.40 $1,228.87 $464.79 $550.40 $1,358.71 $0.00 $0.00 $0.00 Total Labor $36,716.03 $4,223.96 $2,450.46 $3,981.28 $8,888.93 $3,362.01 $3,981.28 $9,828.11 $0.00 $0.00 $0.00
Merlins Custom Cleaners
REV: 02/03 CEF CDM Smith Page 1
FDEP COST ESTI MATEContractor: CDM Smith, Inc.
Date: 6/6/2023
Task #: SubTask 1 Project Management SubTask 6 SVE System O&M and Optimization
Site: SubTask 2 Semi-Annual Groundwater Monitoring SubTask 7 SVE System O&M and Optimization
Activity/Phase: O&M SubTask 3 SVE System O&M and Optimization SubTask 8 Utilities
Project Manager: Kara Fincham SubTask 4 SVE System O&M and Optimization SubTask 9 Utilities
SubTask 5 Annual Groundwater Monitoring SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10
Merlins Custom Cleaners
Travel Vehicle Rental $1,800.00 $120.00 $360.00 $360.00 $240.00 $360.00 $360.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,800.00 $120.00 $360.00 $360.00 $240.00 $360.00 $360.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $500.00 $125.00 $125.00 $0.00 $125.00 $125.00 $0.00 $0.00 $0.00 $0.00
Utilities $8,400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $4,200.00 $4,200.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $8,900.00 $125.00 $125.00 $0.00 $125.00 $125.00 $0.00 $4,200.00 $4,200.00 $0.00 Handling Fee $290.00 $12.50 $12.50 $0.00 $12.50 $12.50 $0.00 $120.00 $120.00 $0.00 Total Subcontractor Cost $9,190.00 $137.50 $137.50 $0.00 $137.50 $137.50 $0.00 $4,320.00 $4,320.00 $0.00
Laboratory Analytical Costs $3,041.00 $292.00 $200.00 $200.00 $949.00 $200.00 $1,200.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $929.00 $163.00 $110.00 $110.00 $326.00 $110.00 $110.00 $0.00 $0.00 $0.00 Total Laboratory $3,970.00 $455.00 $310.00 $310.00 $1,275.00 $310.00 $1,310.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $600.00 $40.00 $120.00 $120.00 $80.00 $120.00 $120.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $870.00 $290.00 $0.00 $0.00 $580.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $400.00 $100.00 $100.00 $0.00 $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $5,220.00 $0.00 $1,305.00 $1,305.00 $0.00 $1,305.00 $1,305.00 $0.00 $0.00 $0.00 Total Field Expenses $7,090.00 $430.00 $1,525.00 $1,425.00 $760.00 $1,525.00 $1,425.00 $0.00 $0.00 $0.00
Subtotal $58,766.03 $4,223.96 $3,592.96 $6,313.78 $10,983.93 $5,774.51 $6,313.78 $12,923.11 $4,320.00 $4,320.00 $0.00 Completion Fee $3,671.61 $422.40 $245.05 $398.13 $888.89 $336.20 $398.13 $982.81 $0.00 $0.00 $0.00
Total Estimated Cost $62,437.64 $4,646.36 $3,838.01 $6,711.91 $11,872.82 $6,110.71 $6,711.91 $13,905.92 $4,320.00 $4,320.00 $0.00
REV: 02/03 CEF CDM Smith Page 2
SITE :
SUBTASK: 2 Semi-Annual Groundwater Monitoring
DATE: 6/6/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Technical Expert S. Cobert Technical Evaluation of Data 4
Professional II K. Turner Travel (1 trip) 2
Semi-Annual Groundwater Sampling - 4 wells 6
Field Preparation (Semi-Annual Sampling) 1
Sample Kit Coordination 1
IDW Management 1
Professional I L. Weber Data Package, Updated Data Tables (Semi-Annual Sampling) 6
Total Hours:
S. Cobert 4
K. Turner 11
L. Weber 6
TOTAL LABOR 21
VEHICLE TYPE RATE UNIT USEAGE
Truck $120 each 1 $120.00
TOTAL VEHICLE $120.00
SUBCONTRACTOR COSTS
NAME PURPOSE UNIT COST
Erwin Remediation IDW Removal 1 $125 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOH 8021/8260 $73.00 4 $292.00
Shipping (Large Cooler) $150.00 1 $150.00
Ice $6.50 2 $13.00
