This document is a Task Assignment Change Order (TACO) issued by the State of Florida Department of Environmental Protection (FDEP) to CDM Smith Inc. for remediation services at Nelson's Cleaners, a commercial dry-cleaning facility located at 1203 West Highway 50 in Clermont, Lake County, Florida (Site ID: ERIC_4822). The change order, effective January 26, 2024, amends the original Task Assignment DC003C under Contract HW681. The contracting parties include the FDEP (represented by Project Manager Aaron Cohen) and CDM Smith Inc. (represented by Project Manager Leslie Semel and authorized signatory Teresa Booeshaghi for FDEP).
The TACO reconciles Work Change Directive 1 in accordance with CDM Smith's cost estimate and scope of work, which includes construction and startup of a soil vapor extraction (SVE) system, baseline and annual groundwater monitoring, system operation and maintenance, and utilities. The amended total Task Assignment value increased from $154,438.72 to $163,591.92, representing a cost increase of $9,153.20, comprised of a fixed unit rate of $162,291.92 and a cost reimbursement of $1,300.00 for utilities. The Task Assignment completion date was extended from February 15, 2024 to August 30, 2024 (197 days total). Deliverables include baseline/annual groundwater monitoring and reporting due September 30, 2023; SVE system construction and startup daily reports and completion report due April 15, 2024; and utilities invoice and handling fee due June 15, 2024. The contract is funded through the State of Florida's Hazardous Waste Cleanup Program with no additional funding information provided.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
DC003C 1 HW681
This Task Assignment Change Order reconciles WCD 1 in accordance with the CDM Smith cost estimate and scope of work. There is a cost reimbursement of $1,300 (Utilities).
Aaron Cohen (850) 245-8974 CDM Smith Inc.
Leslie Semel 704-249-6592
ERIC_4822
Nelson's Cleaners
$ 0.00
$ 162,291.92 $ 153,138.72
$ 1,300.00 $ 1,300.00
$ 163,591.92 $ 154,438.72
02/15/2024 08/30/2024 197
1 1 1
CDM Smith Inc.
Leslie Semel Teresa Booeshaghi
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2024.01.26 13:47:34 -05'00'
1/26/2024
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO:
FROM:
SUBJECT:
DATE:
Site # ERIC_
, Project Manager
Negotiation Summary
HW68
, 202
From: Fincham, Kara E.
To: Cohen, Aaron Subject: Nelson"s Cleaners (ERIC_4822) TACO Date: Thursday, December 21, 2023 3:21:14 PM Attachments: HW681 CEF (CDM Smith) - Nelsons Cleaners Construction DC003C Delta.xlsx
Work Change Directive Form #1 DC003C.pdf 4426-22 Rev 3 CDM Smith Clermont install.pdf HW681 CEF (CDM Smith) - Nelsons Cleaners Construction DC003C Fnial.xlsx HW681 CEF (CDM Smith) - Nelsons Cleaners Construction DC003C Original.xlsx HW681 DC003Csw.pdf
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Aaron, I am submitting the TACO for Nelson’s Cleaners under DC003C, which consists of a reconciliation of the approved/attached WCD, as well as an adjustment in schedule.
Due to the subcontractor availability and some issues with access, we are not able to install this system until sometime in February.
Therefore I would like to have the following schedule changed:
Subtask 3: Due April 15, 2024 Subtask 4: Due June 15, 2024
The current end TA date is 2/15/24 and that will also need to be changed.
Please let me know if you have any questions.
