Task Assignment Summary
This Task Assignment (TA) DC003C is executed under Contract HW681 between the State of Florida Department of Environmental Protection (FDEP) and CDM Smith Inc. for remediation services at Nelson's Cleaners, located at 1203 West Highway 50, Clermont, Lake County, Florida (FDEP Facility ID ERIC_4822). Kyle McMurray serves as the FDEP Project Manager, while Shayne Wood represents CDM Smith Inc. as the contractor's project manager. The task assignment was executed on June 28, 2023, with a completion date of February 15, 2024.
CDM Smith Inc. will construct a soil vapor extraction (SVE) system in accordance with the January 2022 DEP-approved Investigation and Sampling Report Plan (ISRP) and the May 11, 2023 Scope of Work and Cost Proposal. The scope comprises four subtasks: (1) Project Management calculated at 13% of direct labor costs ($4,998.26); (2) Baseline/Annual Groundwater Monitoring and Reporting including collection from 15 monitoring wells, laboratory analysis, and investigation-derived waste (IDW) disposal ($7,412.98); (3) SVE System Construction and Startup including equipment fabrication, installation, startup testing, and a Startup/Construction Completion Report ($140,482.48); and (4) Utilities provision for one month at $1,300 per month plus handling and setup fees ($1,545.00). The total task assignment value is $154,438.72 on a fixed unit rate basis with cost reimbursement components. Key subcontractors include RSI LLC for treatment system fabrication ($46,845.50), PR&D Inc. for installation services ($41,774.00), Erwin Remediation for IDW disposal ($125.00 per drum), and Eurofins Test America Laboratories for groundwater analysis. Deliverables include groundwater monitoring reports due September 30, 2023; construction reports and startup completion report due November 30, 2023; and utility documentation due upon receipt.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW681
DC003C Completion February 15, 2024
CDM Smith Inc. will Construct a soil vapor extraction system (SVE) in accordance with the January 2022 DEP-approved ISRP and the May 11th, 2023 Scope of Work and Cost Proposal.
Kyle McMurray 850-245-8973 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
CDM Smith Inc.
CDM Smith Inc.
Shayne Wood 904-527-6703
ERIC_4822
1203 West Highway 50, Clermont, Lake County, Florida
Nelson's Cleaners
✔ $ 153,138.72 ✔ $ 1,300.00
$ 154,438.72
Scope of Work
Shayne Wood
Vice President
6/28/2023
Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2023.06.28 11:36:40-04'00'
Teresa Booeshaghi
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.06.28 09:51:52 -04'00'
6/28/2023
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Baseline/Annual Groundwater Monitoring and Reporting Updated HASP, Laboratory Analytical Report, Updated Tables
09/30/2023
SVE System Construction and Startup Daily Construction Reports, Startup/Construction Completion Report 11/30/2023
1 month Utilities Setup Fee, Utilities Handling Fee, and Paid Utility Invoice Not to exceed 1,300.00 per month
01/30/2024
Subtask 1 and 2 - Updated HASP, Laboratory Analytical Report, Updated Tables + Project Management $ 12,411.24
Subtask 3 - Daily Construction Reports, Startup/Construction Completion Report $ 140,482.48
Subtask 4 - utilities Handling Fee, and Paid Utility Invoice Utilities not to exceed 1,300.00 per month $ 1,545.00
$ 154,438.72
HW681
DC003C
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
TO:
FROM:
DATE:
SUBJECT:
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
HW681 Contract File
Kyle McMurray, Contract Manager
May 18, 2023
Negotiation Summary Task Assignment DC003C Nelson’s Cleaners
ERIC_4822
SVE System Installation
CDM Smith Inc. (CDM) will construct a soil vapor extraction system (SVE). Specific subtasks are detailed below:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2: Baseline/Annual Groundwater Monitoring And Reporting In accordance with the 2022 ISRP prepared by HSW, groundwater samples will be collected from monitoring wells MW01, MW02, MW04, MW05, MW06, MW07, MW08, MW10, MW011, MW012, MW013, MW014, MW015, MW016, and MW017. The groundwater samples will be submitted to Eurofins Test America Laboratories, Inc. (TA) for laboratory analysis by United States Environmental Protection Agency (EPA) Method 8260 for volatile organic halocarbons (VOHs).
The laboratory analyses in this proposal include fifteen groundwater samples. CDM Smith will collect water levels from fifteen sampled monitoring wells during the baseline sampling event.
Purging and sampling will be in accordance with FDEP’s Standard Operating Procedures (SOP) for Groundwater Sampling. A YSI-556 multi-parameter probe and a turbidimeter will be used to collect purge parameters including dissolved oxygen, pH, conductivity, oxidation reduction potential, temperature, turbidity.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Erwin Remediation for IDW disposal was chosen on a lowest-cost basis. 2 IDW bids are included and the 3rd from EnviroServe was non-responsive.
Subtask 3: Soil Vapor Extraction System Construction and Startup CDM Smith has reviewed the SVE system design and has relied on HSW’s design and recommendations in their FDEP-approved 2022 ISRP. The SVE system described in this proposal is intended to meet or exceed the operational design requirements of the HSW ISRP. The components in Subtask 3 include the SVE blower system, SVE manifold, the control panel, the treatment system enclosure, fencing, transfer piping, and connections. Subtask 3 includes system startup and first week of system operation, followed by the submittal of a Startup/Construction Completion Report. Four copies and an electronic version of a detailed O&M Manual will be provided with the treatment system. Equipment warranty information will be in the O&M Manual along with a completed FDEP property reporting form. The treatment system manufacturer will provide one day of startup testing. CDM Smith will provide construction management and an on-site representative during the construction activities. Petroleum
Resource & Development (PR&D) has been selected to perform the treatment system installation. It is assumed that the on-site construction activities will take approximately five days.