TOTAL LAB $455.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Shallow Groundwater Sampling Kit $290 Day 1 $290.00
Expendables $40.00 day 1 $40.00
Drums $100.00 each 1 $100.00
TOTAL EQUIPMENT $430.00
SITE : Merlins Custom Cleaners SUBTASK: 3 SVE System O&M and Optimization
DATE: 6/6/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Technical Expert S. Cobert System Operation Deliverable 3
Professional I J. LeBlanc Travel to/from site (3 trips) 6
3 O&M Trips 24
Sample Kit Coordination (Air Sample) 1
IDW Management 1
Professional II K. Turner O&M Quarterly Report, updated Data Tables 8
Total Hours:
S. Cobert 3
J. LeBlanc 32
K. Turner 8
TOTAL LABOR 43
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 day 3 $360.00
TOTAL VEHICLE $360.00
SUBCONTRACTOR COSTS
NAME PURPOSE Unit COST
Erwin Remediation IDW Removal 1 $125 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TO-15 $200.00 1 $200.00
Small Cooler $110.00 1 $110.00
TOTAL LAB $310.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Construction/O&M/Pilot kit $360.00 day 3 $1,080.00
Construction/O&M Supplies $75.00 day 3 $225.00
Expendables $40.00 day 3 $120.00
Drums $100.00 each 1 $100.00
TOTAL EQUIPMEN $1,525.00
SITE : Touch of Class Apollo SUBTASK: 4 SVE System O&M and Optimization
DATE: 6/6/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Technical Expert S. Cobert System Operations Deliverable 3
Author Engineering section of RASR/GWMR 2
Project Manager K. Fincham Prepare/Submit RASR/GWMR 4
Professional I J. LeBlanc Travel to/from site (3 trips) 6
3 O&M Trips 24
Sample Kit Coordination (air sample) 1
Assisting with RASR Report 8
Professional II K. Turner Remedial Action Status Report (including GWM), Semi-Annual 32
Figures for RASR 4
Total Hours:
S. Cobert 5
J. LeBlanc 39
K. Fincham 4
K. Turner 36
TOTAL LABOR 84
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 day 3 $360.00
TOTAL VEHICLE $360.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TO-15 $200.00 1 $200.00
Small Cooler $110.00 1 $110.00
TOTAL LAB $310.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Construction/O&M/Pilot kit $360.00 day 3 $1,080.00
Construction/O&M Supplies $75.00 day 3 $225.00
Expendables $40.00 day 3 $120.00
TOTAL EQUIPMEN $1,425.00
SITE :
SUBTASK: 5 Annual Groundwater Monitoring
DATE: 6/6/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Technical Expert S. Cobert Technical Evaluation of Data 2
Professional II K. Turner Travel (1 trip) 2
Annual Groundwater Sampling - 13 wells 10
Field Preparation (Annual Sampling) 1
Sample Kit Preparation 1
Professional I J. LeBlanc Travel (1 trip) 2
Annual Groundwater Sampling - 13 wells 10
IDW Management 2
Professional I L. Weber Data Package, Updated Data Tables Annual Sampling) 4
Total Hours:
S. Cobert 2
K. Turner 14
J. LeBlanc 14
L. Weber 4
TOTAL LABOR 34
VEHICLE TYPE RATE UNIT USEAGE
Truck $120 each 2 $240.00
TOTAL VEHICLE $240.00
SUBCONTRACTOR COSTS
NAME PURPOSE UNIT COST
Erwin Remediation IDW Removal 1 $125 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOH 8021/8260 $73.00 13 $949.00
Shipping (Large Cooler) $150.00 2 $300.00
Ice $6.50 4 $26.00
TOTAL LAB $1,275.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Shallow Groundwater Sampling Kit $290 Day 2 $580.00
Expendables $40.00 day 2 $80.00
Drums $100.00 each 1 $100.00
TOTAL EQUIPMENT $760.00
SUBTASK: 6 SVE System O&M and Optimization
DATE: 6/6/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Technical ExpS. Cobert System Operation Deliverable 3
