This file is a collection of architectural and engineering drawings for the EHRM Infrastructure Upgrades Construction project at James A. Haley Veterans Hospital in Tampa, Florida (VA Project 673-20-107). The drawings, issued for construction on 04/04/2025, cover multiple trailer buildings (73-83 and 99) and include existing condition plans, demolition plans, new work plans, mechanical systems, electrical systems, plumbing, fire protection, and technology infrastructure. The project involves creating new telecommunication rooms (TRs) and technology equipment (TE) cabinets across multiple trailers, with specific locations including TE 74-105, TE 75-105, TE 76-105, TE 78-107, TE 80-125, TE 81-103, TE 82-103, and TE 83-131. The architect of record is CB Design Group (Alexandria, VA), with mechanical, electrical, and structural engineering by Scott Przybysz/IMEG Corporation (St. Louis, MO), and additional consultants including Mark Dyck (Martinsburg, WV), Clare Kramer (Orlando, FL), and Compass (Novelty, OH).

The project scope encompasses demolition of existing walls, doors, fixtures, and infrastructure; installation of new partitions with fire-rated construction; flooring and finishes; mechanical systems including split-unit air conditioning and temperature/humidity sensors; electrical systems with receptacles, circuit breakers, and lighting; and technology infrastructure including Category 6A cabling, equipment racks, network switches, UPS systems, and fire-rated telephone terminal boards. New work includes exposed structure above TRs with 2-hour fire-resistive spray application, suspended lighting fixtures, lay-in ceiling tiles, and static-dissipating flooring in designated areas. The Contracting Officer is Sean Kaminski (SCC, Division Chief, Department of Veterans Affairs Contracting, Independence, OH), with Marco Lopez serving as the Contracting Officer Representative (COR) at the hospital facility.

View the file

Other files

File Type Posted
Amendment 9 - 36C77625R0092 0009.pdf PDF
673-107.Trailer.pdf PDF
673-107. 0-TN002.pdf PDF
673-107.01.Tech.pdf PDF
673-107.36.Tech.pdf PDF
673-107.41.Tech.pdf PDF
673-107.68.Tech.pdf PDF
4-15 RFI TRACKING SHEET - SOLICITATION 36C77625R0092 - Final.pdf PDF
Tampa EHRM Addendum 2 Narrative.pdf PDF
673-107.32.Tech.pdf PDF
673-107.53.Tech.pdf PDF
Amendment 8 - 36C77625R0092 0008.pdf PDF
Amendment 7 - 36C77625R0092 0007.pdf PDF
4-8 RFI TRACKING SHEET - SOLICITATION 36C77625R0092 - Amend 7.pdf PDF
Calculations based on geo report_Sealed.pdf PDF
Amendment 6 - 36C77625R0092 0006.pdf PDF
3-31 RFI TRACKING SHEET No.14 - SOLICITATION 36C77625R0092 Amend 5.pdf PDF
Amendment 5 - 36C77625R0092 0005.pdf PDF
Revised 2.8 and 2.9 Tampa.pdf PDF
010000 TIL General Specification - Tampa Specific.pdf PDF
Tampa EHRM Addendum 1 Narrative.pdf PDF
Amendment 4 - 36C77625R0092 0004.pdf PDF
03-27-2026 Addendum 1 Combined Drawings.pdf PDF
01 32 16.15- Project Schedules-Small Projects.pdf PDF
PKI Readers.pdf PDF
Amendment 3 - 36C77625R0092 0003.pdf PDF
3-27 RFI TRACKING SHEET - SOLICITATION 36C77625R0092 Amend 3.pdf PDF
Amendment 2 - 36C77625R0092 0002.pdf PDF
Amendment 1 - 36C77625R0092 0001.pdf PDF
Site Visit Attendance - Tampa EHRM.pdf PDF
Attachment 3 - Drawings Vol 1 Part1.pdf PDF
Attachment 5 - Drawings Vol 1 Part3.pdf PDF
Attachment 7 - Drawings Vol 1 Part5.pdf PDF
Attachment 10 - Drawings Vol 2 Part3.pdf PDF
Attachment 14 - Construction Wage Rates - Hillsborough 1-2-2025.pdf PDF
RFP - 36C77625R0092.pdf PDF
Attachment 2 - Spec Vol 2 - R1.pdf PDF
Attachment 15 - Limitations on Subcontracting Clause.docx DOCX document
Attachment 16 - Site Visit Instructions.pdf PDF
Attachment 20 - RFI TRACKING SHEET - SOLICITATION 36C77625R0092 - Project 673-20-107.xlsx XLSX spreadsheet
Attachment 1 - Spec Vol 1 - R1.pdf PDF
Attachment 6 - Drawings Vol 1 Part4.pdf PDF
Attachment 9 - Drawings Vol 2 Part2.pdf PDF
Attachment 11 - Drawings Vol 2 Part4.pdf PDF
Attachment 19 - Division Cost Breakdown.xlsx XLSX spreadsheet
Attachment 4 - Drawings Vol 1 Part2.pdf PDF
Attachment 8 - Drawings Vol 2 Part1.pdf PDF
Attachment 13 - Brand Name Justification - Tampa_Redacted.pdf PDF
Attachment 17 - PPQ.docx DOCX document
Attachment 18 - Project Information Sheet for Contractors.docx DOCX document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HANDICAPP ED RAMP

FDOT IND EX #304

HANDICAPP ED RAMP

FDOT IND EX #304

CONCRETE

33.17

S-2

TRASH

DS-BL

EXIT

ENTER

POST

POST

POST

POST

ISLAND

ISLAND

TO P OF W ALL

D

WM

EE

MACHINE ROOM

ELEVATOR

2 ' - 0 "

EX B03

' - 0

E X

B0

UP

B R

U C

E B

D

O W

N S

B L

V D

E FLETCHER AVE

UNIVERSITY OF SOUTH

FLORIDA COLLEGE

E 132ND AVE

N

N

D S

T

N

R

D S

T

L

IV

IN

G

S T

O N

A V

E

N

T

H S

T

N

T

H S

T

E 131ST AVE

E 131ST AVE

B R

U C

B

D

O W

N S

B L

V D

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

421 KING ST

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

LTCAL

EHRM INFRASTRUCTURE UPGRADES

TAMPA, FL.

ISSUED FOR CONSTRUCTION

COVER SHEET- VOLUME 3

GI-300

-2

-1

G I-

.p d f

Department of Veterans Affairs

673-20-107 EHRM INFRASTRUCTURE UPGRADES- VOL 3

ISSUED FOR CONSTRUCTION

PROJECT DIRECTORY

Medical Center Director

Director of Facility Management Service

Medical Director

Project COR

Project CO

Infection Control

Safety Officer

CONTRACTING OFFICER REPRESENTATIVE (COR)

Marco Lopez

James A. Haley Veteran Hospital 13000 Bruce B. Downs Blvd Tampa, FL 33612

PHONE: (813) 972-2000

Marco.Lopez@va.gov

ARCHITECT

CB DESIGN GROUP, INC

412 King St. Ste. 301 Alexandria, VA 22314

PHONE: (888) 585-CBDG (2234)

wbridge@cbdg-ae.com

MEP/FP/STRUCTURAL ENGINEER

Scott Przybysz

IMEG Corporation 15 Sunnen Drive Ste. 104 St. louis, MO 63143

PHONE: (314) 951-2535

scott.r.przybysz@imegcorp.com

CONTRACTING OFFICER (CO)

Sean Kaminski

Contracting Officer SCC, Division Chief Department of Veterans Affairs | Contracting 6150 Oak Tree Blvd Suite 490 Independence, OH 44131

PHONE: (216) 447-8300

Sean.Kaminski@va.gov

APPROVALS

JAMES A. HALEY VETERAN HOSPITAL

13000 BRUCE B. DOWNS BLVD

TAMPA, FL. 33612

N

PLAN

NORTHSCALE: NOT TO SCALE

VICINITY MAP

OFFICE AREA

OFFICE

OFFICE

RESTROOM

STORAGE

OFFICE

OFFICE

101-T73

102-T73

103-T73

104-T73

105-T73

106-T73

107-T73

EXISTING CONDITIONS- GENERAL NOTES

1. EXISTING CONDITION DRAWINGS ARE FOR REFERENCE ONLY. CONTRACTOR SHALL

VERIFY LOCATION OF ALL ITEMS SHOWN ON THIS SHEET PRIOR TO BEGINNING OF WORK.

EXISTING WALL RATING LEGEND

3 HOUR FIRE BARRIER

2 HOUR FIRE BARRIER

1 HOUR FIRE BARRIER

SMOKE BARRIER

SMOKE PARTITION

EXISTING WALL RATING- GENERAL NOTES

1. ALL EXISTING FIRE RATINGS SHOWN HAVE BEEN PROVIDED BY THE VA. CONTRACTOR

SHALL FIELD VERIFY ALL EXISTING PARTITIONS WHERE WORK IS BEING PERFORMED AND

SEAL ALL PENETRATIONS THROUGH ALL FLOOR AND FIRE RATED BARRIERS WITH UL

LISTED ASSEMBLIES TO MAINTAIN FIRE RATED BARRIERS IN PLACE

2. SEE LIFE SAFETY SHEETS FOR DETAILED LIFE SAFETY PLANS.

EXISTING TELECOM

ROOM LOCATION

PLAN LEGEND

NEW TELECOM ROOM/TE

CABINET LOCATION

NOTE: BUILDING 73 SHALL BE FED FROM BUILDING 74. THERE IS NO ARCHITECTURAL

WORK PROPOSED ON THIS LEVEL- SEE ALL CONSULTANTS' SHEETS FOR WORK

THAT IS PROPOSED ON THIS LEVEL.

