This document is a Task Assignment Change Order (TACO #1) issued by the State of Florida Department of Environmental Protection (FDEP) to CDM Smith Inc. for work at the First Coast Cleaners site (ERIC_4535) located at 610 North 3rd Street, Jacksonville Beach, Florida. The original Task Assignment (DC002B) was executed under Contract Number HW681. Kyle McMurray serves as the FDEP Project Manager, while Shayne Wood represents CDM Smith Inc. as the Contractor's Project Manager. The change order was authorized by Teresa Booeshaghi for FDEP and Shayne Wood for CDM Smith Inc., effective August 10, 2023.

The change order reconciles Work Change Directive #1 and increases the total Task Assignment value from $103,860.72 to $105,603.35, representing a cost increase of $1,742.63. The price adjustment results from additional laboratory costs associated with SPLP (Synthetic Precipitation Leaching Procedure) analysis for seven soil samples that exceeded Leachability Soil Cleanup Target Levels. The amended compensation is structured as a fixed unit rate with a total Task Assignment value of $105,603.35. Deliverables consist of Supplemental Site Assessment Fieldwork and Project Management (due July 30, 2023) and a Supplemental Site Assessment Report (due October 30, 2023), with invoice payments allocated as $85,986.87 for Subtasks 1 and 2 (laboratory analytical results, field documentation, and project management) and $19,616.48 for Subtask 3 (the assessment report).

View the file

Other files

File Type Posted
CN-370000-HW681-DC001B.pdf PDF
CN-370000-HW681-DC001E.pdf PDF
CN-370000-HW681-DC002E.pdf PDF
CN-370000-HW681-DC002F.pdf PDF
CN-370000-HW681-DC003B.pdf PDF
CN-370000-HW681-DC005D.pdf PDF
CN-370000-HW681-DC005E.pdf PDF
CN-370000-HW681-DC008B.pdf PDF
CN-370000-HW681-DC008E.pdf PDF
CN-370000-HW681-DC009A.pdf PDF
CN-370000-HW681-DC010A.pdf PDF
CN-370000-HW681-DC010C.pdf PDF
CN-370000-HW681-DC011C.pdf PDF
CN-370000-HW681-DC012D.pdf PDF
CN-370000-HW681-DC013A.pdf PDF
CN-370000-HW681-DC013B.pdf PDF
CN-370000-HW681-DC013C.pdf PDF
CN-370000-HW681-DC013D.pdf PDF
CN-370000-HW681-DC015A.pdf PDF
CN-370000-HW681-DC016C.pdf PDF
CN-370000-HW681-DC017B.pdf PDF
CN-370000-HW681-DC018C.pdf PDF
CN-370000-HW681-DC019B.pdf PDF
CN-370000-HW681-DC01ACO5.pdf PDF
CN-370000-HW681-DC021A.pdf PDF
CN-370000-HW681-DC021B.pdf PDF
CN-370000-HW681-DC021C.pdf PDF
CN-370000-HW681-DC025A.pdf PDF
CN-370000-HW681-DC02BCO2.pdf PDF
CN-370000-HW681-DC02DCO1.pdf PDF
CN-370000-HW681-DC031C.pdf PDF
CN-370000-HW681-DC032D.pdf PDF
CN-370000-HW681-DC033C.pdf PDF
CN-370000-HW681-DC037B.pdf PDF
CN-370000-HW681-DC038B.pdf PDF
CN-370000-HW681-DC038C.pdf PDF
CN-370000-HW681-DC03A.pdf PDF
CN-370000-HW681-DC03CCO1.pdf PDF
CN-370000-HW681-DC03CCO2.pdf PDF
CN-370000-HW681-DC041C.pdf PDF
CN-370000-HW681-DC042B.pdf PDF
CN-370000-HW681-DC042C.pdf PDF
CN-370000-HW681-DC043A.pdf PDF
CN-370000-HW681-DC043B.pdf PDF
CN-370000-HW681-DC04BCO1.pdf PDF
CN-370000-HW681-DC05CCO3.pdf PDF
CN-370000-HW681-DC06BCO4.pdf PDF
CN-370000-HW681-DC07ACO1.pdf PDF
CN-370000-HW681-DC07CCO1.pdf PDF
CN-370000-HW681-DC08CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. ☐ There are no changes to the TA compensation.

