CN-370000-HW681-DC06BCO1.pdf

PDF 3 MB Posted

Attached to
Master Agreement FL|HW681|acc15804f9112ed94de3c1f0669600ae
Contract number
HW681
Issued by
Florida

About this file

This document consists of a Task Assignment (TA) and Task Assignment Change Order (TACO) No. 1 between the State of Florida Department of Environmental Protection (FDEP) and CDM Smith Inc. under Contract No. HW681. The original Task Assignment DC006B, executed on June 5, 2023, and the subsequent change order, executed on June 27, 2023, establish the contractual relationship for environmental assessment services at the Jasper Laundry & Dry Cleaners site located at 214 1st Ave SW, Jasper, Hamilton County, Florida (Project ERIC_4671). Kyle McMurray serves as the FDEP project manager, and Shayne Wood represents CDM Smith Inc. as the contractor's project manager.

CDM Smith Inc. is tasked with conducting supplemental soil sampling, groundwater monitoring, and preparing a revised Interim Source Removal Plan (ISRP) for the contaminated site. The original Task Assignment valued the work at $128,734.39 on a fixed unit rate basis. TACO No. 1, issued on June 27, 2023, increased the total contract value by $31,174.57 to $159,908.97 to accommodate the outsourcing of soil and groundwater PFAS (per- and polyfluoroalkyl substances) analyses to a private laboratory (AEL Laboratories) due to maximum capacity constraints at the FDEP laboratory. The cost increase encompasses analytical services for 71 soil samples and 9 groundwater samples, along with associated shipping and ice costs totaling $25,516.00 for soil analysis and $3,628.00 for groundwater analysis. Deliverables are scheduled for completion by August 30 and September 30, 2023, with invoice payments structured in three subtasks: Subtasks 1 and 2 ($107,199.16), Subtask 3 ($35,293.91), and Subtask 4 ($17,415.90).

View the file

Other files

File Type Posted
CN-370000-HW681-DC001B.pdf PDF
CN-370000-HW681-DC001E.pdf PDF
CN-370000-HW681-DC002E.pdf PDF
CN-370000-HW681-DC002F.pdf PDF
CN-370000-HW681-DC003B.pdf PDF
CN-370000-HW681-DC005D.pdf PDF
CN-370000-HW681-DC005E.pdf PDF
CN-370000-HW681-DC008B.pdf PDF
CN-370000-HW681-DC008E.pdf PDF
CN-370000-HW681-DC009A.pdf PDF
CN-370000-HW681-DC010A.pdf PDF
CN-370000-HW681-DC010C.pdf PDF
CN-370000-HW681-DC011C.pdf PDF
CN-370000-HW681-DC012D.pdf PDF
CN-370000-HW681-DC013A.pdf PDF
CN-370000-HW681-DC013B.pdf PDF
CN-370000-HW681-DC013C.pdf PDF
CN-370000-HW681-DC013D.pdf PDF
CN-370000-HW681-DC015A.pdf PDF
CN-370000-HW681-DC016C.pdf PDF
CN-370000-HW681-DC017B.pdf PDF
CN-370000-HW681-DC018C.pdf PDF
CN-370000-HW681-DC019B.pdf PDF
CN-370000-HW681-DC01ACO5.pdf PDF
CN-370000-HW681-DC021A.pdf PDF
CN-370000-HW681-DC021B.pdf PDF
CN-370000-HW681-DC021C.pdf PDF
CN-370000-HW681-DC025A.pdf PDF
CN-370000-HW681-DC02BCO2.pdf PDF
CN-370000-HW681-DC02DCO1.pdf PDF
CN-370000-HW681-DC031C.pdf PDF
CN-370000-HW681-DC032D.pdf PDF
CN-370000-HW681-DC033C.pdf PDF
CN-370000-HW681-DC037B.pdf PDF
CN-370000-HW681-DC038B.pdf PDF
CN-370000-HW681-DC038C.pdf PDF
CN-370000-HW681-DC03A.pdf PDF
CN-370000-HW681-DC03CCO1.pdf PDF
CN-370000-HW681-DC03CCO2.pdf PDF
CN-370000-HW681-DC041C.pdf PDF
CN-370000-HW681-DC042B.pdf PDF
CN-370000-HW681-DC042C.pdf PDF
CN-370000-HW681-DC043A.pdf PDF
CN-370000-HW681-DC043B.pdf PDF
CN-370000-HW681-DC04BCO1.pdf PDF
CN-370000-HW681-DC05CCO3.pdf PDF
CN-370000-HW681-DC06BCO4.pdf PDF
CN-370000-HW681-DC07ACO1.pdf PDF
CN-370000-HW681-DC07CCO1.pdf PDF
CN-370000-HW681-DC08CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. ☐ There are no changes to the TA compensation.