Prior to system startup, CDM Smith will complete functional tests for all equipment for proper operation, and all system shutoffs and safeguards will be tested. All piping will be inspected for leaks including pressure testing on vapor and air transfer piping and water leaks from the moisture separator system. System startup testing will be completed following the functional testing. The SVE system will be operated for approximately 24 hours and the vacuums and flows will be monitored for equilibration, and an organic vapor analyzer equipped with a photoionization detector (OVA-PID) will be used to monitor vapors from the individual SVE wells, combined influent, and effluent. Vapor sampling for laboratory analyses will be collected for the equilibrated flows following the first 24 hours of operation. The value of allowing the flows to equilibrate is that the vapor samples will not bias the VOC recovery and emission rates too high to represent the rates that will be sustained thereafter. Vapor samples will be collected from the five SVE wells, the combined influent, and the SVE system discharge. The samples will be collected in Suma canisters over a 1-hour period. The CDM Smith representative will remain at the site one additional day following system startup to verify proper system operations. The system startup activities are expected to take two days to complete. CDM Smith will perform operation and maintenance (O&M) activities in one week following system startup. When construction is complete, and following the first week of system operation, CDM Smith will prepare a Startup/Construction Completion Report, as described in the 2022 ISRP. The report will include as-built drawings certified by a professional engineer registered in the State of Florida. The report will summarize the construction activities, changes from the 2022 ISRP and this proposal, and describe the system startup activities and results.
Subtask 4: Utilities CDM Smith will provide utilities for the SVE system and assume $1,300 per month. Handling + setup fees are covered separately in CEF.
FDEP Technical Staff has approved of the proposal dating May 11th, 2023.
CDM and the FDEP confirmed on May 18th, 2023, that an Access Agreement with the current real property owner of the site has been executed.
The final cost total for Task Assignment DC003C is $154,438.72.
FDEP COST ESTI MATEContractor: CDM Smith, Inc.
Date: 9-Jun-23
Task #: SubTask 1 Project Management SubTask 6
Site: Nelson's Cleaners SubTask 2 Baseline/Annual Groundwater Monitoring SubTask 7
Activity/Phase: ISR Implementation SubTask 3 SVE System Startup and Construction/Reporting SubTask 8
Project Manager: Kara Fincham SubTask 4 Utilities SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$63.58 Project Manager K. Fincham 26.2 26.2 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0
$71.37 Senior Technical Expert S. Cobert 22.0 2.0 20.0 0.0 0.0 0.0 0.0 0 0 0 $63.58 Project Technical Lead K. Fincham 13.0 0.0 13.0 0.0 0.0 0.0 0.0 0 0 0
Professional II 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0
$44.84 Professional II A. Ryan 147.0 21.0 126.0 0.0 0.0 0.0 0.0 0 0 0 $23.26 Professional I L. Weber 6.0 6.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $28.17 Professional I J. LeBlanc 24.0 14.0 10.0 0.0 0.0 0.0 0.0 0 0 0 $43.05 Professional II K. Turner 70.0 0.0 70.0 0.0 0.0 0.0 0.0 0 0 0
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0 $0.00 0 0.0 0.0 0.0 0.0 0.0 0.0 0 0 0
Total Hours 308.2 26.2 43.0 239.0 0.0 0.0 0.0 0.0 0 0 0
Direct Labor $14,483.55 $1,666.25 $1,618.32 $11,198.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 135.00% $19,552.79 $2,249.44 $2,184.73 $15,118.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $5,460.31 $628.18 $610.11 $4,222.02 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $39,496.65 $4,543.87 $4,413.16 $30,539.62 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF CDM Smith Page 1
FDEP COST ESTI MATEContractor: CDM Smith, Inc.
Date: 9-Jun-23
Task #: SubTask 1 Project Management SubTask 6
Site: Nelson's Cleaners SubTask 2 Baseline/Annual Groundwater Monitoring SubTask 7
Activity/Phase: ISR Implementation SubTask 3 SVE System Startup and Construction/Reporting SubTask 8
Project Manager: Kara Fincham SubTask 4 Utilities SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $1,440.00 $240.00 $1,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $372.00 $0.00 $372.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,812.00 $240.00 $1,572.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) RSI LLC - Treatment System $46,845.50 $0.00 $46,845.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $46,845.50 $0.00 $46,845.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $2,500.00 $0.00 $2,500.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $49,345.50 $0.00 $49,345.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin $125.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $1,300.00 $0.00 $0.00 $1,300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 PR&D - Construction $41,774.00 $0.00 $41,774.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 RSI LLC - O&M Support $2,000.00 $0.00 $2,000.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $45,199.00 $125.00 $43,774.00 $1,300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $4,634.90 $12.50 $4,377.40 $245.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $49,833.90 $137.50 $48,151.40 $1,545.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $3,295.00 $1,095.00 $2,200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping+prep $1,536.00 $326.00 $1,210.