CN-370000-CN306-T33CO1.pdf
PDF 649 KB Posted
- Contract number
- CN306
- Issued by
- Florida
About this file
Document Summary
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for the "Connect to Municipal Sewer" project at Manatee Springs State Park. The change order involves FDEP, the consultant Hydra Engineering & Construction, LLC, subcontractor O'Neal Surveying & Mapping, Inc., and Levy County Department of Health. The contract number is CN306, Task Assignment TA33, Change Order 1, with FDEP Project Number 61476-C. The project is located at Manatee Springs State Park in Levy County, Florida.
The change order modifies the scope to include expanded survey boundaries for four new septic system locations (#1 Ranger Station, #10 APM Residence, #6 Restroom/Concession Stand, and #3 Hickory Camping Area) and adds permitting fees for the Levy County Department of Health. The changes include removing the original Subtask 2 (Survey) with a credit of $5,733.29 and adding Subtask 2B (Additional Survey) at $10,753.29 in fixed-price costs; Subtask 6B (Septic System Permitting Fees) at $1,765.00 in reimbursable costs; and Subtask 6C (Tree Site Plan) at $4,014.39 in fixed-price costs. The total change order amount is $10,799.39, increasing the cumulative task amount from $64,959.94 to $75,759.33. The project end date remains February 18, 2026, with no change in duration. Payment is contingent upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN306 TA33 1 61476-C
Connect To The Municipalities
Hydra Engineering & Construction, LLC.
Leslie Weiss, P.E. C.G.C. (850) 926-2593 lahope@hydraengineering.com
Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
The purpose of this change order is to include possible relocation areas for the new septic systems in the survey boundary and the septic system permitting fees for Levy County Department of Health based on all new system (four) applications.
$ 64,959.94 $ 64,959.94 $ 64,959.94 $ 64,959.94
$ 1,765.00 $ 9,034.39 $ 10,799.39 $ 1,765.00 $ 73,994.33 $ 75,759.33
09/20/2024
06/28/2025
02/18/2026
2/18/2026
Tamika Bass
Rafael De Leon
Ralph Perkins or successor
Leslie Weiss
Michael W. Foster, Jr., P.E.
61476C 37502013053 080039/23 423001 U3200 134000 QK $ 10,799.39
$ 10,799.39
HYDRA ENGINEERING & CONSTRUCTION, LLC
36 Jasper Thomas Road, Crawfordville, Florida 32327 (850) 926-2593 www.hydraec.com
Rev December 4, 2024
Rafael DeLeon Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399
RE: CN306, TA 33
BDC Project No. 61476-C Manatee Springs State Park – Connect to Municipal Sewer
Dear Mr. DeLeon:
Hydra Engineering & Construction, LLC is pleased to provide the attached change order proposal summary and man-hour documentation for the Septic and Drain Field Repairs at Manatee Springs State Park.
Please see the attached change order proposal summary and deliverables.
Sincerely, Leslie Weiss, P.E., C.G.C.
Hydra Engineering & Construction, LLC
Connect to Municipal Sewer Manatee Springs State Park – Change Order 1
Upon completion of Subtask 1: Site Investigation, it was determined by members of Hydra and the FDEP Project Manager that new systems at the four sites will be necessary. It was determined onsite that the previously listed “#12 Hickory Dump Station” site location is not a location in which the Park has requested updating. The proposed sites for new septic systems are as follows, #1 Ranger Station, #10 APM Residence, #6 Restroom/Concession Stand and #3 Hickory Camping Area. The purpose of this change order is to include possible relocation areas for the new septic systems in the survey boundary and the septic system permitting fees for Levy County Department of Health based on all new system (four) applications.
Subtask 2: Survey (Subtask to be Removed)
Description: O’Neal Surveying & Mapping, Inc. will establish Horizontal and Vertical control based on the Florida State Plane Coordinate System, NAD 83 (2011 Adjustment) NGVD Vertical. A minimum of 2 Benchmarks will be set onsite at all 4 locations in areas where they should not be disturbed by future construction. Topographic Survey for 4 septic tanks and drain field locations extending 10 feet beyond and including all utility lines, electric panels and cleanouts. Locations are shown on the attached Exhibit “A”. Septic and drain field locations to be marked in the field by the client, or representatives thereof, prior to or at the time of the field survey.
Deliverable: Subtask to be removed.
Performance Measure: Subtask to be removed.
