CN-370000-HW681-DC02CCO1.pdf
PDF 2 MB Posted
- Contract number
- HW681
- Issued by
- Florida
About this file
This is a Task Assignment Change Order (TACO No. 1) for Contract HW681 between the State of Florida Department of Environmental Protection (Department) and CDM Smith Inc. (Contractor), with Benjamin Aoki serving as the Department's Project Manager and Clint Noble as the Contractor's Project Manager. The contract pertains to environmental remediation work at the First Coast Cleaners site (ERIC_4535) located at 610 North 3rd Street, Jacksonville Beach, Florida. The underlying contract is a fixed unit rate arrangement, and this change order was executed on June 10, 2024, with an effective date of June 14, 2024.
The change order reconciles Work Change Directive #1 and adjusts labor hours to reflect actual work completed. The amended Task Assignment value is increased from $35,063.36 to $43,308.55, representing a total increase of $8,245.19. The scope of work encompasses three subtasks: preparation of an Interim Source Removal Plan (ISRP) with a deliverable due date of March 8, 2024; project management; and bid specifications and cost estimation. The adjustments include additional labor hours for Clint Noble (10 hours), Steve Cobert (9 hours), and Logan Mueller (33 hours), primarily for FDEP meetings, coordination with the site owner, ISRP bid specifications, and FDEP-directed changes to bid specifications. The total labor allocation is 212.90 man hours. The completion date remains June 14, 2024, with invoicing contingent upon DEP approval of the ISRP and project management deliverables.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
DC002C 1 HW681
Benjamin Aoki 850-245-7527 CDM Smith Inc.
Clint Noble 904-527-6715
ERIC_4535
First Coast Cleaners
$ 43,308.55 $ 35,063.36
$ 43,308.55 $ 35,063.36
06/14/2024 06/14/2024 0
1 1 1
CDM Smith Inc.
Leslie Samel
CDM Contract Manager
Leslie Samel Digitally signed by Leslie Samel Date: 2024.06.10 13:43:56 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.06.10 13:26:14 -04'00'
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
TO:
FROM:
DATE:
SUBJECT:
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
HW681 Contract File
, Manager
SITE : First Coast Cleaners
SUBTASK: 2 - ISRP
DATE: 5/16/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Technical Lead S. Cobert Technical Design Lead/EOR/Site Visit 24
FDEP Meetings, coordination with Site Owner, additional ISRP bid specs 9
Project Manager C. Noble FDEP Meetings, coordination with Site Owner 10
Professional I L. Mueller ISRP Engineering Support/Site Visit 44
FDEP-directed changes to bid specs, including possible Site Visit 33
Professional II M. Blanton ISRP Figure Support 12
Senior Professional M. Passaro ISRP Geotechnical and Structural Support 2
Senior Technical Expert T. Duffy Technical Design 8
Total Hours:
S.Cobert 33
C. Noble 10
L. Mueller 77
M. Blanton 12
M. Passaro 2
T. Duffy 8
TOTAL LABOR 142
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 0 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00
$0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNITS USEAGE Subtotal Baker Design Build Structural Engineering $10,500 1 $10,500.00
TOTAL $10,500.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
$0.00
TOTAL EQUIPMENT $0.00
SUBTASK: 3 - Bid Specifications and Cost Estimate
DATE: 5/16/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Technical Lead S. Cobert Technical Design Lead/EOR/ Q+A 10
Professional II W. Taylor Pre-Bid Doc Prep (3 visits) 12
Pre-Bid Meetings on site (3 meetings) 12
Preparation of bid summaries 4
Professional I L. Mueller Bid Specification Preparation 14
Total Hours:
S. Cobert 10
W. Taylor 28
L. Mueller 14
TOTAL LABOR 52
VEHICLE TYPE RATE UNIT USEAGE
Truck Pre-Bid Meetings $120.00 days 3 $360.00
TOTAL VEHICLE $360.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00
$0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNITS USEAGE Subtotal
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 per day 3 $120.00
TOTAL EQUIPMENT $120.00
SUBTASK: 2 - ISRP
DATE: 5/16/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Technical Lead S. Cobert Technical Design Lead/EOR/Site Visit 0
FDEP Meetings, coordination with Site Owner, additional ISRP bid specs 9
Project Manager C. Noble FDEP Meetings, coordination with Site Owner 10
Professional I L. Mueller ISRP Engineering Support/Site Visit 0
FDEP-directed changes to bid specs, including possible Site Visit 33
Professional II M. Blanton ISRP Figure Support 0
Senior Professional M. Passaro ISRP Geotechnical and Structural Support 0
Senior Technical Expert T. Duffy Technical Design 0
Total Hours:
S.Cobert 9
C. Noble 10
L. Mueller 33
M. Blanton 0
M. Passaro 0
T. Duffy 0
TOTAL LABOR 52
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 Day 0 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00
$0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNITS USEAGE Subtotal Baker Design Build Structural Engineering $10,500 0 $0.00
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
Site Name: Site ID #:
Contract #: Contractor:
� Reason for Work Change Directive :
� Description of Work Change Directive :
� Attachments (if applicable, list documents supporting change):
� Costs (if negotiated unit costs, provide information below):
WCP WCD 07-2018
Authorized Contractor Signature:
Authorized FDEP Signature:
WORK CHANGE DIRECTIVE FORM
FDEP Supervisor Approval:
(if applicable)
Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.
