This document is a Task Assignment (TA) issued under Contract Number HW681 between the State of Florida Department of Environmental Protection (FDEP) and CDM Smith Inc. for environmental remediation services at the Touch of Class Cleaners site in Sarasota, Manatee County, Florida. The Task Assignment Number is DC020C with a completion date of September 22, 2025. Benjamin Aoki serves as the FDEP Project Manager, while Kathy Leggoe is the Contractor's Project Manager. The underlying contract was executed on January 5, 2022, between FDEP and CDM Smith Inc.
This Task Assignment authorizes CDM Smith Inc. to conduct annual groundwater monitoring and monitoring well installation at the remediation site, with a total authorized value of $28,648.18 on a fixed unit rate basis. The scope of work comprises five subtasks: Project Management (13% of direct labor); Monitoring Well Installation with continuous soil sampling to 23 feet depth; 2024 Annual Groundwater Sampling from 12 monitoring wells with PFAS analysis; Monitoring Well Installation and Annual Groundwater Monitoring Report preparation; and IDW Disposal and PFAS Groundwater Data deliverables. Deliverables include well installation data (due 04/24/2025), groundwater monitoring reports with tabulated data and recommendations (due 06/09/2025 and 07/23/2025), and IDW disposal documentation (due 07/23/2025). The invoice schedule allocates costs across subtasks: $7,561.24 for monitoring well installation data, $9,950.13 for groundwater data deliverables, $8,876.23 for combined reports, and $2,260.58 for IDW disposal and PFAS data. Subcontractors include Environmental Drilling Service for drilling ($2,818.00), Site Lines LLC for utility clearance ($600.00), and Erwin Remediation for drum disposal and PFAS waste profiling ($545.00).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
HW681
DC020C September 22, 2025
This Task Assignment authorizes CDM Smith Inc. to conduct Annual Groundwater
Monitoring and Monitoring Well Installation at Touch of Class Cleaners - Sarasota per their scope of work submitted on 03FEB2025.
Benjamin Aoki 850-245-7527 CDM Smith Inc.
Kathy Leggoe 904-527-6727
ERIC_4897
8420 Lockwood Ridge Road, Sarasota, Manatee County, Florida
Touch of Class Cleaners - Sarasota
$ 28,648.18
$ 28,648.18
Scope of Work
CDM Smith Inc.
Leslie Samel
Vice President
Leslie Samel Digitally signed by Leslie Samel Date: 2025.02.05 07:55:29 -05'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2025.02.04 10:21:47 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
TO:
FROM:
DATE:
SUBJECT:
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : TOC Sarasota SUBTASK 2: Monitoring Well Installation DATE: 2/3/2025 (11/18/2024 original)
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager Pre-Field Work meeting and planning 1
Preparation of Data Summary 1
Professional II Mobilization/Demobilization (1 mob, 2 hr each - MW Install) 2
Field Preparation 1
Arrange for Site Access with owner 1
Prepare Field Kit 1
Install (1) monitoring well 8
Preparation of Data Summary 1.5
IDW Sampling & Management 1.5
Total Hours
PM 2
Prof II 16
Total 18
TOTAL LABOR 18
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE Unit COST
Environmental Drilling Service Drilling 1 $2,818.00 $2,818.00
Site Lines, LLC Utility Locate 1 $600.00 $600.00
TOTAL $3,418.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Soil TCLP VOCs (IDW) $210.00 1 $210.00
Cooler (0 to 25 lbs) - Shipping $110.00 1 $110.00
Ice $6.50 2 $13.00
TOTAL LAB $333.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
MW Installation Kit $325.00 1 days $325.00
Expendables $40.00 1 days $40.00
$0.30 foot $0.00
$3.00 foot $0.00
$100.00 each $0.00
TOTAL EQUIPMENT $365.00
FINAL --7/24/96
LEVEL OF EFFORT/EXPENSE WORKSHEET
SUBTASK 3: Annual Groundwater Sampling DATE: 2/3/2025 (11/18/2024 original)