Credit Cost: $5,733.29
Subtask 2B: Additional Survey
Description: O’Neal Surveying & Mapping, Inc. will establish Horizontal and Vertical control based on the Florida State Plane Coordinate System, NAD 83 (2011 Adjustment) NGVD Vertical. A minimum of 2 Benchmarks will be set onsite at all 4 locations in areas where they should not be disturbed by future construction. Survey will include all grade breaks, extended to the centerline of adjacent roadways or outside edge of sidewalks, trails, storm structures, signs, above ground utilities, buildings, parking, sidewalks, septic tanks, drain field locations, all above ground visible utility lines, electric panels and cleanouts or any improvements within the limits of survey sufficient to produce 1-foot contours, supplemented with spot shots, as needed.
Tree species that are 6” DBH or greater in size will be located.
Approximate location survey limits are attached in exhibits A and B below.
Deliverable: Consultant will provide electronic copies (AutoCAD and pdf) digitally signed and sealed of the topographic survey.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2B
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
O'Neal Surveying & Mapping, INC.
Survey Field Crew (2 Man Crew)
$150.00 55 $8,250.00
O'Neal Surveying & Mapping, INC
Licensed Surveyor $155.00 4 $620.00
O'Neal Surveying & Mapping, INC
Drafting $80.00 20 $1,600.00
Hydra Engineering & Construction, LLC
Principal Engineer $279.80 0.5 $139.90
Hydra Engineering & Construction, LLC
Project Engineer $111.92 1 $111.92
Hydra Engineering & Construction, LLC
Office Administrator $62.94 0.5 $31.47
Fixed Price Cost Total: $10,753.29 Total for Subtask 2B: (Fixed Price Cost + Reimbursable) = $10,753.29
Subtask 6B: Levy County Dept. of Health Septic System Design & Permit Application Fees
Description: Florida Department of Environmental Protection / Levy County Department of Health On-site Sewage Disposal System options were chosen for each individual system after Subtask 1:
Site Investigation and discussion with FDEP project manager. Permit application fees are included below based on four new septic systems. Application (four) submittal and (four) payment receipts will be provided to the FDEP Project Manager. Site evaluations performed by Levy County are included in the overall permit costs.
Deliverable: Consultant will provide the permit application receipts and payment receipts in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Reimbursable Cost:
Permit Application Fee 1,765.00
Printing N/A Electronic submittals Overnight Travel (if applicable)
N/A
Mileage (@ $0.445 per mile)
0 miles * 1 trip * 0.445 = $0.00
Reimbursable Total Cost 1,765.00 Total for Subtask 6B: (Reimbursable) = $1,765.00
Subtask 6C: Levy County Tree Official Statement and Tree Site Plan
Description: Based on conversations with Levy County Permitting Department, a tree site plan will be required for the proposed project if more than six trees are demolished in the design of the four new septic systems. If the tree site plan is triggered, a tree site plan will be prepared by Hydra and ASLA Landscape Architect. Hydra will then submit an official statement email to Levy County including the tree site plan and a list of what trees were removed and replaced. The official statement email will not require any fee.
Deliverable: Consultant will provide the official statement in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 6C
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Alan Holt, ASLA Landscape Architect
Landscape Architect $150.04 12 $ 1,800.48
Hydra Engineering & Construction, LLC
Project Engineer $111.92 12 $1,343.04
Hydra Engineering & Construction, LLC
Principal Engineer $279.80 3 $839.40
Hydra Engineering & Construction, LLC
Office Administrator $62.94 0.5 $31.47
Fixed Price Cost Total: $4,014.39 Total for Subtask 6C: (Reimbursable) = $4,014.39
Project Schedule:
Activity Duration
Subtask 2B: Additional Survey 60 Days from Change Order Execution
Subtask 6B: Dept. of Health – Septic System Design and Permitting Fees
50 Days from Subtask 5A and 5B
Subtask 6C: Levy County Tree Permit 50 Days from Subtask 5A and 5B
Summary of Fees:
Subtask Subtask Fixed Price
Cost Subtask Reimbursable
Subtask 2: Survey $5,733.29 (Credit) $0.00
Subtask 2B: Additional Survey $10,753.29 $0.00
Subtask 6B: Dept. of Health - Septic System Design and Permitting Fees
$0.00 $1,765.00
Subtask 6C: Levy County Tree Permit $4,014.39 $0.00
Total Fixed Price Cost: $9,034.39 (including Credits)
Total Reimbursable Cost: $1,765.00
Overall Total Cost: $10,799.39
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
File details come from the government source that posted it. Updated .