Task Assignment DC035C Summary

This Task Assignment (TA) is a state and local contract indefinite delivery vehicle executed between the State of Florida Department of Environmental Protection (FDEP) and CDM Smith Inc. under the underlying Contract Number HW681. The document authorizes site restoration activities at the Professional Cleaners #2 site located at 6052 San Jose Boulevard, Jacksonville, Duval County, Florida (ERIC_4591). The FDEP project manager is Benjamin Aoki, and the contractor's project manager is Kathy Leggoe. The task assignment was effective June 27, 2024, with a completion date of January 21, 2025.

The scope of work consists of two subtasks: Subtask 1 involves project management activities calculated at 13 percent of direct labor costs, and Subtask 2 encompasses the proper abandonment of five monitoring wells and five vapor extraction wells, including removal of concrete pads and manholes, grouting to the surface via tremie pipe, and restoration to preexisting grade conditions with concrete patch. A Site Restoration Report will be prepared to document field activities. The total task assignment value is $8,793.16 on a fixed unit rate basis, comprising 28 labor hours with direct labor costs of $1,647.92, overhead of $2,224.69 at 135 percent, fringe benefits of $621.26 at 37.7 percent, subcontractor drilling costs of $3,254.90 (including a $2,959.00 quote from Environmental Drilling Service), travel costs of $120.00, field expenses of $475.00, and a completion fee of $449.39. The primary deliverable, a Site Restoration Report and project management documentation, is due 11/21/2024 with a single invoice amount of $8,793.16.

View the file

Other files

File Type Posted
CN-370000-HW681-DC001B.pdf PDF
CN-370000-HW681-DC001E.pdf PDF
CN-370000-HW681-DC002E.pdf PDF
CN-370000-HW681-DC002F.pdf PDF
CN-370000-HW681-DC003B.pdf PDF
CN-370000-HW681-DC005D.pdf PDF
CN-370000-HW681-DC005E.pdf PDF
CN-370000-HW681-DC008B.pdf PDF
CN-370000-HW681-DC008E.pdf PDF
CN-370000-HW681-DC009A.pdf PDF
CN-370000-HW681-DC010A.pdf PDF
CN-370000-HW681-DC010C.pdf PDF
CN-370000-HW681-DC011C.pdf PDF
CN-370000-HW681-DC012D.pdf PDF
CN-370000-HW681-DC013A.pdf PDF
CN-370000-HW681-DC013B.pdf PDF
CN-370000-HW681-DC013C.pdf PDF
CN-370000-HW681-DC013D.pdf PDF
CN-370000-HW681-DC015A.pdf PDF
CN-370000-HW681-DC016C.pdf PDF
CN-370000-HW681-DC017B.pdf PDF
CN-370000-HW681-DC018C.pdf PDF
CN-370000-HW681-DC019B.pdf PDF
CN-370000-HW681-DC01ACO5.pdf PDF
CN-370000-HW681-DC021A.pdf PDF
CN-370000-HW681-DC021B.pdf PDF
CN-370000-HW681-DC021C.pdf PDF
CN-370000-HW681-DC025A.pdf PDF
CN-370000-HW681-DC02BCO2.pdf PDF
CN-370000-HW681-DC02DCO1.pdf PDF
CN-370000-HW681-DC031C.pdf PDF
CN-370000-HW681-DC032D.pdf PDF
CN-370000-HW681-DC033C.pdf PDF
CN-370000-HW681-DC037B.pdf PDF
CN-370000-HW681-DC038B.pdf PDF
CN-370000-HW681-DC038C.pdf PDF
CN-370000-HW681-DC03A.pdf PDF
CN-370000-HW681-DC03CCO1.pdf PDF
CN-370000-HW681-DC03CCO2.pdf PDF
CN-370000-HW681-DC041C.pdf PDF
CN-370000-HW681-DC042B.pdf PDF
CN-370000-HW681-DC042C.pdf PDF
CN-370000-HW681-DC043A.pdf PDF
CN-370000-HW681-DC043B.pdf PDF
CN-370000-HW681-DC04BCO1.pdf PDF
CN-370000-HW681-DC05CCO3.pdf PDF
CN-370000-HW681-DC06BCO4.pdf PDF
CN-370000-HW681-DC07ACO1.pdf PDF
CN-370000-HW681-DC07CCO1.pdf PDF
CN-370000-HW681-DC08CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW681

DC035C Completion January 21, 2025

This Task Assignment authorizes CDM Smith Inc. to perform Site Restoration Activities at Professional Cleaners #2 per their proposed scope of work submitted on

05JUN2024

Benjamin Aoki 850-245-7527 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

CDM Smith Inc.

