CN-370000-HW681-DC10BCO1.pdf

PDF 24 MB Posted

Attached to
Master Agreement FL|HW681|acc15804f9112ed94de3c1f0669600ae
Contract number
HW681
Issued by
Florida

About this file

This document is a Task Assignment Change Order (TACO #1) executed between the State of Florida Department of Environmental Protection (FDEP) and CDM Smith Inc. for environmental site assessment services at the Elite Cleaners facility located at 11301 North 56th Street, Temple Terrace, Hillsborough County, Florida. The underlying contract is designated HW681, with the original Task Assignment (DC010B) issued on August 2, 2022. The change order was executed on June 21, 2023, and extends the project completion date by 168 days, from June 30, 2023 to December 15, 2023.

The change order authorizes CDM Smith to perform expanded Phase II assessment activities in response to contamination levels that exceeded initial expectations when Maximum Contaminant Gradient (MAGs) testing data was received. Scope modifications include removing certain soil and groundwater samples from Subtask 2 while adding substantial work under Subtasks 4 and 5, including installation of five monitoring wells, installation and testing of MAGs wells, soil gas sampling, and investigation-derived waste (IDW) management. The original Task Assignment value was $95,708.23; the change order increases the total TA value to $186,537.59, representing a cost increase of $90,829.36. Subcontractors engaged include Environmental Drilling Service Inc. for well installation ($47,555.00), Erwin Remediation for IDW disposal ($6,875.00), Site Lines LLC for utility marking ($800.00), and Southeastern Survey for surveying services ($2,565.00). Labor rates range from $26.45 to $81.53 per hour across multiple staff categories, with an overhead rate of 135 percent and fringe benefits of 37.7 percent. Deliverables are due by June 30, 2023 (Subtasks 2-3), August 30, 2023 (Subtask 4), and November 15, 2023 (Subtasks 1 and 5), with invoice payments scheduled upon FDEP approval of corresponding deliverables.

View the file

Other files

File Type Posted
CN-370000-HW681-DC001B.pdf PDF
CN-370000-HW681-DC001E.pdf PDF
CN-370000-HW681-DC002E.pdf PDF
CN-370000-HW681-DC002F.pdf PDF
CN-370000-HW681-DC003B.pdf PDF
CN-370000-HW681-DC005D.pdf PDF
CN-370000-HW681-DC005E.pdf PDF
CN-370000-HW681-DC008B.pdf PDF
CN-370000-HW681-DC008E.pdf PDF
CN-370000-HW681-DC009A.pdf PDF
CN-370000-HW681-DC010A.pdf PDF
CN-370000-HW681-DC010C.pdf PDF
CN-370000-HW681-DC011C.pdf PDF
CN-370000-HW681-DC012D.pdf PDF
CN-370000-HW681-DC013A.pdf PDF
CN-370000-HW681-DC013B.pdf PDF
CN-370000-HW681-DC013C.pdf PDF
CN-370000-HW681-DC013D.pdf PDF
CN-370000-HW681-DC015A.pdf PDF
CN-370000-HW681-DC016C.pdf PDF
CN-370000-HW681-DC017B.pdf PDF
CN-370000-HW681-DC018C.pdf PDF
CN-370000-HW681-DC019B.pdf PDF
CN-370000-HW681-DC01ACO5.pdf PDF
CN-370000-HW681-DC021A.pdf PDF
CN-370000-HW681-DC021B.pdf PDF
CN-370000-HW681-DC021C.pdf PDF
CN-370000-HW681-DC025A.pdf PDF
CN-370000-HW681-DC02BCO2.pdf PDF
CN-370000-HW681-DC02DCO1.pdf PDF
CN-370000-HW681-DC031C.pdf PDF
CN-370000-HW681-DC032D.pdf PDF
CN-370000-HW681-DC033C.pdf PDF
CN-370000-HW681-DC037B.pdf PDF
CN-370000-HW681-DC038B.pdf PDF
CN-370000-HW681-DC038C.pdf PDF
CN-370000-HW681-DC03A.pdf PDF
CN-370000-HW681-DC03CCO1.pdf PDF
CN-370000-HW681-DC03CCO2.pdf PDF
CN-370000-HW681-DC041C.pdf PDF
CN-370000-HW681-DC042B.pdf PDF
CN-370000-HW681-DC042C.pdf PDF
CN-370000-HW681-DC043A.pdf PDF
CN-370000-HW681-DC043B.pdf PDF
CN-370000-HW681-DC04BCO1.pdf PDF
CN-370000-HW681-DC05CCO3.pdf PDF
CN-370000-HW681-DC06BCO4.pdf PDF
CN-370000-HW681-DC07ACO1.pdf PDF
CN-370000-HW681-DC07CCO1.pdf PDF
CN-370000-HW681-DC08CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. ☐ There are no changes to the TA compensation.

☐ The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO ☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. ☐ There are no changes to the TA Expiration Date.

☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. ☐ There are no changes to the Attachments.

☐ Attachment ___ is replaced with Attachment -____.

7. ☐ No Additional Changes.

☐ Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

DC010B 1 HW681

This Task Assignment Change Order tasks CDM with expanded Phase II assessment activities and 168 day time extension.

Kyle McMurray 850-245-8973 Contractor Contractor

Contractor Contractor

Contractor

CDM Smith Inc.

Shayne Wood 904-527-6703

ERIC 4708

Elite Cleaner

✔ $ 186,537.59 $ 95,708.23

$ 186,537.59 $ 95,708.23 Completion

Completion✔ 06/30/2023 12/15/2023 168

✔ 1 1 1

CDM Smith Inc.