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager Pre-Field Work meeting and planning 1
Preparation of Data Summary 1
Professional II Mobilization/Demobilization (2 mob, 2 hr each - GW sampling) 4
Field Preparation 1
Arrange for Site Access with owner 1
Prepare Sample Kit 1
Inspect and gauge Depth to Water in 23 monitoring wells (10 minutes each well) in one day 3
Sample Monitoring Wells (12) 14
Field data and Sample Management 2
Preparation of Data Summary 1.5
Professional I Mobilization/Demobilization (2 mob, 2 hr each - GW Sampling) 4
Sample Monitoring Wells (12) 14
Inspect and gauge Depth to Water in 23 monitoring wells (10 minutes each well) in one day 3
Field data and Sample Management 1
Total Hours
PM 2
Prof II 27.5 Prof I 22 Total 51.5
TOTAL LABOR 51.5
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 day 4 $480.00
TOTAL VEHICLE $480.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE Unit COST
$0.00
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOH - EPA Method 8260 $73.00 8 $584.00
Drum IDW VOH - EPA Method 8260 $73.00 1 $73.00
Cooler (0 to 25 lbs) - Shipping $110.00 1 $110.00
Ice $6.50 4 $26.00
TOTAL LAB $793.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Groundwater Sampling Kit (1) $290.00 2 days $580.00
Groundwater Sampling Kit (2) $290.00 2 days $580.00
Expendables $40.00 4 days $160.00
HDPE Tubing (12 wells + 5 ft ext/well) $0.30 400 foot $120.00
Silicon Tubing (1/4") $3.00 12 foot $36.00
Drum $100.00 1 each $100.00
TOTAL EQUIPMENT $1,576.00
FINAL --7/24/96
SUBTASK 4: MW Install & Annual Groundwater Monitoring Report DATE: 2/3/2025 (11/18/2024 original)
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Technical Leader Mann-Kendall review,Technical Evaluation of data/ PE review/Seal 3
Project Manager MW + GWMR Conclusions/Recommendations 2
Profesisonal II Preparation of MW+GWMR - body of report, Figures/Maps 20 File Review and summary 4
Professional I Preparation of Data Tables, Backup, writing support 14
Total Hours
PTL 3
PM 2
Prof II 24 Prof I 14 Total 43
TOTAL LABOR 43
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE Unit COST
$0.00 $0.00
Erwin Soil Drum disposal 1 $110.00 $110.00
TOTAL $110.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
SUBTASK 4: MW Install & Annual Groundwater Monitoring Report DATE: 2/3/2025 (11/18/2024 original)
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Technical Leader Technical Guidance on PFAS field support & evaluation of data 1.5 Project Manager Editorial Review of PFAS Data 1.5
Profesisonal II Sample drum for PFAS & shipping 2
Preparation of PFAS IDW Paid Subcontractor Invoices and PFAS IDW Manifests 2
PFAS Data Management/Data Deliverable prep 2
Total Hours
PTL 1.5
PM 1.5
Prof II 6 Prof I 0 Total 9
TOTAL LABOR 9
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE Unit COST
Erwin PFAS Waste Profile - Water 1 $350.00 $350.00 Erwin PFAS Drum disposal - Water 1 $195.00 $195.00
$0.00
TOTAL $545.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
PFAS Groundwater FDEP laboratory $0.00 8 $0.00 FDEP PFAS Drum IDW Sample $0.00 1 $0.00 ice $6.50 4 $26.00
TOTAL LAB $26.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
included in ST3 $0.30 0 foot $0.00 $3.00 0 foot $0.00
TOTAL EQUIPMENT $0.00
9/16/2024
9/16/2024
Preferred Drilling Solutions, Inc.
8820 66th St. North, Pinellas Park, FL 33782
Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com
DIRECT PUSH TECHNOLOGY QUOTE FORM
Date: 5/30/24 FAC ID#: ERIC_4897
Unit Unit Rate Number of Units
Extended Price whole day $1,875.00 -$ half day $1,475.00 1 1,475.00$ per foot $25.00 23 575.00$ each $110.00 -$ each $50.00 -$ each $35.00 -$ per well $150.00 1 150.00$ roundtrip $650.00 1 650.00$ per crew / per night $575.00 -$ each $75.00 2 150.00$ per day $150.00 -$ each $170.00 1 170.00$
TOTAL QUOTE PRICE $3,170.00
Notes: 1. Includes saw cuts, development, standby time, and decon.
