CN-370000-HW681-DC021C.pdf

PDF 4 MB Posted

Attached to
Master Agreement FL|HW681|acc15804f9112ed94de3c1f0669600ae
Contract number
HW681
Issued by
Florida

About this file

This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) under Contract Number HW681. The task assignment authorizes CDM Smith Inc. to conduct Operation and Maintenance (O&M) and Groundwater Monitoring services at the Star Cleaners Depot site located at 7181 Crane Avenue, Jacksonville, Duval County, Florida. The task assignment was executed on December 12, 2024, with a completion date of May 29, 2026, under Project Number ERIC_4613. The Department Project Manager is Benjamin Aoki (850-245-7527), and the Contractor's Project Manager is Kyle Turner (813-262-8851).

The total contract value for this task assignment is $65,894.89, consisting of a Fixed Unit Rate of $57,494.89 and Cost Reimbursement of $8,400.00. Services include eleven subtasks: Project Management (13% of direct labor), Annual Groundwater Monitoring at eight monitoring wells ($5,725.22), SVE System O&M and Optimization for Quarters 14 and 15 ($20,329.85), SVE System O&M and Optimization for Quarters 16 and 17 ($26,792.30), Utilities for four quarters at $2,160.00 per quarter ($8,640.00 total), and Blower Replacement ($4,407.52). Deliverables include field notes, laboratory reports, Semiannual and Annual Remedial Action Status Reports, paid utility invoices, and field documentation. The project encompasses the period from December 2024 through November 2025, with deliverables due on various dates concluding on February 27, 2026. Subcontractor services for IDW removal were obtained from Erwin Remediation at $125 per event. The project involves monitoring of soil vapor extraction (SVE) systems, groundwater sampling using low-flow techniques, and quarterly system optimization activities.

View the file

Other files

File Type Posted
CN-370000-HW681-DC001B.pdf PDF
CN-370000-HW681-DC001E.pdf PDF
CN-370000-HW681-DC002E.pdf PDF
CN-370000-HW681-DC002F.pdf PDF
CN-370000-HW681-DC003B.pdf PDF
CN-370000-HW681-DC005D.pdf PDF
CN-370000-HW681-DC005E.pdf PDF
CN-370000-HW681-DC008B.pdf PDF
CN-370000-HW681-DC008E.pdf PDF
CN-370000-HW681-DC009A.pdf PDF
CN-370000-HW681-DC010A.pdf PDF
CN-370000-HW681-DC010C.pdf PDF
CN-370000-HW681-DC011C.pdf PDF
CN-370000-HW681-DC012D.pdf PDF
CN-370000-HW681-DC013A.pdf PDF
CN-370000-HW681-DC013B.pdf PDF
CN-370000-HW681-DC013C.pdf PDF
CN-370000-HW681-DC013D.pdf PDF
CN-370000-HW681-DC015A.pdf PDF
CN-370000-HW681-DC016C.pdf PDF
CN-370000-HW681-DC017B.pdf PDF
CN-370000-HW681-DC018C.pdf PDF
CN-370000-HW681-DC019B.pdf PDF
CN-370000-HW681-DC01ACO5.pdf PDF
CN-370000-HW681-DC021A.pdf PDF
CN-370000-HW681-DC021B.pdf PDF
CN-370000-HW681-DC025A.pdf PDF
CN-370000-HW681-DC02BCO2.pdf PDF
CN-370000-HW681-DC02DCO1.pdf PDF
CN-370000-HW681-DC031C.pdf PDF
CN-370000-HW681-DC032D.pdf PDF
CN-370000-HW681-DC033C.pdf PDF
CN-370000-HW681-DC037B.pdf PDF
CN-370000-HW681-DC038B.pdf PDF
CN-370000-HW681-DC038C.pdf PDF
CN-370000-HW681-DC03A.pdf PDF
CN-370000-HW681-DC03CCO1.pdf PDF
CN-370000-HW681-DC03CCO2.pdf PDF
CN-370000-HW681-DC041C.pdf PDF
CN-370000-HW681-DC042B.pdf PDF
CN-370000-HW681-DC042C.pdf PDF
CN-370000-HW681-DC043A.pdf PDF
CN-370000-HW681-DC043B.pdf PDF
CN-370000-HW681-DC04BCO1.pdf PDF
CN-370000-HW681-DC05CCO3.pdf PDF
CN-370000-HW681-DC06BCO4.pdf PDF
CN-370000-HW681-DC07ACO1.pdf PDF
CN-370000-HW681-DC07CCO1.pdf PDF
CN-370000-HW681-DC08CCO1.pdf PDF
CN-370000-HW681-DC09BCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW681

