Document Summary
This Task Assignment Change Order (TACO #1) represents an amendment to Task Assignment DC005B under Florida Department of Environmental Protection (FDEP) Contract HW681 with contractor CDM Smith Inc. The document reconciles three previously issued Work Change Directives (#1, #2, and #3) for environmental assessment work at Bay's Cleaners (ERIC_4918), located at 219 N Magnolia Avenue, Ocala, Marion County, Florida. The change order is effective March 31, 2023, with key contacts including Kyle McMurray (FDEP Contract Manager) and Shayne Wood (CDM Smith Contract Manager).
The amended task assignment reflects an overall cost reduction of $26,769.98, bringing the total TA value from $185,025.33 down to $158,255.34, representing a fixed unit rate compensation structure. The cost adjustment accounts for originally planned well installations that were reduced from eight to two wells, offset by additional expenses including 46 groundwater sampling events, 78 SPLP soil sample encores, supplemental IDW drums, plywood, additional Portland cement (40 bags), hole plugs (50 bags), and increased CDM labor and subcontractor time. Deliverables include documentation of baseline groundwater sampling (Subtask 2), supplemental site assessment field activities with monitoring well installation (Subtask 3), and a Supplemental Site Assessment Report with project management (Subtasks 1 and 4), with a completion date of March 15, 2023. Invoice amounts are structured as $29,657.57 for Subtask 2, $111,409.42 for Subtask 3, and $17,188.35 for Subtasks 1 and 4.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Name:
4. ☐ There are no changes to the TA compensation.
☐ The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO ☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. ☐ There are no changes to the TA Expiration Date.
☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. ☐ There are no changes to the Attachments.
☐ Attachment ___ is replaced with Attachment -____.
7. ☐ No Additional Changes.
☐ Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
DC005B 1 HW681
This Task Assignment Change Order reconciles Work Change Directive #1, #2, and #3.
Kyle McMurray 850-245-8973 Contractor Contractor
Contractor Contractor
Contractor
CDM Smith Inc.
Shayne Wood 904-527-6703
ERIC 4918
Bay's Cleaners
✔ $ 158,255.34 $ 185,025.33
$ 158,255.34 $ 185,025.33 ✔ Completion
Completion 0
✔ 1 1 1
CDM Smith Inc.
Shayne Wood
CDM Contract Manager
3/22/2023
Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2023.03.22 08:45:18-04'00'
Teresa Booeshaghi
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.03.21 16:26:09 -04'00'
3/31/2023
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01_18
Contract Number:
Task Assignment #:
Change Order #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Delivered
Delivered
HW681
DC005B
$ 158,255.34
Documentation of completion of baseline groundwater sampling including groundwater sampling logs and laboratory analytical report(s) - Subtask 2
Documentation of completion of supplemental site assessment field activities including photolog depicting site conditions before and after well installation, field notes, boring logs, and laboratory analytical reports - Subtask 3
Supplemental Site Assessment Report and Project Management - Subtasks 1 and 4
Subtasks 2: FDEP approval of documentation of completion of soil and groundwater assessment including photo log of site conditions before and after intrusive activities, soil boring logs, field notes, and sampling chain of custody forms
Subtasks 1 and 4: Site Assessment Report and Project Management
Subtask 3: FDEP approval of documentation of monitoring well installation and sampling field work completion
03/15/2023
$ 111,409.42
$ 29,657.57
$ 17,188.35
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
TO: HW681 Contract File
FROM: Kyle McMurray, Contract Manager
DATE: March 14, 2023
SUBJECT: Task Assignment DC005B
TACO #1
ERIC_4918
This Task Assignment Change Order reconciles WCD #1, #2, and #3 which authorizes an overall reduction in cost for 6 wells not being installed. Addition cost was accrued for 46 GW sampling events, 78 encores for SPLP soil samples, additional drums, Plywood, CDM labor, 40 additional bags of Portland cement, 50 additional bags of hole plug, and subcontractor time. In accordance with the CDM Smith (CDM) Change Order Request and cost estimate forms received on March 6th, 2023.
Changes to the original CDM scope of work include the following:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2: Site Preparation and Baseline Groundwater Sampling Subtask 2 has an overall cost increase for additional GW sampling events and associated travel, materials, and labor. An additional 5 IDW drums were required.
Subtask 3: Field Investigation Subtask 3 has an overall cost reduction due to only 2 of the proposed 8 wells being installed.
Additional cost was accrued for additional grout, encore sampling, plywood, ROW permitting, CDM labor, and subcontractor time.