Thanks Kara
Kara E. Fincham, PMP Senior Project Manager 4651 Salisbury Road, Suite 420 Jacksonville, FL 32256 O: 904.527.6716 M: 904.716.8184 cdmsmith.com
SITE : Nelson's Cleaners SUBTASK: 2 Baseline/Annual Groundwater Monitoring
DATE: 12/21/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Technical Expert S. Cobert Technical Evaluation of Data 2
Professional II A. Ryan Travel (1 trip) 2
Annual Groundwater Sampling - 15 wells 12
Field Preparation (Annual Sampling) 1
HASP Update 1
Sample Kit Preparation 1
IDW Management 4
Professional I J. LeBlanc Travel (1 trip) 2
Annual Groundwater Sampling - 15 wells 12
Professional I L. Weber Data Package, Updated Data Tables (Annual Sampling) 6
Total Hours:
S. Cobert 2
A. Ryan 21
J. LeBlanc 14
L. Weber 6
TOTAL LABOR 43
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 days 2 $240.00
TOTAL VEHICLE $240.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00
$0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNITS USEAGE Subtotal
Erwin Remediation IDW Removal $125 drum 1 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES
VOH 8021/8260 $73.00 15 $1,095.00
Shipping (Large Cooler) $150.00 2 $300.00
Ice $6.50 4 $26.00
TOTAL LAB $1,421.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Shallow GW Sampling Kit $290.00 day 2 $580.00
Expendables $40.00 day 2 $80.00
Drums $100.00 each 1 $100.00
TOTAL EQUIPMENT $760.00
SUBTASK: 3 SVE System Startup and Construction/Reporting
DATE: 12/21/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Technical Lead K. Fincham Startup/Construction Completion Report Review 4
Daily Progress Reports 9
Professional II A. Ryan Travel (PreCon Meeting) 2
PreCon Meeting at Site 2
Travel (Construction oversight) 10
Construction oversight 50
Coordination with Utility Engineer, Establish Account 6
Travel (Site Visit to Meet Utility Engineer) 2
Travel (Day 1 and 2 Startup) 2
Day 1 System Startup/Testing 10
Day 2 System Startup/Vapor Sampling 10
Travel (Week 1 Startup) 2
Week 1 System Startup/Vapor Monitoring 10
Professional I J. LeBlanc Travel (Month 1 O&M) 2
Month 1 O&M 8
Professional II K. Turner Travel (Day 1 and 2 Startup) 2
Preparation of Electrical Drawings (6) 16
Day 1 System Startup/Testing 10
Day 2 System Startup/Vapor Sampling 10
Startup/Construction Completion Report 48
Professional II A. Ryan Figures/As-Builts for Construction Completion Report 20
Sr. Technical Lead S. Cobert PE Oversight/Review of Construction Completion Report/As-Builts 20
Review of Electrical Drawings 6
Total Hours:
S. Cobert 26
K. Fincham 13
J. LeBlanc 10
K. Turner 86
A. Ryan 126
TOTAL LABOR 261
VEHICLE TYPE RATE UNIT USEAGE
Truck (Construction Oversight) $480.00 week 1 $480.00
Truck (Day 1 and 2 Startup) $120.00 day 2 $240.00
Truck (Week 1 Startup) $120.00 day 1 $120.00
Truck (Month 1 O&M) $120.00 day 1 $120.00
Truck (Meet w/ Utility Engineer) $120.00 day 1 $120.00
Truck (PreCon Meeting) $120.00 day 1 $120.00
TOTAL VEHICLE $1,200.00
PER DIEM STAFF RATE UNIT USEAGE
Per Diem K.Turner $36.00 day 2 $72.00
Hotel K.Turner $150.00 Day 2 $300.00
TOTAL PER DIEM $372.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNITS USEAGE Subtotal
RSI LLC Treatment System $46,845.50 each 1 $46,845.50
RSI LLC (2 events) O&M Support (1 week, 1 month) $2,000.00 each 1 $2,000.00
PR&D, Inc Remedial Construction,Electrical Connection $46,653.00 each 1 $46,653.00
TOTAL $95,498.50
LABORATORY COSTS
PARAMETER RATE # SAMPLES
TO-15 for VOHs $200.00 11 $2,200.00
Shipping (small cooler) $110.00 11 $1,210.00
TOTAL LAB $3,410.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 9 $360.00
Soil Vapor Sampling Kit $290.00 day 3 $870.00
Construction/O&M/Pilot Test kit $360.00 day 8 $2,880.00
Construction/O&M Supplies $75.00 day 4 $300.00
TOTAL EQUIPMENT $4,410.00
SUBTASK: 4 Utilities
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR
VEHICLE TYPE RATE UNIT USEAGE
$0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE UNIT COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