CDM Smith Inc.

Kathy Leggoe 904-527-6727

ERIC_4591

6052 San Jose Boulevard, Jacksonville, Duval County, Florida

Professional Cleaners #2

✔ $ 8,793.16

$ 8,793.16

Scope of Work

Leslie Samel

Vice President

Leslie Samel Digitally signed by Leslie Samel Date: 2024.06.27 06:50:30 -04'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2024.06.26 13:08:40 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW681

DC035C

Subtasks 1 & 2: Site Restoration Report; Project Management 11/21/2024

Subtasks 1 & 2: Site Restoration Report; Project Management $ 8,793.16

$ 8,793.16

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

TO:

FROM:

DATE:

SUBJECT:

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

HW681 Contract File

Benjamin Aoki, Project Manager

June 26, 2024

Task Assignment DC035C Professional Cleaners #2

ERIC_4591

Site Restoration will permit and abandon wells that are located within the excavation area. Wells will be abandoned bottom up using Portland cement grout. Completion reports will be obtained following well abandonment at wells MW002S, MW004S, MW004I, MW004D, MW005S, MW005I, MW005D, MW008S, MW008I, and MW008D.

This Task Assignment authorizes CDM Smith Inc., hereby referred to as CDM, to conduct Site Restoration Activities at Professional Cleaners #2, Duval County, Florida (FL). Environmental Drilling Service (EDS) was selected as the lowest responsive and responsible bidder. Specific subtasks are detailed below:

Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.

Subtask 2: Monitoring Well and Vapor Extraction Well Abandonment CDM will properly abandon five (5) monitoring wells (MWs) and five (5) Vapor Extraction Wells (VEWs). All boreholes will be properly grouted to the surface via tremie pipe and restored to preexisting grade conditions with concrete patch.

A Site Restoration Report will be prepared to summarize the field activities conducted.

The final cost for Task Assignment DC035B is $8,793.16 with 28 labor hours.

recommendations, source removal activities will be conducted. The following sequence of activities is proposed for the source removal. The excavation activities will be conducted using a track-mounted excavator. Initially the deeper soils (up to 12 feet below land surface) with impacts will be excavated, stockpiled, and loaded for offsite disposal. Once the deeper

FDEP COST ESTI MATEContractor: CDM Smith Inc.

Date: 6/5/2024

Task #: DC035C Proposal SubTask 1 Project Management SubTask 6

Site: Professional Cleaners #2 SubTask 2 Site Restoration Field and Reporting SubTask 7

Activity/Phase: Site Restoration SubTask 3 SubTask 8

Project Manager: Kathy Leggoe SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$76.49 Project Manager 3 2.5 $100.97 Senior Officer 0 0 0 0 0 0 0 0 0 0

$86.25 Senior Technical Expert 0 0 0 0 0 0 0 0 0 0 $76.49 Project Technical Leader 0 0 0 0 0 0 0 0 0 0 $76.49 Project Manager 6 6.0 0.0 0 0 0 0 0 0 0 $71.58 Senior Professional 0 0 0 0 0 0 0 0 0 0 $52.60 Professional II 19 19.0 0.0 0 0 0 0 0 0 0 $34.90 Professional I 0 0.0 0 0 0 0 0 0 0 0 $54.63 Senior Technician 0 0.0 0 0 0 0 0 0 0 0 $30.76 Staff Technician 0 0 0 0 0 0 0 0 0 0 $42.43 Project Administration 0 0 0 0 0 0 0 0 0 0 $42.53 Senior Support Services 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 28 2.5 25.0 0.0 0 0 0 0 0 0 0

Direct Labor $1,647.92 $189.58 $1,458.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $2,224.69 $255.93 $1,968.76 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $621.26 $71.47 $549.79 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,493.87 $516.98 $3,976.89 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

FDEP COST ESTI MATEContractor: CDM Smith Inc.