The overall cost reduction related to this Change Order is $26,769.98.
The FDEP project manager agrees to the scope of work and final cost associated with the Task Assignment Change Order. The final cost total for Task Assignment DC023A is $158,255.34.
There is a $0.01 difference in the CEF due to rounding errors.
FDEP COST ESTIMATEContractor: CDM Smith, Inc.
Date: 3/3/2023
Task #: SubTask 1 Project Management SubTask 6
Site: Bays Cleaners SubTask 2 Site Preparation and Baseline Groundwater sampling SubTask 7
Activity/Phase: Site Assessment SubTask 3 Field Investigation SubTask 8
Project Manager: SubTask 4 SSAR SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$59.98 Project Manager 46.2 46.2 $59.98 Project Technical Leader KF 46.0 8 22 16 0 0 0 0 0 0 $39.10 Professional II AR 241.0 43 166 32 0 0 0 0 0 0 $26.45 Professional I JL 277.0 71 190 16 0 0 0 0 0 0 $40.87 Professional II MB 36.0 36 0 0 0 0 0 0 0 0
Total Hours 650.2 46.2 158.0 378.0 68.0 0 0 0 0 0 0
Direct Labor $24,076.09 $2,769.82 $5,510.41 $12,835.66 $2,960.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 135.00% $32,502.72 $3,739.26 $7,439.05 $17,328.14 $3,996.27 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $9,076.68 $1,044.22 $2,077.42 $4,839.04 $1,116.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $65,655.49 $7,553.30 $15,026.88 $35,002.84 $8,072.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $3,480.00 $1,200.00 $2,280.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $3,534.00 $930.00 $2,604.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $7,014.00 $2,130.00 $4,884.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $41,088.00 $0.00 $41,088.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $2,565.00 $0.00 $2,565.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $1,600.00 $800.00 $800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Extra Cement $1,200.00 $0.00 $1,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Private Utility Locate $800.00 $800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $47,253.00 $1,600.00 $45,653.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $4,725.30 $160.00 $4,565.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $51,978.30 $1,760.00 $50,218.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $12,114.00 $2,409.00 $9,705.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $1,793.00 $489.00 $1,304.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $13,907.00 $2,898.00 $11,009.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $1,260.00 $350.00 $910.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $960.00 $320.00 $640.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $3,000.00 $0.00 $3,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,245.00 $0.00 $1,245.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $1,600.00 $800.00 $800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $5,070.00 $4,870.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $13,135.00 $6,340.00 $6,795.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $151,689.79 $7,553.30 $28,154.88 $107,909.14 $8,072.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $6,565.55 $755.33 $1,502.69 $3,500.28 $807.25 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $158,255.34 $8,308.63 $29,657.57 $111,409.42 $8,879.72 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
* Difference of $0.01 due to rounding.
REV: 02/03 CEF ARCADIS Page 1
SITE :
SUBTASK:
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager KF Field Event Preparation 4
Data Analysis of 33 different wells 4
Professional II AR Field Event Preparation 4
Travel (Orlando - Ocala) (3 days) 6
Groundwater sampling of 33 existing wells 25
Data Validation/Analysis of data from 33 existing wells 8
Professional II MB Travel (Tampa--Ocala) (4 Mobs) 6
Groundwater Sampling of 33 MWs 20
Acquirement and delivery of additional drums 10
Professional I JL Confirm current Offsite Access Agreements 2
Utilities Oversight 10
Travel (Tampa - Ocala) (2 mobs - 1 Utilities oversight, 1 GW sampling) 6
Groundwater Sampling of 33 Existing Wells 45
Figure and Table creation from data from 33 existing wells 8
TOTAL LABOR 158
VEHICLE TYPE RATE UNIT USEAGE
Truck $480 Week 2 $960.00
Truck $120.00 Day 2 $240.00
TOTAL VEHICLE $1,200.00
PER DIEM STAFF RATE UNIT USEAGE
JL Per Diem $36.00 Day 5 $180.00
JL Hotel $150.00 Day 5 $750.00
TOTAL PER DIEM $930.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Site Lines Mark utilities $800.00
Erwin IDW 8 each $100.00 $800.00
TOTAL $1,600.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Groundwater 8260B $73 33 0 $2,409.00
Sample Shipping $150.00 3 0 $450.00
Ice $6.50 6 $39.00
TOTAL LAB $2,898.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 8 $320.00
Level D PPE $35.00 person 10 $350.00
Site Recon Kit $150.00 day 1 $150.00
Deep Monitoring Well Kit $415.00 day 8 $3,320.00
HDPE Tubing $0.40 foot 3500 $1,400.00