☐ The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO ☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. ☐ There are no changes to the TA Expiration Date.

☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. ☐ There are no changes to the Attachments.

☐ Attachment ___ is replaced with Attachment -____.

7. ☐ No Additional Changes.

☐ Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

DC006B 1 HW681

This Task Assignment Change Order tasks CDM with sourcing the soil and groundwater PFAS analyses to a private lab (AEL).

Kyle McMurray 850-245-8973 Contractor Contractor

Contractor Contractor

Contractor

CDM Smith Inc.

Shayne Wood 904-527-6703

ERIC 4671

Jasper Laundry & Dry Cleaners

✔ $ 159,908.97 $ 128,734.39

$ 159,908.97 $ 128,734.39 ✔ Completion

Completion 0

✔ 1 1 1

CDM Smith Inc.

Shayne Wood

CDM Contract Manager

6/27/2023

Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2023.06.27 15:49:24-04'00'

Teresa Booeshaghi

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.06.27 13:57:00 -04'00'

6/27/2023

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01_18

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW681

DC006B

$ 159,908.97

Supplemental Soil Assessment Report

Groundwater Sampling - Updated Tables, Field Notes, and Laboratory Analytical Report

Revised ISRP

Subtasks 1 and 2: FDEP Review and approval of Supplemental Soil Assessment Report, and Project Management

Subtask 4: FDEP Review and approval of Revised ISRP

Subtask 3: FDEP Review and approval of Groundwater Sampling - Updated Tables, Field Notes, and Laboratory Analytical Report

08/30/2023

08/30/2023

09/30/2023

$ 35,293.91

$ 107,199.16

$ 17,415.90

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

TO: HW681 Contract File

FROM: Kyle McMurray, Contract Manager

DATE: June 26th, 2023

SUBJECT: Negotiation Summary

Task Assignment DC006B

TACO #1

ERIC_4671

This Task Assignment Change Order is to task CDM with sourcing the soil and groundwater PFAS analyses to a private lab (AEL). The FDEP lab is currently at maximum capacity and cannot facilitate the analyses. In accordance with the CDM Smith (CDM) Change Order Request and cost estimate forms received on June 21st, 2023.

Changes to the original CDM scope of work include the following:

Subtask 2 and 3: Supplemental Soil Assessment & Groundwater Monitoring Subtask 2 and 3 has an overall price increase due to outsourcing PFAS analyses to private lab (AEL) which includes additional costs for 71 soil samples, 9 groundwater samples, shipping/ice, and CDM labor.

The overall cost increase related to this Change Order is $31,174.57.

The FDEP project manager agrees to the scope of work and final cost associated with the Task Assignment Change Order. The final cost total for Task Assignment DC006B is $159,908.97.

FDEP COST ESTI MATEContractor: CDM Smith, Inc.

Date: 6/13/23 TACO 1

Task #: SubTask 1 Project Management SubTask 6

Site: Jasper Laundry & Dry Cle SubTask 2 Supplemental Soil Assessment SubTask 7

Activity/Phase: SubTask 3 Groundwater Monitoring SubTask 8

Project Manager: Clint Noble SubTask 4 ISRP SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$60.42 Project Manager 47 46.9 $81.53 Senior Officer T. Duffey 23 15 0 8 0 0 0 0 0 0 $81.15 Senior Technical Expert L. Wiseman 0 0 0 0 0 0 0 0 0 0 $60.42 Project Technical Leader C. Noble 39 24 3 12 0 0 0 0 0 0 $55.47 Senior Professional M. Passaro 8 0 0 8 0 0 0 0 0 0 $40.87 Professional II M. Blanton 0 0 0 0 0 0 0 0 0 0 $69.63 Project Technical Lead S. Cobert 46 26 12 8 0 0 0 0 0 0 $26.45 Professional I J. LeBlanc 101 44 57 0 0 0 0 0 0 0 $43.01 Professional II A. Ryan 102 24 78 0 0 0 0 0 0 0 $42.00 Professional II K. Turner 80 44 0 36 0 0 0 0 0 0 $33.50 Professional I L. Mueller 46 8 8 30 0 0 0 0 0 0 $30.36 Professional I K. Profitko 40 10 0 30 0 0 0 0 0 0 $94.91 Senior Technical Expert T. Macbeth 8 8 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 540 47 203 158 132 0 0 0 0 0 0