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

421 KING ST

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

LTCAL

EHRM INFRASTRUCTURE UPGRADES

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 73 - EXISTING CONDITION

PLAN - OVERALL FIRST FLOOR

73-GC101

-2

-1

-G

C

/1

/2

.p d f

N

TRUE NORTH

SITE KEY PLAN

SCALE: NOT TO SCALE

1/4" = 1'-0"A10

TRAILER 73 - EXISTING CONDITION - 1ST FLOOR N

PLAN

NORTH

N

TRUE

NORTH

H T

OFFICE AREA

COMM

RESTROOM

OFFICE

OFFICE

OFFICE

OFFICE

101-T75

105-T75

104-T75

103-T75

102-T75 107-T75

106-T75

H T

RESTROOM

H T

OFFICE AREA

RESTROOM

STORAGE

OFFICE

OFFICE

OFFICE

OFFICE

101-T76

104-T76

105-T76

103-T76

102-T76 107-T76

106-T76

H T

NEW TE

74-105

PROVIDE TEMPERATURE AND HUMIDITY SENSORS FOR

ALL TELECOMMUNICATION SPACES INCLUDING

LOCATIONS WITH TE CABINETS INSTALLED. SENSORS

SHALL CONNECT TO CAMPUS FACILITY MANAGEMENT

CONTROL SYSTEM (FMCS) FOR SPACE MONITORING

ONLY.

SSU-T74105

CU-T74105

ROUTE 3/4"DPP DN AND

CONNECT WITH P-TRAP OF

LAVATORY.

REF

PROVIDE TEMPERATURE AND HUMIDITY SENSORS FOR ALL

TELECOMMUNICATION SPACES INCLUDING LOCATIONS WITH TE

CABINETS INSTALLED. SENSORS SHALL CONNECT TO CAMPUS

FACILITY MANAGEMENT CONTROL SYSTEM (FMCS) FOR SPACE

MONITORING ONLY.

SSU-T75105

CU-T75105

ROUTE 3/4"DPP DN AND

CONNECT WITH P-TRAP

OF LAVATORY.

REF

PROVIDE TEMPERATURE AND HUMIDITY SENSORS FOR ALL

TELECOMMUNICATION SPACES INCLUDING LOCATIONS WITH TE

CABINETS INSTALLED. SENSORS SHALL CONNECT TO CAMPUS

FACILITY MANAGEMENT CONTROL SYSTEM (FMCS) FOR SPACE

MONITORING ONLY.

SSU-T78107

CU-T78107

ROUTE 3/4"DPP DN AND

CONNECT WITH P-TRAP OF

LAVATORY.

REF

PROVIDE TEMPERATURE AND HUMIDITY SENSORS

FOR ALL TELECOMMUNICATION SPACES INCLUDING

LOCATIONS WITH TE CABINETS INSTALLED. SENSORS

SHALL CONNECT TO CAMPUS FACILITY MANAGEMENT

CONTROL SYSTEM (FMCS) FOR SPACE MONITORING

ONLY.

SSU-T76105

CU-T76105

ROUTE 3/4"DPP DN AND

CONNECT WITH P-TRAP

OF LAVATORY.

REF

N

TRUE NORTH

SITE KEY PLAN

SCALE: NOT TO SCALE

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

950 N. WASHINGTON ST

SUITE 334

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

DRAWINGS NOT INTENDED FOR

CONSTRUCTION.

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

BHAACHRUSARN

EHRM INFRASTRUCTURE UPGRADE

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 73 TO 78 - OVERALL

FIRST FLOOR PLAN -

MECHANICAL

T70-MH101

-2

-1

T -M

H

/0

/2

.p d f

N O R

HT

1/8" = 1'-0"

TRAILER 74 - OVERALL FIRST FLOOR PLAN - MECHANICAL

1 N

O R

HT

1/8" = 1'-0"

TRAILER 75 - OVERALL FIRST FLOOR PLAN - MECHANICAL

N O R

HT

1/8" = 1'-0"

TRAILER 78 - OVERALL FIRST FLOOR PLAN - MECHANICAL

N O R

HT

1/8" = 1'-0"

TRAILER 76 - OVERALL FIRST FLOOR PLAN - MECHANICAL

COMM

RESTROOM

OFFICE

OFFICE

OFFICE

OFFICE

101-T75

105-T75

104-T75

103-T75

102-T75 107-T75

106-T75

E

RESTROOM

E

OFFICE AREA

RESTROOM

STORAGE

OFFICE

OFFICE

OFFICE

OFFICE

101-T76

104-T76

105-T76

103-T76

102-T76 107-T76

106-T76

E

E

E

{LS1}

E

E

{LS1}

E

E

{LS1}

E

E

{LS1}

NEW TE

74-105

T70-EP101

A7

CU-T74105DS-CU-T74105 4

T70-EP101

A10

CU-T75105DS-CU-T75105 4

T70-EP101

A16

CU-T78107 4DS-CU-T78107

T70-EP101

A13

CU-T76105DS-CU-T76105 4

NEW TE

78-107

+48"

AC-SCP-1

SSU-T78107

MX-SSU-T78107

F1F1

O

NEW TE

74-105

AC-SCP-1

SSU-T74105

MX-SSU-T74105

F1F1

O

NEW TE

75-105

+48"

AC-SCP-1

SSU-T75105

MX-SSU-T75105

F1F1

O

NEW TE

76-105

+48"

AC-SCP-1

SSU-T76105

MX-SSU-T76105

F1F1

O

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

421 KING ST

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

DRAWINGS NOT INTENDED FOR

CONSTRUCTION.

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

SSYHND

EHRM INFRASTRUCTURE UPGRADE

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 73 TO 78 - OVERALL FIRST

FLOOR PLAN - ELECTRICAL

T70-EP101

-2

-1

T -E

P

/2

/2

.p d f

1/8" = 1'-0"

TRAILER 74 - OVERALL FIRST FLOOR PLAN - ELECTRICAL

D9

1/8" = 1'-0"

TRAILER 75 - OVERALL FIRST FLOOR PLAN - ELECTRICAL

G91/8" = 1'-0"

TRAILER 78 - OVERALL FIRST FLOOR PLAN - ELECTRICAL

G16

N

BUILDING

NORTH

N

TRUE

NORTH

GENERAL NOTES:

1. CONTRACTOR SHALL REFER TO SHEET 0-E001,

0-E002, 0-E003, 0-E501, 0-E502, 0-E601 AND 0-

E701 FOR LEGENDS, SCHEDULES, DETAILS,

NOTES AND OTHER GENERAL INFORMATION.

2. CONTRACTOR IS PERMITTED TO ADJUST

LAYOUT AS NECESSARY TO ACCOMMODATE

OTHER SYSTEMS AND COORDINATE WITH

EXISTING DUCT WORK. GENERAL LOCATION

SHALL BE MAINTAINED. DO NOT MOUNT

LUMINAIRES TO THE DUCT WORK. MOUNT

LUMINAIRE SUCH THAT SHADOWS ARE NOT

CAST.

N

TRUE NORTH

SITE KEY PLAN

SCALE: NOT TO SCALE

777874

KEYNOTES:

1. INSTALL RECEPTACLES FOR PDU AND UPS ON

WALL BEHIND RACK, ALIGNED WITH THE

CUTOUT ON THE TELECOMMUNICATIONS

ENCLOSURE.

2. CIRCUIT NEW RECEPTACLES IN THIS SPACE TO

NEAREST PANEL, PROVIDE 2#12 & 1#12 EGC IN

3/4"C.

3. CIRCUIT NEW ACCESS CONTROL PANEL TO

NEAREST PANEL, PROVIDE 2#12 & 1#12 EGC IN

3/4"C.

4. CIRCUIT NEW CONDENSING UNIT IN THIS

SPACE TO NEAREST PANEL, PROVIDE 30A/2P

CIRCUIT BREAKER WITH 2#10 & 1#10 EGC IN

3/4"C.

5. SPLIT SYSTEM UNIT IS POWER FROM

ASSOCIATED CONDENSING UNIT. ROVIDE 2#12

& 1#12 EGC IN 3/4" CONDUIT FROM

CONDENSING UNIT. COORDINATE

CONNECTION WITH MECHANICAL

CONTRACTOR PRIOR TO PERFORMING WORK.

6. CIRCUIT NEW LIGHT FIXTURE IN THIS SPACE

TO NEAREST PANEL, PROVIDE 2#12 & 1#12 EGC

IN 3/4"C.