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $4,831.00 $1,421.00 $3,410.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $440.00 $80.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Other $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,450.00 $580.00 $870.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW drums) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $3,180.00 $0.00 $3,180.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $5,170.00 $760.00 $4,410.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $150,489.05 $4,543.87 $6,971.66 $137,428.52 $1,545.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $3,949.67 $454.39 $441.32 $3,053.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $154,438.72 $4,998.26 $7,412.98 $140,482.48 $1,545.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF CDM Smith Page 2
SITE : Nelson's Cleaners SUBTASK: 2 Baseline/Annual Groundwater Monitoring
DATE: 6/9/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Technical Expert S. Cobert Technical Evaluation of Data 2
Professional II A. Ryan Travel (1 trip) 2
Annual Groundwater Sampling - 15 wells 12
Field Preparation (Annual Sampling) 1
HASP Update 1
Sample Kit Preparation 1
IDW Management 4
Professional I J. LeBlanc Travel (1 trip) 2
Annual Groundwater Sampling - 15 wells 12
Professional I L. Weber Data Package, Updated Data Tables (Annual Sampling) 6
Total Hours:
S. Cobert 2
A. Ryan 21
J. LeBlanc 14
L. Weber 6
TOTAL LABOR 43
VEHICLE TYPE RATE UNIT USEAGE
Truck $120.00 days 2 $240.00
TOTAL VEHICLE $240.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNITS USEAGE Subtotal
Erwin Remediation IDW Removal $125 drum 1 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES
VOH 8021/8260 $73.00 15 $1,095.00
Shipping (Large Cooler) $150.00 2 $300.00
Ice $6.50 4 $26.00
TOTAL LAB $1,421.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Shallow GW Sampling Kit $290.00 day 2 $580.00
Expendables $40.00 day 2 $80.00
Drums $100.00 each 1 $100.00
TOTAL EQUIPMENT $760.00
SUBTASK: 3 SVE System Startup and Construction/Reporting
DATE: 6/9/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Technical Lead K. Fincham Startup/Construction Completion Report Review 4
Daily Progress Reports 9
Professional II A. Ryan Travel (PreCon Meeting) 2 PreCon Meeting at Site 2 Travel (Construction oversight) 10 Construction oversight 50 Coordination with Utility Engineer, Establish Account 6 Travel (Site Visit to Meet Utility Engineer) 2 Travel (Day 1 and 2 Startup) 2 Day 1 System Startup/Testing 10 Day 2 System Startup/Vapor Sampling 10 Travel (Week 1 Startup) 2 Week 1 System Startup/Vapor Monitoring 10
Professional I J. LeBlanc Travel (Month 1 O&M) 2
Month 1 O&M 8
Professional II K. Turner Travel (Day 1 and 2 Startup) 2 Day 1 System Startup/Testing 10 Day 2 System Startup/Vapor Sampling 10 Startup/Construction Completion Report 48
Professional II A. Ryan Figures/As-Builts for Construction Completion Report 20 Sr. Technical Lead S. Cobert PE Oversight/Review of Construction Completion Report/As-Builts 20
Total Hours:
S. Cobert 20
K. Fincham 13
J. LeBlanc 10
K. Turner 70
A. Ryan 126
TOTAL LABOR 239
VEHICLE TYPE RATE UNIT USEAGE
Truck (Construction Oversight) $480.00 week 1 $480.00
Truck (Day 1 and 2 Startup) $120.00 day 2 $240.00
Truck (Week 1 Startup) $120.00 day 1 $120.00
Truck (Month 1 O&M) $120.00 day 1 $120.00
Truck (Meet w/ Utility Engineer) $120.00 day 1 $120.00
Truck (PreCon Meeting) $120.00 day 1 $120.00
TOTAL VEHICLE $1,200.00
PER DIEM STAFF RATE UNIT USEAGE
Per Diem K.Turner $36.00 day 2 $72.00
Hotel K.Turner $150.00 Day 2 $300.00
TOTAL PER DIEM $372.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNITS USEAGE Subtotal
RSI LLC Treatment System $46,845.50 each 1 $46,845.50
RSI LLC (2 events) O&M Support (1 week, 1 month) $2,000.00 each 1 $2,000.00
PR&D, Inc Remedial Construction,Electrical Connection $41,774.00 each 1 $41,774.00
TOTAL $90,619.50
LABORATORY COSTS
PARAMETER RATE # SAMPLES
TO-15 for VOHs $200.00 11 $2,200.00
Shipping (small cooler) $110.00 11 $1,210.00
TOTAL LAB $3,410.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 9 $360.00
Soil Vapor Sampling Kit $290.00 day 3 $870.00
Construction/O&M/Pilot Test kit $360.00 day 8 $2,880.00
Construction/O&M Supplies $75.00 day 4 $300.00
TOTAL EQUIPMENT $4,410.00
SUBTASK: 4 Utilities
DATE:
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
O&M Month 1 Utilities Utility Charges (Electric) $1,300.00 month 1 $1,300.00
Utility Setup Fee $225.00 each 1 $225.00
Handling Fee $20.00 month 1 $20.00
TOTAL EQUIPMENT $1,545.00
6/9/2023
4651 Salisbury Road, Suite 420
Jacksonville, Florida 32256 tel: 904.731.7109
June 12, 2023
Mr. Kyle McMurray Florida Department of Environmental Protection Hazardous Waste Cleanup Section 2600 North Blair Stone Road, MS 4520 Tallahassee, Florida 32399-2400
Subject: Proposal for 2023 Remediation Services
Nelson’s Cleaners
ERIC_4822
1203 West Highway 50
Clermont, Lake County, Florida
Dear Mr. McMurray:
CDM Smith Inc. (CDM Smith) is pleased to respond to the Florida Department of Environmental Protection (FDEP) Task Assignment Request to construct a soil vapor extraction (SVE) system, conduct baseline/annual groundwater sampling, groundwater monitoring well installation, and SVE system operation and maintenance (O&M) for Nelson's Cleaners (the Site) located at 1203 West Highway 50, Suite G, in Clermont, Lake County, Florida, ERIC_4822. Our project understanding, the scope of work, and project schedule are described below, and the cost estimate is also attached.