Professional I J. LeBlanc Travel to/from site (3 trips) 6
3 O&M Trips 24
Sample Kit Coordination (air sample) 1
IDW Management 1
Professional II K. Turner O&M Quarterly Report, Updated data tables 8
Total Hours:
S. Cobert 3
J. LeBlanc 32
K. Turner 8
TOTAL LABOR 43
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 day 3 $360.00
TOTAL VEHICLE $360.00
SUBCONTRACTOR COSTS
NAME PURPOSE Unit COST
Erwin Remediation IDW Removal 1 $125 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TO-15 $200.00 1 $200.00
Small Cooler $110.00 1 $110.00
TOTAL LAB $310.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Construction/O&M/Pilot kit $360.00 day 3 $1,080.00
Construction/O&M Supplies $75.00 day 3 $225.00
Expendables $40.00 day 3 $120.00
Drums $100.00 each 1 $100.00
TOTAL EQUIPMEN $1,525.00
SITE : Touch of Class Apollo SUBTASK: 7 SVE System O&M and Optimization
DATE: 6/6/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Technical ExpS. Cobert System Operations Deliverable 3
Author Engineering section of RASR/GWMR 2
Project Manager K. Fincham Prepare/Submit RASR/GWMR 4
Professional I J. LeBlanc Travel to/from site (3 trips) 6
3 O&M Trips 24
Sample Kit Coordination 1
Assisting with RASR 8
Professional II K. Turner Remedial Action Status Report (including GWM), Annual 40
Figures for RASR 4
Total Hours:
S. Cobert 5
J. LeBlanc 39
K. Fincham 4
K. Turner 44
TOTAL LABOR 92
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 day 3 $360.00
TOTAL VEHICLE $360.00
SUBCONTRACTOR COSTS
NAME PURPOSE Unit COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TO-15 $200.00 6 $1,200.00
Small Cooler $110.00 1 $110.00
TOTAL LAB $1,310.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Construction/O&M/Pilot kit $360.00 day 3 $1,080.00
Construction/O&M Supplies $75.00 day 3 $225.00
Expendables $40.00 day 3 $120.00
TOTAL EQUIPMEN $1,425.00
SUBTASK: 8 Utilities
DATE: 6/6/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS
O&M Quarter 9 Utilities Utility Charges (Electric) $700.00 month 3 $2,100.00
Quarter 9 Handling Fee Utility Handling Fee $20.00 Month 3 $60.00
O&M Quarter 10 Utiliites Utility Charges (Electric) $700.00 month 3 $2,100.00
Quarter 10 Handling Fee Utility Handling Fee $20.00 Month 3 $60.00
TOTAL EQUIPMEN $4,320.00
SUBTASK: 9 Utilities
DATE: 6/6/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS
O&M Quarter 11 Utilities Utility Charges (Electric) $700.00 month 3 $2,100.00
Quarter 11 Handling Fee Utility Handling Fee $20.00 Month 3 $60.00
O&M Quarter 12 Utiliites Utility Charges (Electric) $700.00 month 3 $2,100.00
Quarter 12 Handling Fee Utility Handling Fee $20.00 month 3 $60.00
TOTAL EQUIPMEN $4,320.00
4651 Salisbury Road, Suite 420
Jacksonville, Florida 32256 tel: 904.731.7109
May 18, 2022
Mr. Kyle McMurray Florida Department of Environmental Protection Hazardous Waste Cleanup Section 2600 North Blair Stone Road, MS 4520 Tallahassee, Florida 32399-2400
Subject: Operation and Maintenance and Groundwater Monitoring Proposal Merlin’s Custom Cleaners
ERIC_5345
26936 US Highway 19 North Clearwater, Pinellas County, Florida
Dear Mr. McMurray:
CDM Smith Inc. (CDM Smith) is pleased to respond to the Florida Department of Environmental Protection (FDEP) Task Assignment Request to provide O&M and groundwater monitoring services for the Merlin Custom Cleaners site under Contract Number HW681. Our project understanding, scope of work, and project schedule are described below, and the cost estimate is also attached.