Date: 6/5/2024

Task #: DC035C Proposal SubTask 1 Project Management SubTask 6

Site: Professional Cleaners #2 SubTask 2 Site Restoration Field and Reporting SubTask 7

Activity/Phase: Site Restoration SubTask 3 SubTask 8

Project Manager: Kathy Leggoe SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $2,959.00 $2,959.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $2,959.00 $2,959.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $295.90 $295.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $3,254.90 $3,254.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $435.00 $435.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $475.00 $475.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $8,343.77 $516.98 $7,826.79 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $449.39 $51.70 $397.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $8,793.16 $568.68 $8,224.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Professional Cleaners #2 SUBTASK 2: Site Restoration Field and Reporting

DATE: 6/5/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

PTL/PM 2

Professional II Field Preparation 1

Mobilization (1 hour each way) 2

Site Restoration Deliverable 5

PTL/PM 6

Professional II 19

TOTAL LABOR 25

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 Day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

EDS MW and VEW Abandonment $2,959.00 $2,959.00

TOTAL $2,959.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 Day 1 $40.00 Construction/O&M/Pilot Kit $360.00 Each 1 $360.00 Construction/O&M Supplies $75.00 Each 1 $75.00

TOTAL EQUIPMENT $475.00

MW and VEW Abandonment Oversight

Site Access Coordination with Owner

Preparation of Abandonment Memo Technical Evaluation of Abandonment/Restoration

FINAL --7/24/96

4651 Salisbury Rd., Suite 420, Jacksonville, FL 32256 | tel: 904-731-7109

June 5, 2024

Mr. Benjamin Aoki

Environmental Specialist II

Florida Department of Environmental Protection

Waste Site Cleanup Section

2600 Blair Stone Road, MS 4520

Tallahassee, FL 32399-2400

Subject: Site Restoration

Professional Cleaners #2 (ERIC_4591)

6052 San Jose Boulevard, Jacksonville, Duval County, Florida

Dear Mr. Aoki:

CDM Smith Inc. (CDM Smith) is pleased to respond to the Florida Department of Environmental

Protection (FDEP) Task Assignment Request to provide supplemental site assessment (SSA) services for the Professional Cleaners #2 site under Contract Number HW681. The scope of work and project schedule are described below, and the cost estimate for is attached in Table 1.

CDM Smith submitted a Site Assessment Report (SAR) to the FDEP on April 8, 2024. On May 7, 2024, FDEP approved the site for closure and the issuance of a Site Rehabilitation Completion Order (SRCO).

Once FDEP issues the SRCO and the 21-day period with no filing for administrative hearing, the FDEP will require site restoration to include the abandonment of all monitoring wells and vapor extraction wells.

Scope of Work

CDM Smith presents the following proposed subtasks to complete site restoration.

Subtask 1 – Project Management

Project management activities performed under this task consist of administrative functions required to maintain the project schedule, adhere to budget, and deliver the quality of the work products defined by CDM Smith’s quality standards. CDM Smith will prepare and submit invoices upon approval of each deliverable or milestone completion.

Project Kickoff and Progress Meetings

CDM Smith expects to have a kickoff meeting or telephone conference with the FDEP to review the status of the project and address FDEP comments regarding the Task Assignment. CDM Smith will prepare meeting agendas and notes as part of this task.

Project Quality Technical Review

CDM Smith’s Quality Management System guidelines will be followed. Internal quality reviews will be conducted on plans and on investigation findings and reports.

Mr. Benjamin Aoki

4651 Salisbury Rd., Suite 420, Jacksonville, FL 32256 | tel: 904-731-7109

Project Status Reports

CDM Smith’s Project Manager will prepare and submit monthly status reports to accompany each invoice throughout the duration of this project. The Project Manager will also discuss the status of the project with the FDEP on a bi-weekly basis until the project is complete.