Drums $100.00 Each 8 $800.00
TOTAL EQUIPMENT $6,340.00
Bays Cleaners 2 - Site Preparation a 3/3/2023
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager KF Field Event Preparation 4
Determine Field Activities based on Field Data 12
ROW Permitting 6 Professional II AR Field Event Preparation 4
Travel (Orlando - Ocala) (13 days) 36
Soil Boring/MW Installation Oversight 120
Groundwater Sampling of new MWs 6
Professional I JL Travel (Tampa--Ocala) (4 Mobs) 24
Field Event Preparation 12
Soil boring/MW Installation oversight 120
Groundwater Sampling of new MWs 6
Surveying Oversight/IDW Management 28
TOTAL LABOR 378
VEHICLE TYPE RATE UNIT USEAGE
Truck $480 Week 4 $1,920.00
Truck $120.00 Day 3 $360.00
TOTAL VEHICLE $2,280.00
PER DIEM STAFF RATE UNIT USEAGE
JL Per Diem $36.00 Day 14 $504.00
JL Hotel $150.00 Day 14 $2,100.00
TOTAL PER DIEM $2,604.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNIT USEAGE Transport Cost
Preferred Drilling Solutions See Attachment C $41,088.00
Preferred Drilling Solutions
Preferred Drilling Solutions Additional Grout 1 $1,200.00 $1,200.00
Southeastern Survey See Attachment C $2,565.00
Erwin 8 $100.00 $800.00
TOTAL $45,653.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Soil 8260B 73 77 0 $5,621.00
Groundwater 8260B $73 2 0 $146.00
Soil TCLP VOCs $210.00 5 0 $1,050.00
Water TCLP VOCs $205.00 8 0 $1,640.00
Encores $16.00 78 $1,248.00
Sample Shipping $150.00 8 0 $1,200.00
Ice $6.50 16 $104.00
TOTAL LAB $11,009.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Days 16 $640.00
Level D PPE $35.00 Man-Days 26 $910.00
Soil Sampling Kit $175.00 Days 6 $1,050.00
Deep Groundwater Sampling kit $415.00 Days 3 $1,245.00
Monitoring Well Installation Kit $325.00 Days 6 $1,950.00
Drums $100.00 each 8 $800.00
ROW Permitting $50.00 each 4 $200.00
TOTAL EQUIPMENT $6,795.00
Bay's Cleaners 3 - Field Oversight/So 3/3/2023
FDEP COST ESTIMATEContractor: CDM Smith, Inc.
Date: 3/1/2023
Task #: SubTask 1 Project Management SubTask 6
Site: Bays Cleaners SubTask 2 Site Preparation and Baseline Groundwater sampling SubTask 7
Activity/Phase: Site Assessment SubTask 3 Field Investigation SubTask 8
Project Manager: Walsta Jean-Baptiste SubTask 4 SSAR SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$59.98 Project Manager 6.6 6.6 $59.98 Project Technical Leader KF 10.0 2.0 8.0 0.0 0 0 0 0 0 0 $26.45 Professional I JL 36.0 20.0 16.0 0.0 0 0 0 0 0 0 $40.87 Professional II MB 36.0 36.0 0.0 0.0 0 0 0 0 0 0
Total Hours 88.6 6.6 58.0 24.0 0.0 0 0 0 0 0 0
Direct Labor $3,416.35 $393.03 $2,120.28 $903.04 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 135.00% $4,612.07 $530.59 $2,862.38 $1,219.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $1,287.97 $148.17 $799.35 $340.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $9,316.39 $1,071.79 $5,782.01 $2,462.59 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $360.00 $240.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $930.00 $930.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,290.00 $1,170.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) ($35,295.00) $0.00 ($35,295.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW ($3,620.00) $800.00 ($4,420.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Drilling Conventional $1,200.00 $0.00 $1,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal ($37,715.00) $800.00 ($38,515.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee ($2,980.01) $80.00 ($3,060.01) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost ($40,695.01) $880.00 ($41,575.01) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs ($723.00) $0.00 ($723.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory ($723.00) $0.00 ($723.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $140.00 $140.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $240.00 $200.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $1,300.00 $500.00 $800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $1,430.00 $1,230.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $3,110.00 $2,070.00 $1,040.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal ($27,701.62) $1,071.79 $9,902.01 ($38,675.42) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $931.64 $107.18 $578.20 $246.26 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost ($26,769.98) $1,178.97 $10,480.21 ($38,429.16) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager KF Historical Document Review 2
Professional II MB Travel (Tampa - Ocala) (2 Mobs) to deliver drums 6
GW sampling of 33 wells 20
Acquirement and delivery of additional drums 10
Professional I JL Confirm current Offsite Access Agreements 0
Groundwater Sampling of 33 Existing Wells 20
TOTAL LABOR 58
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 2 $240.00
TOTAL VEHICLE $240.00
PER DIEM STAFF RATE UNIT USEAGE
MB Per Diem $36.00 Day 5 $180.00
MB Hotel $150.00 Day 5 $750.00