1/8" = 1'-0"

TRAILER 76 - OVERALL FIRST FLOOR PLAN - ELECTRICAL

D16

1/2" = 1'-0"

ENLARGED ELECTRICAL PLAN TR

T78-107 A16 1/2" = 1'-0"

ENLARGED ELECTRICAL PLAN TR

T74-105 A71/2" = 1'-0"

ENLARGED ELECTRICAL PLAN TR

T75-105 A10

1/2" = 1'-0"

ENLARGED ELECTRICAL PLAN TR

T76-105 A13

OFFICE

RESTROOM

STORAGE

OFFICE

OFFICE

101-T73

102-T73

103-T73

104-T73

105-T73

106-T73

107-T73

2D2V

3D 2V

3D2V

3D 2V 2D 2V 2D 2V

3D2V

6D4V

6V 6D

1D-WAP 1D-WAP

D

D

D

D

D

3D 3D 3D

D

3D 3 D

3D

3D

1D-GWAP

1D-WAP

OFFICE AREA

COMM

RESTROOM

OFFICE

OFFICE

OFFICE

OFFICE

101-T75

105-T75

104-T75

103-T75

102-T75 107-T75

106-T75

2D2V

2D2V

2D 2V

2D2V

2D 2V 3D 2V

3D2V

2D2V

1D-WAP

1D-WAP

1D-GWAP

2D2V

OFFICE AREA

RESTROOM

STORAGE

OFFICE

OFFICE

OFFICE

OFFICE

101-T76

104-T76

105-T76

103-T76

102-T76 107-T76

106-T76

3D2V

3D 2V

3D 2V

D

V

2D 2V 2D 2V

D

3D2V

D

V

3D2V

3D 2V

1D 2V

2D2V 2D2V

1D 2V

1D-WAP 1D-WAP1D-GWAP

RESTROOM

3D2V

3D 2V

3D2V

3D 2V

3D2V 3D2V 3D2V

3D 2V

3D2V

3D 2V 3D 2V 3D 2V

1D-WAP

1D-GWAP 1D-WAP

2D2V

RESTROOM

3D2V 3D2V 3D2V 3D2V 3D2V 3D2V 3D2V 3D2V

3D 2V

3D2V

3D 2V3D 2V3D 2V3D 2V

3D2V

3D 2V

1D-WAP 1D-GWAP 1D-WAP

NEW TE

74-105

EXISTING TR

EXISTING TR

EXISTING TR

N

TRUE NORTH

SITE KEY PLAN

SCALE: NOT TO SCALE

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

950 N. WASHINGTON ST

SUITE 334

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

BARPDN

EHRM INFRASTRUCTURE UPGRADE

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 73 TO 78 - OVERALL

FIRST FLOOR DEMO PLAN -

TECHNOLOG

T73-TD101

-2

-1

T -T

D

/0

/2

.p d f

1/8" = 1'-0"

TRAILER 73 - OVERALL FIRST FLOOR DEMO PLAN - TECHNOLOGY

A9

1/8" = 1'-0"

TRAILER 74 - OVERALL FIRST FLOOR DEMO PLAN - TECHNOLOGY

D9

1/8" = 1'-0"

TRAILER 75 - OVERALL FIRST FLOOR DEMO PLAN - TECHNOLOGY

G9

1/8" = 1'-0"

TRAILER 76 - OVERALL FIRST FLOOR DEMO PLAN - TECHNOLOGY

A15

1/8" = 1'-0"

TRAILER 77 - OVERALL FIRST FLOOR DEMO PLAN - TECHNOLOGY

D15

1/8" = 1'-0"

TRAILER 78 - OVERALL FIRST FLOOR DEMO PLAN - TECHNOLOGY

G15

N

TRUE

NORTH

N

BUILDING

NORTH

N

TRUE

NORTH

N

BUILDING

NORTH

N

TRUE

NORTH

N

BUILDING

NORTH

N

TRUE

NORTH

N

BUILDING

NORTH

N

TRUE

NORTH

N

BUILDING

NORTH

N

TRUE

NORTH

N

BUILDING

NORTH

NOTES:

1. REFER TO TN000 TECHNOLOGY COVERSHEET FOR SYMBOL LIST.

2. REFER TO INSTALLATION NOTES ON SHEET TN000 FOR MORE INFORMATION ON EXISTING CONDUITS.

3. EXISTING CABLING TO BE REMOVED FROM END TO END AND REPLACED WITH NEW DATA CABLES.

OFFICE

RESTROOM

STORAGE

OFFICE

OFFICE

101-T73

102-T73

103-T73

104-T73

105-T73

106-T73

107-T73

2D

2D

2D

2D 2D 2D

2D

2D 2D

2D 2D

1D-WAP 1D-WAP

D

D

D

D

D

2D 2D 2D

D

2D 2 D

2D

2D

1D-GWAP

1D-WAP

OFFICE AREA

COMM

RESTROOM

OFFICE

OFFICE

OFFICE

OFFICE

101-T75

105-T75

104-T75

103-T75

102-T75 107-T75

106-T75

2D

2D

2D

2D

2D 2D

2D

2D

1D-WAP

1D-WAP

1D-GWAP

2D

OFFICE AREA

RESTROOM

STORAGE

OFFICE

OFFICE

OFFICE

OFFICE

101-T76

104-T76

105-T76

103-T76

102-T76 107-T76

106-T76

2D

2D

2D

D

2D 2D

D

2D

D

2D

2D

2D

2D 2D

2D

1D-WAP 1D-WAP1D-GWAP

RESTROOM

2D

2D

2D

2D

2D 2D 2D

2D

2D

2D 2D 2D

1D-WAP

1D-GWAP 1D-WAP

2D

RESTROOM

2D 2D 2D 2D 2D 2D 2D 2D

2D

2D

2D2D2D2D

2D

2D

1D-WAP 1D-GWAP 1D-WAP

GENERAL NOTES:

1. ALL NEW LOW VOLTAGE CABLING IN THIS BUILDING WILL ROUTE TO TR 105-T74 IN BUILDING 74.

NEW TE

74-105

GENERAL NOTES:

1. ALL NEW LOW VOLTAGE CABLING IN THIS BUILDING WILL ROUTE TO TR 105-T74.

TR 105-T74

T73-TN102

G15

GENERAL NOTES:

1. ALL NEW LOW VOLTAGE CABLING IN THIS BUILDING WILL ROUTE TO TR 105-T75.

TR 105-T75

T73-TN102

B15

GENERAL NOTES:

1. ALL NEW LOW VOLTAGE CABLING IN THIS BUILDING WILL ROUTE TO TR 105-T75 IN BUILDING 75.

T76-TN103

G16

GENERAL NOTES:

1. ALL NEW LOW VOLTAGE CABLING IN THIS BUILDING WILL ROUTE TO TR 107 IN BUILDING 78.

TR 107

GENERAL NOTES:

1. ALL NEW LOW VOLTAGE CABLING IN THIS BUILDING WILL ROUTE TO TR 107.

T76-TN103

B16

N

TRUE NORTH

SITE KEY PLAN

SCALE: NOT TO SCALE

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

950 N. WASHINGTON ST

SUITE 334

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

BARPDN

EHRM INFRASTRUCTURE UPGRADE

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 73 TO 78 - OVERALL

FIRST FLOOR PLAN -

TECHNOLOGY

T73-TN101

-2

-1

T -T

N

/0

/2

.p d f

1/8" = 1'-0"

TRAILER 73 - OVERALL FIRST FLOOR PLAN - TECHNOLOGY

A9

1/8" = 1'-0"

TRAILER 74 - OVERALL FIRST FLOOR PLAN - TECHNOLOGY

D9

1/8" = 1'-0"

TRAILER 75 - OVERALL FIRST FLOOR PLAN - TECHNOLOGY

G9

1/8" = 1'-0"

TRAILER 76 - OVERALL FIRST FLOOR PLAN - TECHNOLOGY

A15

1/8" = 1'-0"

TRAILER 77 - OVERALL FIRST FLOOR PLAN - TECHNOLOGY

D15

1/8" = 1'-0"

TRAILER 78 - OVERALL FIRST FLOOR PLAN - TECHNOLOGY

G15

NOTES:

1. REFER TO TN000 TECHNOLOGY COVERSHEET FOR TECHNOLOGY GENERAL NOTES, TECHNOLOGY

INSTALLATION NOTES AND SYMBOL LIST.

2. REFER TO TN700 FOR GENERAL TECHNOLOGY EQUIPMENT SCHEDULE.

3. CONTRACTOR TO INCLUDE AN ALLOWANCE FOR 10 ADDITIONAL 2-PORTS CAT 6A INFORMATION OUTLETS

IN THEIR PROPOSAL FOR THIS SHEET. FUTURE INFORMATION OUTLET LOCATIONS WILL BE DETERMINED BY

THE VA AT A LATER DATE.

4. CONTRACTOR TO FIELD VERIFY CONDUIT RISER ROUTE WITH OWNER PRIOR TO INSTALLATION.

5. ALL INFORMATION OUTLETS ON THIS SHEET TO BE CABLED ON A SCHEDULED BASIS WITH OWNER WHILE

OCCUPIED WITH STAFF AND PATIENTS. COORDINATE DEMO AND CABLE REPLACEMENT WITH OWNER.

M

R1

CSS

M

R1

CSS

SC-MPP-1

OWNER

PROVIDED

EQUIPMENT

SC-FDC-1

SC-MPP-1

OWNER

PROVIDED

EQUIPMENT

SC-FDC-1

NEW TE

74-105

SC-CAB-1

SC-GND-1

PW-CPW-1

(TYP. OF 2)

PW-CPW-1

AC-SCP-1

SC-TTB

T73-TN102

(TYP.)