Project Understanding CDM Smith understands that FDEP requires the construction, startup, and operation of an SVE system at the Site. This proposal to complete this work also includes one month of SVE system O&M, SVE system monitoring and optimization, and a System Start-Up/Construction Completion Report. The project duration will be approximately four months, including system installation and start-up, one month of operation, and delivery of the System Start-Up/Construction Completion Report. CDM Smith understands that the Site is an actively operating facility, and the site work must accommodate the Site operations.
Nelson's Cleaners Construction Proposal 06_23
Scope of Work CDM Smith’s proposed scope of work is described below. To complete this project, support services will be required from several subcontractors. Competitive bids were obtained for drilling and SVE System construction and installation. The laboratory and disposal services will be provided by companies with approved rates previously negotiated for use on the Waste Cleanup Program Contract HW681. The companies selected by CDM Smith for the Nelson’s Cleaners project are identified in the associated task descriptions.
Subtask 1 – Project Management Project management activities performed under this task consist of administrative functions required to maintain the project schedule, adhere to budget, and deliver the quality of the work products defined by CDM Smith's quality standards. We will prepare and submit invoices upon approval of each deliverable or milestone completion.
Project Kickoff and Progress Meetings CDM Smith expects to have a kickoff meeting or telephone conference with the FDEP to review the status of the project and address FDEP comments regarding the Task Assignment. CDM Smith will prepare meeting agendas and notes as part of this task.
Project Quality Technical Review CDM Smith's Quality Management System guidelines will be followed. Internal quality reviews will be conducted on plans and on investigation findings and reports.
Project Status Reports CDM Smith's Project Manager will prepare and submit monthly status reports to accompany each invoice throughout this project. The Project Manager will also discuss the project's status with the FDEP bi-weekly until it is complete.
Subtask 2 – Baseline/Annual Groundwater Monitoring and Reporting Groundwater sampling was last performed at the Site in August 2022. CDM Smith proposes to perform a baseline groundwater sampling event before SVE system startup. Annual groundwater monitoring is current being performed at the Site, and it is anticipated that the baseline and annual groundwater sampling will be combined into one event. CDM Smith anticipates the baseline sampling event will be performed soon after the Task Assignment is awarded to CDM Smith. A site-specific Health and Safety Plan (HASP) will be prepared by CDM Smith prior to commencing any site activities. The HASP will be comprehensive of all sitework anticipated for this site.
In accordance with the 2022 ISRP prepared by HSW, groundwater samples will be collected from monitoring wells MW01, MW02, MW04, MW05, MW06, MW07, MW08, MW10, MW011, MW012, MW013, MW014, MW015, MW016, and MW017. The groundwater samples will be submitted to Eurofins Test America Laboratories, Inc. (TA) for laboratory analysis by United States Environmental Protection Agency (EPA) Method 8260 for volatile organic halocarbons (VOHs). The laboratory analyses in this proposal include fifteen groundwater samples.
CDM Smith will collect water levels from fifteen sampled monitoring wells during the baseline sampling event. Purging and sampling will be in accordance with FDEP’s Standard Operating Procedures (SOP) for Groundwater Sampling, FS 2200, and will be collected using low-flow techniques with a peristaltic pump and dedicated polyethylene tubing. A YSI-556 multi-parameter probe and a turbidimeter will be used to collect purge parameters including dissolved oxygen, pH, conductivity, oxidation reduction potential, temperature, turbidity. The instrumentation will be properly calibrated and recorded. Purge water will be contained in drums for characterization and disposal as nonhazardous investigation-derived waste (IDW). CDM Smith assumes that one IDW drum will require disposal under this task assignment. The baseline sample results will be evaluated in the Semi-Annual Remedial Action Status Report submitted as part of Subtask 5.
Deliverables: HASP, Laboratory Analytical Report, Updated Tables
Subtask 3 – Soil Vapor Extraction System Construction and Startup CDM Smith has reviewed the SVE system design and has relied on HSW’s design and recommendations in their FDEP-approved 2022 ISRP. CDM Smith has not verified all ISRP design elements in the HSW ISRP and has not identified a need to do so, based on a rudimentary review.
The SVE system described in this proposal is intended to meet or exceed the operational design requirements of the HSW ISRP. The components in Subtask 3 include the SVE blower system, SVE manifold, the control panel, the treatment system enclosure, fencing, transfer piping, and connections. Subtask 3 includes system startup and first month of system operation, followed by the submittal of a Startup/Construction Completion Report.
Treatment System Construction
The SVE system will be enclosed, pre-wired (entire system including electrical control panel and equipment UL-certified at factory), pre-piped, and tested prior to arriving at the site. The system will be equipped with a process logic controller (PLC) controller system that will integrate the operations of all equipment. The controllers will be programmed to shut down the entire system upon failure of any of the fail-safes and provide remote shut-down and restart capabilities. The treatment system will be constructed by RSI LLC. The major component details are provided below:
SVE Blower System
Vapor Extraction Blower: Ametek Rotron Model DR833, ten horsepower (hp), 3-phase (or equivalent) regenerative blower capable of a maximum flow rate of 184 standard cubic feet per minute (scfm) and a maximum vacuum of 174 inches of water (“H2O). Equipped with a particulate filter, bleed air valve with inlet filter, and silencer.
Air Injection Blower: Ametek Rotron Model DR505, two hp, 3-phase (or equivalent) regenerative blower capable of a maximum flow rate of 150 scfm and a maximum pressure of 88 “H2O. Equipped with a particulate filter, bleed air valve with inlet filter, and silencer.