TOTAL PER DIEM $930.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin 8 each $100.00 $800.00
TOTAL $800.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 5 $200.00
Level D PPE $35.00 person 4 $140.00
Deep Monitoring Well Kit $415.00 day 2 $830.00
HDPE Tubing $0.40 foot 1000 $400.00
Drums $100.00 Each 5 $500.00
TOTAL EQUIPMENT $2,070.00
Bays Cleaners 2 - Site Preparation a 3/1/2023
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager KF POW Permitting Requirements Review 2
ROW Permit Application Preparation 6
Professional I JL Travel (Tampa--Ocala) (4 Mobs) 0
ROW Permit Documentation/Figure 8
Surveying Oversight/IDW Management (WCD #2) 8
TOTAL LABOR 24
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 1 $120.00
TOTAL VEHICLE $120.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNIT USEAGE Transport Cost
Preferred Drilling Solutions See Attachment C ($35,295.00)
Preferred Drilling Solutions WCD#3 Additional Grout $1,200.00 $1,200.00
Erwin New 8 $100.00 $800.00
Clark Environmental See Attachment C -58 $90.00 ($5,220.00)
TOTAL ($38,515.00)
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Soil 8260B 73 -1 0 -73 Groundwater 8260B 73 -6 0 -438 Soil TCLP VOCs 210 -5 0 -1050 Water TCLP VOCs 205 -2 0 -410 Encores (WCD#2) 16.00$ 78 $1,248.00
TOTAL LAB ($723.00)
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Days 1 $40.00 ROW Permitting $50.00 Each 4 $200.00
Drums $100.00 each 8 $800.00
TOTAL EQUIPMENT $1,040.00
Bay's Cleaners 3 - Field Oversight/So 3/1/2023
FDEP COST ESTI MATEContractor: CDM Smith, Inc.
Date: 2/28/2023
Task #: SubTask 1 Project Management SubTask 6
Site: Bays Cleaners SubTask 2 Site Preparation and Baseline Groundwater sampling SubTask 7
Activity/Phase: Site Assessment SubTask 3 Field Investigation SubTask 8
Project Manager: Walsta Jean-Baptiste SubTask 4 SSAR SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$59.98 Project Manager 40 39.6 $81.53 Senior Technical Expert TD 4 0 0 4 0 0 0 0 0 0 $59.98 Project Technical Leade KF 36 6 14 16 0 0 0 0 0 0
$0.00 Senior Professional 0 0 0 0 0 0 0 0 0 0 $39.10 Professional II AR 241 43 166 32 0 0 0 0 0 0 $26.45 Professional I JL 241 51 174 16 0 0 0 0 0 0
Total Hours 562 40 100 354 68 0 0 0 0 0 0
Direct Labor $20,659.73 $2,376.78 $3,390.13 $11,932.62 $2,960.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 135.00% $27,890.64 $3,208.65 $4,576.68 $16,109.04 $3,996.27 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $7,788.73 $896.05 $1,278.08 $4,498.60 $1,116.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $56,339.10 $6,481.48 $9,244.89 $32,540.26 $8,072.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $3,120.00 $960.00 $2,160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $2,604.00 $0.00 $2,604.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $5,724.00 $960.00 $4,764.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $76,383.00 $0.00 $76,383.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $2,565.00 $0.00 $2,565.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $5,220.00 $0.00 $5,220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Private Utility Locate $800.00 $800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $84,968.00 $800.00 $84,168.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $7,705.31 $80.00 $7,625.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $92,673.31 $880.00 $91,793.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $12,837.00 $2,409.00 $10,428.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $1,793.00 $489.00 $1,304.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $14,630.00 $2,898.00 $11,732.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $1,120.00 $210.00 $910.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $720.00 $120.00 $600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $3,000.00 $0.00 $3,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,245.00 $0.00 $1,245.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $300.00 $300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $3,640.00 $3,640.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $10,025.00 $4,270.00 $5,755.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $179,391.41 $6,481.48 $18,252.89 $146,584.57 $8,072.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $5,633.92 $648.15 $924.49 $3,254.03 $807.25 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $185,025.33 $7,129.63 $19,177.38 $149,838.60 $8,879.72 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Site Name: Site ID #:
Contract #: Contractor:
• Reason for Work Change Directive :
• Description of Work Change Directive :
• Attachments (if applicable, list documents supporting change):
• Costs (if negotiated unit costs, provide information below):
WCP WCD 07-2018
Authorized Contractor Signature:
Authorized FDEP Signature:
WORK CHANGE DIRECTIVE FORM
FDEP Supervisor Approval:
(if applicable)
Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.