Direct Labor $24,646.95 $2,835.49 $9,858.33 $6,147.25 $5,805.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $33,273.39 $3,827.91 $13,308.75 $8,298.79 $7,837.94 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $9,291.90 $1,068.98 $3,716.59 $2,317.51 $2,188.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $67,212.24 $7,732.38 $26,883.67 $16,763.55 $15,832.64 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $1,920.00 $960.00 $960.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $3,348.00 $1,860.00 $1,488.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $5,268.00 $2,820.00 $2,448.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF CDM SMITH Page 1

Task #: SubTask 1 Project Management SubTask 6

Site: Jasper Laundry & Dry Cle SubTask 2 Supplemental Soil Assessment SubTask 7

Activity/Phase: SubTask 3 Groundwater Monitoring SubTask 8

Project Manager: Clint Noble SubTask 4 ISRP SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $6,275.00 $6,275.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Laboratory Specialty $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $1,300.00 $1,300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin $500.00 $0.00 $500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $8,075.00 $7,575.00 $500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $807.50 $757.50 $50.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $8,882.50 $8,332.50 $550.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $59,787.00 $50,306.00 $9,481.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $6,031.00 $4,890.00 $1,141.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $65,818.00 $55,196.00 $10,622.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $280.00 $280.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $674.00 $160.00 $514.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $1,197.00 $1,197.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $3,456.00 $1,136.00 $2,320.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $400.00 $0.00 $400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $6,007.00 $2,773.00 $3,234.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $153,187.74 $7,732.38 $96,005.17 $33,617.55 $15,832.64 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $6,721.23 $773.24 $2,688.37 $1,676.36 $1,583.26 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $159,908.97 $8,505.62 $98,693.54 $35,293.91 $17,415.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost from Prior CEF: $128,734.39 Manual Entry Cost from Delta CEF; $31,174.57 Manual Entry

Cost (Prior + Delta): $159,908.96 Auto-Calculated Rounding Error: $0.01 Auto-Calculated

Final Total Cost: $159,908.97 Auto-Calculated

REV: 02/03 CEF CDM SMITH Page 2

SITE : Jasper Laundry & Dry Cleaners SUBTASK 2Supplemental Soil Assessment

DATE: 6/13/23 TACO 1

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Workplan and Field Activities

Project Techical Leader C. Noble FDEP-Directed Workplan Revisions/Additions 12

Professional II K. Turner Travel to/from site (1 trips) 7

Site Prep/Locate Borings 6.5

29 Soil Borings 25

Foundation Excavation 5

Senior Officer T. Duffy FDEP-Directed Workplan Revisions/Additions 15

Senior Technical Expert S. Cobert FDEP-Directed Workplan Revisions/Additions 14

Professional I J. LeBlanc Travel to/from site (1 trip) 7

Site Prep/Locate Borings 7

29 Soil Borings 25

Foundation Excavation 5

SSA Reporting Project Techical Leader C. Noble Prepare recommendations and conclusions and prepare final report 12

Senior Technical Expert S. Cobert Preparation of Engineering Section of Report 12

Professional II A. Ryan Preparation of Soil Data Summary and Report Text 24

Professional I L. Mueller Preparation of Data Tables, Summaries 8

Professional I K. Profitko Soil Figure/Map preparation 10

Senior Technical Expert T.MacBeth DEP directed PFAS expert review of Project for Recc. and Data Gaps 8