Moisture Separator: Rotron Model MS200DS moisture separator (or equivalent) with a 10-gallon capacity and maximum air flow of 200 scfm and vacuum of 22 inches of mercury (“Hg), equipped with a high moisture level alarm to shut down the extraction blower.
Vapor-Phase Carbon Treatment: One Carbtrol G-3S vapor-phase carbon drum (or equivalent) containing 140 pounds of granular activated carbon (GAC).
Instrumentation: Sample ports, liquid-filled vacuum gauges (1.5 inch minimum), liquid-filled pressure gauges (1.5 inch minimum), temperature gauges, vacuum transmitter, temperature transmitter, and pitot tubes.
SVE Manifold
Five 2-inch Schedule 40 PVC SVE feeder lines with “cam-lock” style quick disconnects. Each line will be clearly labeled (SVE-1 through SVE-5).
Five 2-inch Schedule 40 PVC air injection feeder lines tied into SVE feeder lines. Each line will be clearly labeled (INJ-1 through INJ-5).
Each SVE and air injection feeder line will be equipped with a 2-inch diameter brass globe valve for flow control.
Each feeder line will be equipped with a brass sample port suitable for manometer use, and a port suitable for anemometer use.
Piping from the vacuum blower to the manifold will consist of 4-inch diameter Schedule 40 PVC. The 2-inch diameter feeder lines will be piped from the man 4-inch line using tees (no tap or saddle-type fittings).
Fifteen feet of 2-inch diameter Spiralite 090 (or equivalent) clear suction hose equipped with two female “cam-lock” style fittings per point.
Control Panel
Will be a PLC-based control panel with ability to:
Acknowledge faults and shut down/restart system from remote location.
Send out daily status reports.
Monitor vacuum and temperature transmitters.
The control panel will be constructed with:
NEMA 4 (waterproof/weather resistant) enclosure.
Manual motor starters with thermal overload protection (selected device to be approved by
Engineer).
Intrinsic safety barrier.
Hand/off/auto switches for SVE blower and air injection blower.
Push to test lights.
Green “when running” lights for both blowers.
Auto restart after power failure.
The control panel must be UL (or equivalent) Listed.
A fused main disconnect.
A primary motor circuit protection using circuit breakers (fuses not acceptable).
Hour meters for both blowers.
Amp meters for both blowers.
A main power interrupt counter.
Individual red alarm lights for SVE low vacuum, moisture separator high level, and high temperature.
Lightning and surge protection for the control panel and the phone line (if equipped).
Cellular connection preferred.
A 120-volt convenience outlet mounted on control panel.
Treatment System Enclosure
The treatment system enclosure will be constructed as follows:
All equipment will be installed inside an acoustically insulated container.
A roof-mounted ventilation fan will be installed in the enclosure to allow safe equipment operation and working conditions.
Equipment will be arranged in the enclosure to provide as much working space as possible.
All equipment will be installed inside the enclosure except the control panel and carbon vessels. The enclosure will include precut outlets for the SVE piping and carbon vessels.
Minimum enclosure dimensions are eight feet wide x 16 feet long x 7 feet high. Larger enclosures will require prior approval of the Site owner, as space is limited at the site.
Hurricane rated and secured to comply with local ordinances.
Air inlet louvers with sound hoods to reduce noise.
Circuit breaker protection for interior lighting and fan.
Four copies and an electronic version of a detailed O&M Manual will be provided with the treatment system. Equipment warranty information will be in the O&M Manual along with a completed FDEP property reporting form. The treatment system manufacturer will provide one day of startup testing.
Fencing, Transfer Piping, and System Connections
CDM Smith will provide construction management and an on-site representative during the construction activities. Petroleum Resource & Development (PR&D) has been selected to perform the treatment system installation. The selected contractor will perform the following under the direct supervision of CDM Smith personnel:
Installation of piping, fittings, valves, gauges, sample ports, etc., required to complete the scope of work. The total piping lengths based on the ISRP will be approximately 55 feet indoors and 90 feet outdoors. The ceiling type is not known, and the hanger types required cannot be identified now. It is assumed that conventional hangers will be appropriate and modifications to the existing structure will not be required.
Surface restoration (including sod installation, landscape plants and materials, and asphalt concrete paving, if needed).
Install engineering controls for surface runoff and sediments (as needed).
Construction and demolition debris disposal.
Providing equipment suitable to lift carbon vessels and equipment and move them into position.
Proper installation of required anchors and tie-down straps for treatment system enclosure.
Provide an electrical drop (3-phase, 200-amp), including permitting fees and the use of a licensed electrician. Includes the installation of temporary service pole and disconnect at the location specified by the Engineer (assume maximum 20 feet from control panel), and connection to the treatment system control panel (aboveground). The electrician will also be available for one 8-hour day at startup.
Installing up to 30 feet of 6-foot-high wooden fence around the treatment system enclosure, including a main gate capable of allowing the treatment system to be removed.
It is assumed that the on-site construction activities will take approximately five days.
System Startup and Monitoring
Prior to system startup, CDM Smith will complete functional tests for all equipment for proper operation, and all system shutoffs and safeguards will be tested. All piping will be inspected for leaks including pressure testing on vapor and air transfer piping and water leaks from the moisture separator system.
System startup testing will be completed following the functional testing. The SVE system will be operated for approximately 24 hours and the vacuums and flows will be monitored for equilibration, and an organic vapor analyzer equipped with a photoionization detector (OVA-PID) will be used to monitor vapors from the individual SVE wells, combined influent, and effluent.