Shayne Wood

CDM Contract Manager

6/21/2023

Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2023.06.21 16:17:37-04'00'

Teresa Booeshaghi

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.06.21 12:59:17 -04'00'

6/21/2023

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01_18

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW681

DC010B

$ 186,537.59

Subtasks 2 and 3: Documentation of completion of soil and groundwater assessment including photo log depicting site conditions before and after intrusive activities, soil boring logs, field notes, and sampling chain of custody forms

Subtask 4: Documentation of monitoring well installation and sampling field work completion

Subtasks 1 and 5: Site Assessment Report and Project Management

Subtasks 2 and 3: FDEP approval of documentation of completion of soil and groundwater assessment including photo log of site conditions before and after intrusive activities, soil boring logs, field notes, and sampling chain of custody forms

Subtasks 1 and 5: Site Assessment Report and Project Management

Subtask 4: FDEP approval of documentation of monitoring well installation and sampling field work completion

06/30/2023

08/30/2023

11/15/2023

$ 108,416.57

$ 43,748.90

$ 34,372.12

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

TO: HW681 Contract File

FROM: Kyle McMurray, Contract Manager

DATE: June 12th, 2023

SUBJECT: Negotiation Summary Task Assignment DC010B

TACO #1

ERIC_4708

This Task Assignment Change Order tasks CDM with expanded Phase II assessment activities and 168-day time extension. In accordance with the CDM Smith (CDM) Change Order Request and cost estimate forms received on June 5th, 2023.

Upon receipt of the MAGs testing data contamination levels were higher then expected. After discussions with FDEP Technical Staff and Project Manager it has been decided to expand this original Task Assignments scope to complete Site Assessment.

Changes to the original CDM scope of work include the following:

Subtask 3: Stage I Field Investigation Subtask 2 has an overall price decrease due to change in scope. Removed 7 soil samples, 36 groundwater samples, 1 TCLP VOCs, subcontractor GWP, shipping costs, and equipment costs.

The work remaining in subtask 3 has already been completed prior to this change order reduction. All additional work that is required to complete the Site Assessment Report is added to subtask 4 and 5.

Subtask 4: Stage III Field Investigation Subtask 4 has an overall price increase due to additional vehicle costs, Monitoring wells installations (5), MAGs well installations, Mark utilities subcontractor costs, IDW costs, 12 Soil Gas samples, 5 Groundwater samples, shipping costs, equipment costs, and CDM labor.

Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Erwin Remediation for IDW disposal was chosen on a lowest-cost basis.

Subtask 5: Site Assessment Report Subtask 5 has an overall price increase due to additional CDM labor.

The overall cost increase related to this Change Order is $90,829.35.

The FDEP project manager agrees to the scope of work and final cost associated with the Task Assignment Change Order. The final cost total for Task Assignment DC010B is $186,537.59.

FDEP COST ESTI MATEContractor: CDM Smith, Inc.

Date: 6/1/2023

Task #: SubTask 1 Project Management SubTask 6

Site: Elite Cleaners SubTask 2 Site Preparation SubTask 7

Activity/Phase: Site Assessment SubTask 3 Stage I Field Investigation SubTask 8

Project Manager: Kara Fincham SubTask 4 Stage II Field Investigation SubTask 9

SubTask 5 Site Assessment Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$59.98 Project Manager 57 57.1 $0.00 Senior Officer 0 0 0 0 0 0 0 0 0 0

$81.53 Senior Technical Expert TD 9 0 5 0 4 0 0 0 0 0 $59.98 Project Technical Leader KF 30 0 10 4 16 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $40.87 Professional II MB 174 0 76 48 50 0 0 0 0 0 $26.45 Professional I JL 122 12 68 18 24 0 0 0 0 0 $30.36 Professional I KP 16 0 0 0 16 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

$63.58 Project Technical Leader KF 25 0 0 25 0 0 0 0 0 0 $71.37 Senior Professional SC 48 0 0 34 14 0 0 0 0 0 $28.17 Professional I JL 42 0 0 42 0 0 0 0 0 0 $43.05 Professional II KT 158 0 0 98 60 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 681 57 12 159 269 184 0 0 0 0 0

Direct Labor $29,783.99 $3,426.48 $317.40 $5,912.17 $12,095.90 $8,032.04 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $40,208.39 $4,625.75 $428.49 $7,981.43 $16,329.47 $10,843.25 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $11,228.56 $1,291.78 $119.66 $2,228.89 $4,560.15 $3,028.08 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $81,220.94 $9,344.01 $865.55 $16,122.49 $32,985.52 $21,903.37 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF CDM Smith Page 1

Task #: SubTask 1 Project Management SubTask 6

Site: Elite Cleaners SubTask 2 Site Preparation SubTask 7

Activity/Phase: Site Assessment SubTask 3 Stage I Field Investigation SubTask 8

Project Manager: Kara Fincham SubTask 4 Stage II Field Investigation SubTask 9

SubTask 5 Site Assessment Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $2,640.00 $120.00 $1,080.00 $1,440.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $2,640.00 $120.00 $1,080.00 $1,440.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $56,466.50 $0.00 $8,911.50 $47,555.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $2,565.00 $0.00 $0.00 $2,565.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $6,875.00 $0.00 $0.00 $6,875.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities

$600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utility Locate $1,400.00 $0.00

$0.00 $800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $67,306.50 $600.00 $8,911.50 $57,795.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $6,730.65 $60.00 $891.15 $5,779.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $74,037.15 $660.00 $9,802.65 $63,574.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $9,742.00 $0.00 $7,342.00 $2,400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $1,976.40 $0.00 $1,226.40 $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $3,430.00 $0.00 $1,467.00 $1,963.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $15,148.40 $0.00 $10,035.40 $5,113.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $455.00 $35.00 $420.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $920.00 $40.00 $240.00 $640.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $1,945.00 $0.00 $970.00 $975.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,634.00 $0.00 $1,344.00 $290.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $265.00 $0.00 $165.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $150.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $5,369.00 $225.00 $3,139.00 $2,005.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $178,415.49 $9,344.01 $1,870.55 $40,179.54 $105,118.02 $21,903.37 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $8,122.10 $934.40 $86.56 $1,612.25 $3,298.55 $2,190.34 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $186,537.59 $10,278.41 $1,957.11 $41,791.79 $108,416.57 $24,093.71 $0.00 $0.00 $0.00 $0.00 $0.00