Project Understanding This former dry-cleaning facility has been redeveloped into a Lowes Home Center. O&M services are required for a soil vapor extraction (SVE) system that consists of 11 SVE wells, SVE blower, air injection blower, moisture separator, and a granulated activated carbon (GAC) vapor treatment drum. All SVE wells are in outdoor locations.
The SVE system began operating in February 2020. The 2018 Interim Source Removal Plan (ISRP) provided a SVE system sampling schedule for 1 year of operation. SVE system influent air samples are sampled on a quarterly basis and submitted for laboratory analysis by United States Environmental Protection Agency (EPA) Method TO-15 for volatile organic halocarbons. Air samples are collected from five of the operating SVE wells on an annual basis and submitted for laboratory analysis by EPA Method TO-15. Operation and Maintenance (O&M) site visits are being completed monthly, and O&M reports are submitted quarterly.
Groundwater monitoring is being completed annually at 13 monitoring wells and 4 wells semiannually for volatile organic halocarbons (VOHs). Semiannual and Annual Remedial Action Status Reports (RASR) are submitted. The semiannual groundwater sampling event would take place in August 2023, and the annual sampling event would be performed in February 2024.
Mr. McMurray May 18, 2023
Scope of Work This cost proposal covers SVE system O&M and groundwater monitoring for one year, beginning in August 2023 and ending in July 2024.
Subtask 1 – Project Management Project management activities performed under this task consist of administrative functions required to maintain the project schedule, adhere to budget, and deliver the quality of the work products defined by CDM Smith's quality standards. We will prepare and submit invoices upon approval of each deliverable or milestone completion.
Project Kickoff and Progress Meetings CDM Smith expects to have a kickoff meeting or telephone conference with the FDEP to review the status of the project and address FDEP comments regarding the Task Assignment. CDM Smith will prepare meeting agendas and notes as part of this task.
Project Quality Technical Review CDM Smith's Quality Management System guidelines will be followed. Internal quality reviews will be conducted on plans and on investigation findings and reports.
Project Status Reports CDM Smith's Project Manager will prepare and submit monthly status reports to accompany each invoice throughout the duration of this project. The Project Manager will also discuss the status of the project with the FDEP on a bi-weekly basis until the project is complete.
Subtask 2 – Semi-Annual Groundwater Monitoring The semi-annual groundwater monitoring requirements for the site were identified in the 2018 ISRP. CDM Smith will complete the semi-annual groundwater sampling event in August 2023. The required laboratory analyses and the wells included in the monitoring program are listed in the attached Table 1.
CDM Smith will collect water levels from all sampled monitoring wells during the sampling event.
Purging and sampling will be in accordance with FDEP’s Standard Operating Procedures for Groundwater Sampling, FS 2200, and will be collected using low-flow techniques with a peristaltic pump and dedicated polyethylene tubing. A YSI-556 multi-parameter probe and a turbidimeter will be used to collect well purge parameters including dissolved oxygen, pH, conductivity, oxidation reduction potential, temperature, turbidity. The instrumentation will be properly calibrated and recorded. All purge water will be contained in drums for characterization and disposal as nonhazardous investigation-derived waste (IDW). CDM Smith assumes that one IDW drum will require disposal under this task assignment.
Deliverables: Laboratory Reports, field notes, and updated tables for the groundwater sampling event
Subtask 3 and 4 – SVE System Operation and Maintenance, Optimization O&M site visits will be completed monthly, and the following work will be completed during each visit.