NOTES:

1. ALL ELECTRICAL AND MECHANICAL EQUIPMENT INCLUDING BUT NOT LIMITED LIGHTS,

ELECTRICAL PANELS, MECHANICAL UNIT, ETC.ARE SHOWN FOR REFERENCE. REFER TO THE

MECHANICAL AND ELECTRICAL DRAWINGS FOR COMPLETE INFORMATION AND SCOPE

REQUIREMENTS.

2. ALL WIRE BASKET SHALL BE MOUNTED 6" ABOVE THE EQUIPMENT RACK UNLESS OTHERWISE

NOTED.

KEYNOTES:

1. CAMERA TO BE MOUNTED AT 7' 0 FACING DOORWAY. REFER TO TECHNOLOGY EQUIPMENT

SCHEDULE FOR ADDITIONAL INFORMATION ON THE CAMERA TYPE. REFER TO THE CSS

SCHEDULE FOR ADDITIONAL INFORMATION ON SECURITY WITHIN EACH OF THE

TELECOMMUNICATION SPACES.

2. REFER TO H15/0-TN501 FOR DETAILS ON GROUND BAR FOR THIS SPACE. MOUNT GROUND BAR

AT 7'-0" FROM FINISHED FLOOR.

3. THE FIRE RATED TELEPHONE TERMINAL BOARD SHALL COVER ALL THE WALLS INT HE

TELECOMMUNICATIONS ROOM AS SHOWN ABOVE. SHOULD THE WALLS REQUIRE TO BE

PAINTED, THE PAINT SHALL BE "FIRE SAFE" PAINT. IF PAINTED, THE FIRE RATED LABEL ON EACH

BOARD SHALL NOT BE PAINTED. REFER TO THE SPECIFICATIONS FOR ADDITIONAL

INFORMATION.

4. REFER TO THE ELECTRICAL DRAWINGS FOR LIGHTING REQUIREMENTS.

G10

74-105

CM-1

74-01

NEW TE

75-105

T73-TN102

B11

PW-CPW-1

AC-SCP-1

SC-TTB

SC-GND-1

(TYP.)

NOTES:

1. ALL ELECTRICAL AND MECHANICAL EQUIPMENT INCLUDING BUT NOT LIMITED

LIGHTS, ELECTRICAL PANELS, MECHANICAL UNIT, ETC.ARE SHOWN FOR

REFERENCE. REFER TO THE MECHANICAL AND ELECTRICAL DRAWINGS FOR

COMPLETE INFORMATION AND SCOPE REQUIREMENTS.

2. ALL WIRE BASKET SHALL BE MOUNTED 6" ABOVE THE EQUIPMENT RACK UNLESS

OTHERWISE NOTED.

KEYNOTES:

1. CAMERA TO BE MOUNTED AT 7' 0 FACING DOORWAY. REFER TO TECHNOLOGY

EQUIPMENT SCHEDULE FOR ADDITIONAL INFORMATION ON THE CAMERA TYPE.

REFER TO THE CSS SCHEDULE FOR ADDITIONAL INFORMATION ON SECURITY WITHIN

EACH OF THE TELECOMMUNICATION SPACES.

2. REFER TO H15/0-TN501 FOR DETAILS ON GROUND BAR FOR THIS SPACE. MOUNT

GROUND BAR AT 7'-0" FROM FINISHED FLOOR.

3. THE FIRE RATED TELEPHONE TERMINAL BOARD SHALL COVER ALL THE WALLS IN

THE TELECOMMUNICATIONS ROOM AS SHOWN ABOVE. SHOULD THE WALLS

REQUIRE TO BE PAINTED, THE PAINT SHALL BE "FIRE SAFE" PAINT. IF PAINTED, THE

FIRE RATED LABEL ON EACH BOARD SHALL NOT BE PAINTED. REFER TO THE

SPECIFICATIONS FOR ADDITIONAL INFORMATION.

4. REFER TO THE ELECTRICAL DRAWINGS FOR LIGHTING REQUIREMENTS.

75-105

CM-1

75-01

SC-CAB-1

(TYP. OF 2)

SPACE RESERVED

FOR ELECTRICAL

RECEPTICLES

OUTGOING HORIZONTAL PATHWAY

INCOMING BACKBONE PATHWAY

SC-GND-1

SC-CAB-1

NOTES:

1. ALL EQUIPMENT SHALL BE LOCATED IN ITS DESIGNATED SPOT AS DEFINED BY THIS LAYOUT UNLESS OTHERWISE NOTED. ALL EQUIPMENT IS SIZED (BY RACK UNITS) ACCORDING TO THE BASIS OF DESIGN MANUFACTURER AND MODEL. THE FINAL LAYOUT AND EQUIPMENT SIZE MAY VARY BASED ON THE FINAL SELECTION OF THE EQUIPMENT. ANY CHANGES TO THE LAYOUT SHOWN ABOVE SHALL BE COORDINATED WITH THE E.O.R AND C.O.R. PRIOR TO INSTALLATION. REFER TO THE GENERAL TECHNOLOGY EQUIPMENT

SCHEDULE AND SPECIFICATIONS FOR ADDITIONAL INFORMATION.

2. PROVIDE AND INSTALL A NEW SC-GND-2 TO THE REAR SIDE OF THE RACK.

3. REFER TO E SERIES DRAWINGS FOR ADDITIONAL EQUIPMENT INSTALLED ON THE REAR OF THE RACKS INCLUDING THE UPS, ZONE

PDU AND VERTICAL PDU'S.

SC-FDC-1

SC-BLA-1

SC-BLA-1

SC-HWM-2

SC-MPP-2

SC-HWM-1

SC-MPP-2

SC-HWM-2

NETWORK SWITCH

SC-HWM-2

NETWORK SWITCH

SC-HWM-1

SC-BLA-1

SC-BLA-1

SC-BLA-1

SC-BLA-1

SC-PDU-1

SC-PDU-1

SC-UPS-2

SC-BLA-1

SC-BLA-1

NOTES:

1. ALL EQUIPMENT SHALL BE LOCATED IN ITS DESIGNATED SPOT AS DEFINED BY THIS LAYOUT UNLESS OTHERWISE NOTED. ALL EQUIPMENT IS SIZED (BY RACK UNITS) ACCORDING TO THE BASIS OF DESIGN MANUFACTURER AND MODEL.

THE FINAL LAYOUT AND EQUIPMENT SIZE MAY VARY BASED ON THE FINAL SELECTION OF THE EQUIPMENT. ANY CHANGES TO THE LAYOUT SHOWN ABOVE SHALL BE COORDINATED WITH THE E.O.R AND C.O.R. PRIOR TO INSTALLATION. REFER TO THE GENERAL TECHNOLOGY EQUIPMENT SCHEDULE AND SPECIFICATIONS FOR ADDITIONAL

INFORMATION.

2. PROVIDE AND INSTALL A NEW SC-GND-2 TO THE REAR SIDE OF THE RACK.

3. REFER TO E SERIES DRAWINGS FOR ADDITIONAL EQUIPMENT INSTALLED ON THE REAR OF THE RACKS INCLUDING THE

UPS, ZONE PDU AND VERTICAL PDU'S.

NOTES:

1. THIS RISER IS DIAGRAMMATIC AND MAY NOT SHOW ACTUAL ROUTING OR

QUANTITIES OF MATERIALS SHOWN. THIS RISER IS SHOWN FOR

CLARIFICATION OF CONNECTION(S), LOCATIONS AND CABLE TYPE. ALL

INFORMATION OUTLETS ARE TYPICAL OF THE OUTLETS IN THE AREA SHOWN.

REFER TO FLOOR PLANS FOR MORE SPECIFIC ROUTING INFORMATION.

REFER TO SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS.

2. REFER TO FLOOR PLANS FOR QUANTITY OF CABLES AND JACKS TO BE

INSTALLED AT EACH INFORMATION OUTLET.

KEYNOTES:

1. C# INDICATES DATA FACEPLATE CONFIGURATION. REFER TO THE

INFORMATION OUTLET SCHEDULE AND SPECIFICATIONS FOR ADDITIONAL

INFORMATION.

2. RACK(S) OR CABINET(S) AS DEFINED ON THE TELECOM ROOM LAYOUT.

REFER TO THE TELECOM ROOM REFERENCES MATRIX ON THE COVERPAGE

FOR LOCATION.

3. REFER TO SPECIFICATIONS FOR FIBER PATCH CORD REQUIREMENTS.

4. RJ-45 TO RJ45 CATEGORY 6A UTP PATCH CORDS, REFER TO SPECIFIATIONS.

5. 4-PAIR, CATEGORY 6A, UNSHIELDED TWISTED PAIR CABLE, REFER TO

SPECIFICATIONS.

6. FIBER OPTIC CABLE. REFER TO THE FIBER COPPER DIAGRAM ON XXX FOR

ADDITIONAL INFORMATION.