Cost from Prior CEF: $95,708.23 Manual Entry Cost from Delta CEF; $86,943.20 Manual Entry

Cost (Prior + Delta): $182,651.43 Auto-Calculated

REV: 02/03 CEF CDM Smith Page 2

$0.00

Task #: SubTask 1 Project Management SubTask 6

Site: Elite Cleaners SubTask 2 Site Preparation SubTask 7

Activity/Phase: Site Assessment SubTask 3 Stage I Field Investigation SubTask 8

Project Manager: Kara Fincham SubTask 4 Stage II Field Investigation SubTask 9

SubTask 5 Site Assessment Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Rounding Error: $3,886.16 Auto-Calculated

Final Total Cost: $186,537.59 Auto-Calculated

REV: 02/03 CEF CDM Smith Page 3

SITE :

SUBTASK:

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Professional I JL Utilities Oversight 10

Travel 2

TOTAL LABOR 12

VEHICLE TYPE RATE UNIT USEAGE

Truck $120 each 1 $120.00

TOTAL VEHICLE $120.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Site Lines LLC Mark utilities $600.00

$0.00

TOTAL $600.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day 1 $40.00

Level D PPE $35.00 person 1 $35.00

Site Recon Kit $150.00 Each 1 $150.00

TOTAL EQUIPMENT $225.00

Elite Cleaners 2 - Mobilization 6/1/2023

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Officer TD Determine field activities based on VEW/MAGs data 5

Project Manager KF Field Event Preparation 4

Determine Field Activities based on field data 6

Professional II MB Field Event Preparation 4

Travel (6 days) 12

5 soil borings (1 day) 10

Vapor Extraction Well Installation (1 days) 10

Vapor Monitoring Point Installation (1 day) 10

MAGs Testing (2 days) 20

7 Vertical profiles (1 days) 10

Professional I JL Travel (5 days) 10

5 soil borings 10

Vapor Extraction Well Installation 10

Vapor Monitoring Point Installation 10

MAGS Testing 20

IDW Management 8

TOTAL LABOR 159

VEHICLE TYPE RATE UNIT USEAGE

Truck $480 weekly 2 $960.00

Truck $120.00 daily 1 $120.00

TOTAL VEHICLE $1,080.00

Elite Cleaners 3 - Stage I Field Inve

SUBCONTRACTOR COSTS

NAME PURPOSE RATE UNIT USEAGE

Groundwater Protection $8,911.50

TOTAL $8,911.50

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Soil 8260B 73 84 0 $6,132.00

1 week turnaround 20% $1,226.40

Sample Shipping $150.00 7 $1,050.00

Ice $6.50 14 $91.00

Soil Gas TO-15 $200.00 5 0 $1,000.00

Soil TCLP VOCs $210.00 1 0 $210.00

Sample Shipping $150.00 2 0 $300.00

Ice $6.50 4 $26.00

TOTAL LAB $10,035.40

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Encore Sampler $16.00 Each 84 $1,344.00

Expendables $40.00 Days 6 $240.00

Level D PPE $35.00 Man-Days 12 $420.00

Soil Sampling Kit (through concrete) $235.00 Days 2 $470.00

Mags Investigation Kit $500.00 Days 1 $500.00

Summa Canister $33.00 each 5 $165.00

TOTAL EQUIPMENT $3,139.00

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager KF Determine Field activities based on field data 0

FDEP Discussions/Data Review/TACO 25

Sr. Professional SC FDEP Discussions regarding change in conditions 34

Professional II KT Field Event Preparation 0

Travel (MW/MAGS Well installation) 10

Install 5 Monitoring Wells (3 days) 0

Install MAGS Wells (5 days) 50

Travel (MAGS Testing) 6

MAGS Testing (3 days) 30

Travel (MW Sampling) 0

Sample 5 Monitoring Wells 2

Professional I JL Travel (MAGS Testing) 6

MAGS Testing (3 days) 30

Travel (MW Sampling) 0

Sample 5 Monitoring Wells 2

Survey oversight/IDW Management 4

Project Manager KF Determine Field activities based on field data 4

Professional II MB Field Event Preparation 4

Travel 8

Install 7 Monitoring Well 30

Sample 7 Monitoring Wells 6

Professional I JL Travel 2

Sample 7 Monitoring Wells 6

Survey oversight/IDW Management 10

TOTAL LABOR 269

VEHICLE TYPE RATE UNIT USEAGE

Truck (MW/MAGS well install) $480.00 Week 2 $960.00

Truck (MAGS Testing) $120.00 Day 3 $360.00

Truck (GW Sampling) $120.00 Day 1 $120.00

TOTAL VEHICLE $1,440.00

Elite Cleaners 4 - Stage III Field In

NAME PURPOSE COST

EDS MW/MAGS Installation $47,555.00 $47,555.00

Southeastern Survey Survey $2,565.00 $2,565.00

Site Lines LLC Mark utilities $800.00 $800.00

Erwin Remediation IDW Disposal ` 55 $125.00 $6,875.00

TOTAL $57,795.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Soil Gas TO-15 $200.00 12 0 $2,400.00

Groundwater 8260B $150.00 5 0 $750.00

Sample Shipping $150.00 13 0 $1,950.00

Ice $6.50 2 $13.00

TOTAL LAB $5,113.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Days 13 $520.00

Shallow Groundwater Sampling Kit $290.00 Days 1 $290.00

Monitor Well Installation Kit $325.00 Days 3 $975.00

Drums $100.00 Each 1 $100.00

Tubing/HDPE $0.40 per foot 300 $120.00

TOTAL EQUIPMENT $2,005.00

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager CN SAR Preparation 4

Sr. Professional SC Engineering Evaluation of Data/SAR Sign and Seal 10

Cross Section/CSM Preparation 4

Project Manager KF SAR Preparation 16

Professional II MB SAR Preparation 50

Professional II KT Additional Figures/Data Preparation/review 40

Cross Section/CSM Preparation 20

Professional I JL Assist in SAR Preparation 24

Professional I KP Prepare Figures 16

TOTAL LABOR 184

Elite Cleaners 5 - Site Assessment Re

FDEP COST ESTIMATEContractor: CDM Smith, Inc.