Task Assignment #: Work Change Directive #:
Maximum Estimated Increase in Task Amount:
Bay's Cleaners ERIC_4918
HW681 CDM Smith
DC005B 1
More IDW generated than anticipated; the site is located in an unsafe neighborhood--several homeless people have approached staff in a hostile manner during this sampling event. Teams cannot split up to sample as originally planned, which will mean more time will be required to complete the baseline sampling event.
Additional labor time for CDM Smith staff to sample wells safely. Additional drums, subcontractors needed due to more IDW than anticipated.
Additional costs captured in HW681 Cost Estimate form - Delta capture additional labor and materials
Labor, materials, subcontractor costs. This increases the TA by $14,000
$ 14,000.00
Kara E. Fincham, PMP Digitally signed by Kara E. Fincham, PMP DN: C=US, E=finchamke@cdmsmith.com, O="CDM Smith, Inc", CN="Kara E. Fincham, PMP" Date: 2022.09.21 14:10:51-04'00'
Kevin Kane Digitally signed by Kevin Kane Date: 2022.09.21 14:57:35 -04'00'
Aaron Cohen Digitally signed by Aaron Cohen Date: 2022.09.21 15:56:05 -04'00'
• Reason for Work Change Directive :
• Description of Work Change Directive :
• Attachments (if applicable, list documents supporting change):
• Costs (if negotiated unit costs, provide information below):
WCP WCD 07-2018
Authorized Contractor Signature:
Authorized FDEP Signature:
WORK CHANGE DIRECTIVE FORM
FDEP Supervisor Approval:
(if applicable)
Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.
Task Assignment #: Work Change Directive #:
Maximum Estimated Increase in Task Amount:
Bay's Cleaners ERIC_4918
HW681 CDM Smith
DC005B 2
Add encores for SPLP soil samples; IDW Management requires Haz Waste Management after receiving data from GW
Addition of 78 Encores for SPLP collection. Fifty-eight (58) drums of IDW are anticipated; assume 6 drums per sheet of plywood for 10 sheets total. ROW Permitting with City of Ocala
Additional costs captured in HW681- Delta Cost Estimate.
Labor, materials. This increases the TA by approximately $3,450
$ 3,450.00
Kara E. Fincham, PMP Digitally signed by Kara E. Fincham, PMP DN: C=US, E=finchamke@cdmsmith.com, O="CDM Smith, Inc", CN="Kara E. Fincham, PMP" Date: 2022.10.10 12:50:56-04'00'
Kevin Kane Digitally signed by Kevin Kane Date: 2022.10.18 13:48:05 -04'00'
Aaron Cohen Digitally signed by Aaron Cohen Date: 2022.10.18 14:49:19
• Reason for Work Change Directive :
• Description of Work Change Directive :
• Attachments (if applicable, list documents supporting change):
• Costs (if negotiated unit costs, provide information below):
WCP WCD 07-2018
Authorized Contractor Signature:
Authorized FDEP Signature:
WORK CHANGE DIRECTIVE FORM
FDEP Supervisor Approval:
(if applicable)
Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.