Staff Total Hours C. Noble 24

K. Turner 44

T. Duffy 15

S. Cobert 26

J. LeBlanc 44

A. Ryan 24

L. Mueller 8

K. Profitko 10

T.MacBeth 8 Total 203 TOTAL LABOR 203

VEHICLE TYPE RATE UNIT USEAGE

Truck $480.00 week 2 $960.00

TOTAL VEHICLE $960.00

PER DIEM STAFF RATE UNIT USEAGE

Per Diem K. Turner $36.00 day 5 $180.00

Hotel K. Turner $150.00 day 5 $750.00

Per Diem J. LeBlanc $36.00 day 5 $180.00

Hotel J. LeBlanc $150.00 day 5 $750.00

TOTAL PER DIEM $1,860.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

PDS Soil Borings $6,275.00 $6,275.00

Southeastern Surveying Survey $1,300.00 $1,300.00

TOTAL $7,575.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QA/QC

Soil 8260B $73.00 71 $5,183.00

TPH by FL-PRO $88.00 80 $7,040.00

SPLP nonaqeous zero HS $55.00 16 $880.00

VOHs leachate from SPLP $73.00 16 $1,168.00

TRPH Speciation (No contract rate, see attached quote) $220.00 16 $3,520.00

Carcinogenic polycyclic aromatic hydrocarbons by Method 8270C $110.00 74 $8,140.00

PFAS (FDEP lab) $325.00 71 4 $24,375.00

Shipping (Large Cooler (25-50 lbs)) $150.00 30 $4,500.00

Ice $6.50 60 $390.00

TOTAL LAB $55,196.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

En Core® Sampler $16.00 Each 71 $1,136.00

Expendables $40.00 Days 4 $160.00

Level D PPE $35.00 Man-Days 8 $280.00

Soil Sampling Kit (through concrete) $235.00 Days 4 $940.00

Concrete Core Drill $105.00 Days 1 $105.00

Concrete Core Drill Bit $82.00 Days 1 $82.00

Portable Generator $70.00 Days 1 $70.00

TOTAL EQUIPMENT $2,773.00

SUBTASK 4Groundwater Monitoring

DATE: 6/13/23 TACO 1

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Workplan and Field

Senior Technical Expert S. Cobert Interpretation of Lab Data Eval 10

PTL/PM C. Noble Prepare Field Scope of work 3

Professional II A. Ryan Mobilization/Demob (1 trip) 7

Field Preparation 1

Tech Oversight 1

Monitor Well Locate/Inventory/Inspection 10

Prepare Sample Kit Request 1

Sample Wells (58) 50

Professional I J. LeBlanc Mobilization/Demob (4 trip) 7

Sample Wells (58) 50

Field Activities Senior Technical Expert S. Cobert Technical Data Evaluation 2

Professional II A. Ryan Preparation of Data Summaries for Groundwater field data chemistry and flow 8

Professional II L. Mueller Preparation of Data Tables, Summaries analytical data 8

Staff Total Hours C. Noble 3

S. Cobert 12

J. LeBlanc 57

A. Ryan 78

L. Mueller 8

Total 158

TOTAL LABOR 158

VEHICLE TYPE RATE UNIT USEAGE

4.1 Truck (2) GW Sampling $480.00 week 2 $960.00

TOTAL VEHICLE $960.00

PER DIEM STAFF RATE UNIT USEAGE

Per Diem K. Turner $36.00 day 4 $144.00

Hotel K. Turner $150.00 day 4 $600.00

Per Diem J. LeBlanc $36.00 day 4 $144.00

Hotel J. LeBlanc $150.00 day 4 $600.00

TOTAL PER DIEM $1,488.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin Remediation $125 Per Drum 4 $500.00

TOTAL $500.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QA/QC

2.1 - Groundwater Sampling EPA 8260 for VOHs $73.00 58 $4,234.00

TPH by FL-PRO $88.00 9 $792.00

Carcinogenic polycyclic aromatic hydrocarbons by Method 8270C $110.00 9 $990.00

PFAS (FDEP lab) $315.00 9 2 $3,465.00

Shipping - Large Cooler $150.00 7 $1,050.00

Ice $6.50 14 $91.00

TOTAL LAB $10,622.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

2.1 GW Sampling

55 gal drum $100.00 per drum 4 $400.00

Shallow GW Sampling Kit $290.00 per day 8 $2,320.00

Silicon tubing $3.00 per foot 58 $174.00

Tubing Poly/HDPE $0.30 per foot 600 $180.00

Expendables $40.00 per day 4 $160.00

TOTAL EQUIPMENT $3,234.00

SUBTASK 4:ISRP

DATE: 6/13/23 TACO 1

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Techical Leader C. Noble Prepare recommendations and conclusions and prepare final report 12