Task #: SubTask 1 Project Management SubTask 6

Site: Elite Cleaners SubTask 2 Site Preparation SubTask 7

Activity/Phase: Site Assessment SubTask 3 Stage I Field Investigation SubTask 8

Project Manager: Kara Fincham SubTask 4 Stage II Field Investigation SubTask 9

SubTask 5 Site Assessment Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$59.98 Project Manager 28 28.2 $0.00 Senior Officer 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

$63.58 Project Technical Leader KF 25 0 0 25 0 0 0 0 0 0 $71.37 Senior Professional SC 48 0 0 34 14 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $28.17 Professional I JL 42 0 0 42 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $43.05 Professional II KT 158 0 0 98 60 0 0 0 0 0

$0.00 Project Administration 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Support Services 0 0 0 0 0 0 0 0 0 0 $0.00 Staff Support Services 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 301 28 0 0 199 74 0 0 0 0 0

Direct Labor $14,690.34 $1,690.04 $0.00 $0.00 $9,418.12 $3,582.18 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $19,831.95 $2,281.55 $0.00 $0.00 $12,714.46 $4,835.94 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $5,538.26 $637.15 $0.00 $0.00 $3,550.63 $1,350.48 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $40,060.55 $4,608.74 $0.00 $0.00 $25,683.21 $9,768.60 $0.00 $0.00 $0.00 $0.00 $0.00

Task #: SubTask 1 Project Management SubTask 6

Site: Elite Cleaners SubTask 2 Site Preparation SubTask 7

Activity/Phase: Site Assessment SubTask 3 Stage I Field Investigation SubTask 8

Project Manager: Kara Fincham SubTask 4 Stage II Field Investigation SubTask 9

SubTask 5 Site Assessment Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $840.00 $0.00 $0.00 $840.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $840.00 $0.00 $0.00 $840.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $38,125.50 $0.00 ($897.50) $39,023.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $5,475.00 $0.00 $0.00 $5,475.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Locate $800.00 $0.00 $0.00 $800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $44,400.50 $0.00 ($897.50) $45,298.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $4,440.05 $0.00 ($89.75) $4,529.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $48,840.55 $0.00 ($987.25) $49,827.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs ($2,007.00) $0.00 ($3,344.00) $1,337.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $122.20 $0.00 ($627.80) $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $659.00 $0.00 ($978.00) $1,637.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory ($1,225.80) $0.00 ($4,949.80) $3,724.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection ($175.00) $0.00 $0.00 ($175.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $360.00 $0.00 $0.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) ($1,665.00) $0.00 ($1,665.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) ($112.00) $0.00 ($112.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) ($100.00) $0.00 $0.00 ($100.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses ($1,692.00) $0.00 ($1,777.00) $85.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $86,823.30 $4,608.74 $0.00 ($7,714.05) $80,160.01 $9,768.60 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $4,006.05 $460.87 $0.00 $0.00 $2,568.32 $976.86 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $90,829.35 $5,069.61 $0.00 ($7,714.05) $82,728.33 $10,745.46 $0.00 $0.00 $0.00 $0.00 $0.00

DATE:

SUBCONTRACTOR COSTS

NAME PURPOSE RATE UNIT USEAGE

Groundwater Protection ($897.50)

TOTAL ($897.50)

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Soil 8260B 73 -7 0 ($511.00)

1 week turnaround 20% ($102.20)

Groundwater 8260B $73 -36 0 ($2,628.00)

1 week turnaround 20% ($525.60)

Water TCLP VOCs $205.00 -1 0 ($205.00)

Sample Shipping $150.00 -6 0 ($900.00)

Ice $6.50 -12 ($78.00)

TOTAL LAB ($4,949.80)

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Encore Sampler $16.00 Each -7 ($112.00)

Soil Sampling Kit (through concrete) $235.00 Days -2 ($470.00)

Shallow Groundwater Sampling/Soil Vapor Screening $290.00 Days -3 ($870.00)

Monitoring Well Installation Kit $325.00 Days -1 ($325.00)

TOTAL EQUIPMENT ($1,777.00)

Elite Cleaners 3 - Stage I Field Inve

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager KF Determine Field activities based on field data 0

FDEP Discussions/Data Review/TACO 25

Sr. Professional SC FDEP Discussions regarding change in conditions 34

Professional II KT Field Event Preparation 0

Travel (MW/MAGS Well installation) 10

Install 5 Monitoring Wells (3 days) 0

Install MAGS Wells (5 days) 50

Travel (MAGS Testing) 6

MAGS Testing (3 days) 30

Travel (MW Sampling) 0

Sample 5 Monitoring Wells 2

Professional I JL Travel (MAGS Testing) 6

MAGS Testing (3 days) 30

Travel (MW Sampling) 0

Sample 5 Monitoring Wells 2

Survey oversight/IDW Management 4

Project Manager KF Determine Field activities based on field data 0

Professional II MB Field Event Preparation 0

Travel 0

Install 7 Monitoring Well 0

Sample 7 Monitoring Wells 0

Professional I JL Travel 0

Sample 7 Monitoring Wells 0

Survey oversight/IDW Management 0

TOTAL LABOR 199

VEHICLE TYPE RATE UNIT USEAGE

Truck (MW/MAGS well install) $480.00 Week 1 $480.00

Truck (MAGS Testing) $120.00 Day 3 $360.00

TOTAL VEHICLE $840.00

Elite Cleaners 4 - Stage III Field In

NAME PURPOSE COST

Groundwater Protection ($8,532.00) ($8,532.00)