Vapor sampling for laboratory analyses will be collected for the equilibrated flows following the first 24 hours of operation. The value of allowing the flows to equilibrate is that the vapor samples will not bias the VOC recovery and emission rates too high to represent the rates that will be sustained thereafter.
Vapor samples will be collected from the five SVE wells, the combined influent, and the SVE system discharge. The samples will be collected in Suma canisters over a 1-hour period. The 2022 ISRP does not specify a sample duration. The samples will be laboratory analyzed by TA using EPA Method TO-15.
The CDM Smith representative will remain at the site one additional day following system startup to verify proper system operations. The system startup activities are expected to take two days to complete. CDM Smith will perform operation and maintenance (O&M) activities in one week following system startup. Vapor samples will be collected from the five SVE wells, and field screened with an OVA-PID. Combined influent and system effluent samples will be collected for laboratory analysis by EPA Method TO-15.
Reporting
When construction is complete, and following the first month of system operation, CDM Smith will prepare a Startup/Construction Completion Report, as described in the 2022 ISRP. The report will include as-built drawings certified by a professional engineer registered in the State of Florida. The report will summarize the construction activities, changes from the 2022 ISRP and this proposal, and describe the system startup activities and results.
Deliverables: Daily Construction Reports, Startup/Construction Completion Report
Subtask 4 – Utilities CDM Smith will provide utilities for the SVE system and assume $1,300 per month including administrative costs.
Deliverable: Setup Fee, Utilities Handling Fee, and receipt for first month invoice (Cost Plus Fixed Fee)
Subcontractor Selection For fabrication of the treatment system and enclosure, costs we solicited from PRM, ESD Waste 2 Water, MK Environmental, and RSI LLC. As the lowest bidder meeting the specifications provided, RSI LLC was selected to build the SVE system.
For installation of the treatment system, piping, connections, and electrical service, costs we solicited from PR&D, Central Florida Environmental Services, and CC Petroleum. As the lowest bidder meeting the provided specifications, PR&D was selected to install the SVE system.
Subcontractor Evaluation and supporting bids are included in Attachment A.
Schedule CDM Smith will schedule field activities based on availability of the subcontractors upon receipt of formal notice to proceed (NTP). The deliverables will be submitted as detailed below.
Subtask 2: Baseline/Annual Groundwater Monitoring and Reporting Deliverable: Updated HASP, Laboratory Analytical Report, Updated Tables Due Date: September 30, 2023
Subtask 3: SVE System Construction and Startup Deliverables: Daily Construction Reports, Startup/Construction Completion Report Due Date: November 30, 2023 Subtask 4: Utilities Deliverables: Setup Fee, Utilities Handling Fee, and Paid Utility Invoice Due Date: Upon Receipt
We look forward to working on this important project. Feel free to contact me at 904-527-6716 or by email with any questions or concerns.
Sincerely, Kara E. Fincham, PMP Shayne Wood, P.E., PMP. BCEE Senior Project Manager Vice President CDM Smith Inc. CDM Smith Inc.
FinchamKE@cdmsmith.com woodsh@cdmsmith.com cc: Shayne Wood, P.E., CDM Smith Steve Cobert, P.E., CDM Smith
Attachment A Subcontractor Bids
SVE Treatment System Job Details - treatment system fabrication, delivery, and startup assistance
On-Site Startup Testing and Training
Tax Total Lead Time
$2,600.00 $4,919.22 $75,193.72 10 to 12 weeks
$4,200.00 $6,240.78 $95,394.78 18 to 20 weeks
$2,000.00 $3,195.50 $48,845.50 10 to 12 weeks
SVE System Installation Job Details - electrical, permitting, piping, startup testing, etc.
Investigative Derived Waste (IDW) Management Job Details - Per 55-gallon Drum
Hepaco $142.00 $210.00 $146.22 $50.00 $338.22 $406.22
EnviroServe $80.00 $80.00 $50.00 $50.00 $180.00 $180.00
Erwin Remediation $110.00 $110.00 Included Included $110.00 $110.00
Total
5 days
PR&D $41,774.00 5 days
CCPetroleum No Bid
Liquid Soil Fee Liquid Company
Disposal
Per Event
Transportation
Soil
Company SVE System Shipping
ESD Waste 2 Water $84,354.00 $600.00
RSI LLC $43,650.00 $0.00
Company SVE System Installation Duration
CFES $59,535.00
Subcontractor Evaluation Nelson's Cleaners
Monday, May 1, 2023
$64,687.00 $2,987.50PRM Filtration
May 1, 2023
Logen J. Weber
Environmental Scientist
CDM Smith
101 Southhall Ln Ste 200, Maitland, FL 32751
Via e-mail at weberlj@cdmsmith.com
Subject: Quote for New System
Nelson's Cleaners
1203 West Highway 50, Suite G
FDEP Facility ID No. ERIC_4822
Dear Logen, Remedial Systems Integrated, LLC (RSI) is pleased to provide you with this quote for a new system. Herein are costs provided as requested.
System, as per specifications and PI&D [$41,400.00] + applicable taxes
Assumptions: three phase 208V, EN833 10hp SVE blower, EN505 3hp injection blower, fully enclosed skid, no internal manifolds, no carbon filtration (vapor or liquid phase)
Optional Items:
Delivery to the site [$0.00]
Startup Assistance, per day [$1,000.00]
Cellular Telemetry [$2,250.00]+tax
Should you have any questions or would like to discuss options presented in this proposal, please do not hesitate to contact me directly at remedialsystems@outlook.com or via my cell at (813)
585-8769.