Senior Officer T. Duffey Develop Excavation Cutlines 8

Senior Professional M. Passaro Geotechnical Engineering 8

Senior Technical Expert S. Cobert Engineer of Record 8

Professional II L. Mueller Preparation of ISRP Tables, Appendix, Geotechnical Summary 30

Professional I K. Profitko Figure/Map preparation inc. GW plume maps 30

Professional II K. Turner Draft ISRP (body) 36

TOTAL LABOR 132

Task #: SubTask 1 Project Management SubTask 6

Site: Jasper Laundry & Dry Cle SubTask 2 Supplemental Soil Assessment SubTask 7

Activity/Phase: SubTask 3 Groundwater Monitoring SubTask 8

Project Manager: Clint Noble SubTask 4 ISRP SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$60.42 Project Manager 1.3 1.3 $81.53 Senior Officer T. Duffey 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $81.15 Senior Technical Expert L. Wiseman 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $60.42 Project Technical Leader C. Noble 3.0 2.0 1.0 0.0 0 0 0 0 0 0 $55.47 Senior Professional M. Passaro 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $40.87 Professional II M. Blanton 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $69.63 Project Technical Lead S. Cobert 6.0 4.0 2.0 0.0 0 0 0 0 0 0 $26.45 Professional I J. LeBlanc 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $43.01 Professional II A. Ryan 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $42.00 Professional II K. Turner 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $33.50 Professional I L. Mueller 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $30.36 Professional I K. Profitko 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $94.91 Senior Technical Expert T. Macbeth 0.0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 10.3 1.3 6.0 3.0 0.0 0 0 0 0 0 0

Direct Labor $676.92 $77.88 $399.36 $199.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $913.85 $105.14 $539.14 $269.57 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $255.20 $29.36 $150.56 $75.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $1,845.97 $212.38 $1,089.06 $544.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Task #: SubTask 1 Project Management SubTask 6

Site: Jasper Laundry & Dry Cle SubTask 2 Supplemental Soil Assessment SubTask 7

Activity/Phase: SubTask 3 Groundwater Monitoring SubTask 8

Project Manager: Clint Noble SubTask 4 ISRP SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Laboratory Specialty $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $27,840.00 $24,375.00 $3,465.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $1,304.00 $1,141.00 $163.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $29,144.00 $25,516.00 $3,628.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $30,989.97 $212.38 $26,605.06 $4,172.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $184.60 $21.24 $108.91 $54.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $31,174.57 $233.62 $26,713.97 $4,226.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

SUBTASK 2Supplemental Soil Assessment

DATE: 6/13/23 TACO 1

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Workplan and Field Activities

Project Techical Leader C. Noble FDEP-Directed Workplan Revisions/Additions 2

Professional II K. Turner Travel to/from site (1 trips) 0

Site Prep/Locate Borings 0

29 Soil Borings 0

Foundation Excavation 0

Senior Officer T. Duffy FDEP-Directed Workplan Revisions/Additions 0

Senior Technical Expert S. Cobert FDEP-Directed Workplan Revisions/Additions 4

Professional I J. LeBlanc Travel to/from site (1 trip) 0

Site Prep/Locate Borings 0

29 Soil Borings 0

Foundation Excavation 0

SSA Reporting Project Techical Leader C. Noble Prepare recommendations and conclusions and prepare final report 0

Senior Technical Expert S. Cobert Preparation of Engineering Section of Report 0

Professional II A. Ryan Preparation of Soil Data Summary and Report Text 0

Professional I L. Mueller Preparation of Data Tables, Summaries 0

Professional I K. Profitko Soil Figure/Map preparation 0

Senior Technical Expert T.MacBeth DEP directed PFAS expert review of Project for Recc. and Data Gaps 0