Erwin Remediation -14 $100.00 ($1,400.00)

EDS MW/MAGS Installation $47,555.00 $47,555.00

Site Lines LLC Mark utilities $800.00 $800.00

Erwin Remediation IDW Disposal ` 55 $125.00 $6,875.00

TOTAL $45,298.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

Groundwater 8260B $73.00 -6 0 ($438.00)

Soil TCLP VOCs $210.00 -2 0 ($420.00)

Water TCLP VOCs $205.00 -1 0 ($205.00)

Soil Gas TO-15 $200.00 12 0 $2,400.00

Groundwater 8260B $150.00 5 0 $750.00

Sample Shipping $150.00 11 0 $1,650.00

Ice $6.50 -2 ($13.00)

TOTAL LAB $3,724.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Days 9 $360.00

Level D PPE $35.00 Man-Days -5 ($175.00)

Drums $100.00 Each -1 ($100.00)

TOTAL EQUIPMENT $85.00

DATE:

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager CN SAR Preparation 0

Sr. Professional SC Engineering Evaluation of Data/SAR Sign and Seal 10

Cross Section/CSM Preparation 4

Project Manager KF SAR Preparation 0

Professional II MB SAR Preparation 0

Professional II KT Additional Figures/Data Preparation/review 40

Professional I JL Assist in SAR Preparation 0

Professional I KP Prepare Figures 0

Professional II KT Cross Section/CSM Preparation 20

TOTAL LABOR 74

Elite Cleaners 5 - Site Assessment Re

Date: 7/22/2022

Task #: SubTask 1 Project Management SubTask 6

Site: Elite Cleaners SubTask 2 Site Preparation SubTask 7

Activity/Phase: Site Assessment SubTask 3 Stage I Field Investigation SubTask 8

Project Manager: Kara Fincham SubTask 4 Stage II Field Investigation SubTask 9

SubTask 5 Site Assessment Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$59.98 Project Manager 29 29.0 $0.00 Senior Officer 0 0 0 0 0 0 0 0 0 0

$81.53 Senior Technical Expert TD 9 0 5 0 4 0 0 0 0 0 $59.98 Project Technical Leader KF 30 0 10 4 16 0 0 0 0 0

$0.00 Senior Professional 0 0 0 0 0 0 0 0 0 0 $40.87 Professional II MB 174 0 76 48 50 0 0 0 0 0 $26.45 Professional I JL 122 12 68 18 24 0 0 0 0 0 $30.36 Professional I KP 16 0 0 0 16 0 0 0 0 0

$0.00 Staff Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Project Administration 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Support Services 0 0 0 0 0 0 0 0 0 0 $0.00 Staff Support Services 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 380 29 12 159 70 110 0 0 0 0 0

Direct Labor $15,093.65 $1,736.44 $317.40 $5,912.17 $2,677.78 $4,449.86 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $20,376.42 $2,344.19 $428.49 $7,981.43 $3,615.00 $6,007.31 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $5,690.31 $654.64 $119.66 $2,228.89 $1,009.52 $1,677.60 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $41,160.38 $4,735.27 $865.55 $16,122.49 $7,302.30 $12,134.77 $0.00 $0.00 $0.00 $0.00 $0.00

Date: 7/22/2022

Task #: SubTask 1 Project Management SubTask 6

Site: Elite Cleaners SubTask 2 Site Preparation SubTask 7

Activity/Phase: Site Assessment SubTask 3 Stage I Field Investigation SubTask 8

Project Manager: Kara Fincham SubTask 4 Stage II Field Investigation SubTask 9

SubTask 5 Site Assessment Report SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $1,800.00 $120.00 $1,080.00 $600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,800.00 $120.00 $1,080.00 $600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $18,341.00 $0.00 $9,809.00 $8,532.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $2,565.00 $0.00 $0.00 $2,565.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $1,400.00 $0.00 $0.00 $1,400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $600.00 $600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $22,906.00 $600.00 $9,809.00 $12,497.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $2,290.60 $60.00 $980.90 $1,249.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $25,196.60 $660.00 $10,789.90 $13,746.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $11,749.00 $0.00 $10,686.00 $1,063.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $1,854.20 $0.00 $1,854.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $2,771.00 $0.00 $2,445.00 $326.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $16,374.20 $0.00 $14,985.20 $1,389.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $630.00 $35.00 $420.00 $175.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $440.00 $40.00 $240.00 $160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $3,610.00 $0.00 $2,635.00 $975.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,746.00 $0.00 $1,456.00 $290.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $365.00 $0.00 $165.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $270.00 $150.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $7,061.00 $225.00 $4,916.00 $1,920.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $91,592.18 $4,735.27 $1,870.55 $47,893.59 $24,958.00 $12,134.77 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $4,116.05 $473.53 $86.56 $1,612.25 $730.23 $1,213.48 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $95,708.23 $5,208.80 $1,957.11 $49,505.84 $25,688.23 $13,348.25 $0.00 $0.00 $0.00 $0.00 $0.00

*Please reference the Bid Specifications for a complete description of the items listed below

ITEM UNIT QUANTITY COST TOTAL

Preconstruction Activities: Includes permitting, health and safety, pre-drill meeting, mobilization of equipment and manpower to the site, utility locate, and hydrant hook-up for drilling water. There is a hydrant located on the SW corner of the property.