☐ The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO ☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. ☐ There are no changes to the TA Expiration Date.

☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. ☐ There are no changes to the Attachments.

☐ Attachment ___ is replaced with Attachment -____.

7. ☐ No Additional Changes.

☐ Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

DC002B 1 HW681

This Task Assignment Change Order reconciles WCD #1

Kyle McMurray 850-245-8973 Contractor Contractor

Contractor Contractor

Contractor

CDM Smith Inc.

Shayne Wood 904-527-6703

ERIC 4535

First Coast Cleaners

✔ $ 105,603.35 $ 103,860.72

$ 105,603.35 $ 103,860.72 ✔ Completion

Completion 0

✔ 1 1 1

CDM Smith Inc.

Shayne Wood

CDM Contract Manager

8/10/2023

Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2023.08.10 14:09:24-04'00'

Teresa Booeshaghi

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.08.10 11:21:08 -04'00'

8/10/2023

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01_18

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW681

DC002B

$ 105,603.35

Supplemental Site Assessment Fieldwork & Project Management

Supplemental Site Assessment Report

Subtasks 1 and 2: Laboratory analytical results, and field documentation, data tables and paid invoices to subcontractors + Project Management

Subtask 3: Supplemental Site Assessment Report

07/30/2023

10/30/2023

$ 19,616.48

$ 85,986.87

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

TO: HW681 Contract File

FROM: Kyle McMurray, Contract Manager

DATE: August 10th, 2023

SUBJECT: Negotiation Summary

Task Assignment DC002B

TACO #1

ERIC_4535

This Task Assignment Change Order is to reconcile WCD #1. In accordance with the CDM Smith (CDM) Change Order Request and cost estimate forms received on July 27th, 2023.

Changes to the original CDM scope of work include the following:

Subtask 2: Supplemental Site Assessment Field Work Subtask 2 has an overall price increase due to additional laboratory costs associated with SPLP.

The overall cost increase related to this Change Order is $1,742.63

The FDEP project manager agrees to the scope of work and final cost associated with this Task Assignment Change Order. The final cost total for Task Assignment DC002B is $105,603.35.

FDEP COST ESTIMATEContractor: CDM Smith, Inc.

Date: 7-Mar-23

Task #: SubTask 1 Project Management SubTask 6

Site: First Coast Cleaners SubTask 2 2 - Supplemental Site Assessment Field Work SubTask 7

Activity/Phase: SSAR SubTask 3 3 - SSAR and Geotechnical/Structural Evaluation SubTask 8

Project Manager: Clint Noble SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$60.42 Project Technical Lead/Pr C. Noble 44.8 44.8 $0.00 Senior Officer 0.0 0.0 0.0 0 0 0 0 0 0 0

$69.63 Senior Technical Expert S. Cobert 32.0 28.0 4.0 0 0 0 0 0 0 0 $60.42 Project Technical Lead/Pr C. Noble 42.0 34.0 8.0 0 0 0 0 0 0 0 $43.01 Professional II A. Ryan 203.0 163.0 40.0 0 0 0 0 0 0 0

0.0 0 0 0 0 0 0 0 $33.43 Professional I K. Profitko 40.0 0.0 40.0 0 0 0 0 0 0 0

0.0 0.0 0.0 0 0 0 0 0 0 0 $57.50 Sen Geotechnical PE M. Passaro 24.0 0.0 24.0 0 0 0 0 0 0 0

0.0 0.0 0.0 0 0 0 0 0 0 0 $33.50 Professional I L. Mueller 138.0 98.0 40.0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 523.80 44.80 323.00 156.00 0 0 0 0 0 0 0