Subtask 2 – Monitoring Well and Vapor Extraction Well Abandonment

CDM Smith will properly abandon five (5) monitoring wells (MWs) and five (5) Vapor Extraction Wells

(VEWs) with a licensed Florida Water Well Contractor. This includes the removal of the 2’x2’ concrete well pads when applicable, manhole covers, and the 2” diameter PVC for VEWs. All boreholes will be properly grouted to the surface via tremie pipe and restored to preexisting grade conditions with concrete patch.

A Site Restoration Report will be prepared to summarize the field activities conducted.

Deliverables: Site Restoration Report to include field documentation, and paid invoices to subcontractors.

Subcontractors:

Drillers

Bids to abandon MWs and VEWs were submitted to Groundwater Protection, Environmental Drilling

Service (EDS) and Preferred Drilling Solutions (PDS). EDS was selected as the licensed driller with the lowest bid, as shown in Attachment A, which includes a summary of the subcontractor cost comparisons.

Assumptions

CDM Smith will communicate with the FDEP in a timely manner is schedule delays are encountered and will prepare necessary paperwork for change orders.

Schedule

CDM Smith’s proposed project schedule is shown below, with targeted completion within four months.

The deliverable and due date is provided in Table 2.

Mr. Benjamin Aoki

4651 Salisbury Rd., Suite 420, Jacksonville, FL 32256 | tel: 904-731-7109

Table 2: Deliverable Schedule

Subtask 2 Deliverable:

Due Date:

Site Restoration Report

4 Months past Notice to Proceed/Task Assignment Issuance

CDM Smith looks forward to working on this important project. Feel free to contact me at 904-527-6727 or by email with any questions or comments.

Sincerely, Kathy R. Leggoe, P.G., PMP

Geologist / Project Manager

CDM Smith Inc.

LeggoeKR@CDMSmith.com cc: Kara. E. Fincham, PMP, CDM Smith

David L. Anderson, P.G., CDM Smith

KYLE M TURNER

Oval

KYLE M TURNER

Oval

KYLE M TURNER

Oval

KYLE M TURNER

Oval

KYLE M TURNER

Oval

KYLE M TURNER

Oval

KYLE M TURNER

Oval

KYLE M TURNER

Oval

KYLE M TURNER

Oval

KYLE M TURNER

Oval

Driller

Item Est. Qty. Units Rate Total Est. Qty. Units Rate Total Est. Qty. Units Rate Total

Mobilization/Demobilization including crew HASP (1) and Water Mgt.

District Well Installation Permits 1 each $800.00 $800.00 1 each $600.00 $600.00 1 each $650.00 $650.00

Construct Temporary Decontamination Pad 0 lump sum NA NA 1 lump sum NA NA 0 lump sum NA NA

Crew Per Diem 0 night NA NA 0 night NA NA 0 night NA NA

Night Work Allowance/After Work Hours Surcharge 0 each NA NA 0 each NA NA 0 each NA NA

Well Abandonment: 1" diameter, with removal of 2'x2' pad/8" manhole, concrete patch 88 per liner foot $6.00 $528.00 NA NA NA NA NA NA NA NA

Well Abandonment: 2" diameter (0.75-2" PDS&EDS), with removal of

2'x2' pad/8" manhole, concrete patch 38 per liner foot $8.00 $304.00 151 each $9.00 $1,359.00 151 per linear foot $12.00 $1,812.00

Removal of 8" BD Manhole Lid/Ring and Fill w/concrete 4 each $75.00 $300.00 10 each $100.00 $1,000.00 NA NA NA NA

2'x2 Well Pad Removal and Patch (exterior)/Donut Pad Removal and

Patch - PDS 1 each $100.00 $100.00 9 each Included Included 10 each $125.00 $1,250.00

VEW Abandonment w/removal w/8" BD lid/Ring and Fill w/concrete

(GWP)