System operation and alarm status and blower run time.
Moisture separator liquid volume.
System vacuums and velocity/flow rate at blower, before/after GAC, and after moisture separator.
Blower oil changes, based on manufacturer recommendations.
SVE well vacuum/pressure and flow rate.
Total organic vapors measured with a photoionization detector from operating SVE wells, system influent, and system effluent.
Water levels from MW002, MW008, and MW009.
Adjust vacuums and injection pressures on the SVE wells to optimize the SVE system performance.
The information will be consistently recorded in the field on pre-prepared forms.
SVE system influent samples will be collected quarterly for laboratory analyses by Method TO-15.
The required laboratory analyses and the SVE included in the monitoring program are listed in the attached Table 1.
Following the completion of Subtask 3 and 4 O&M activities, CDM Smith will prepare a Semi-annual RASR, and an Annual RASR will be prepared following the Subtask 5 and 6 activities. The report will summarize the history of the Site, all field work completed by CDM Smith, field and laboratory data, conclusions, and recommendations. Additional elements of the report will include the following:
Figures depicting site conditions.
Figures depicting groundwater data and estimated extent of impact.
Groundwater elevation contour map.
Tables summarizing field and analytical data.
Groundwater sampling logs and field equipment calibration records.
Laboratory analytical reports and chain of custody documentation.
Waste disposal manifests and weigh tickets.
CDM Smith assumes up to one drum of liquid IDW will be collected by the moisture separator requiring disposal over six months of system operation. Disposal services will be provided by Erwin
Remediation, using rates previously approved for use on the Waste Cleanup Program Contract
HW681.
Deliverables: Semi-Annual Remedial Action Status Report
Subtask 5 – Annual Groundwater Monitoring The annual groundwater monitoring requirements for the site were identified in the 2018 ISRP.
CDM Smith will complete the annual groundwater sampling event in February 2024. The required laboratory analyses and the wells included in the monitoring program are listed in the attached Table 1.
CDM Smith will collect water levels from all sampled monitoring wells during the sampling event.
Purging and sampling will be in accordance with FDEP’s Standard Operating Procedures for Groundwater Sampling, FS 2200, and will be collected using low-flow techniques with a peristaltic pump and dedicated polyethylene tubing. A YSI-556 multi-parameter probe and a turbidimeter will be used to collect well purge parameters including dissolved oxygen, pH, conductivity, oxidation reduction potential, temperature, turbidity. The instrumentation will be properly calibrated and recorded. All purge water will be contained in drums for characterization and disposal as nonhazardous investigation-derived waste (IDW). CDM Smith assumes that one IDW drum will require disposal under this task assignment.
Deliverables: Laboratory Reports, field notes, and updated tables for the groundwater sampling event
Subtask 6 and 7 – SVE System Operation and Maintenance, Optimization O&M site visits will be completed monthly, and the following work will be completed during each visit.
System operation and alarm status and blower run time.
Moisture separator liquid volume.
System vacuums and velocity/flow rate at blower, before/after GAC, and after moisture separator.
Blower oil changes, based on manufacturer recommendations.
SVE well vacuum/pressure and flow rate.
Total organic vapors measured with a photoionization detector from operating SVE wells, system influent, and system effluent.
Water levels from MW002, MW008, and MW009.
Adjust vacuums and injection pressures on the SVE wells to optimize the SVE system performance.
The information will be consistently recorded in the field on pre-prepared forms.
SVE system influent samples will be collected quarterly for laboratory analyses by Method TO-15.
In addition, air samples will be collected from five operating SVE wells and submitted for laboratory analysis by EPA Method TO-15. The required laboratory analyses and the SVE included in the monitoring program are listed in the attached Table 1.
Following the completion of Subtask 6 and 7 O&M activities, CDM Smith will prepare an Annual RASR. The report will summarize the history of the Site, all field work completed by CDM Smith, field and laboratory data, conclusions, and recommendations. Additional elements of the report will include the following:
Figures depicting site conditions.