Direct Labor $23,545.84 $2,708.81 $14,297.55 $6,539.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $31,786.88 $3,656.89 $19,301.69 $8,828.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $8,876.78 $1,021.22 $5,390.18 $2,465.38 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $64,209.50 $7,386.92 $38,989.42 $17,833.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF CDM Smith Page 1

Task #: SubTask 1 Project Management SubTask 6

Site: First Coast Cleaners SubTask 2 2 - Supplemental Site Assessment Field Work SubTask 7

Activity/Phase: SSAR SubTask 3 3 - SSAR and Geotechnical/Structural Evaluation SubTask 8

Project Manager: Clint Noble SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $2,160.00 $2,160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $2,160.00 $2,160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $11,325.00 $11,325.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin $770.00 $770.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Hepaco (test pits) $1,200.00 $1,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Locate Firm $900.00 $900.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $14,195.00 $14,195.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $1,419.50 $1,419.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $15,614.50 $15,614.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $10,560.40 $10,560.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping+prep $1,630.00 $1,630.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $12,190.40 $12,190.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $1,588.00 $1,588.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Other $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $2,520.00 $2,520.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW drums) $700.00 $700.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $5,008.00 $5,008.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $99,182.40 $7,386.92 $73,962.32 $17,833.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $6,420.95 $738.69 $3,898.94 $1,783.32 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $105,603.35 $8,125.61 $77,861.26 $19,616.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost from Prior CEF: $103,860.72 Manual Entry Cost from Delta CEF; $1,742.65 Manual Entry

Cost (Prior + Delta): $105,603.37 Auto-Calculated Rounding Error: ($0.02) Auto-Calculated

Final Total Cost: $105,603.35 Auto-Calculated

REV: 02/03 CEF CDM Smith Page 2

SITE : First Coast Cleaners SUBTASK: 2 - Supplemental Site Assessment Field Work

DATE: 3/7/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

2.1 - GW Sampling

Senior Technical ExpeS. Cobert Interpretation of Lab Data Eval 4

Interpretation of Lab Data Eval (SPLP) 2

FDEP-Directed Workplan Additions 8

PTL/PM C. Noble Prepare Field Scope of work 4

Determine Field Activities based on Field Data 4

FDEP-Directed Workplan Additions 8

Preparation of data summaries 2

Preparation of data summaries (SPLP) 2

Professional II A. Ryan Mobilization/Demob (2 trips) 8

Field Preparation 1

Arrange for site access with owner 2

Prepare Sample Kit Request 1

Prepare HASP 1

Sample Wells (14) 22

Preparation of data summaries 4

2.2 Soil Borings, MAGS/VMP Install, MAGS testing, and Test Pits Senior Technical ExpeS. Cobert Sr. Level Data Evaluation 4