Staff Total Hours C. Noble 2

K. Turner 0

T. Duffy 0

S. Cobert 4

J. LeBlanc 0

A. Ryan 0

L. Mueller 0

K. Profitko 0

T.MacBeth 0 Total 6 TOTAL LABOR 6

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QA/QC

PFAS $325.00 71 4 $24,375.00

Shipping (Large Cooler (25-50 lbs)) $150.00 7 $1,050.00

Ice $6.50 14 $91.00

TOTAL LAB $25,516.00

SUBTASK 4Groundwater Monitoring

DATE: 6/13/23 TACO 1

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Workplan and Field

Senior Technical Expert S. Cobert Interpretation of Lab Data Eval 2

PTL/PM C. Noble Prepare Field Scope of work 1

Professional II A. Ryan Mobilization/Demob (1 trip) 0

Field Preparation 0

Tech Oversight 0

Monitor Well Locate/Inventory/Inspection 0

Prepare Sample Kit Request 0

Sample Wells (58) 0

Professional I J. LeBlanc Mobilization/Demob (4 trip) 0

Sample Wells (58) 0

Field Activities Senior Technical Expert S. Cobert Technical Data Evaluation 0

Professional II A. Ryan Preparation of Data Summaries for Groundwater field data chemistry and flow 0

Professional II L. Mueller Preparation of Data Tables, Summaries analytical data 0

Staff Total Hours C. Noble 1

S. Cobert 2

J. LeBlanc 0

A. Ryan 0

L. Mueller 0

Total 3

TOTAL LABOR 3

LABORATORY COSTS

PARAMETER RATE # SAMPLES # QA/QC

2.1 - Groundwater Sampling

PFAS $315.00 9 2 $3,465.00

Shipping - Large Cooler $150.00 1 $150.00

Ice $6.50 2 $13.00

TOTAL LAB $3,628.00

Date: 5/18/23 rev

Task #: SubTask 1 Project Management SubTask 6

Site: Jasper Laundry & Dry Cle SubTask 2 Supplemental Soil Assessment SubTask 7

Activity/Phase: SubTask 3 Groundwater Monitoring SubTask 8

Project Manager: Clint Noble SubTask 4 ISRP SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$60.42 Project Manager 46 45.6 $81.53 Senior Officer T. Duffey 23 15 0 8 0 0 0 0 0 0 $81.15 Senior Technical Expert L. Wiseman 0 0 0 0 0 0 0 0 0 0 $60.42 Project Technical Leader C. Noble 36 22 2 12 0 0 0 0 0 0 $55.47 Senior Professional M. Passaro 8 0 0 8 0 0 0 0 0 0 $40.87 Professional II M. Blanton 0 0 0 0 0 0 0 0 0 0 $69.63 Project Technical Lead S. Cobert 40 22 10 8 0 0 0 0 0 0 $26.45 Professional I J. LeBlanc 101 44 57 0 0 0 0 0 0 0 $43.01 Professional II A. Ryan 102 24 78 0 0 0 0 0 0 0 $42.00 Professional II K. Turner 80 44 0 36 0 0 0 0 0 0 $33.50 Professional I L. Mueller 46 8 8 30 0 0 0 0 0 0 $30.36 Professional I K. Profitko 40 10 0 30 0 0 0 0 0 0 $94.91 Senior Technical Expert T. Macbeth 8 8 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 530 46 197 155 132 0 0 0 0 0 0

Direct Labor $23,970.03 $2,757.61 $9,458.97 $5,947.57 $5,805.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $32,359.54 $3,722.77 $12,769.61 $8,029.22 $7,837.94 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $9,036.70 $1,039.62 $3,566.03 $2,242.23 $2,188.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $65,366.27 $7,520.00 $25,794.61 $16,219.02 $15,832.64 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Date: 5/18/23 rev

Task #: SubTask 1 Project Management SubTask 6

Site: Jasper Laundry & Dry Cle SubTask 2 Supplemental Soil Assessment SubTask 7

Activity/Phase: SubTask 3 Groundwater Monitoring SubTask 8

Project Manager: Clint Noble SubTask 4 ISRP SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $1,920.00 $960.00 $960.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $3,348.00 $1,860.00 $1,488.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $5,268.00 $2,820.00 $2,448.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $6,275.00 $6,275.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Laboratory Specialty $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $1,300.00 $1,300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin $500.00 $0.00 $500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $8,075.00 $7,575.00 $500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $807.50 $757.50 $50.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $8,882.50 $8,332.50 $550.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $31,947.00 $25,931.00 $6,016.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $4,727.00 $3,749.00 $978.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $36,674.00 $29,680.00 $6,994.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $280.00 $280.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $674.00 $160.00 $514.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $1,197.00 $1,197.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $3,456.00 $1,136.00 $2,320.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $400.00 $0.00 $400.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $6,007.00 $2,773.00 $3,234.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $122,197.77 $7,520.00 $69,400.11 $29,445.02 $15,832.64 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $6,536.62 $752.00 $2,579.46 $1,621.90 $1,583.26 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $128,734.39 $8,272.00 $71,979.57 $31,066.92 $17,415.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

McMurray, Kyle

From: Cobert, Steven C. <cobertsc@cdmsmith.com> Sent: Wednesday, June 21, 2023 10:10 AM To: McMurray, Kyle Cc: Noble, Clint C.; Fincham, Kara E.