Respectfully, Remedial Systems Integrated, LLC
Simo Koncalovic, Owner mailto:remedialsystems@outlook.com
Proposal For System Purchase
Prepared for:
Steven Smith CDM Smith
Prepared For: CDM Smith
Environmental Remediation & Landfill Equipment Solutions
Created by:
Justin Stahl Product Recovery Management, Inc.
200 20th Street
Butner, NC, 27509, United States
Product Recovery Management, Inc. | 200 20th Street, Butner, NC 27509 | (919) 957-8890
Quote 9304 Due Date: 5/1/2023
Sales Rep: Justin Stahl justin.stahl@prmfiltration.com | (919) 957-8890
Sold To Ship To
Steven C. Cobert, P.E.
CDM Smith 101 Southhall Lane, Suite 200
Maitland, FL 32751
Nelson’s Cleaners 1203 West Highway 50, Suite G
Type of System:
Treatment Trailer
(7' x 16' Enclosed Trailer)
(example image, actual system may differ)
Butner, NC, 27509, United States
Product Recovery Management, Inc. | 200 20th Street, Butner, NC 27509 | (919) 957-8890
Proposed System
PRM proposes to provide a fully packaged system for your project in accordance with our written design specifications. The equipment is itemized in the written proposal below.
Treatment Trailer
7' x 16' Enclosed trailer
• 3/4" PT plywood treated floor
• Single side door and double back doors
• Dual 7000 lb torsion axles w/ electric brakes
• Running and brake lights, and std 7 way plug for lights and brakes
• Radial tires
• Factory supplied door hold backs.
• Trailer will be insulated for sound
• Sound hoods shipped loose for all vents
• Wall vents throughout for proper ventilation.
• Trailer to be rated and wired for Non Classified location
• (4) Heavy duty corner jacks installed
• Thermostatically controlled exhaust fan with fan guard
• Standard lighting, ventilation
• Includes full fabrication of treatment system, including plumbing, electrical, and thorough testing as well as labeling.
• Entire System to be 3rd party listed
SVE System - Regenerative Blower
• Ametek Rotron DR-833 Regenerative vacuum blower
• Coupled to a 10HP 3 phase Phase XP motor
• Liquid filled vacuum gauge on inlet
• Temp switch
• Outlet temperature gauges
• Liquid filled Pressure gauge on discharge
• Sample port
• Exhaust will plumb to the carbon vessel
• Pressure gauge on stack
Manifold
• 4" x 2" manifold will be plumbed with 5 legs
• Each of the 5 legs will consist of the following equipment:
• Sample ports
• Air flow manometer port with 1/2 inch threaded plug
• Ball valves, and gate valves
Butner, NC, 27509, United States
Product Recovery Management, Inc. | 200 20th Street, Butner, NC 27509 | (919) 957-8890
• Schedule 80 PVC construction
• Legs will plumb through walls and be capped off for others to connect to
• 5- 15 ft sections of green PVC suction hose with cam locks installed on both ends
Moisture Separator
• PRM model MS-30moisture separator, aluminum construction. Designed for hi-vac application.
• Centrifugal design with bolt down lid and 6" clean out.
• Solberg 235P inlet filter, filter will be integral to MS tank design
• Kunkle automatic vacuum relief valve provided to protect blower.
• 1” manual drain valve
• 2” Gate valve for dilution air mounted on MS tank. Includes inlet filter/silencer
• 0-30” Hg Vacuum gauge
• Sight glass assembly mounted to side of tank with single float stem switch to control Blower
Bio Sparge - Regenerative Blower
• Ametek Rotron DR-505Regenerative vacuum blower
• Coupled to a 2Hp three Phase XP motor
• Liquid filled Pressure gauge on inlet
• Check Valve
• Outlet temperature gauges
• Liquid filled Pressure gauge on discharge
• Sample port
• Sch 80 PVC piping to the outlet manifold
Main System Industrial Control Panel
• NEMA 4 enclosure will mount on exterior of the enclosure. Panel will be 3rd party certified.
• Hand-Off-Auto switches and green running lights and red alarm lights on HMI
• Intrinsically safe relays for all switches were applicable
• Contacts and relays
• Motor starters with thermal overload and circuit protection.
• Siemens S7-1200PLC with color HMI touch screen
• 7” color Comfort HMI with complete HMI system control
• Remote I/O mounted in panel board
• Includes all license fees, Smartservice for Internet based connectivity and control via secure log in.
Butner, NC, 27509, United States
Product Recovery Management, Inc. | 200 20th Street, Butner, NC 27509 | (919) 957-8890
• All reporting will be via email or text messaging through a messaging service.
• PRM to provide wireless service that will be pre-programmed prior to system arrival. Service will be good till the end of the calendar year. Additional years will be invoiced in Jan for all proceeding years, current rate is $917 / year which is subject to change based on market increases.
• GFCI all weather outlet located underneath control panel
• Standard lightning protection module
• CyberPower 825 UPS and surge protector
• System will restart automatically if it is safe to do so.
Vapor Phase Carbon Vessels
• (1) PRM VP-85Vapor Phase Carbon Vessels
• Filled with140 lbs of Granulated 4x10 Carbon
• 3" inlet/out connection ports
• Drain valve
• Pressure gauges and sample ports
• Includes hose connections and 6 ft stack
SCADA Interface PRM uses a program interface that is accessible locally or remotely through our secure internet connection. PRM has thousands of connected SCADA interfaces in the field and the interface below is a typical representation of a typical remediation system.
PRM has the flexibility to customize per client request.
Butner, NC, 27509, United States
Product Recovery Management, Inc. | 200 20th Street, Butner, NC 27509 | (919) 957-8890
Power at the above referenced facility is: ___________________________120/230V three phase CLOSED DELTA ONLY
Please note that a system connected to an open delta electrical system can cause warranty issues. Please see Warranty disclaimer below. Warranty issues are at the discretion of PRM.