Task Assignment #: Work Change Directive #:
Maximum Estimated Increase in Task Amount:
Bay's Cleaners ERIC_4918
HW681 CDM Smith Inc
DC005B 3
Driller needs more grout than anticipated to fill up deep well
40 additional bags of portland cement; 50 additional bags of hole plug
None
$1400
$ 1,400.00
Kara E. Fincham, PMP Digitally signed by Kara E. Fincham, PMP DN: C=US, E=finchamke@cdmsmith.com, O="CDM Smith, Inc", CN="Kara E. Fincham, PMP" Date: 2022.10.24 14:45:59-04'00'
Kevin Kane Digitally signed by Kevin Kane Date: 2022.10.24 14:59:03 -04'00'
Aaron Cohen Digitally signed by Aaron Cohen Date: 2022.10.24 15:05:15
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Joe Kinard
CDM Smith
4651 Salisbury Road, Suite 420
Jacksonville, FL 32256 kinardjm@cdmsmith.com
February 1, 2022
Re: Non-Hazardous Drum Disposal
Mr. Kinard:
The price for the transportation and disposal (T&D) of drums of non-hazardous soil, mud and water is listed below.
Non-Hazardous Chlorinated VOHs, Petroleum and Metals:
Description Rate Unit
T&D - Non-Haz Soil $ 100.00 Per Drum
T&D - Non-Haz Mud/Water $ 100.00 Per Drum
The prices listed are all inclusive without any additional fees or charges (fuel surcharge, low volume stop fee etc.) and are valid for all regions in the State of Florida except for the Florida Keys.
Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
755 Prairie Industrial Parkway, Mulberry, Florida 33860 Telephone (863) 425-4884 Facsimile (863) 425-2854 www.clarkenvironmental.com
Disposal & Transportation Pricing for CDM Smith Effective January 21, 2022
55 Gallon DRUMS - Mileage Based from Mulberry fl, *low volume stop fee applies per stop
WASTE PROCESSING
Size (gal) Trans Liquid
Light Debris
Sludge or Oil Dry Solids Gels
Lab Packs
Empty Trans
Empty Disp
1 $2 $5 $5 $8 $8 $8 $25 $3 $5 5 $5 $10 $10 $12 $12 $15 $75 $5 $5
10 $10 $20 $20 $20 $20 $30 $75 $5 $5 15-25 $15 $40 $40 $55 $55 $65 $100 $10 $8
55 Below $60 $60 $80 $80 $105 $175 $10 $15 85 Below $80 $80 $125 $125 $155 $15 $20 yd³ Below $180 $210 $250 $250 $350 $80
251-400 miles - $50/drum ($60/85-gal) Totes- $200 *<11 drums/site – Surcharge of $200/site 101-250 miles - $40/drum ($50/85-gal) Totes- $160 *< 6 drums/site – Surcharge of $50/site 0-100 miles - $30/drum ($40/85-gal) Totes- $120 *< 6 drums/site – Surcharge of $50/site
BULK WASTE PROCESSING (BC/BW Codes) Based on Centrifuge Testing (v/v) per CLARK SOP
Liquids <10% Solid
Petroleum Contact Waters
Sludge 10-25% Solid Solids
Sludge >25%
Light Debris
$0.030/lb $0.26/gal $0.045/lb $0.040/lb $0.070/lb $0.080/lb
BULK SOILS BR Codes (Recycling)
Tons Regular/Ton < 14 tons $500 minimum 14 - 140 $35.00
141 – 700 $33.00 701 – 1400 $30.00 1401 – 2100 Negotiable
> 2100 Negotiable Excess Debris or Moisture Surcharge $5.00 / Ton
TCLP TESTING TOTALS TESTING DRUM SUPPLIES
8 Metals $290.00 4 Metals $100.00 Bolts $2.00 Volatiles $195.00 TRPH $125.00 Gaskets $5.00 4 Metals $225.00 8270 (VOH) $125.00 Lids $10.00 Benzene $135.00 Virgin Preburn $470.00 Rings & Bolts $10.00
PCBs $125.00 8260 (VOA) $125.00 New 55-Gal Drum $40.00 8081 (Pests) $205.00 85-Gal Overpack $200.00 8151 (Herbs) $205.00
Hazardous Waste E-Manifest Fee - $35/manifest
Petroleum Testing Requirements for Spills:
Virgin Oils – SDS only Virgin Diesel – SDS only Unleaded Gasoline – TCLP Benzene Used Oil – TCLP Benzene & TCLP 4 Metals Antifreeze – TCLP Benzene & TCLP 4 Metals Tank Bottoms – TCLP Benzene & TCLP 4 Metals Used Transformer Oil – TCLP 4 Metals and PCB Leaded Gasoline – TCLP Benzene & TCLP Lead
755 Prairie Industrial Parkway, Mulberry, Florida 33860 Telephone (863) 425-4884 Facsimile (863) 774-22200 www.ClarkEnv.com