O&M Month 1 Utilities Utility Charges (Electric) $1,300.00 month 1 $1,300.00
Utility Setup Fee $225.00 each 1 $225.00
Handling Fee $20.00 month 1 $20.00
TOTAL EQUIPMENT $1,545.00
12/21/2023
SUBTASK: 3 SVE System Startup and Construction/Reporting
DATE: 12/21/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Technical Lead K. Fincham Startup/Construction Completion Report Review 0
Daily Progress Reports 0
Professional II A. Ryan Travel (PreCon Meeting) 0
PreCon Meeting at Site 0
Travel (Construction oversight) 0
Construction oversight 0
Coordination with Utility Engineer, Establish Account 0
Travel (Site Visit to Meet Utility Engineer) 0
Travel (Day 1 and 2 Startup) 0
Day 1 System Startup/Testing 0
Day 2 System Startup/Vapor Sampling 0
Travel (Week 1 Startup) 0
Week 1 System Startup/Vapor Monitoring 0
Professional I J. LeBlanc Travel (Month 1 O&M) 0
Month 1 O&M 0
Professional II K. Turner Travel (Day 1 and 2 Startup) 0
Preparation of Electrical Drawings (6) 16
Day 1 System Startup/Testing 0
Day 2 System Startup/Vapor Sampling 0
Startup/Construction Completion Report 0
Professional II A. Ryan Figures/As-Builts for Construction Completion Report 0
Sr. Technical Lead S. Cobert PE Oversight/Review of Construction Completion Report/As-Builts 0
Review of Electrical Drawings 6
Total Hours:
S. Cobert 6
K. Fincham 0
J. LeBlanc 0
K. Turner 16
A. Ryan 0
TOTAL LABOR 22
VEHICLE TYPE RATE UNIT USEAGE
Truck (Construction Oversight) $480.00 week 0 $0.00
Truck (Day 1 and 2 Startup) $120.00 day 0 $0.00
Truck (Week 1 Startup) $120.00 day 0 $0.00
Truck (Month 1 O&M) $120.00 day 0 $0.00
Truck (Meet w/ Utility Engineer) $120.00 day 0 $0.00
Truck (PreCon Meeting) $120.00 day 0 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
Per Diem K.Turner $36.00 day 0 $0.00
Hotel K.Turner $150.00 Day 0 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNITS USEAGE Subtotal
RSI LLC Treatment System $46,845.50 each 0 $0.00
RSI LLC (2 events) O&M Support (1 week, 1 month) $2,000.00 each 0 $0.00
PR&D, Inc Remedial Construction,Electrical Connection $4,879.00 each 1 $4,879.00
TOTAL $4,879.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES
TO-15 for VOHs $200.00 0 $0.00
Shipping (small cooler) $110.00 0 $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 0 $0.00
Soil Vapor Sampling Kit $290.00 day 0 $0.00
Construction/O&M/Pilot Test kit $360.00 day 0 $0.00
Construction/O&M Supplies $75.00 day 0 $0.00
TOTAL EQUIPMENT $0.00
Site Name: Site ID #:
Contract #: Contractor:
� Reason for Work Change Directive :
� Description of Work Change Directive :
� Attachments (if applicable, list documents supporting change):
� Costs (if negotiated unit costs, provide information below):
WCP WCD 07-2018
Authorized Contractor Signature:
Authorized FDEP Signature:
WORK CHANGE DIRECTIVE FORM
FDEP Supervisor Approval:
(if applicable)
Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.
Task Assignment #: Work Change Directive #:
Maximum Estimated Increase in Task Amount:
Nelson's Cleaners ERIC_4822
HW681 CDM Smith Inc
DC003C 1
Need electrical drawings for permit for SVE system installation; change in conditions at site required re-configuration of system
Increased costs from PR&D; costs for electrical drawings
CEF/LOE; quote from PR&D
$10,500
$ 10,500.00
Kara E. Fincham Digitally signed by Kara E. Fincham DN: C=US, E=finchamke@cdmsmith.com, O=CDM Smith, CN=Kara E. Fincham Date: 2023.11.16 10:56:13-05'00'
Aaron Cohen Digitally signed by Aaron Cohen Date: 2023.11.16 12:30:14 -05'00'
Aaron Cohen Digitally signed by Aaron Cohen Date: 2023.11.16 12:30:24 -05'00'
Proposal Nelson's Cleaners
PR&D Quote # 4426-22 Rev 3 To:
CDM Smith 101 Southhall Lane, Suite 200 Maitland, Fl 32751
Attn: Steve Cobert, PE REFERENCE: Tel. NO. TERMS: DATE:
Nelson's Cleaners 407-660-6356 Net 30 days 11/14/2023 We are pleased to offer the following proposal for your consideration.