Project No.:
Subcontract Company Name: Preferred Drilling Solutions, Inc. (727) 561-7477
Subcontract Mailing Address: 8820 66th St, Pinellas Park, FL 33782
Signature and Title of Person Submitting Quote: ___________________________________Austin Bonacum, Estimator Date: 5/30/24
Days to Complete Scope of Work: 0.5
Direct Push Daily Rate 1 - on-site day
Equipment Type: Geoprobe 8040DT, 3230DT, 7822DT, 6620DT, 6712DT
*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner
Other (specify)
Other (specify)
Other (specify)
GeoProbe Consumables (includes tubing, points, liners, concrete patch, asphalt patch, and grouting)
DOT Approved 55-gal Drum
Per Diem
Mobilization
DIRECT PUSH TECHNOLOGY
MISCELLANEOUS
Permits
Site Name and Location: Touch of Class Cleaners
Consultant Name: CDM Smith
PROPOSED SCOPE OF WORK:
(1) 2" x 23' MW with 5' .010 screen, continuous soil sampling, drum soil & water, pad and 8" manhole
8420 N Lockwood Ridge Road, Sarasota, Manatee County, FL
Well Completion (includes MH w/ cover, concrete pad, and locking well cap)
Well Riser (includes all materials) ID 1" 5' Length
Slotted PVC Well Screen (includes all materials) 5' Length Pack OD 3.5"
Pre-Packed Well Screen (includes all materials) ID 1" 5' Length Pack OD 3.5"
Auger Attachment, 2" Well Install
Direct Push Half-Day Rate 1 - on-site half day
9/16/24
SITE LINES LLC
Utility Locating 1143 59th Avenue North (727) 432-9482 St. Petersburg, FL 33703 bhardy@sitelinesllc.com
Ms. Kathy R. Leggoe, P.G., PMP CDM Smith 4651 Salisbury Road, Suite 420 Jacksonville, FL 32256
May 29, 2024
SITE: Touch of Class Cleaners Site – Sarasota, Florida PROPOSAL: 01477p
Dear Ms. Leggoe:
Thank you for contacting Site Lines LLC regarding the private utility locate at your project site. Attached is our proposal in response to your inquiry.
Please review the proposal to ensure I have accurately captured the project details.
If you agree to the proposal, including the terms and conditions, and the statement of work, please sign, initial and date where indicated. Upon signing, the proposal will serve as the Agreement of the parties as to the above-referenced Project.
If you have any questions, please feel free to contact me. I look forward to working with you.
Sincerely, Site Lines LLC
William L. Hardy II Geophysicist President
Enclosure
September 16, 2024
SITE LINES LLC PROPOSAL
SITE LOCATION
Touch of Class Cleaners Site – 8420 N. Lockwood Ridge Road, Sarasota, FL
PROPOSED SCOPE OF WORK
Site Lines (“Company”) will use Ground Penetrating Radar (GPR) and conventional electromagnetic (EM) pipe and cable locators to determine the location of underground utilities at the site identified by CDM Smith (“Client”).
RESULTS OF THE INVESTIGATION
The estimated depth and location of utilities identified during the investigation will be marked on the ground surface using spray paint or other method to be agreed upon by the parties. The American Public Works Association Uniform Color Codes for the marking of underground utilities will be used.
PROJECT FEE
The fee to complete the project as described within this proposal is: Six Hundred Dollars [$600.00].
Client shall pay Company in full within thirty (30) days of the invoice date, unless the parties have agreed to another payment arrangement in writing. If during the investigation, Company determines that the goals of the project cannot be achieved with the resources available to Company, Company will notify Client as soon as reasonably possible. Under such circumstances, Company will charge Client only for time expended and materials used to date.
CLIENT REQUIREMENTS
Client is responsible for all site access, maintenance of traffic (MOT), site clearing and/or any other logistical considerations necessary to conduct the utility locate.