C#

C#

C#

NOTES:

1. THIS RISER IS DIAGRAMMATIC AND MAY NOT SHOW ACTUAL ROUTING OR

QUANTITIES OF MATERIALS SHOWN. THIS RISER IS SHOWN FOR

CLARIFICATION OF CONNECTION(S), LOCATIONS AND CABLE TYPE. ALL

INFORMATION OUTLETS ARE TYPICAL OF THE OUTLETS IN THE AREA SHOWN.

REFER TO FLOOR PLANS FOR MORE SPECIFIC ROUTING INFORMATION.

REFER TO SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS.

2. REFER TO FLOOR PLANS FOR QUANTITY OF CABLES AND JACKS TO BE

INSTALLED AT EACH INFORMATION OUTLET.

KEYNOTES:

1. C# INDICATES DATA FACEPLATE CONFIGURATION. REFER TO THE

INFORMATION OUTLET SCHEDULE AND SPECIFICATIONS FOR ADDITIONAL

INFORMATION.

2. RACK(S) OR CABINET(S) AS DEFINED ON THE TELECOM ROOM LAYOUT.

REFER TO THE TELECOM ROOM REFERENCES MATRIX ON THE COVERPAGE

FOR LOCATION.

3. REFER TO SPECIFICATIONS FOR FIBER PATCH CORD REQUIREMENTS.

4. RJ-45 TO RJ45 CATEGORY 6A UTP PATCH CORDS, REFER TO SPECIFIATIONS.

5. 4-PAIR, CATEGORY 6A, UNSHIELDED TWISTED PAIR CABLE, REFER TO

SPECIFICATIONS.

6. FIBER OPTIC CABLE. REFER TO THE FIBER COPPER DIAGRAM ON XXX FOR

ADDITIONAL INFORMATION.

C#

C#

C#

SC-FDC-1

SC-BLA-1

SC-BLA-1

SC-HWM-2

SC-MPP-2

SC-HWM-1

SC-MPP-2

SC-HWM-2

SC-HWM-2

SC-HWM-1

SC-BLA-1

SC-BLA-1

SC-BLA-1

SC-BLA-1

SC-BLA-1

SC-BLA-1

SC-PDU-1

SC-PDU-1

SC-UPS-2

NETWORK SWITCH

NETWORK SWITCH

OUTGOING HORIZONTAL PATHWAY INCOMING BACKBONE PATHWAY

SPACE RESERVED

FOR ELECTRICAL

RECEPTICLES

SC-GND-1

SC-CAB-1

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

950 N. WASHINGTON ST

SUITE 334

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

BARPDN

EHRM INFRASTRUCTURE UPGRADE

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 74 & 75 - TECHNOLOGY

ENLARGEMENT

T73-TN102

-2

-1

T -T

N

/0

/2

.p d f

1/2" = 1'-0"

TECHNOLOGY EQUIPMENT ROOM

BUILDING T74 TE-105-T74

G15

1/2" = 1'-0"

TECHNOLOGY EQUIPMENT ROOM

BUILDING T75 TE-105-T75

B15

1" = 1'-0"

TECHNOLOGY EQUIPMENT ROOM

ELEVATION BUILDING T74

TE-105-T75

B11

NO SCALE

HORIZONTAL COPPER DIAGRAM

H5

NO SCALE

HORIZONTAL COPPER DIAGRAM

D5

1" = 1'-0"

TECHNOLOGY EQUIPMENT ROOM

ELEVATION BUILDING T74

TE-105-T74

G10

M

R1

CSS

M

R1

CSS

SC-MPP-1

OWNER

PROVIDED

EQUIPMENT

SC-FDC-1

SC-MPP-1

OWNER

PROVIDED

EQUIPMENT

SC-FDC-1

NEW TE

76-105

T76-TN103

G11

PW-CPW-1

(TYP. OF 2)

PW-CPW-1

AC-SCP-1

SC-CAB-1

SC-GND-1

SC-TTB

(TYP.)

NOTES:

1. ALL ELECTRICAL AND MECHANICAL EQUIPMENT INCLUDING BUT NOT LIMITED LIGHTS,

ELECTRICAL PANELS, MECHANICAL UNIT, ETC.ARE SHOWN FOR REFERENCE. REFER TO

THE MECHANICAL AND ELECTRICAL DRAWINGS FOR COMPLETE INFORMATION AND

SCOPE REQUIREMENTS.

2. ALL WIRE BASKET SHALL BE MOUNTED 6" ABOVE THE EQUIPMENT RACK UNLESS

OTHERWISE NOTED.

KEYNOTES:

1. CAMERA TO BE MOUNTED AT 7' 0 FACING DOORWAY. REFER TO TECHNOLOGY

EQUIPMENT SCHEDULE FOR ADDITIONAL INFORMATION ON THE CAMERA TYPE. REFER

TO THE CSS SCHEDULE FOR ADDITIONAL INFORMATION ON SECURITY WITHIN EACH OF

THE TELECOMMUNICATION SPACES.

2. REFER TO H15/0-TN501 FOR DETAILS ON GROUND BAR FOR THIS SPACE. MOUNT

GROUND BAR AT 7'-0" FROM FINISHED FLOOR.

3. THE FIRE RATED TELEPHONE TERMINAL BOARD SHALL COVER ALL THE WALLS INT HE

TELECOMMUNICATIONS ROOM AS SHOWN ABOVE. SHOULD THE WALLS REQUIRE TO BE

PAINTED, THE PAINT SHALL BE "FIRE SAFE" PAINT. IF PAINTED, THE FIRE RATED LABEL

ON EACH BOARD SHALL NOT BE PAINTED. REFER TO THE SPECIFICATIONS FOR

ADDITIONAL INFORMATION.

4. REFER TO THE ELECTRICAL DRAWINGS FOR LIGHTING REQUIREMENTS.

(TYP. OF 2)

76-105

CM-1

76-01

NEW TE

78-107

T76-TN103

B11

PW-CPW-1

(TYP. OF 2)

PW-CPW-1

SC-GND-1

SC-CAB-1

AC-SCP-1

SC-TTB

(TYP.)

NOTES:

1. ALL ELECTRICAL AND MECHANICAL EQUIPMENT INCLUDING BUT NOT LIMITED LIGHTS,

ELECTRICAL PANELS, MECHANICAL UNIT, ETC.ARE SHOWN FOR REFERENCE. REFER TO

THE MECHANICAL AND ELECTRICAL DRAWINGS FOR COMPLETE INFORMATION AND

SCOPE REQUIREMENTS.

2. ALL WIRE BASKET SHALL BE MOUNTED 6" ABOVE THE EQUIPMENT RACK UNLESS

OTHERWISE NOTED.

KEYNOTES:

1. CAMERA TO BE MOUNTED AT 7' 0 FACING DOORWAY. REFER TO TECHNOLOGY

EQUIPMENT SCHEDULE FOR ADDITIONAL INFORMATION ON THE CAMERA TYPE. REFER

TO THE CSS SCHEDULE FOR ADDITIONAL INFORMATION ON SECURITY WITHIN EACH OF

THE TELECOMMUNICATION SPACES.

2. REFER TO H15/0-TN501 FOR DETAILS ON GROUND BAR FOR THIS SPACE. MOUNT

GROUND BAR AT 7'-0" FROM FINISHED FLOOR.

3. THE FIRE RATED TELEPHONE TERMINAL BOARD SHALL COVER ALL THE WALLS INT HE

TELECOMMUNICATIONS ROOM AS SHOWN ABOVE. SHOULD THE WALLS REQUIRE TO BE

PAINTED, THE PAINT SHALL BE "FIRE SAFE" PAINT. IF PAINTED, THE FIRE RATED LABEL

ON EACH BOARD SHALL NOT BE PAINTED. REFER TO THE SPECIFICATIONS FOR

ADDITIONAL INFORMATION.

4. REFER TO THE ELECTRICAL DRAWINGS FOR LIGHTING REQUIREMENTS.

78-107

CM-1

78-01

SPACE RESERVED

FOR ELECTRICAL

RECEPTICLES

OUTGOING HORIZONTAL PATHWAY

INCOMING BACKBONE PATHWAY

SC-GND-1

SC-CAB-1

NOTES:

1. ALL EQUIPMENT SHALL BE LOCATED IN ITS DESIGNATED SPOT AS DEFINED BY THIS LAYOUT UNLESS OTHERWISE NOTED.

ALL EQUIPMENT IS SIZED (BY RACK UNITS) ACCORDING TO THE BASIS OF DESIGN MANUFACTURER AND MODEL. THE FINAL LAYOUT AND EQUIPMENT SIZE MAY VARY BASED ON THE FINAL SELECTION OF THE EQUIPMENT. ANY CHANGES TO THE LAYOUT SHOWN ABOVE SHALL BE COORDINATED WITH THE E.O.R AND C.O.R. PRIOR TO INSTALLATION. REFER TO THE GENERAL TECHNOLOGY EQUIPMENT SCHEDULE AND SPECIFICATIONS FOR ADDITIONAL INFORMATION.

2. PROVIDE AND INSTALL A NEW SC-GND-2 TO THE REAR SIDE OF THE RACK.

3. REFER TO E SERIES DRAWINGS FOR ADDITIONAL EQUIPMENT INSTALLED ON THE REAR OF THE RACKS INCLUDING THE

UPS, ZONE PDU AND VERTICAL PDU'S.