Figures depicting groundwater data and estimated extent of impact.
Groundwater elevation contour map.
Tables summarizing field and analytical data.
Groundwater sampling logs and field equipment calibration records.
Laboratory analytical reports and chain of custody documentation.
Waste disposal manifests and weigh tickets.
CDM Smith assumes up to one drum of liquid IDW will be collected by the moisture separator requiring disposal over six months of system operation. Disposal services will be provided by Erwin Remediation, using rates previously approved for use on the Waste Cleanup Program Contract
HW681.
Deliverables: Annual Remedial Action Status Report
Subtasks 8 and 9 – Utilities CDM Smith will provide utilities for the SVE system and assume $700 per month including administrative costs.
Deliverable: Utilities Handling Fee, receipt of 12 months of invoices (Cost Plus Fixed Fee)
Subcontractors Subcontracted services are required for IDW disposal. Rates for IDW removal and disposal were previously requested for HW681 from Erwin Remediation, Enviroserve (formerly Clark
Environmental), and Hepaco. Erwin Remediation was the lowest cost and has been selected as the IDW disposal subcontractor for this project as shown in Attachment A.
Schedule Subtask 2: Semi-Annual Groundwater Monitoring
Deliverable: Laboratory Reports, Field notes
Due Date: August 31, 2023
Subtasks 3 and 4: SVE System O&M and Optimization – Quarters 9 and 10 (August 2023-January 2024)
Deliverable: Semi-Annual Remedial Action Status Report, including Groundwater Monitoring
Due Date: March 15, 2024
Subtask 5: Annual Groundwater Monitoring
Deliverable: Laboratory Reports, Field notes
Due Date: March 31, 2023
Subtasks 6 and 7: SVE System O&M and Optimization – Quarters 11 and 12 (February 2024–July 2024)
Deliverable: Annual Remedial Action Status Report, including Groundwater Monitoring
Due Date: September 15, 2024
Subtask 8 and 9: Utilities
Deliverable: Paid Utility Invoices
Due Date: Semi-Annually
We look forward to working on this important project. Feel free to contact me at 904-527-6716 or by email with any questions or comments.
Sincerely, Kara E. Fincham, PMP Shayne Wood, P.E., PMP, BCEE Senior Project Manager Vice President CDM Smith CDM Smith FinchamKE@cdmsmith.com WoodSH@CDMSmith.com cc: Steve Cobert, P.E., CDM Smith
Table
Sample ID Monthly Quarterly Semiannual Annual SVE Influent V,F,P 4,V,F,P
VE-001 V,F,P V,F,P
VE-002 V,F,P V,F,P
VE-003 V,F,P V,F,P 4,V,F,P
VE-004 V,F,P V,F,P
VE-005 V,F,P V,F,P
VE-006 V,F,P V,F,P
VE-007 V,F,P V,F,P 4,V,F,P
VE-008 V,F,P V,F,P 4,V,F,P
VE-009 V,F,P V,F,P 4,V,F,P
VE-010 V,F,P V,F,P 4,V,F,P
VE-011 V,F,P V,F,P
MW001 L 1,7
MW002 L 1,7 1,7
MW003 1,7 1,7
MW005 L 1,7
MW006 L 1,7
MW007 1,7 1,7
MW008 L L 1,7
MW009 L L 1,7
MW010 L 1,7
MW011 L 1,7
MW012 1,7 1,7
MW013 1,L 1,7
MW014 L 1,7
1 = VOHs by Method 8260B
4 = VOHs by Method TO-15
V = Vacuum/Pressure
F = Flow Rate
P = PID
L = Depth to Water
Table 1: Sampling Schedule Merlin's Custom Cleaners
ERIC_5345
Clearwater, Pinellas County, Florida
Attachment A Subcontractor Quotes
Investigative Derived Waste (IDW) Management Job Details - Per 55-gallon Drum
Per Event Hepaco $142 $210 $146.22 $50.00 $388.67 $467.15 EnviroServe $80 $80 $50.00 $50.00 $198.00 $198.00 Erwin Remediation $125 $125 Included Included $125 $125
IDW Subcontractor Evaluation CDM Smith - HW681
Tuesday, May 23, 2023
Company Disposal Transportation Total
Liquid Soil Fee Liquid Soil
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Ms. Kara Fincham CDM Smith 4651 Salisbury road, Suite 420 Jacksonville, FL 32256
May 22, 2023
Re: Non-Hazardous Drum Disposal
Ms. Fincham:
The price for the transportation and disposal (T&D) of 55-gallon drums of non-hazardous soil, mud, and water is listed below:
Impacted with Non-Hazardous Dry-Cleaning Solvents:
Description Rate Unit
T&D - Non-Haz Mud/Water $ 125.00 Per Drum
T&D - Non-Haz Soil $ 125.00 Per Drum
All drum lids should be properly secured, and drums should be placed on level ground (i.e., not on a pallet, etc.). A single False Mobilization fee will apply if our driver is not able to locate a drum on site or if we are unable to access the property due to a locked gate, etc.