Mob to the site.
Prepare the area to run piping inside of the building.
Run a 2" sch 40 pvc line from (3) wells inside, over to & up the wall to a common area in the wall to exit.
Go thru the concrete block wall and run the piping along the wall to the outside well piping.
Run a 2" sch 40 pvc line from (2) outside wells, over to & straight up the wall and run with the inside pipes.
Supply & install (5) 8" manholes for well head access.
Trench 25' for the wells and electric and finish the trenches with 5000 psi concrete that is mixed onsite.
On the outside, strap the pipe to the wall & transition to the roof eave, back to the wall and to the compound.
All of the piping that is strapped to the wall/eave will utilize unistrut and pipe straps.
Set the customer supplied trailer on jacks, level and secure using trailer tie down straps in the 1st bay.
Build a fence enclosure from the end of the stall on each side out approximately 10'.
Install a 12' double gate on the front for trailer removal.
Plumb from the trailer to the piping and to the carbon with customer supplied hoses.
Run underground power from the transformer to the wall next to the trailer & install a meter can & disconnect on the wall.
Wire from the disconnect to the remediation system disconnect.
Clean up & dispose of any PR&D related constuction debris.
Demob.
NOTES:
Includes 1 day of an electrician onsite.
If needed, 4" bollards place at the corner of the fence, add 450.00 per bollard
Estimated a total of 5 days onsite for the installation.
This price will remain firm for ninety days from the proposal date.
THE TOTAL PRICE IS AS FOLLOWS:
INSTALLATION - 46,653.00
TOTAL PRICE 46,653.00
We appreciate the opportunity of offering this proposal and trust we may be favored with your most valued business.
CDM Smith Kenneth P. Richard Company Name Sales Representative
Petroleum Resources & Development, Inc.
Signature Date
Title
(321) 986-6036
Petroleum Resources & Development, Inc.
2460 N Courtenay Pkwy, Suite 212
Merritt Island, Florida 32953
(321) 986-6026
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor�st �s Project Manager: ontractor�s t�s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
HW681
DC003C Completion February 15, 2024
CDM Smith Inc. will Construct a soil vapor extraction system (SVE) in accordance with the January 2022 DEP-approved ISRP and the May 11th, 2023 Scope of Work and Cost Proposal.
Kyle McMurray 850-245-8973 Contractor CDM Smith Inc. Contractor
Contractor Shayne Wood Contractor 904-527-6703
ERIC_4822
1203 West Highway 50, Clermont, Lake County, Florida
Nelson's Cleaners
Contractor Contractor
$ 153,138.72
$ 1,300.00
$ 154,438.72
Scope of Work
CDM Smith Inc.
Contractor
Shayne Wood
Vice President
6/28/2023
Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2023.06.28 11:36:40-04'00'
Teresa Booeshaghi
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.06.28 09:51:52 -04'00'
6/28/2023
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Baseline/Annual Groundwater Monitoring and Reporting Updated HASP, Laboratory Analytical Report, Updated Tables 09/30/2023
SVE System Construction and Startup Daily Construction Reports, Startup/Construction Completion Report 11/30/2023
1 month Utilities Setup Fee, Utilities Handling Fee, and Paid Utility Invoice Not to exceed 1,300.00 per month
01/30/2024
Subtask 1 and 2 - Updated HASP, Laboratory Analytical Report, Updated Tables + Project Management $ 12,411.24
Subtask 3 - Daily Construction Reports, Startup/Construction Completion Report $ 140,482.48
Subtask 4 - utilities Handling Fee, and Paid Utility Invoice Utilities not to exceed 1,300.00 per month $ 1,545.00
$ 154,438.72
HW681
DC003C
File details come from the government source that posted it. Updated .