Client will also provide all pertinent maps of the project site, including those that show the boundaries of the utility locate, pertinent landmarks, and known utilities (if available). Company is not a substitute for Chapter 556, Florida Statutes.
Accordingly, Client is responsible for calling Sunshine State One Call of Florida
(811) before undertaking any invasive activities, whether through Company, any other entity, or on its own.
DESCRIPTION OF COMPANY INVESTIGATION AND LIMITATIONS
A GSSI SIR-4000 GPR system will be used with a 900, 400, or 270 megahertz antenna configuration depending on site conditions and desired targets. The GPR will assist in locating nonmetallic and metallic utilities. Physical surface conditions, subsurface conditions and technical limitations effect the ability of GPR to resolve targeted utilities and/or subsurface structures. Depth and/or diameter of the utility, soil type, moisture/ionic content of the soil, and electrical properties of the soil compared to that of the utility can prevent the GPR from identifying utilities at the site. The diameter of a utility cannot be determined by GPR data. Estimated depths of utilities are directly affected by soil conditions and the material of the utility. A margin of error of +/- 20-25% in depth should be expected when performing invasive activities.
An RD 8000 will be used for the EM survey. Electromagnetic induction which transmits a signal directly into the desired target and passive power detection which locates naturally occurring magnetic fields in energized lines will be identified by detecting and following the signals with a receiver. The EM survey will assist in finding only metallic utilities. The magnetic field and/or induced signal should emanate from the target in a circular geometry. When this occurs, the receiver will receive its peak signal directly above the target. However, when metallic utilities are running near each other, or there is environmental interference from fences, cars or overhead power lines, the signal can become distorted and the peak no longer can be directly over the utility. Care must be taken when doing any invasive work around the utilities. A margin of error of +/- 20-25% in depth should be expected when performing invasive activities. Company’s personnel are highly experienced and certified operators of GPR and EM pipe and cable locators.
Due to the limitations described above, when Client is working around indicated utilities, a minimum of two (2)-feet clearance from either side of the marked utility will be maintained. For absolute confirmation, Client is responsible for exposing any indicated underground utility.
Company will conduct utility investigations in accordance with the level of care and generally accepted professional practices as ordinarily exercised by members of the same profession practicing in the same locality under similar conditions.
REPRESENTATIONS AND WARRANTIES
Neither Company nor its employees or agents are licensed surveyors under Florida law, nor do they represent themselves as such. Accordingly, the work Company is to perform is not a substitute for work typically completed by a licensed surveyor.
Company specifically and expressly disclaims any liability for any type of property damage or personal injury, including but not limited to death, arising from client’s failure to determine that the services of a licensed surveyor are necessary or to retain a licensed surveyor to perform necessary services.
Limitations in technology, complexity of the physical characteristics of the subsurface conditions, and circumstances beyond Company’s control may limit the performance of Company’s utility investigation. For these reasons, Company expresses no guarantee that all utilities and underground structures will be identified and located during this project.
Company is responsible only for locating underground utilities, the presence of which is both known and indicated on site maps to be provided by Client to Company before Company performs the utility locate. Company will use its best efforts to locate both known and unknown utilities within the project boundaries. However, Company will only be responsible for locating utilities, the presence of which is known before Company undertakes its investigation.
Company expressly disclaims any and all warranties regarding specific or desired results.
TERMS AND CONDITIONS
Additional Insured: If requested, Company will name Client as an additional insured with respect to the services to be performed under this agreement.
Indemnity: Company agrees to indemnify, protect and hold harmless Client from and against all liabilities, claims or demands of every kind of injury, including death, or damages to any person or property related in any way to Company’s performance of this Agreement, except to the extent such liabilities, claims or demands are caused by the negligence or willful misconduct of Client.
Client agrees to indemnify, protect and hold harmless Company from and against all liabilities, claims or demands of every kind of injury, including death, or damages to any person or property related in any way to Client’s performance of this Agreement, except to the extent such liabilities, claims or demands are caused by the negligence or willful misconduct of Company.