The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida Keys.
Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.
Respectfully, Robert Donado Erwin Remediation, Inc.
Email: robert@erwinremediation.com
Leggoe, Kathy R.
From: Leggoe, Kathy R.
Sent: Wednesday, March 1, 2023 4:07 PM
To: stephenharris@enviroserve.com
Subject: Drum Quote Request for CDM Smith
Greetings Steve, nice to be writing you from a new place of business. I have joined the CDM Smith team and working with the dry cleaning program. We are trying to get a current quote for 2023. Kara Fincham sent you the message below back in January. I thought I would try to send the same message to your new email. See below and respond with a quote if you would like us to use you.
We are renewing the rates for IDW for 2023—I will need a general cost proposal for the pickup and disposal of all investigation derived waste associated with our FDEP projects for one year. The rates should include non-hazardous waste, liquid and solid, generally in 55-gallon drums. The majority of the IDW will most likely be contained in 55-gallon drums and consist of soil and groundwater from environmental site investigations, but we are going to start doing more
PFAS work this year, so if there is a separate cost associated with PFAS IDW (soil/Groundwater), please include it in your proposal.
The sites are located throughout the state, including Pensacola, Jacksonville, North Florida, South Florida, Tampa, and
Orlando. The lowest bidder will win the work for the remainder of 2023.
If you are interested, please submit a proposal by Thursday, March 9, 2023.
If you are not interested in bidding, please reply to let us know.
Very Respectfully, Kathy R. Leggoe, PG, PMP
Geologist
Project Manager
CDM Smith
4651 Salisbury Road, Suite 420
Jacksonville, Florida 32256
(office) 904.527.6727, (cell) 904.651.0740 cdmsmith.com
03/02/2023
Kathy Leggoe
CDM Smith
PG, PMP, Geologist
4651 Salisbury Road
Jacksonville, FL, 32256 leggoekr@cdmsmith.com
904*651*0740
Subject: IDW Drums
Quote Number: QT-1093
Dear Kathy, Thank you for the opportunity to provide this proposal for the IDW drums located in the Florida Area.
HEPACO is a premier environmental contractor with coverage from 45 offices. We specialize in emergency response, industrial services, remediation, and waste services. HEPACO serves a multitude of customers including transportation companies, energy companies, environmental consultants, industrial facilities, terminals, environmental service companies, general contractors, property owners, and many other public and private-sector clients.
HEPACO, with its well-rounded and cross-trained staff, can effectively and efficiently complete this project and appreciates the opportunity. We stand firmly behind our work and always strive to deliver exceptional value and a high level of service at reasonable pricing.
Scope of Work
HEPACO will provide the following:
Pickup / Transportation and Disposal of Non-Hazardous IDW drums throughout the state of
Florida
Provide pricing per incident for disposal of Hazardous IDW Drums and PFAS waste.
Assumptions
HEPACO assumes the following:
Pricing for PFAS Drums and Hazardous IDW Drums will be priced according to location. PFAS drums can be transported to WM site in Alabama. Pricing is cost plus 30%.