5 each $200.00 $1,000.00 NA NA NA NA NA NA NA NA

Permits 1 each Included Included 1 each Included Included 2 each $25.00 $50.00

Total Project duration 1 days 1 days 1 days

$3,032.00 $2,959.00 $3,762.00Total Total Total

Subcontractor Evaluation

Professional Cleaners #2

Well Abandonment

Groundwater Prtotection (GWP) Environmental Drilling Service (EDS) Preferred Drilling Solutions (PDS)

Attachment A: Subcontractor Quotes Professional Cleaners #2

ERIC_4591

Jacksonville, Duval County, Florida

Sonic Auger DPT Injection Well Abandonment

DATE: 5/14/2024

ESTIMATE #: 524033

CDM Smith

ID QTY Unit Rate TOTAL

1 1 each 800.00$ 800.00$

2 night 300.00$ -$

3 88 each 6.00$ 528.00$

4 38 each 8.00$ 304.00$

5 4 each 75.00$ 300.00$

6 1 each 100.00$ 100.00$

7 5 each 200.00$ 1,000.00$

8 Permits: (MW Only - Required w/ No Fee. N/A for VE Wells)

Subtotal 3,032.00$

Todd Hodgson

Todd Hodgson TOTAL 3,032.00$

Partner

If you have any questions concerning this proposal contact Todd Hodgson at (407) 426-7885 at Todd@drillprollc.com.

DESCRIPTION

Mobilization

Per Diem - 2 Man Crew Est. (Min. Hotel Cost + $50/per man)

Completion: 1 day

1" PVC Well Abandonment (Total of 88')

THANK YOU FOR YOUR BUSINESS!

Jacksonville, Florida 4010 W Boy Scout Blvd

(813) 262-8851 2" Well Abandonment w/Removal of Surface Complietion

(3) 1" x 22' MW Abandonment w/Removal of 8" Manhole Lid/Ring Fill with Concrete Patch (Concrete)

(1) 2" x 38' MW Abandonment w/Removal of 8" Lid/Ring Fill with Concrete Patch (Concrete)

(5) 2"x 5' SVE Well Abandonment w/Removal of 8" Manhole Lid/Ring and Fill w/Concrete Patch (Concrete)

Locations must be accessible with track mounted DPT Rig

Damage to utilities on private property are the responsibility of the client

Utility Locates on Private Property are the responsibility of the client

2" x 5' VEW Abandonment w/Removal w/8" BD Lid/Ring and Fill with

Concrete Patch

Removal w/8" BD Manhole Lid/Ring and Fill with Concrete Patch

Removal 2' x 2' Conrete Pad w/8" BD Manhole/Rake Level (Grass)

2" PVC Well Abandonment (Total of 38')

"Actual quantities used and days onsite will be invoiced"

PROJECT

Professional Cleaners #2 6052 San Jose Blvd.

Kyle Turner, MS, GIT

CUSTOMER

Project Description:

Tampa, Florida 33607

(1) 1" x 22' MW Abandonment w/Removal of 8" BD Manhole w/ 2' x 2' Pad, Rake Level (Grass)

2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586

Preferred Drilling Solutions, Inc.

8820 66th St, Pinellas Park, FL 33782

Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com

Date: 5/14/24 FAC ID#: ERIC_4591

*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner

Unit Unit Rate Number of Units Extended Price

Rig Type: Auger/Mud Rotary_____

HSA Drilling & Split Spoon Collection (continuous or 5' intervals) (can be used in conjunction with well installation)

<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00

Borehole Grouting

4 - inch borehole diameter per foot $0.00 6 - inch borehole diameter per foot $0.00 8 - inch borehole diameter per foot $0.00

1" - 2" Well Installation (includes screen, riser, sand pack, seal and grout)

<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00

4" Well Installation (includes screen, riser, sand pack, seal and grout)

<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00

Double Cased Well $0.00

6" Surface Casing per foot $0.00 per well $0.00

3/4"- 2" Well Abandonment (includes grouting) per foot $12.00 151 $1,812.00 3"- 4" Well Abandonment (includes grouting) per foot $0.00 5"- 6" Well Abandonment (includes grouting) per foot $0.00 2' x 2' Well Pad Removal and Patch each $125.00 10 $1,250.00