SC-FDC-1

SC-BLA-1

SC-BLA-1

SC-HWM-2

SC-MPP-2

SC-HWM-1

SC-MPP-2

SC-HWM-2

NETWORK SWITCH

SC-HWM-2

NETWORK SWITCH

SC-HWM-1

SC-BLA-1

SC-BLA-1

SC-BLA-1

SC-BLA-1

SC-PDU-1

SC-PDU-1

SC-UPS-2

SC-BLA-1

SC-BLA-1

SC-GND-1

SC-CAB-1

SPACE RESERVED

FOR ELECTRICAL

RECEPTICLES

OUTGOING HORIZONTAL PATHWAY

INCOMING BACKBONE PATHWAY

NOTES:

1. ALL EQUIPMENT SHALL BE LOCATED IN ITS DESIGNATED SPOT AS DEFINED BY THIS LAYOUT UNLESS OTHERWISE NOTED.

ALL EQUIPMENT IS SIZED (BY RACK UNITS) ACCORDING TO THE BASIS OF DESIGN MANUFACTURER AND MODEL. THE FINAL LAYOUT AND EQUIPMENT SIZE MAY VARY BASED ON THE FINAL SELECTION OF THE EQUIPMENT. ANY CHANGES TO THE LAYOUT SHOWN ABOVE SHALL BE COORDINATED WITH THE E.O.R AND C.O.R. PRIOR TO INSTALLATION. REFER TO THE GENERAL TECHNOLOGY EQUIPMENT SCHEDULE AND SPECIFICATIONS FOR ADDITIONAL INFORMATION.

2. PROVIDE AND INSTALL A NEW SC-GND-2 TO THE REAR SIDE OF THE RACK.

3. REFER TO E SERIES DRAWINGS FOR ADDITIONAL EQUIPMENT INSTALLED ON THE REAR OF THE RACKS INCLUDING THE

UPS, ZONE PDU AND VERTICAL PDU'S.

SC-FDC-1

SC-BLA-1

SC-BLA-1

SC-HWM-2

SC-MPP-2

SC-HWM-1

SC-MPP-2

SC-HWM-2

NETWORK SWITCH

SC-HWM-2

NETWORK SWITCH

SC-HWM-1

SC-BLA-1

SC-BLA-1

SC-BLA-1

SC-BLA-1

SC-PDU-1

SC-PDU-1

SC-UPS-2

SC-BLA-1

SC-BLA-1

NOTES:

1. THIS RISER IS DIAGRAMMATIC AND MAY NOT SHOW ACTUAL ROUTING OR

QUANTITIES OF MATERIALS SHOWN. THIS RISER IS SHOWN FOR

CLARIFICATION OF CONNECTION(S), LOCATIONS AND CABLE TYPE. ALL

INFORMATION OUTLETS ARE TYPICAL OF THE OUTLETS IN THE AREA SHOWN.

REFER TO FLOOR PLANS FOR MORE SPECIFIC ROUTING INFORMATION.

REFER TO SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS.

2. REFER TO FLOOR PLANS FOR QUANTITY OF CABLES AND JACKS TO BE

INSTALLED AT EACH INFORMATION OUTLET.

KEYNOTES:

1. C# INDICATES DATA FACEPLATE CONFIGURATION. REFER TO THE

INFORMATION OUTLET SCHEDULE AND SPECIFICATIONS FOR ADDITIONAL

INFORMATION.

2. RACK(S) OR CABINET(S) AS DEFINED ON THE TELECOM ROOM LAYOUT.

REFER TO THE TELECOM ROOM REFERENCES MATRIX ON THE COVERPAGE

FOR LOCATION.

3. REFER TO SPECIFICATIONS FOR FIBER PATCH CORD REQUIREMENTS.

4. RJ-45 TO RJ45 CATEGORY 6A UTP PATCH CORDS, REFER TO SPECIFIATIONS.

5. 4-PAIR, CATEGORY 6A, UNSHIELDED TWISTED PAIR CABLE, REFER TO

SPECIFICATIONS.

6. FIBER OPTIC CABLE. REFER TO THE FIBER COPPER DIAGRAM ON XXX FOR

ADDITIONAL INFORMATION.

C#

C#

C#

NOTES:

1. THIS RISER IS DIAGRAMMATIC AND MAY NOT SHOW ACTUAL ROUTING OR

QUANTITIES OF MATERIALS SHOWN. THIS RISER IS SHOWN FOR

CLARIFICATION OF CONNECTION(S), LOCATIONS AND CABLE TYPE. ALL

INFORMATION OUTLETS ARE TYPICAL OF THE OUTLETS IN THE AREA SHOWN.

REFER TO FLOOR PLANS FOR MORE SPECIFIC ROUTING INFORMATION.

REFER TO SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS.

2. REFER TO FLOOR PLANS FOR QUANTITY OF CABLES AND JACKS TO BE

INSTALLED AT EACH INFORMATION OUTLET.

KEYNOTES:

1. C# INDICATES DATA FACEPLATE CONFIGURATION. REFER TO THE

INFORMATION OUTLET SCHEDULE AND SPECIFICATIONS FOR ADDITIONAL

INFORMATION.

2. RACK(S) OR CABINET(S) AS DEFINED ON THE TELECOM ROOM LAYOUT.

REFER TO THE TELECOM ROOM REFERENCES MATRIX ON THE COVERPAGE

FOR LOCATION.

3. REFER TO SPECIFICATIONS FOR FIBER PATCH CORD REQUIREMENTS.

4. RJ-45 TO RJ45 CATEGORY 6A UTP PATCH CORDS, REFER TO SPECIFIATIONS.

5. 4-PAIR, CATEGORY 6A, UNSHIELDED TWISTED PAIR CABLE, REFER TO

SPECIFICATIONS.

6. FIBER OPTIC CABLE. REFER TO THE FIBER COPPER DIAGRAM ON XXX FOR

ADDITIONAL INFORMATION.

C#

C#

C#

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

950 N. WASHINGTON ST

SUITE 334

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

BARPDN

EHRM INFRASTRUCTURE UPGRADE

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 76 & 78 - TECHNOLOGY

ENLARGEMENT

T76-TN103

-2

-1

T -T

N

/0

/2

.p d f

1/2" = 1'-0"

TECHNOLOGY EQUIPMENT ROOM

BUILDING T76 TE-105-T76

G16

1/2" = 1'-0"

TECHNOLOGY EQUIPMENT ROOM

BUILDING T78 TE-107-T78

B16

1" = 1'-0"

TECHNOLOGY EQUIPMENT ROOM

ELEVATION BUILDING 76

TE-105-T76

G11

1" = 1'-0"

TECHNOLOGY EQUIPMENT ROOM

ELEVATION BUILDING T78

TE-107-T78

B11

NO SCALE

HORIZONTAL COPPER DIAGRAM

H5

NO SCALE

HORIZONTAL COPPER DIAGRAM

C5

OFFICE

COMM

RESTROOM

OFFICE

OFFICE

101-T74

107-T74

106-T74

105-T74

104-T74

103-T74

102-T74

NEW TE CABINET

74-AE401

A14

74-AE401

D14

EXISTING CONDITIONS- GENERAL NOTES

1. EXISTING CONDITION DRAWINGS ARE FOR REFERENCE ONLY. CONTRACTOR SHALL

VERIFY LOCATION OF ALL ITEMS SHOWN ON THIS SHEET PRIOR TO BEGINNING OF WORK.

EXISTING WALL RATING LEGEND

3 HOUR FIRE BARRIER

2 HOUR FIRE BARRIER

1 HOUR FIRE BARRIER

SMOKE BARRIER

SMOKE PARTITION

EXISTING WALL RATING- GENERAL NOTES

1. ALL EXISTING FIRE RATINGS SHOWN HAVE BEEN PROVIDED BY THE VA. CONTRACTOR

SHALL FIELD VERIFY ALL EXISTING PARTITIONS WHERE WORK IS BEING PERFORMED AND

SEAL ALL PENETRATIONS THROUGH ALL FLOOR AND FIRE RATED BARRIERS WITH UL

LISTED ASSEMBLIES TO MAINTAIN FIRE RATED BARRIERS IN PLACE

2. SEE LIFE SAFETY SHEETS FOR DETAILED LIFE SAFETY PLANS.

EXISTING TELECOM

ROOM LOCATION

PLAN LEGEND

NEW TELECOM ROOM/TE

CABINET LOCATION

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

421 KING ST

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

LTCAL

EHRM INFRASTRUCTURE UPGRADES

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 74 - EXISTING CONDITION

PLAN - OVERALL FIRST FLOOR

74-GC101

-2

-1

-G

C

/2

/2

.p d f

1/4" = 1'-0"A11

TRAILER 74 - EXISTING CONDITION - 1ST FLOOR

N

TRUE NORTH

SITE KEY PLAN

SCALE: NOT TO SCALE

N

PLAN

NORTH

N

OFFICE

COMM

RESTROOM

OFFICE

OFFICE

101-T74

107-T74

106-T74

105-T74

104-T74

103-T74

102-T74

R1

CSS

74-AE401

A14

74-AE401

D14

E X

IS

TI

N G

V .I.

F.

4'

1"

EXISTING V.I.F.