CDM Smith/Clark Mulberry fl Transportation Pricing
Effective January 21, 2022
PORTAL TO PORTAL (CLARK to CLARK) HOURS AND PREP TIME AT FACILITY
CLARK to CLARK - Mulberry Fl <200 Miles Overtime & Vehicles w/Driver – 4 hour minimum One-Way Weekends Wet Vacuum $120.00 per hour $150.00 per hour Tractor w/Rails $110.00 per hour $140.00 per hour Roll Off Truck/Straight Rails $110.00 per hour $140.00 per hour Tractor with Dump Trailer $110.00 per hour $140.00 per hour Tanker $110.00 per hour $140.00 per hour
Miscellaneous Support Items & Materials Frac Tank Daily Usage $ 60.00 per day/each Frac Tanker Drop Off/Pick Up Varies per Site Roll-off Open Top Daily Usage $ 15.00 per day Closed Top Roll-off $ 20.00 per day Vacuum Box Roll-off $ 50.00 per day Liner – Visqueen $ 45.00 each Flatbed Trailer $ 60.00 per day Hotsy $ 40.00 per hour Pickup Truck $ 25.00 per hour, CLARK to CLARK, $200/day Other Equipment – Flexible Hose $ 3.50 per foot Personal Protective Equipment (PPE) $ 35.00 per man per day Duct Tape $ 14.00 per roll Other 3rd party equipment, labor & items Cost plus 25%
Personnel Senior Project Manager $ 90.00 per hour $120.00 per hour Chemist $ 75.00 per hour $100.00 per hour Project Manager $ 85.00 per hour $110.00 per hour Safety Officer $ 60.00 per hour $ 85.00 per hour Supervisor $ 75.00 per hour $100.00 per hour Equipment Operator $ 65.00 per hour $ 85.00 per hour Field Technician $ 45.00 per hour $ 65.00 per hour Per Diem $ 200 per man per day
Power Washouts (upon completion of job at Clark Environmental, Inc.)
Power Washout Standard (1 hour minimum/disposal) $155.00 per hour Power Washout Standard (1 hour minimum/no disposal) $225.00 per hour Power Washout with confined space entry (1 hour minimum) $300.00 per hour
Overtime is considered -
1) Any time beyond eight (8) consecutive hours on clock; or,
2) Any time between Friday after 4:30 PM and Monday before 8:00 AM (4 hour minimum)
3) Plant after hours - $65.00 per man-hour, two-man minimum, $130.00/hour
Kinard, Joseph M.
From: John Anderson <j.anderson@ersfl.com> Sent: Monday, January 31, 2022 3:49 PM To: Kinard, Joseph M.; Noble, Clint C.
Cc: John Anderson Jr; Valtious Morris Subject: RE: IDW Disposal Bid
The pricing would be as follows:
Transportation Rate, $2.90 Per Mile (all Florida). Based on our main office located at 760 Talleyrand Ave., Jacksonville Fl 32202 Non Hazardous Disposal Rate ( drill cuttings/water/soil) per drum, $60.00 Non Hazardous Disposal Rate, per tote $265.00 Non Hazardous Disposal Rate, Soi in Roll-off, per ton $36.00 ( cannot exceed 14 tons max per roll-off container) Non Hazardous Roll-off Containers Rental , per day $15.00 Roll-off container liner fee, per container $50.00
Hazardous waste disposal fee varies depending on waste stream but transportation rates are $3.10 per mile.
Respectfully, John Anderson, Sr.
ERS CORP, President Jacksonville FL - Little Rock, AR - Houston, TX Cell: 904-545-9833 Email - j.anderson@ersfl.com
Service Matters
From: Kinard, Joseph M. <kinardjm@cdmsmith.com> Sent: Monday, January 31, 2022 2:37 PM To: John Anderson <j.anderson@ersfl.com> Cc: John Anderson Jr <ja.anderson@ersfl.com>; Valtious Morris <v.morris@ersfl.com> Subject: RE: IDW Disposal Bid
Clint asked if you can at least do NE Florida? Maybe a list of counties you’d cover?
Joe Kinard, GIT Geologist III CDM Smith 4651 Salisbury Road, Suite 420 Jacksonville, FL 32256 O: 904.527.6714 M: 904.316.7522 cdmsmith.com
To help protect you r priv acy, Microsoft Office prevented automatic download of this picture from the Internet.