EA 1

3,700.00 3,700.00

Monitor Well Installation: Monitoring wells will need to be completed via roto-sonic drilling. A total of 5 monitor wells are proposed. We are anticipating a total depth of 75 ft bls with 10' of 2" diameter, 0.010" slotted screen, 65 feet of 2" riser, a 20/30 sand filter pack, a four foot 30/65 sand seal, and grout to the surface. Wells will be finished in 2' by 2' concrete pad with an 8" boltdown manhole and LWP.

Feet 375

40 15,000.00

Well Development: Develop monitor well until extracted water appears clear and free of silts (30 min). This will need to be completed via submersible pump due to the depth to water.

Hour 2.5

100 250

VEW Well Installation: A total of 12 Vapor Extraction Wells will be installed. Total depths varry. Two VEWS will be screened 1-11 ft bls with 1 foot of riser. Five VEWs will be screened 20-35 ft bls with 20 feet of riser.

Five VEWS will be screened 40-55 ft bls with 40 feet of riser. VEWs will be constructed of 2" diameter SCH40 PVC with 0.010" slotted screens, a 20/30 sand filter pack, a 30/65 sand seal, and grouted to the surface. All VEWs will be finished in a 2' by 2' concrete pad with an 8" boltdown manhole and LWP.

Feet 472

40 18,880.00

Soil Core: Continuous soil core recovery will be needed from the first monitor well installed to determine exact depths of the shallow aquifer.

For the remaining four wells, we would like soil core recovery for the bottom 20 feet. Core recovery (via sonic or hand auger) will be needed for deep VEWs from land surface to bottom of the borehole.

Feet 275

15 4,125.00 IDW: Includes FDOT-approved 55-gallon drums and movement of drums to on-site staging area determined by CDM1.

Drums 80 70 5,600.00

$47,555.00

TIME ESTIMATE

Days required for well installation days 8 days

Notes:

1. Number of drums required to be specified by drilling contractor.

Environmental Drilling Service, Inc.

COMPANY NAME

Carl Leonhardt VP of Operations

PRINT NAME TITLE

5/5/2023

SIGNATURE DATE

QUOTE IS VALID FOR 60 DAYS

TOTAL:

BID FORM - DRILLER

Elite Cleaner

11301 North 56th Street Temple Terrace, Hillsborough County, Florida

FDEP Facility ID No. ERIC_4708

Sonic Auger DPT Injection Well Abandonment

Date 5/8/2023

ESTIMATE #: 523013

ID QTY Unit Rate TOTAL

1 1 ls 1,500.00$ 1,500.00$

1a 1 ls 750.00$ 750.00$

2 7 night 450.00$ 3,150.00$

3 9 day 4,250.00$ 38,250.00$

4 847 foot 12.00$ 10,164.00$

5 17 each 150.00$ 2,550.00$

6 Well Development (up to 1/2 hour per well) 17 each 75.00$ 1,275.00$

7 17 each 65.00$ 1,105.00$

8 8 each 65.00$ 520.00$

9 Bobcat Loader for Tooling and IDW Mgt. 1 ls 1,000.00$ Included

10 Hydrant Meter Rental and Use 1 ls 600.00$ 600.00$

11 -$

Subtotal 59,864.00$

Signature : Todd Hodgson

Todd Hodgson TOTAL 59,864.00$

Vice President/Partner

Mobilization/Demobilization

Per Diem

Drum (Soil) (Estimated)

Materials: 2" PVC Well Installation

2' x 2' Concrete Pad w/8" Flush Manhole Completion

Sonic Rig and Crew

Shift Change

THANK YOU FOR YOUR BUSINESS!

Drum (Water) (Estimated)

Permits (SWFLWMD-Not Applicable for FDEP Projects

If you have any questions concerning this proposal contact Todd Hodgson at (407) 426-7885 or Todd@drillprollc.com.

"Actual quantities & days on site will be invoiced"

Completion: 8-9 Days Due to Distance Between/Locations of Wells

DESCRIPTION

PROJECT DESCRIPTION:

ROW Permits and MOT Responsibility of Client Locations must be accessible with track sonic rig and support equipment

Utility locates on Private Property are the responsibility of the client.

Damage to utilities on private property during borehole clearance are the responsibility of the client.

(5) 2" x 35' PVC VEW w/15' of .010 Slot Screen, 2' x 2' Concrete Pad w/8" Flush Manhole, No Sampling

Drum all IDW and a Fire Hydrant is available at SW Corner of Property

(5) 2" x 55' PVC VEW w/15' of .010 Slot Screen, 2' x 2' Concrete Pad w/8" Flush Manhole, Soil Sampling

(2) 2" x 11' PVC VEW w/10' of .010 Slot Screen, 2' x 2' Concrete Pad w/8" Flush Manhole, No Sampling

Borehole clearance to 5' bgs beyond 20 minutes willrequire a change order for additional time and cost.

Note: It is Groundwater Protection policy that if 'Pea Gravel' is encountered, ANY type of boring/drilling will be terminated immediately and the boring location will need to be relocated to a clear location by the client.

(5) 2" x 75' PVC MW w/10' of .010 Slot Screen, 2' x 2' Concrete Pad w/8" Flush Manhole, Soil Sampling at the First MW Location. The other 4 wells will be sampled the last 20' of boring.

PROJECT

Elite Cleaners 11301 N 56th Street

CUSTOMER

Kyle M. Turner, MS, GIT

CDM

2002 N. Lois Avenue, Ste. 200 Tampa, Florida 33607

(813) 262-8851

Temple Terrace, Florida

Sonic Well Installation

2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586 mailto:Mike@amrc-environmental.com mailto:Mike@amrc-environmental.com mailto:Mike@amrc-environmental.com

*Please reference the Bid Specifications for a complete description of the items listed below

ITEM UNIT QUANTITY COST TOTAL

Preconstruction Activities: Includes permitting, health and safety, pre-drill meeting, mobilization of equipment and manpower to the site, utility locate, and hydrant hook-up for drilling water. There is a hydrant located on the SW corner of the property.