Release of Information. Client authorizes Company to release any information regarding Client and this Agreement as may be permitted by Company's privacy policy or as may be required by law or requested by governmental authorities or agencies, law enforcement agencies or courts including, but not limited to, officials from local and state code enforcement agencies.
Governing Law; Jurisdiction; Severability; Waiver of Jury Trial. This Agreement shall be governed and construed in accordance with the laws of the State of Florida. Whenever possible, each provision of this Agreement shall be interpreted in such manner as to be effective and valid under Florida law, but if any provision of this Agreement shall be invalid or prohibited under Florida law, such provision shall be ineffective only as to the invalid portion of the provision without invalidating the remainder of such provision or the remaining provisions of this Agreement.
Client agrees to waive his or her rights to a jury trial for any and all claims made against or through Company. Client further agrees that Company will be notified of all claims no later than the earlier of thirty (30) days from the initial discovery of the claim or default or thirty (30) days following the expiration or termination of this Agreement. Client also agrees that failure to notify Company of any and all claims within this time period will result in the forfeiture of said claim.
Any claims by Client arising under this Agreement must be brought in a state or federal court of competent jurisdiction located in Pinellas County, Florida or in the
United States District Court for the Middle District of Florida in Tampa, Florida.
Client waives any objection to the jurisdiction and venue of such courts. This exclusive choice of jurisdiction and venue does not preclude Client or Company from bringing an action to enforce any judgment or judicial order in any other jurisdiction. The prevailing party in any dispute will be entitled to recover from the losing party its costs, including, but not limited to, costs of collection, reasonable attorney’s fees, and investigative fees.
Assignment; Succession; Third-Party Beneficiaries. Client shall not assign this Agreement or the rights thereto to any other person or entity without the express written consent of the Company. Company may assign or transfer this Agreement without the consent of Client and, after such assignment or transfer, Company shall be released from all obligations under this Agreement occurring after such assignment or transfer. All of the provisions of this Agreement shall apply to, bind and be obligatory upon the heirs, executors, administrators, representatives, successors and assigns of the parties hereto. This Agreement is for the sole benefit of the parties to this Agreement and their respective successors and permitted assigns. Nothing in this Agreement, express or implied, is intended to or shall confer on any other person or entity any legal or equitable right benefit or remedy of any nature whatsoever under or by reason of this Agreement. Notwithstanding the foregoing, any Company Agent is a third-party beneficiary of this Agreement and has the right to enforce the provisions of this Agreement directly against the Client.
Modification of Agreement. No term of this Agreement can be waived or modified except by a writing signed by both parties. If any provision of this Agreement is deemed not to apply, is illegal, or is against public policy, the remainder of the Agreement’s provisions shall retain their full force and effect.
Entire Agreement. This Agreement, including any addenda or schedules specifically incorporated by reference herein, constitutes the entire agreement between Client and Company. This Agreement contains all representations and agreements between Client and Company. Client agrees that Company has not promised Client anything that is not written on the face of this Agreement.
Disclosure Statement. These terms and conditions apply to Projects to which the Company agrees to engage, whether such agreement is made via the Company’s online website, by email, by telephone, or in person. Be advised that the terms and conditions are subject to change without notice.
SITE LINES PROPOSAL ACCEPTANCE
SIGNATURE PAGE
Site Lines Proposal Number: 01477p Proposal Date: May 29, 2024
Project Site: Touch of Class Cleaners Site –8420 N. Lockwood Ridge Rd., Sarasota, FL
Project Fee: $600.00
Payment Terms: [PAYABLE WITHIN 30-DAYS OF INVOICE]
INVOICE TO:
Client: CDM Smith Address: 4651 Salisbury Road, Suite 420, Jacksonville, FL 32256 Attention: Kathy R. Leggoe, P.G., PMP Phone: (904) 527-6727 Email: leggoekr@cdmsmith.com
Special Instructions:
In witness thereof, the parties hereto have made and executed this agreement
FOR [CLIENT] FOR SITE LINES LLC
Signature: Signature:
By: By: William L. Hardy II
Title: Title: President
Date Signed: Date Signed: May 29, 2024
September 16, 2024