Subject: Jasper Laundry - ERIC_4671 TACO for PFAS Lab Costs Attachments: HW681 Cost Estimate Form Jasper ISRP_Original.xlsx; HW681 Cost Estimate Form Jasper

ISRP_Delta.xlsx; HW681 Cost Estimate Form Jasper ISRP_Final.xlsx

Follow Up Flag: Follow up Flag Status: Flagged

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Kyle, attached is the TACO for the costs associated with sourcing the soil and groundwater PFAS analyses to a private lab (AEL). The costs include labor associated with lab coordination and contracting, as well as the analytical and shipping costs. Please reach out with any questions or comments. Thanks.

Steve

Steven C. Cobert, P.E.

Environmental Engineer CDM Smith 101 Southhall Lane, Suite 200 Maitland, Florida 32751

407.660.6356 office

407.756.5853 mobile

McMurray, Kyle

From: Crain, Kelly Sent: Friday, June 9, 2023 3:53 PM To: Ayres, Joshua Cc: Tate, Kerry; McMurray, Kyle; Dalton, James B Subject: RE: PFAS Sample Kit Request - CDM Smith - ERIC_4671 Jasper

Follow Up Flag: Follow up Flag Status: Flagged

Hey Josh- this was probably my oversight. I can see why it wasn’t included in the PFAS schedule we provided you- but it should have been.

Anyways, we can outsource this one to a private lab, we will let the contractor know. Thanks Josh!

From: Ayres, Joshua <Joshua.Ayres@FloridaDEP.gov> Sent: Friday, June 9, 2023 3:02 PM To: Crain, Kelly <Kelly.Crain@dep.state.fl.us> Cc: Tate, Kerry <Kerry.Tate@FloridaDEP.gov> Subject: FW: PFAS Sample Kit Request - CDM Smith - ERIC_4671 Jasper

Kelly –

I didn’t see this request (See attached) on the proposed sampling schedule. Is there an alternate date?

I don’t think we’ll be able to accommodate an additional 85 samples in July. We’re already around the limit for what the lab can handle for that month.

SIS’ July request really hit us hard (277 samples) and their proposed sample requests for September and October aren’t looking any better.

Just so you’re aware, the lab can only handle about 350 samples per month without running into complications.

This number is divided amongst all PFAS projects for: DOH, DIV-WASTE, and SIS.

JULY PFAS SCHEDULE

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW681

DC006B Completion November 30, 2023

CDM Smith Inc. will conduct supplemental soil sampling, groundwater sampling, and prepare a revised ISRP for the Jasper Laundry & Dry Cleaning site located in Jasper, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on March 15, 2023.

Kyle McMurray 850-245-8973 Contractor CDM Smith Inc. Contractor

Contractor Shayne Wood Contractor 904-527-6703

ERIC_4671

214 1st Ave SW, Jasper, Hamiltion County, Florida

Jasper Laundry & Dry Cleaners

Contractor Contractor

✔ $ 128,734.39

$ 128,734.39

Scope of Work

CDM Smith Inc.

Contractor Shayne Wood

Vice President

6/5/2023

Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2023.06.05 13:42:59-04'00'

Teresa Booeshaghi

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.06.05 11:01:57 -04'00'

6/5/23

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Supplemental Soil Assessment Report 08/30/2023

Groundwater Sampling - Updated Tables, Field Notes, and Laboratory Analytical Report 08/30/2023

Revised ISRP 09/30/2023

Subtasks 1 and 2: FDEP Review and approval of Supplemental Soil Assessment Report, and Project Management $ 80,251.57

Subtask 3: FDEP Review and approval of Groundwater Sampling - Updated Tables, Field Notes, and Laboratory Analytical Report $ 31,066.92

Subtask 4: FDEP Review and approval of Revised ISRP $ 17,415.90

$ 128,734.39

HW681

DC006B