EA 1

Monitor Well Installation: Monitoring wells will need to be completed via roto-sonic drilling. A total of 5 monitor wells are proposed. We are anticipating a total depth of 75 ft bls with 10' of 2" diameter, 0.010" slotted screen, 65 feet of 2" riser, a 20/30 sand filter pack, a four foot 30/65 sand seal, and grout to the surface. Wells will be finished in 2' by 2' concrete pad with an 8" boltdown manhole and LWP.

Feet 375

Well Development: Develop monitor well until extracted water appears clear and free of silts (30 min). This will need to be completed via submersible pump due to the depth to water.

Hour 2.5

VEW Well Installation: A total of 12 Vapor Extraction Wells will be installed. Total depths varry. Two VEWS will be screened 1-11 ft bls with 1 foot of riser. Five VEWs will be screened 20-35 ft bls with 20 feet of riser.

Five VEWS will be screened 40-55 ft bls with 40 feet of riser. VEWs will be constructed of 2" diameter SCH40 PVC with 0.010" slotted screens, a 20/30 sand filter pack, a 30/65 sand seal, and grouted to the surface. All VEWs will be finished in a 2' by 2' concrete pad with an 8" boltdown manhole and LWP.

Feet 472

Soil Core: Continuous soil core recovery will be needed from the first monitor well installed to determine exact depths of the shallow aquifer.

For the remaining four wells, we would like soil core recovery for the bottom 20 feet. Core recovery (via sonic or hand auger) will be needed for deep VEWs from land surface to bottom of the borehole.

Feet 275

IDW: Includes FDOT-approved 55-gallon drums and movement of drums to on-site staging area determined by CDM1.

Drums

TIME ESTIMATE

Days required for well installation days

Notes:

1. Number of drums required to be specified by drilling contractor.

COMPANY NAME

PRINT NAME TITLE

SIGNATURE DATE

QUOTE IS VALID FOR DAYS

TOTAL:

BID FORM - DRILLER

Elite Cleaner

11301 North 56th Street Temple Terrace, Hillsborough County, Florida

FDEP Facility ID No. ERIC_4708

$1,500.00 $1,500.00

$52.00 $19,500.00

$125.00 $312.50

$52.00 $24,544.00

$15.00 $4,125.00

55 $70.00 $3,850.00

$53,831.50

SITE LINES LLC

Utility Locating 1143 59th Avenue North (727) 432-9482 St. Petersburg, FL 33703 bhardy@sitelinesllc.com

Mr. Kyle M. Turner, MS, GIT CDM Smith 2002 N Lois Avenue, Suite 200 Tampa, FL 33607

May 16, 2023

SITE: Elite Cleaners Site – Temple Terrace, Florida PROPOSAL: 01280p

Dear Mr. Turner:

Thank you for contacting Site Lines LLC regarding the private utility locate at your project site. Attached is our proposal in response to your inquiry.

Please review the proposal to ensure I have accurately captured the project details.

If you agree to the proposal, including the terms and conditions, and the statement of work, please sign, initial and date where indicated. Upon signing, the proposal will serve as the Agreement of the parties as to the above-referenced Project.

If you have any questions, please feel free to contact me. I look forward to working with you.

Sincerely, Site Lines LLC

William L. Hardy II Geophysicist President

Enclosure

SITE LINES LLC PROPOSAL

SITE LOCATION

Elite Cleaners Site – 11301 N 56th Street, Temple Terrace, FL

PROPOSED SCOPE OF WORK

Site Lines (“Company”) will use Ground Penetrating Radar (GPR) and conventional electromagnetic (EM) pipe and cable locators to determine the location of underground utilities at the site identified by CDM Smith (“Client”). Of specific concern is the location of utilities within the area of approximately 6 proposed drilling locations. A map of the locations was provided and is attached to the back of this document.

RESULTS OF THE INVESTIGATION

The estimated depth and location of utilities identified during the investigation will be marked on the ground surface using spray paint or other method to be agreed upon by the parties. Designated utilities will also be documented on a field sketch.

The American Public Works Association Uniform Color Codes for the marking of underground utilities will be used.

PROJECT FEE

The fee to complete the project as described within this proposal is: Eight Hundred Dollars [$800.00].

Client shall pay Company in full within thirty (30) days of the invoice date, unless the parties have agreed to another payment arrangement in writing. If during the investigation, Company determines that the goals of the project cannot be achieved with the resources available to Company, Company will notify Client as soon as reasonably possible. Under such circumstances, Company will charge Client only for time expended and materials used to date.

CLIENT REQUIREMENTS

Client is responsible for all site access, maintenance of traffic (MOT), site clearing and/or any other logistical considerations necessary to conduct the utility locate.

Client will also provide all pertinent maps of the project site, including those that show the boundaries of the utility locate, pertinent landmarks, and known utilities (if available). Company is not a substitute for Chapter 556, Florida Statutes.

Accordingly, Client is responsible for calling Sunshine State One Call of Florida

(811) before undertaking any invasive activities, whether through Company, any other entity, or on its own.

DESCRIPTION OF COMPANY INVESTIGATION AND LIMITATIONS

A GSSI SIR-4000 GPR system will be used with a 900, 400, or 270 megahertz antenna configuration depending on site conditions and desired targets. The GPR will assist in locating nonmetallic and metallic utilities. Physical surface conditions, subsurface conditions and technical limitations effect the ability of GPR to resolve targeted utilities and/or subsurface structures. Depth and/or diameter of the utility, soil type, moisture/ionic content of the soil, and electrical properties of the soil compared to that of the utility can prevent the GPR from identifying utilities at the site. The diameter of a utility cannot be determined by GPR data. Estimated depths of utilities are directly affected by soil conditions and the material of the utility. A margin of error of +/- 20-25% in depth should be expected when performing invasive activities.