All work will be completed in one mobilization unless otherwise noted
If groundwater is encountered, additional pricing for transportation, disposal, management, and/or containment will apply. This will be charged according to the HEPACO Time and Materials
Rate Sheet.
Prices do not include any required permitting unless otherwise noted
Prices do not include any surgical excavation around utilities, surface and/or subsurface structures
(it is assumed utilities are not present)
Client will provide any required sampling/analysis, technical reports, surveying, compaction testing and/or private utility locating services unless otherwise noted
All disposal prices are based on final profile approval and waste acceptance by the disposal facility
Client is responsible for any additional price associated with non-conforming waste as determined by the disposal facility
Field crew will be on-site working eight (8) hours per day M-F with no weekend or holiday work unless otherwise noted
Customer is responsible for disposal prices unless otherwise noted
Quantities are speculative. Except for minimums, all billing will be based on actual quantities.
Price
A pricing itemization is provided in Attachment A.
HEPACO Basic Conditions:
All projects require a two (2) week notice to proceed. HEPACO will make every effort possible to meet all our client’s requests; however, HEPACO cannot guarantee a project start date with less than two (2) weeks’ notice to proceed.
This proposal is contingent upon credit approval and valid for thirty days
For any additional work beyond the original scope of work, time and material rates will apply.
Except for minimums, billing will be based on actual quantities at unit prices (see Attachment A).
A four (4)-hour minimum will apply to all unit pricing quoted by the hour
Unit prices quoted by the day will be billed at the full day rate for any work on site. There will be no partial billing for partial workdays.
Unit prices quoted by the day apply up to eight hours per day. After eight hours per day, the day rate will be pro-rated for additional hours.
Unit prices are based on a non-union work force, no prevailing wages, no overtime work, and no performance bond.
Additional costs related to unexpected, concealed, or unknown conditions or any delays at the project site shall be incurred by customer.
HEPACO will not be held responsible if underground or above ground structures, cables, conduits, site features, property, materials, or equipment are destroyed, damaged, or rendered inoperable during the project.
Pricing includes HEPACO’s standard insurance coverage. Adding additional insured or increased coverages will be at additional pricing and will be quoted on a case-by-case basis.
Again, thank you for the opportunity and we look forward to completing this project.
Sincerely, Kevin Hamilton
Kevin Hamilton
HEPACO Territory Account Manager
Subject: IDW Drums
Quote Number: QT-1093
By signing below the customer acknowledges that they have received, reviewed, and agree to the HEPACO
Proposal
Owner or Owner Agent:
Signature:
Date of Acceptance:
Print Name
Owner or Owner Agent
ATTACHMENT A
PRICING ITEMIZATION TABLE
PRICING ITEMIZATION TABLE
PRICING SUMMARY TABLE
Item Type Total Price
MOBILIZATION
LABOR
MATERIALS
PPE
VEHICLES
BOATS
HEAVY EQUIPMENT
RECOVERY/TMT/STORAGE
MISC. EQUIPMENT
MONITORING/SAMPLING
LABORATORY/ANALYTICAL
COMMUNICATION
MISC.
SUBCONTRACTOR
DISPOSAL
DEMOBILIZATION
REPORT
FEES
Fee Calculated As Total Dollar Amount
Energy, Security and Recovery Fee Percentage of Total $82.15
Estimated Total Quote Price: $629.82
Item Name or Description Estimated Quantity Unit Price Units of Measure Total Line-Item Price
TRUCK DRIVER 1 $69.60 HOUR $69.60
FLATBED W/LIFT GATE 1 $76.32 HOUR $76.32
NON-HAZ SOLIDS DISPOSAL (PER
DRUM) 1 $210.00 DRUM $210.00
NON-HAZ LIQUIDS DISPOSAL (PER
DRUM) 1 $141.75 DRUM $141.75
LTL WASTE TRANSPORTATION PER
DRUM 1 $50.00 FEE $50.00