Task Assignment #: Work Change Directive #:
Maximum Estimated Increase in Task Amount:
First Coast Cleaners ERIC_4535
HW681 CDM Smith
DC002C 1
FDEP-directed revisions to bid quotes per request of OGC plus site visit
Work with General Contractor who does interior restoration for kitchen and bathroom to get more detailed bids, site visit, extra site owner and FDEP coordination
CEF/LOE
$8300
$ 8,300.00
Kara E. Fincham Digitally signed by Kara E. Fincham DN: C=US, E=finchamke@cdmsmith.com, O=CDM Smith, CN=Kara E. Fincham Date: 2024.04.10 09:32:03-04'00'
Benjamin Aoki Digitally signed by Benjamin Aoki Date: 2024.04.15 12:30:35 -04'00'
From: Noble, Clint C.
To: Aoki, Benjamin Cc: Grubbs, Benjamin; Fincham, Kara E.
Subject: RE: First Coast Cleaners TACO - Date: Sunday, May 19, 2024 5:40:28 PM Attachments: HW681 CEF (CDM Smith) Original - First Coast Cleaners.xlsx
HW681 CEF (CDM Smith) Delta - First Coast Cleaners.xlsx HW681 CEF (CDM Smith) Final - First Coast Cleaners.xlsx (signed) Work Change Directive Form FCC WCD#1 DC002C.pdf
Importance: High
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Benjamin, my mistake. Please use the attached. I realized we went over the WCD amount, so I removed the $120 vehicle charge from ST2.
Total Delta/Change addition is $8,245.18 and the new TA total is $43,308.55.
Thanks and I hope you all are recovering from the storm.
Clint
From: Noble, Clint C. <noblecc@cdmsmith.com> Sent: Friday, May 17, 2024 9:29 AM To: Aoki, Benjamin <Benjamin.Aoki@FloridaDEP.gov> Cc: Grubbs, Benjamin <Benjamin.Grubbs@FloridaDEP.gov>; Fincham, Kara E.
<finchamke@cdmsmith.com> Subject: First Coast Cleaners TACO - Importance: High
Benjamin, Please see attached TACO. This covers work CDM has done to date at FCC and we need it processed so that we can submit one single invoice for this TA DC002C before we proceed with remediation under a new TA. This TA ends 6/14/24.
Below is a summary of the TACO:
Subtask 2:
Added 10 hours for C. Noble for FDEP Meetings, coordination with Site Owner including site review/inspection, and solicitation of restoration bids.
Added 9 hours for S. Cobert for FDEP Meetings, coordination with Site Owner, additional ISRP bid specs relative to site restoration Added 33 hours for L. Mueller for “FDEP directed changes to bid specs (drawings), solicitation of restoration bids including Site Visit with bidders” Added 1 Day of Truck useage
Subtask 3: No changes
The rounding error is $0.01.
Call my cell with any questions anytime!
Clint Noble, P.G., PMP Senior Project Manager CDM Smith 4651 Salisbury Road, Suite 420 Jacksonville, FL 32256 O: 904.527.6715 M: 904-625-2125 noblecc@cdmsmith.com Connect with me on LinkedIn cdmsmith.com