DC021C May 29, 2026

This Task Assignment authorizes CDM Smith Inc. to conduct Operation and

Maintenance (O&M) and Groundwater Monitoring at Star Cleaners Depot per their proposed scope of work submitted on 21NOV2024.

Benjamin Aoki 850-245-7527 CDM Smith Inc.

Kyle Turner 813-262-8851

ERIC_4613

7181 Crane Avenue, Jacksonville, Duval County, FL

Star Cleaners Depot

$ 57,494.89

$ 8,400.00

$ 65,894.89

Scope of Work

CDM Smith Inc.

Leslie Samel

Vice President

Leslie Samel Digitally signed by Leslie Samel Date: 2024.12.12 10:04:09 -05'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2024.12.12 08:19:00 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number: HW681 Task Assignment #: DC021C

Deliverables:

Deliverable Deliverable Due Date Subtask 2: Annual Groundwater Monitoring - Field notes, laboratory report, updated tables /2 /2025 Subtask 3 & 4: SVE System O&M and Optimization - Quarters 14 & 15 (DEC24-MAY25) - Semiannual RASR, including Groundwater Monitoring /2 /2025

Subtask 1, 5, & 6: SVE System O&M and Optimization - Quarters 16 & 17 (JUN25-NOV25) - Annual RASR; Project Management /2 /2026

Subtask 7: Utilities - Quarter 14 - Paid Utility Invoices / /2025

Subtask 8: Utilities - Quarter 15 - Paid Utility Invoices /2 /2025

Subtask 9: Utilities - Quarter 16 - Paid Utility Invoices 1 /21/2025

Subtask 10: Utilities - Quarter 17 - Paid Utility Invoices /2 /2026

Subtask 11: Blower Replacement - Field Documentation / /2025

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced Subtask 2: Annual Groundwater Monitoring - Field notes, laboratory report, updated tables

5,725.22

Subtask 3 & 4: SVE System O&M and Optimization - Quarters 14 & 15 (DEC24-MAY25) - Semiannual RASR, including Groundwater Monitoring

20,329.85

Subtask 1, 5, & 6: SVE System O&M and Optimization - Quarters 16 & 17 (JUN25-NOV25) - Annual RASR; Project Management

26,792.30

Subtask 7: Utilities - Quarter 14 - Paid Utility Invoices 2,160.00

Subtask 8: Utilities - Quarter 15 - Paid Utility Invoices 2,160.00

Subtask 9: Utilities - Quarter 16 - Paid Utility Invoices 2,160.00

Subtask 10: Utilities - Quarter 17 - Paid Utility Invoices 2,160.00

Subtask 11: Blower Replacement - Field Documentation 4,407.52

TOTAL COST $65,894.89

BWC TAFORM 01_18

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

TO:

FROM:

DATE:

SUBJECT:

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

SITE :

SUBTASK: 2 Annual Groundwater Monitoring

DATE: 11/20/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Leader Technical Evaluation of Data/trend analysis 4

Professional II Site Access with Site Owner 1

Sample Kit Coordination 1

IDW Management 1

Data Package Preparation (Annual Sampling) 6

Professional I Travel (1 trip) 2

Annual Groundwater Sampling (8 wells) 6

Field Preparation (Annual Sampling) 1

Staff Technician Travel (1 trip) 2

Annual Groundwater Sampling (8 wells) 6

Total Hours:

PTL 4

Professional II 9

Professional I 9

Staff Technician 8

TOTAL LABOR 30

VEHICLE TYPE RATE UNIT USEAGE

Truck $120 each 2 $240.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOH 8021/8260 $73.00 8 $584.00

Shipping (Large Cooler) $150.00 1 $150.00

Ice $6.50 2 $13.00

TOTAL LAB $747.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Shallow Groundwater Sampling Kit $290 Day 2 $580.00

Expendables $40.00 day 1 $40.00

Drums $100.00 each 1 $100.00

TOTAL EQUIPMENT $720.00

Star Cleaners Depot ERIC_461

SUBTASK: 3 SVE System O&M and Optimization

DATE: 11/20/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Leader System Optimization 3

Engineering Evaluation 2

Project Manager Quarterly O&M Documentation Technical Review 1

Staff Technician Travel to/from Site (3 Trips) 6

O&M Site Visit (3 Months) 18

Professional II Updated Data Tables / Review and Interpretation 4

Quarterly O&M Documentation Package 6

Sample Kit Coordination 1

Total Hours:

PTL 5

PM 1

Staff Technician 24

Professional II 11

TOTAL LABOR 41

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE Unit COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TO-15 $200.00 1 $200.00

Small Cooler $110.00 1 $110.00

TOTAL LAB $310.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Construction/O&M/Pilot kit $360.00 day 3 $1,080.00

Construction/O&M Supplies $75.00 day 3 $225.00

Expendables $40.00 day 3 $120.00

TOTAL EQUIPMEN $1,425.00

Star Cleaners Depot ERIC_4

SUBTASK: 4 SVE System O&M and Optimization

DATE: 11/20/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Leader System Optimization / Operations Review 3

Author Engineering Section of Semiannual RASR 2

Project Manager Semiannual RASR / GWMR Technical Review 4

Professional II Semiannual RASR preparation (including GWM) 32

Figures for Semiannual RASR 4

Sample Kit Coordination (Soil Vapor Sample) 1

Staff Technician Travel to/from Site (3 Trips) 6

O&M Site Visit (3 Months) 18

Total Hours:

PTL 5

PM 4

Professional II 37

Staff Technician 24

TOTAL LABOR 70

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

Staff Technician $150.00 Hotel 3 $450.00

Staff Technician $36.00 Per Diem 3 $108.00

TOTAL PER DIEM $558.00

SUBCONTRACTOR COSTS

NAME PURPOSE Unit COST

Erwin Remediation IDW Removal (Water) 1 $125.00 $125.00

TOTAL $125.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TO-15 $200.00 1 $200.00

Small Cooler $110.00 1 $110.00

TOTAL LAB $310.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Construction/O&M/Pilot kit $360.00 day 3 $1,080.00

Construction/O&M Supplies $75.00 day 3 $225.00

Expendables $40.00 day 3 $120.00

SUBTASK: 5 SVE System O&M and Optimization

DATE: 11/20/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Leader System Optimization 3

Engineering Evaluation 2

Project Manager Quarterly O&M Documentation Technical Review 1

Staff Technician Travel to/from Site (3 Trips) 6

O&M Site Visit (3 Months) 18

Professional II Updated Data Tables / Review and Interpretation 4

Quarterly O&M Documentation Package 6

Sample Kit Coordination 1

Total Hours:

PTL 5

PM 1

Staff Technician 24

Professional II 11

TOTAL LABOR 41

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE Unit COST

Erwin Remediation IDW Removal 0 $125 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TO-15 $200.00 1 $200.00