4' - 0" ±

D2

D1

D4

74-105

6 7

NEW TE

74-105

ALIGN

6'

5"

4' - 8"

FLOOR PLAN LEGEND

A3WALL AND DOOR TO REMAIN /

EXISTING CONDITION

WALL AND DOOR TO BE

DEMOLISHED

NEW WORK PARTITION /

NEW WORK DOOR

NEW PARTITION TAG

DEMO PARTITION

NEW PARTITION

NEW PARTITION INFILL

TO MATCH EXISTING

ADJACENT

CONSTRUCTION

PLYWD-01 3/4" AC GRADE FRT

PLYWOOD- SEE

KEYNOTE 8 & FINISH

SCHEDULE

FEC SEMI-RECESSED FIRE

EXTINGUISHER

CABINET- SEE AE-502

FOR DETAILS

ICRA PARTITION- SEE

GC SHEETS FOR ICRA

DETAILS

NOTE: NOT ALL DEMOLITION AND PLAN KEYNOTES APPLY

TO THE FLOOR PLANS ON THIS SHEET

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

421 KING ST

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

LTCAL

EHRM INFRASTRUCTURE UPGRADES

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 74- 1ST FLOOR- ENLARGED

PLANS- DEMO AND NEW WORK

74-AE401

-2

-1

-A

E

/2

/2

.p d f

N

TRUE NORTH

SITE KEY PLAN

SCALE: NOT TO SCALE

N

PLAN

NORTH

N

1/4" = 1'-0"A11

TRAILER 74 - OVERALL 1ST FLOOR

1/2" = 1'-0"A14

74 TRAILER - 1ST FLOOR- DEMO WORK PLAN

1/2" = 1'-0"D14

74 TRAILER - 1ST FLOOR- NEW WORK PLAN

KEYNOTES - DEMOLITION

D1 REMOVE EXISTING DOOR, FRAME, AND HARDWARE IN THEIR ENTIRETY.

D2 REMOVE EXISTING FLOOR FINISH AND BASE WHERE REQUIRED. PREP SUBSURFACE, AS

REQUIRED, TO RECEIVE NEW FLOOR FINISH- SEE FINISH SCHEDULE

D3 REMOVE PORTION OF EXISTING WALL, AS REQUIRED, AND PREP OPENING TO RECEIVE NEW

DOOR AND DOOR FRAME- SEE DOOR SCHEDULE

D4 REMOVE EXISTING WALL IN ITS ENTIRETY TO EXTENTS SHOWN ON FLOOR PLAN.

D5 REMOVE ALL EXISTING PLUMBING FIXTURES IN THEIR ENTIRETY. CAP ALL PIPES AND VALVES

PRIOR TO START OF NEW WORK- SEE PLUMBING DRAWINGS FOR ADDITIONAL INFORMATION.

PATCH/REPAIR WALL AND PREP, AS REQUIRED, TO RECEIVE NEW FINISH

D6 REMOVE PORTION OF EXISTING WALL TO EXTENTS SHOWN ON FLOOR PLAN.

D7 EXISTING COLUMN SHALL REMAIN. CONTRACTOR SHALL COVER AND PROTECT EXISTING

COLUMNS DURING DEMO AND NEW WORK PHASES.

D8 REMOVE EXISTING CASEWORK AND COUNTERTOPS IN THEIR ENTIRETY. REMOVE ALL EXISTING

APPLIANCES, AS REQUIRED, AND RETURN TO VA.

D9 REMOVE EXISTING DOOR, FRAME, AND HARDWARE IN THEIR ENTIRETY. PREP EXISTING

OPENING TO RECEIVE NEW DOOR AND DOOR FRAME- SEE DOOR SCHEDULE FOR NEW DOOR

SIZE.

D10 REMOVE EXISTING WINDOW IN ITS ENTIRETY. PREP OPENING TO RECEIVE NEW WALL INFILL-

SEE NEW WORK FLOOR PLAN

D11 REMOVE EXISTING SLIDING DOOR STOREFRONT SYSTEM IN ITS ENTIRETY. PREP EXISTING

OPENING TO RECEIVE NEW DOORS AND NEW WALL INFILL- SEE NEW WORK FLOOR PLAN

D12 REMOVE EXISTING CONCRETE CURB IN ITS ENTIRETY. PREP SUBFLOOR TO RECEIVE NEW

FLOOR FINISH- SEE NEW WORK FLOOR PLAN

D13 REMOVE EXISTING FENCE, FENCE STRUCTURE, GATE AND HARDWARE IN THEIR ENTIRETY.

KEYNOTES - PLAN

1 PROVIDE AND INSTALL NEW DOOR, DOOR FRAME, AND HARDWARE- SEE DOOR SCHEDULE

2 NEW PARTITION- SEE WALL TYPE. PREP NEW PARTITION, AS REQUIRED, TO SEE NEW

FINISHES- SEE FINISH SCHEDULE

3 PROVIDE AND INSTALL NEW FLOORING AND WALL BASE, AS REQUIRED, FLOORING AND WALL

BASE SHALL MATCH EXISTING ADJACENT FLOORING AND WALL BASE. PREP WALL TO RECEIVE

NEW FINISHES ON EXISTING SIDE OF WALL. NEW FINISHES SHALL MATCH EXISTING.

4 PROVIDE AND INSTALL STAINLESS STEEL SECURITY MESH AT ALL WINDOWS. APPLY BLACK

OUT FILM (BF-01) TO WINDOW GLAZING PRIOR TO INSTALLATION OF SECURITY MESH. SEE

DETAIL

5 RE-FRAME OPENING TO RECEIVE NEW WALL INFILL. WALL INFILL SHALL MATCH EXISTING

WALL CONSTRUCTION. NEW WALL INFILL SHALL BE FLUSH WITH ADJACENT WALL

CONSTRUCTION, TAPE, MUD, AND FLOAT, AS REQUIRED, AND PREP TO RECEIVE NEW PAINT.

6 PROVIDE & INSTALL NEW 3/4" AC GRADE FRT PLYWOOD ON WALLS TO EXTENTS SHOWN ON

PLANS. BOTTOM EDGE OF PLYWOOD SHALL BE INSTALLED 12" AFF- SEE FINISH SCHEDULE

7 PROVIDE & INSTALL NEW FLOOR FINISH AND WALL BASE- SEE FINISH SCHEDULE. REFER TO

ELECTRICAL DRAWINGS FOR GROUND OF STATIC DISSIPATING FLOOR.

8 INFILL EXISTING OPENING IN FLOOR ASSEMBLY WHERE EXISTING CHASE WAS REMOVED. NEW

CONCRETE INFILL SHALL MATCH THE EXISTING ADJACENT FLOOR/ROOF ASSEMBLY

CONSTRUCTION TO MAINTAIN THE EXISTING RATING OF THE FIRE RATED ASSEMBLY. TOP OF

INFILL FINISH SHALL BE ALIGNED WITH AND BE FLUSH WITH ADJACENT TOP OF SLAB

ELEVATION. REFER TO STRUCTURAL DRAWINGS FOR ADDITONAL INFORMATION. PREP NEW

CONCRETE INFILL, AS REQUIRED, TO RECEIVE NEW FLOOR FINISH- SEE FINISH SCHEDULE

9 FRAME OPENING IN EXISTING WALL TO PROVIDE ACCESS TO NEW DOOR AND NEW TR ROOM

10 PROVIDE AND INSTALL NEW BLACK OUT FILM ON INTERIOR SIDE OF EXISTING WINDOW. SEE

BF-01 IN FINISH SCHEDULE.

D#

6" PLUMB WALL

OFFICE

OFFICE

COMM

RESTROOM

OFFICE

OFFICE

101-T74

107-T74

106-T74

105-T74

104-T74

103-T74

102-T74

GENERAL NOTE APPLICABLE TO ALL DRAWINGS - ITEMS AND CONDITIONS DETAILED NOTED OR

OTHERWISE IDENTIFIED ON ONE OF THE SECTIONS OR DETAILS ARE APPLICABLE AND BINDING

TO ALL OTHER SECTIONS AND DETAILS FOR IDENTICAL OR SIMILAR CONDITIONS.

1. CONTRACTOR SHALL REFERENCE ICRA, HAZARDOUS MATERIALS, DEMOLITION AND NEW

WORK SHEETS FOR ALL DISCIPLINES IN COORDINATING AND CONFIRMING DEMOLITION

SCOPE, REQUIREMENTS, PROCEDURES, AND WASTE REMOVAL.

2. CONTRACTOR SHALL COMPLY WITH APPLICABLE REGULATIONS, AS DEFINED ELSEWHERE

IN THE SPECIFICATIONS AND DRAWINGS, TO INCLUDE OSHA SILICA DUST CONTROL

REGULATIONS 29 CFR 1926.1153, 29 CFR 1910.134.

3. GENERAL CONTRACTOR SHALL FILL OUT ATTACHMENT C OF 138-022HV LOCATED IN SPEC

SECTION 01 35 26.19 FOR ALL DEMOLISHED EQUIPMENT INSTALLED IN THIS SCOPE OF

WORK.

FIRE PROTECTION DEVICES, EXIT SIGNS, AND TELECOMMUNICATION EQUIPMENT WITHIN THE

SCOPE OF WORK IS TO BE DEMOLISHED.