FDEP-Directed Workplan Additions 10

PTL/PM C. Noble Prepare Field Scope of work 4

FDEP-Directed Workplan Additions 10

Professional II A. Ryan Site Inspection 8

Mobilization/Demob (8 trips) 32

Field Preparation 2

Arrange for site access with owner 1

Prepare Sample Kit Request 1

Concrete Coring, Soil Borings, OVA, soil samples, MAGS/VMP wells 50

MAGS testing 10

Test Pits 20

Professional I L. Mueller Utility Locate Oversight 8

Concrete Coring, Soil Borings, OVA, soil samples, MAGS/VMP wells 50

MAGS testing 10

Test Pit 20

Field Preparation Support 2

IDW Management 8

TOTAL LABOR 323

VEHICLE TYPE RATE UNIT USEAGE

2.1 Truck GW Sampling $120.00 days 2 $240.00

2.2 Truck Soil Borings/Well Install $480.00 week 2 $960.00

2.2 Truck Test Pits/MAGS testing $480.00 week 2 $960.00

TOTAL VEHICLE $2,160.00

SUBCONTRACTOR COSTS

NAME PURPOSE RATE UNITS USEAGE Subtotal

Hepaco Test Pits, Pavement Repair (2.2) $1,200 Per Day 1 $1,200.00

EDS, Inc. $11,325 LS 1 $11,325.00

Erwin Remediation $110 Per Drum 7 $770.00

Utility Locate Firm $900 Per Day 1 $900.00

TOTAL $14,195.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES

2.1 - Groundwater Sampling EPA 8260 for VOHs $73.00 14 $1,022.00

EPA 9060 for TOC $30.00 3 $90.00

RSK175 for volatile gasses $180.00 3 $540.00

FL-PRO for TRPH $88.00 5 $440.00

Shipping - Large Cooler $150.00 2 $300.00

Ice $6.50 4 $26.00

2.2 - Soil Borings and MAGS testing $0.00

VOHs by 8260 37 borings x 2 samples $73.00 74 $5,402.00

VOHs by 8260 5-day TAT $14.60 74 $1,080.40

EPA 8260 for VOHs (SPLP) $73.00 7 $511.00

EPA 8260 for VOHs (Extraction) $50.00 7 $350.00

Sieve 6913/7928 $130.00 3 $390.00

Atterberg 4318 $85.00 1 $85.00

Organic Content 2974 $50.00 1 $50.00

VOCs by TO-15 $200.00 3 $600.00

Shipping - Large Cooler $150.00 8 $1,200.00

Ice $6.50 16 $104.00

TOTAL LAB $12,190.40

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

2.1 GW Sampling

55 gal drum $100.00 per drum 1 $100.00

Shallow GW Sampling Kit $290.00 per day 2 $580.00

Silicon tubing $3.00 per foot 14 $42.00

Tubing Poly/HDPE $0.30 per foot 140 $42.00

Expendables $40.00 per day 2 $80.00

2.2 Soil Borings- Test Pits - MAGS testing $0.00

Soil Sampling Kit (through Concrete) $940.00 per week 1 $940.00

55 gallon Drum $100.00 per drum 6 $600.00

OVA $500.00 per week 1 $500.00

Expendables $40.00 per day 6 $240.00

Survey Station $200.00 per week 1 $200.00

Encores $16.00 each 74 $1,184.00

MAGS Investigation Kit $500.00 day 1 $500.00

TOTAL EQUIPMENT $5,008.00

Task #: SubTask 1 Project Management SubTask 6

Site: First Coast Cleaners SubTask 2 2 - Supplemental Site Assessment Field Work SubTask 7

Activity/Phase: SSAR SubTask 3 3 - SSAR and Geotechnical/Structural Evaluation SubTask 8

Project Manager: Clint Noble SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$60.42 Project Technical Lead/P C. Noble 0.6 0.6 $0.00 Senior Officer 0.0 0.0 0.0 0 0 0 0 0 0 0

$69.63 Senior Technical Expert S. Cobert 2.0 2.0 0.0 0 0 0 0 0 0 0 $60.42 Project Technical Lead/P C. Noble 2.0 2.0 0.0 0 0 0 0 0 0 0 $43.01 Professional II A. Ryan 0.0 0.0 0.0 0 0 0 0 0 0 0

0.0 0 0 0 0 0 0 0 $33.43 Professional I K. Profitko 0.0 0.0 0.0 0 0 0 0 0 0 0

0.0 0.0 0.0 0 0 0 0 0 0 0 $57.50 Sen Geotechnical PE M. Passaro 0.0 0.0 0.0 0 0 0 0 0 0 0

0.0 0.0 0.0 0 0 0 0 0 0 0 $33.50 Professional I L. Mueller 0.0 0.0 0.0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 4.60 0.60 4.00 0.00 0 0 0 0 0 0 0

Direct Labor $293.91 $33.81 $260.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $396.78 $45.64 $351.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $110.81 $12.75 $98.06 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $801.50 $92.20 $709.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Task #: SubTask 1 Project Management SubTask 6