Mobilization roundtrip $650.00 1 $650.00

Per Diem per crew / per night $0.00 DOT Approved 55-gal Drum each $0.00 each $25.00 2 $50.00

$0.00

$0.00

$0.00 Standby/Delay/Difficult Access Time per hour $0.00 Additional Development Time per hour $0.00 Additional Decontamination Time per hour $0.00

TOTAL QUOTE PRICE $3,762.00

Project No.:

Signature and Title of Person Submitting Quote: _________________________________ Austin Bonacum, Estimator Date: 5/14/24

Days to Complete Scope of Work: 1

6052 San Jose Blvd, Jacksonville, Duval County, FL

Well Completion (includes MH w/ cover, concrete pad, locking well cap, DRILLING

MISCELLANEOUS

Permits

Consultant Name: CDM Smith

Site Name & Location: Professional Cleaners #2

PROPOSED SCOPE OF WORK:

Abandon (10) 1" - 2" wells between 5' - 38', total depth: 151', remove pads and manholes, restore grade

CDM Smith, Professional Cleaners #2, Jacksonville, FL (abandonment)

COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_v2.pdf
Subtask 1 – Project Management
Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling
Subtask 3 –Monitoring Well Installation
Right-of-Way Permitting
Utility Locate and Drilling Subcontractors
Monitoring Well Installation
Subtask 4 – Monitoring Well Sampling and Surveying
Laboratory Analysis
Trip Report
Subtask 5 – Investigation Derived Waste
Trip Report
Subtask 6 – Supplemental Site Assessment Report
Invoice and Deliverable Schedule:
ATTACHMENT A
ATTACHMENT B
ATTACHMENT C
ATTACHMENT D
ATTACHMENT E
ATTACHMENT F
Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v1.pdf
Cost Estimate
Subtask 2
Subtask 3
Subtask 4
Subtask 5
Subtask 6
2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev1_12-12-22.pdf
Table 1 for SAWP
Monitoring Well Locations
Utility Locate Bids_Compiled.pdf
Geosyntec Utility-272_Geotek_1500
Geoview Utility Quote_2000_COT FTF SIS
Tallahassee Fire Training Division_V1_Bloodhound_3700
Drilling Bids_Compiled.pdf
PDS_Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (sonic)
Direct Push
City of Tallahassee Fire Training Site_GW Protection PFAS Free Water Estimate Email
Cascade_Geosyntec Consultants, Inc. - City of Tallahassee Fire Training Facility - PN221026-118844
GW Protection_Geosyntec (T) 1022060 S.pdf
Invoice
Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (MOT).xlsx.pdf
Sheet1
COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v1.pdf
Subtask 1 – Project Management
Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling
Subtask 3 –Monitoring Well Installation
Right-of-Way Permitting
Utility Locate and Drilling Subcontractors
Monitoring Well Installation
Subtask 4 – Monitoring Well Sampling and Surveying
Laboratory Analysis
Trip Report
Subtask 5 – Investigation Derived Waste
Trip Report
Subtask 6 – Supplemental Site Assessment Report
Invoice and Deliverable Schedule:
ATTACHMENT A
ATTACHMENT B
ATTACHMENT C
ATTACHMENT D
ATTACHMENT E
ATTACHMENT F
COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v2.pdf
Subtask 1 – Project Management
Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling
Subtask 3 –Monitoring Well Installation
Right-of-Way Permitting
Utility Locate and Drilling Subcontractors
Monitoring Well Installation
Subtask 4 – Monitoring Well Sampling and Surveying
Laboratory Analysis
Trip Report
Subtask 5 – Investigation Derived Waste
Trip Report
Subtask 6 – Supplemental Site Assessment Report
Invoice and Deliverable Schedule:
ATTACHMENT A
ATTACHMENT B
ATTACHMENT C
ATTACHMENT D
ATTACHMENT E
ATTACHMENT F
Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v2.pdf
Cost Estimate
Subtask 2
Subtask 3
Subtask 4
Subtask 5
Subtask 6
2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev2.pdf
Table 1 for SAWP
Monitoring Well Locations

File details come from the government source that posted it. Updated .