End of written proposal. Please see attached warranty disclaimer and security agreement. If your project payment schedule includes progress payments, then a security agreement may not be required. The written security agreement is intended to reserve PRM’s right of ownership of the equipment in the event of a default of payment due to bankruptcy or some other unforeseen event. A security agreement is required in order for PRM to file for a UCC for the equipment.
We have quoted prices with terms that we feel best represent the client's needs based on review of the request. PRM can offer flexible alternative payment terms on the project based on customer request with terms up to 270 days. Note that if PRM has provided progress payment terms, these terms are structured to offer the client the best overall value as we have reduced pricing and not included any financing terms for the project. Extended payment terms do incur pricing increases due to the cost of PRM internally financing projects for customers due to the cost of carrying money for these durations. If we have quoted with terms that you prefer to change, please contact your sales agent to discuss. Note that extended terms are typically offered on State or Federally funded projects where the funding structure is such that extended terms may be required.
*********IMPORTANT*********
Upon taking receipt of equipment that has physical signs of damage, it is the responsibility of the client to document that damage on the Bill of Lading at the time of receipt of the equipment. In the event that the Bill of Lading is not properly marked and the damage is visible, PRM has no ability to make a claim against the carrier and thus the recipient would become responsible for all charges of damage repairs. The client must also notify PRM Corporate headquarters in writing within 24 hours with a written description of all damage as well as digital images of the damage. PRM selects the best carriers in the nation to do our transporting however there is always potential for damage, especially on longer journeys. Our carriers all carry freight damage insurance which we can make claims against, but only if we follow the rules and the most critical rule is that the damage must be documented on the Bill of Lading at receipt of the equipment.
Loose Items Integrations - PRM typically manufactures systems complete in our facility where components or subsystems may require detachment for shipping and reassembly onsite. Unless specifically quoted in our written proposal, PRM will package loose equipment separately for that shipment. It is the onsite systems contractor or other subcontractors to un-package and reinstall these components onsite. In the event the client needs or requires for PRM to install the components, there will be a required additional charge to do so. If a clients specification states that PRM is to reassemble those components, it is understood and agreed that PRM is not including pricing to do so in our base pricing unless specifically stated by PRM. PRM ships hundreds of modular systems each year and in >99% of the cases, all of our clients have the site contractors perform the components installations. It typically may not be price competitive for PRM to perform site installation work and in many cases PRM may be banned by state requirements due to contracting licenses.
Butner, NC, 27509, United States
Product Recovery Management, Inc. | 200 20th Street, Butner, NC 27509 | (919) 957-8890
System Pricing
Ln # Qty Description Unit Price Subtotal
1 REMEDIATION SYSTEM PRICING $64,687.00 $64,687.00
1 ESTIMATED SHIPPING & HANDLING $2,987.50 $2,987.50
1 ONSITE START UP & TRAINING $2,600.00 $2,600.00
Subtotal $70,274.50
Tax $4,919.22
Total $75,193.72
Notes
Shipping is always estimated at the time of the quote. Due to volatile fuel costs during the past decade, PRM reserves the right to adjust shipping prices based on the national average fuel cost at the time of delivery vs. at the time of the quote.
Any purchase authorization must include PRM's signed/completed acceptance form (below) and a signed PRM Security Agreement as furnished by PRM.
Lead time is determined at time of order, but is typically 10-12 weeks from receipt of approved submittals.
Sales and Use Taxes on the quote are for reference. Actual State and County Sales taxes will be invoiced at the time of billing at the most current rates
Payment Terms and Conditions
25% down at time of order 50% prior to shipping balance net 30
Authorized & Accepted By (Signature) By signing, you agree to the below Standard Terms and Conditions
Date PO # / Project Reference
Butner, NC, 27509, United States
Product Recovery Management, Inc. | 200 20th Street, Butner, NC 27509 | (919) 957-8890
System Options (not required) Please select any optional items below. Options are not necessarily upgrades, they are listed as alternatives. It is up to the engineer working for you to make the ultimate decision that the option chosen is in your best interest. Options chosen may be an invalidation of strictly following a Request for Proposal or a Specification. You accept this option as an approved alternative to the specification. PRM provides the options typically to enhance the system. The system options below will be in addition to the base system quoted above.
Option Name Price QTY Subtotal
$0.00 1 $0.00
Subtotal $0.00
Tax $0.00
Total $0.00
Authorized & Accepted By (Signature) By signing, you agree to the below Standard Terms and Conditions
Date PO # / Project Reference
Butner, NC, 27509, United States
Product Recovery Management, Inc. | 200 20th Street, Butner, NC 27509 | (919) 957-8890
Warranty
WARRANTY DISCLAIMER
Product Recovery Management (PRM) will warrant all new equipment manufactured by PRM to be free of defects in materials and workmanship for a period of 1 year from the date of manufacture as established by PRM provided the following conditions are met:
1. Equipment must be operated and maintained in accordance with the guidelines established in the O&M manual(s) provided with the equipment or with the individual Equipment O&M manuals.. This includes the site specific manual as provided by PRM as well as the individual component manuals provided.
2. Warranty service shall not be applicable unless a complete logbook of routine maintenance is kept and provided to PRM upon request. For warranty coverage to be ensured,, PRM requires that O&M logs be sent to PRM staff quarterly so PRM can confirm previous maintenance, not after a warranty claim.
3. Warranty service shall not be applicable unless all outstanding invoices which are over terms are paid in full.
4. PRM will not warrant electrical…