Site: First Coast Cleaners SubTask 2 2 - Supplemental Site Assessment Field Work SubTask 7

Activity/Phase: SSAR SubTask 3 3 - SSAR and Geotechnical/Structural Evaluation SubTask 8

Project Manager: Clint Noble SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Hepaco (test pits) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Locate Firm $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $861.00 $861.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping+prep $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $861.00 $861.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Other $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW drums) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $1,662.50 $92.20 $1,570.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $80.15 $9.22 $70.93 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $1,742.65 $101.42 $1,641.23 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

SITE : First Coast Cleaners SUBTASK: 2 - Supplemental Site Assessment Field Work

DATE: 3/7/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

2.1 - GW Sampling

Senior Technical ExpeS. Cobert Interpretation of Lab Data Eval (SPLP) 2

PTL/PM C. Noble Prepare Field Scope of work 0

Preparation of data summaries (SPLP) 2

TOTAL LABOR 4

LABORATORY COSTS

PARAMETER RATE # SAMPLES

2.1 - Groundwater Sampling EPA 8260 for VOHs (SPLP) $73.00 7 $511.00

EPA 8260 for VOHs (Extraction) $50.00 7 $350.00

TOTAL LAB $861.00

Task #: SubTask 1 Project Management SubTask 6

Site: First Coast Cleaners SubTask 2 2 - Supplemental Site Assessment Field Work SubTask 7

Activity/Phase: SSAR SubTask 3 3 - SSAR and Geotechnical/Structural Evaluation SubTask 8

Project Manager: Clint Noble SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$60.42 Project Technical Lead/P C. Noble 44.3 44.3 $0.00 Senior Officer 0.0 0.0 0.0 0 0 0 0 0 0 0

$69.63 Senior Technical Expert S. Cobert 30.0 26.0 4.0 0 0 0 0 0 0 0 $60.42 Project Technical Lead/P C. Noble 40.0 32.0 8.0 0 0 0 0 0 0 0 $43.01 Professional II A. Ryan 203.0 163.0 40.0 0 0 0 0 0 0 0

0.0 0 0 0 0 0 0 0 $33.43 Professional I K. Profitko 40.0 0.0 40.0 0 0 0 0 0 0 0

0.0 0.0 0.0 0 0 0 0 0 0 0 $57.50 Sen Geotechnical PE M. Passaro 24.0 0.0 24.0 0 0 0 0 0 0 0

0.0 0.0 0.0 0 0 0 0 0 0 0 $33.50 Professional I L. Mueller 138.0 98.0 40.0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 519.30 44.30 319.00 156.00 0 0 0 0 0 0 0

Direct Labor $23,251.93 $2,675.00 $14,037.45 $6,539.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $31,390.11 $3,611.25 $18,950.56 $8,828.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $8,765.98 $1,008.48 $5,292.12 $2,465.38 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $63,408.02 $7,294.73 $38,280.13 $17,833.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Task #: SubTask 1 Project Management SubTask 6

Site: First Coast Cleaners SubTask 2 2 - Supplemental Site Assessment Field Work SubTask 7

Activity/Phase: SSAR SubTask 3 3 - SSAR and Geotechnical/Structural Evaluation SubTask 8

Project Manager: Clint Noble SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $2,160.00 $2,160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $2,160.00 $2,160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $11,325.00 $11,325.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin $770.00 $770.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Hepaco (test pits) $1,200.00 $1,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Locate Firm $900.00 $900.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $14,195.00 $14,195.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $1,419.50 $1,419.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $15,614.50 $15,614.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $9,699.40 $9,699.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping+prep $1,630.00 $1,630.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $11,329.40 $11,329.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $1,588.00 $1,588.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Other $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $2,520.00 $2,520.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW drums) $700.00 $700.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $5,008.00 $5,008.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $97,519.92 $7,294.73 $72,392.03 $17,833.16 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $6,340.80 $729.47 $3,828.01 $1,783.32 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $103,860.72 $8,024.20 $76,220.04 $19,616.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Site Name: Site ID #:

Contract #: Contractor:

• Reason for Work Change Directive :

• Description of Work Change Directive :

• Attachments (if applicable, list documents supporting change):

• Costs (if negotiated unit costs, provide information below):

WCP WCD 07-2018

Authorized Contractor Signature:

Authorized FDEP Signature:

WORK CHANGE DIRECTIVE FORM

FDEP Supervisor Approval:

(if applicable)

Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.