From: John Anderson <j.anderson@ersfl.com> Sent: Monday, January 31, 2022 2:19 PM To: Kinard, Joseph M. <kinardjm@cdmsmith.com> Cc: John Anderson Jr <ja.anderson@ersfl.com>; Valtious Morris <v.morris@ersfl.com> Subject: RE: IDW Disposal Bid
Yes we are interested in Jacksonville only.
John Anderson, Sr.
ERS CORP, President Jacksonville FL - Little Rock, AR - Houston, TX Cell: 904-545-9833 Email - j.anderson@ersfl.com
Service Matters
From: Kinard, Joseph M. <kinardjm@cdmsmith.com> Sent: Monday, January 31, 2022 2:14 PM To: John Anderson <j.anderson@ersfl.com> Subject: IDW Disposal Bid
Hey John, How have you been? I have some work that I thought you may be interesting in bidding on concerning our 10 year FDEP contract work.
If you are interested, I would like to request a cost proposal for the pickup and disposal of all investigation derived waste associated with our FDEP projects for one year.
The proposal should include both non-hazardous and hazardous waste (you can hold off on the hazardous if it’s an issue), liquid and solid, and varying quantities (drums, roll-offs, 250-gallon totes). It should also include rates for sites located throughout the state.
If accepted, the costs outlined in the proposal would be agreed upon for a year before renegotiations. The sites will be spread throughout Florida and include Pensacola, Jacksonville, Tampa, Orlando and South Florida.
The majority of the waste will be non-haz soil and groundwater in 55-gallon drums.
If you are interested, please submit a proposal by the end of next week. Please feel free to reach out with any questions.
Thanks, Joe Kinard, GIT Geologist III CDM Smith 4651 Salisbury Road, Suite 420 Jacksonville, FL 32256 O: 904.527.6714 M: 904.316.7522
To help protect you r priv acy, Microsoft Office prevented automatic download of this picture from the Internet.
McMurray, Kyle
From: Fincham, Kara E. <finchamke@cdmsmith.com> Sent: Monday, March 6, 2023 6:45 AM To: McMurray, Kyle Subject: FW: Bay's Cleaners Subtask 3 Deliverable DC005B
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Morning Kyle, We will want to reconcile the TACO before approving/invoicing for these deliverables.
Thanks Kara
From: Fincham, Kara E.
Sent: Friday, March 3, 2023 12:43 PM To: McMurray, Kyle <Kyle.McMurray@FloridaDEP.gov> Subject: Bay's Cleaners Subtask 3 Deliverable DC005B
Kyle, I just sent the deliverable for Subtask 3 for DC005B—the size of the attachment was 14MB. If you didn’t receive it, please let me know so I can send it via the Sendit File Transfer.
Thanks Kara
Kara E. Fincham, PMP Senior Project Manager 4651 Salisbury Road, Suite 420 Jacksonville, FL 32256 O: 904.527.6716 M: 904.716.8184
To help protect you r priv acy, Microsoft Office prevented automatic download of this picture from the Internet.
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bas s, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW681
DC005B Completion June 30, 2023
This Task Assignment Change Order authorizes CDM Smith (CDM) to supplemental site assessment in accordance with the CDM scope of work, cost estimate, bid documentation, and schedule received on July 26, 2022.
Walsta Jean-Baptiste 850-245-8973 Contractor CDM Contractor
Contractor Shayne Wood Contractor 904-527-6703
ERIC_4918
219 N Magnolia Ave, Ocala, Marion County
Bay's Cleaners
Contractor Contractor
$ 0.00 ✔ $ 185,025.33
$ 0.00
$ 185,025.33
Scope of Work
CDM
Contractor Shayne Wood
CDM Contract Manager
Teresa Booeshaghi
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Documentation of completion of baseline groundwater sampling including groundwater sampling logs and laboratory analytical report(s) - Subtask 2 10/17/2022
Documentation of completion of supplemental site assessment field activities including photolog depicting site conditions before and after well installation, field notes, boring logs, and laboratory analytical reports - Subtask 3
01/16/2023
Supplemental Site Assessment Report and Project Management - Subtasks 1 and 4 03/15/2023
FDEP approval of documentation of completion of baseline groundwater sampling including groundwater sampling logs and laboratory analytical report(s) - Subtask 2 $ 19,177.38
FDEP approval of documentation of completion of supplemental site assessment field activities including photolog depicting site conditions before and after well installation, field notes, boring logs, and laboratory analytical reports - Subtask 3
$ 149,838.60
FDEP approval of Supplemental Site Assessment Report and Project Management - Subtasks 1 and 4 $ 16,009.35
$ 185,025.33
HW681
DC005B