An RD 8000 will be used for the EM survey. Electromagnetic induction which transmits a signal directly into the desired target and passive power detection which locates naturally occurring magnetic fields in energized lines will be identified by detecting and following the signals with a receiver. The EM survey will assist in finding only metallic utilities. The magnetic field and/or induced signal should emanate from the target in a circular geometry. When this occurs, the receiver will receive its peak signal directly above the target. However, when metallic utilities are running near each other, or there is environmental interference from fences, cars or overhead power lines, the signal can become distorted and the peak no longer can be directly over the utility. Care must be taken when doing any invasive work around the utilities. A margin of error of +/- 20-25% in depth should be expected when performing invasive activities. Company’s personnel are highly experienced and certified operators of GPR and EM pipe and cable locators.

Due to the limitations described above, when Client is working around indicated utilities, a minimum of two (2)-feet clearance from either side of the marked utility will be maintained. For absolute confirmation, Client is responsible for exposing any indicated underground utility.

Company will conduct utility investigations in accordance with the level of care and generally accepted professional practices as ordinarily exercised by members of the same profession practicing in the same locality under similar conditions.

REPRESENTATIONS AND WARRANTIES

Neither Company nor its employees or agents are licensed surveyors under Florida law, nor do they represent themselves as such. Accordingly, the work Company is to perform is not a substitute for work typically completed by a licensed surveyor.

Company specifically and expressly disclaims any liability for any type of property damage or personal injury, including but not limited to death, arising from client’s failure to determine that the services of a licensed surveyor are necessary or to retain a licensed surveyor to perform necessary services.

Limitations in technology, complexity of the physical characteristics of the subsurface conditions, and circumstances beyond Company’s control may limit the performance of Company’s utility investigation. For these reasons, Company expresses no guarantee that all utilities and underground structures will be identified and located during this project.

Company is responsible only for locating underground utilities, the presence of which is both known and indicated on site maps to be provided by Client to Company before Company performs the utility locate. Company will use its best efforts to locate both known and unknown utilities within the project boundaries. However, Company will only be responsible for locating utilities, the presence of which is known before Company undertakes its investigation.

Company expressly disclaims any and all warranties regarding specific or desired results.

TERMS AND CONDITIONS

Additional Insured: If requested, Company will name Client as an additional insured with respect to the services to be performed under this agreement.

Indemnity: Company agrees to indemnify, protect and hold harmless Client from and against all liabilities, claims or demands of every kind of injury, including death, or damages to any person or property related in any way to Company’s performance of this Agreement, except to the extent such liabilities, claims or demands are caused by the negligence or willful misconduct of Client.

Client agrees to indemnify, protect and hold harmless Company from and against all liabilities, claims or demands of every kind of injury, including death, or damages to any person or property related in any way to Client’s performance of this Agreement, except to the extent such liabilities, claims or demands are caused by the negligence or willful misconduct of Company.

Release of Information. Client authorizes Company to release any information regarding Client and this Agreement as may be permitted by Company's privacy policy or as may be required by law or requested by governmental authorities or agencies, law enforcement agencies or courts including, but not limited to, officials from local and state code enforcement agencies.

Governing Law; Jurisdiction; Severability; Waiver of Jury Trial. This Agreement shall be governed and construed in accordance with the laws of the State of Florida. Whenever possible, each provision of this Agreement shall be interpreted in such manner as to be effective and valid under Florida law, but if any provision of this Agreement shall be invalid or prohibited under Florida law, such provision shall be ineffective only as to the invalid portion of the provision without invalidating the remainder of such provision or the remaining provisions of this Agreement.

Client agrees to waive his or her rights to a jury trial for any and all claims made against or through Company. Client further agrees that Company will be notified of all claims no later than the earlier of thirty (30) days from the initial discovery of the claim or default or thirty (30) days following the expiration or termination of this Agreement. Client also agrees that failure to notify Company of any and all claims within this time period will result in the forfeiture of said claim.

Any claims by Client arising under this Agreement must be brought in a state or federal court of competent jurisdiction located in Pinellas County, Florida or in the

United States District Court for the Middle District of Florida in Tampa, Florida.

Client waives any objection to the jurisdiction and venue of such courts. This exclusive choice of jurisdiction and venue does not preclude Client or Company from bringing an action to enforce any judgment or judicial order in any other jurisdiction. The prevailing party in any dispute will be entitled to recover from the losing party its costs, including, but not limited to, costs of collection, reasonable attorney’s fees, and investigative fees.

Assignment; Succession; Third-Party Beneficiaries. Client shall not assign this Agreement or the rights thereto to any other person or entity without the express written consent of the Company. Company may assign or transfer this Agreement without the consent of Client and, after such assignment or transfer, Company shall be released from all obligations under this Agreement occurring after such assignment or transfer. All of the provisions of this Agreement shall apply to, bind and be obligatory upon the heirs, executors, administrators, representatives, successors and assigns of the parties hereto. This Agreement is for the sole benefit of the parties to this Agreement and their respective successors and permitted assigns. Nothing in this Agreement, express or implied, is intended to or shall confer on any other person or entity any legal or equitable right benefit or remedy of any nature whatsoever under or by reason of this Agreement. Notwithstanding the foregoing, any Company Agent is a third-party beneficiary of this Agreement and has the right to enforce the provisions of this Agreement directly against the Client.

Modification of Agreement. No term of this Agreement can be waived or modified except by a writing signed by both parties. If any provision of this Agreement is deemed not to apply, is illegal, or is against public policy, the remainder of the Agreement’s provisions shall retain their full force and effect.

Entire Agreement. This Agreement, including any addenda or schedules specifically incorporated by reference herein, constitutes the entire agreement between Client and Company. This Agreement contains all representations and agreements between Client and Company. Client agrees that Company has not promised Client anything that is not written on the face of this Agreement.

Disclosure Statement. These terms and conditions apply to Projects to which the Company agrees to engage, whether such agreement is made via the Company’s online…