Task Assignment #: Work Change Directive #:

Maximum Estimated Increase in Task Amount:

First Coast Cleaners ERIC_4535

HW681 CDM Smith

DC002B 1

Based on the soil analytical results, 7 samples require SPLP analysis based on the exceedance of the Leachability SCTL.

Adding SPLP analysis for 7 soil samples.

CEF as backup for additional costs.

Laboratory and CDM labor costs. +20% for contingency.

$ 2,100.00

Clint C. Noble Digitally signed by Clint C. Noble DN: C=US, E=noblecc@cdmsmith.com, O=CDM Smith Inc, OU="Environmental ", CN=Clint C. Noble Reason: I have reviewed this document Date: 2023.06.22 14:34:45-04'00'

Kyle McMurray Digitally signed by Kyle McMurray Date: 2023.06.22 15:31:14 -04'00'

Aaron Cohen Digitally signed by Aaron Cohen Date: 2023.06.22 16:01:46 -04'00'

McMurray, Kyle

From: Noble, Clint C. <noblecc@cdmsmith.com> Sent: Thursday, July 27, 2023 8:59 AM To: McMurray, Kyle Cc: Fincham, Kara E.

Subject: First Coast Cleaners - SPLP TACO Attachments: HW681 CEF (CDM Smith) - First Coast Cleaners_TACO 1 Original.xlsx; HW681 CEF (CDM Smith) - First

Coast Cleaners_TACO 1 Delta.xlsx; HW681 CEF (CDM Smith) - First Coast Cleaners_TACO 1 Final.xlsx;

RE: First Coast ERIC_4535 Soil Results; HW681 DC002B WCD #1 signed.pdf

Follow Up Flag: Follow up Flag Status: Flagged

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Kyle, Please see attached TACO for FCC regarding the SPLP analysis. Also attached is the WCD that this TACO reconciles.

Best regards, Clint Noble, P.G., PMP Senior Project Manager CDM Smith 4651 Salisbury Road, Suite 420 Jacksonville, FL 32256 O: 904.527.6715 M: 904-625-2125 noblecc@cdmsmith.com Connect with me on LinkedIn cdmsmith.com

To help protect you r priv acy, Microsoft Office prevented automatic download of this picture from the Internet.

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW681

DC002B Completion December 20, 2023

CDM Smith Inc. will conduct a Supplemental Site Assessment at the First Coast Cleaners site located in Jacksonville Beach, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on March 7, 2023.

Kyle McMurray 850-245-8973 Contractor CDM Smith Inc. Contractor

Contractor Shayne Wood Contractor 904-527-6703

ERIC_4535

610 North 3rd Street, Jacksonville Beach, Florida

First Coast Cleaners

Contractor Contractor

✔ $ 103,860.72

$ 103,860.72

Scope of Work

CDM Smith Inc.

Contractor Shayne Wood

Vice President

3/30/2023

Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2023.03.30 13:30:01-04'00'

Teresa Booeshaghi

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.03.30 11:01:15 -04'00'

3/30/2023

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Supplemental Site Assessment Fieldwork & Project Management 07/30/2023

Supplemental Site Assessment Report 10/30/2023

Subtasks 1 and 2: Laboratory analytical results, and field documentation, data tables and paid invoices to subcontractors + Project Management $ 84,244.24

Subtask 3: Supplemental Site Assessment Report $ 19,616.48

$ 103,860.72

HW681

DC002B