Small Cooler $110.00 1 $110.00

TOTAL LAB $310.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00

Construction/O&M/Pilot kit $360.00 day 3 $1,080.00

Construction/O&M Supplies $75.00 day 3 $225.00

Expendables $40.00 day 3 $120.00

Drums $100.00 each 0 $0.00

SUBTASK: 6 SVE System O&M and Optimization

DATE: 11/20/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Leader System Optimization / Operations Review 3

Author Engineering Section of Annual RASR 2

Project Manager Annual RASR Technical Review 4

Professional II Annual RASR preparation 36

Figures for Annual RASR 4

Sample Kit Coordination (Soil Vapor Sample) 1

Staff Technician Travel to/from Site (3 Trips) 6

O&M Site Visit (3 Months) 18

Total Hours:

PTL 5

PM 4

Professional II 41

Staff Technician 24

TOTAL LABOR 74

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

Staff Technician $150.00 Hotel 3 $450.00

Staff Technician $36.00 Per Diem 3 $108.00

TOTAL PER DIEM $558.00

SUBCONTRACTOR COSTS

NAME PURPOSE Unit COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TO-15 $200.00 5 $1,000.00

Small Cooler $110.00 5 $550.00

TOTAL LAB $1,550.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Construction/O&M/Pilot kit $360.00 day 3 $1,080.00

Construction/O&M Supplies $75.00 day 3 $225.00

Expendables $40.00 day 3 $120.00

Star Cleaners Depot ERIC_4613

SUBTASK: 7 Utilities - Qtr 14

DATE: 11/20/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

O&M Quarter 14 Utilities Utility Charges (Electric) $700.00 month 3 $2,100.00

Quarter 14 Handling Fee Utility Handling Fee $20.00 Month 3 $60.00

TOTAL EQUIPMEN $2,160.00

Star Cleaners Depot ERIC_4613

SUBTASK: 8 Utilities - Qtr 15

DATE: 11/20/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

O&M Quarter 15 Utilities Utility Charges (Electric) $700.00 month 3 $2,100.00

Quarter 15 Handling Fee Utility Handling Fee $20.00 Month 3 $60.00

SUBTASK: 9 Utilities - Qtr 16

DATE: 11/20/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

O&M Quarter 16 Utilities Utility Charges (Electric) $700.00 month 3 $2,100.00

Quarter 16 Handling Fee Utility Handling Fee $20.00 Month 3 $60.00

SUBTASK: 10 Utilities - Qtr 17

DATE: 11/20/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

O&M Quarter 17 Utilities Utility Charges (Electric) $700.00 month 3 $2,100.00

Quarter 17 Handling Fee Utility Handling Fee $20.00 Month 3 $60.00

SUBTASK: 11 Blower Replacement

DATE: 11/20/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Professional I Travel to/from Site (1 Trip) 2

Repair Oversight and Documentation 6

Total Hours:

PTL 0

PM 0

Professional I 8

Staff Technician 0

TOTAL LABOR 8

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 Day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00

$0.00

$0.00

$0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

RSI Blower Replacement (Fuji + Labor) 1 $3,100.00 $3,100.00

TOTAL $3,100.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00

$0.00

$0.00

$0.00

$0.00

$0.00

TOTAL LAB $0.00

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 1 $40.00

TOTAL EQUIPMEN $40.00

November 18, 2024

Kyle M. Turner Geologist CDM Smith

Subject: Quote for Blower Replacement Star Cleaners Depot 7181 Crane Ave, Jacksonville, FL

Remedial Systems Integrated, LLC (RSI) is pleased to provide CDM Smith with this quote for blower replacement.

. Blower Replacement o Rotron blower, 3 hp, (lead time 10 weeks) [$7,800] (or) o Fuji blower, 2.5hp, 154 cfm, (lead time 1 week) [$1,500]

Labor [$1,600]

Should you have any questions or would like to discuss options presented in this proposal, please do not hesitate to contact me directly at remedialsystems@outlook.com or via my cell at (813) 585-8769.

Respectfully, Remedial Systems Integrated, LLC

Simo Koncalovic, Owner