GENERAL DEMOLITION RCP NOTES

DEMO PLASTER /

GYPSUM BOARD CEILING

RCP LEGEND

NOTE: SPOT ELEVATION SUFFIX "C.H." INDICATES FLAT CEILING HEIGHT ABOVE FINISH FLOOR.

SUFFIX "L.P." AND "H.P." INDICATE LOW POINT AND HIGH POINT OF SLOPED CEILING. WHERE ADJACENT, TRANSITION BETWEEN FLAT AND SLOPED CEILINGS SHALL UTILIZE APPROVED PRE-

FINISHED ALUMINUM TRANSITION STRIP. REFER TO SPECIFICATIONS.

DEMO 2X4 ACT CEILING

TILE & GRID

DEMO 2X2 ACT CEILING

TILE & GRID

DEMO 2X4 LIGHT

FIXTURE

DEMO SUPPLY

DIFFUSER

DEMO RETURN

DIFFUSER

NEW 2X2 ACT CEILING

TILE & GRID

NEW 2X4 LIGHT

FIXTURE - SEE ELEC

NEW SUPPLY

DIFFUSER - SEE MECH

NEW RETURN

DIFFUSER - SEE MECH

NEW 6" X 4'-0 LIGHT

FIXTURE - SEE ELEC

NEW 6" DIA. DOWN LIGHT

FIXTURE - SEE ELEC

GENERAL NOTE APPLICABLE TO ALL DRAWINGS - ITEMS AND CONDITIONS DETAILED NOTED OR

OTHERWISE IDENTIFIED ON ONE OF THE SECTIONS OR DETAILS ARE APPLICABLE AND BINDING

TO ALL OTHER SECTIONS AND DETAILS FOR IDENTICAL OR SIMILAR CONDITIONS.

1. ALL NEW TRS SHALL BE OPEN TO DECK ABOVE.

2. REFER TO ELECTRICAL DRAWINGS FOR LIGHT PATTERN AND EXIT LIGHT LOCATIONS.

NOTIFY ARCHITECT OF DISCREPANCIES PRIOR TO SHOP DRAWINGS.

3. ALL WALLS SHOWN SHALL EXTEND TO THE STRUCTURAL DECK (SEE WALL TYPES).

CORRIDOR CHASE WALLS AND LOCKER WING WALLS SHALL EXTEND 4" MINIMUM ABOVE

THE CEILING.

4. WHERE CEILING TILES ARE SCHEDULED, REFER TO MECHANICAL, PLUMBING AND

ELECTRICAL DRAWINGS FOR ITEMS NOT SHOWN ON CEILING PLAN. GRILLES, SPEAKERS,

SPRINKLERS, HEAT & SMOKE DETECTORS, SHALL BE CENTERED IN TILES (WHERE

SCHEDULED) UNLESS NOTED OTHERWISE.

5. IN AREAS OF EXPOSED STRUCTURE, PAINT EXPOSED STRUCTURE, UNDERSIDE OF DECK,

SPRINKLER PIPING, CONDUIT AND ALL MISCELLANEOUS OVERHEAD ITEMS. COLORS SHALL

BE SELECTED BY ARCHITECT.

GENERAL RCP NOTES

74-AE701

E11

74-AE701

E8

D33

D30

D41 D43

NEW TE

74-105

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

421 KING ST

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

LTCAL

EHRM INFRASTRUCTURE UPGRADES

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 74- 1ST FLOOR- REFLECTED

CEILING PLANS- DEMO AND NEW

WORK

74-AE701

-2

-1

-A

E

/2

/2

.p d f

KEYNOTES - DEMOLITION RCP

D30 REMOVE EXISTING CEILING TILE, GRID, SUPPORTS, AND FRAMING IN THEIR ENTIRETY.

D31 REMOVE EXISTING LIGHT FIXTURES, DIFFUSERS,GRILLES AND ALL CEILING MOUNTED

ACCESORRIES LOCATED WITHIN EXISTING CEILING BEING DEMOLISHED.

D32 REMOVE EXISTING GYPSUM BOARD CEILING AND SUPPORTS IN THEIR ENTIRETY TO EXTENTS

SHOWN ON REFLECTED CEILING PLAN.

D33 EXISTING CEILING SHALL REMAIN. CONTRACTOR SHALL REWORK EXISTING CEILING GRID, TILE, LIGHTING, AND AIR REGISTERS, AS REQUIRED.

D36 EXISTING PLASTER CEILING, AIR TERMINALS, LIGHT FIXTURES, AND CEILING FAN SHALL

REMAIN

D37 EXISTING PLASTER CEILING SHALL REMAIN. CONTRACTOR SHALL REMOVE EXISTING AIR

TERMINALS, LIGHTS FIXTURES, AND CEILING FAN IN THEIR ENTIRETY FROM EXISTING PLASTER

CEILING.

D38 EXISTING CEILING OPEN TO STRUCTURE ABOVE. CONTRACTOR SHALL REMOVE EXISTING

LIGHT FIXTURES AND AIR TERMINALS, AS REQUIRED.

D39 REMOVE EXISTING SOFFIT AND SUPPORTS, IN THEIR ENTIRETY, TO EXTENTS SHOWN ON

REFLECTED CEILING PLAN

D40 REMOVE EXISTING MINISPLIT IN ITS ENTIRETY- SEE MECHANICAL DRAWINGS

D41 EXISTING CEILING AND SUPPORTS SHALL REMAIN

D42 REMOVE EXISTING CEILING MOUNTED CURTAIN TRACK IN ITS ENTIRETY.

D43 EXISTING LIGHT FIXTURE SHALL REMAIN. CONTRACTOR SHALL PROTECT EXISTING ITEMS TO

REMAIN, AS REQUIRED, THROUGHOUT DEMOLITION AND NEW CONSTRUCTION WORK

KEYNOTES - RCP

1 NEW TR SHALL BE EXPOSED TO STRUCTURE ABOVE. ALL EXPOSED STRUCTURE AND DECK

SHALL BE SPRAYED WITH 2HR FIRE RESISTIVE MATERIAL PER UL N759

2 NEW SUSPENDED LIGHTING FIXTURE- SEE ELECTRICAL. NEW LIGHT FIXTURE SHALL BE HUNG

FROM UNDERSIDE OF EXISTING DECK ABOVE

3 NEW LAY IN CEILING TILE AND GRID SHALL MATCH EXISTING ADJACENT CEILING TILE AND GRID IN SIZE, TYPE, AND COLOR. PROVIDE AND INSTALL NEW LIGHT FIXTURES CENTERED IN

NEW CEILING TILE.

4 EXISTING CEILING, SOFFIT, MOLDING, TRIM AND CEILING FIXTURES SHALL REMAIN.

CONTRACTOR SHALL REWORK EXISTING CEILING AND SOFFIT TO REMAIN, AS REQUIRED.

5 RELOCATED LIGHT FIXTURE IN EXISTING CEILING GRID

6 RELOCATED AIR TERMINAL. CONTRACTOR SHALL TEST AND BALANCE AS REQUIRED- SEE

MECHANICAL FOR DETAILS

7 EXISTING LAY-IN CEILING TILE, CEILING GRID, LIGHT FIXTURES AND ALL CEILING MOUNTED

EQUIPMENT SHALL REMAIN. CONTRACTOR SHALL REWORK EXISTING CEILING, AS REQUIRED,

FOR DEMOLITION AND NEW WORK

8 PROVIDE AND INSTALL NEW LAY IN CEILING TILE AND GRID. NEW TILE AND GRID SHALL MATCH

EXISTING ADJACENT CEILING TILE AND GRID IN SIZE, TYPE, AND COLOR.

9 PROVIDE AND INSTALL NEW DRYWALL CEILING AND SUPPORTS, AS REQUIRED, TO EXTEND

EXISTING DRYWALL CEILING TO NEW WALL. NEW DRYWALL CEILING SHALL MATCH EXISTING

CEILING HEIGHT ABOVE FINISH FLOOR. TAPE, MUD, AND FLOAT, AS REQUIRED, TO PROVIDE

SMOOTH TRANSITION BETWEEN EXISTING AND NEW. PREP TO RECEIVE NEW PAINT.

N

TRUE NORTH

SITE KEY PLAN

SCALE: NOT TO SCALE

N

PLAN

NORTH

N 1/4" = 1'-0"A11

TRAILER 74- 1ST FLOOR REFLECTED CEILING PLAN

1/2" = 1'-0"E11

TRAILER 74- 1ST FLOOR- DEMO WORK RCP

1/2" = 1'-0"E8

TRAILER 74- 1ST FLOOR- NEW WORK RCP

TRUE

NORTH

COMM

RESTROOM

OFFICE

OFFICE

OFFICE

OFFICE

101-T75

105-T75

104-T75

103-T75

102-T75 107-T75

106-T75

NEW TE CABINET

75-AE401

A14

75-AE401

D14

EXISTING CONDITIONS- GENERAL NOTES

1. EXISTING CONDITION DRAWINGS ARE FOR REFERENCE ONLY. CONTRACTOR SHALL

VERIFY LOCATION OF ALL ITEMS SHOWN ON THIS SHEET PRIOR TO BEGINNING OF WORK.

EXISTING WALL RATING LEGEND

3 HOUR FIRE BARRIER

2 HOUR FIRE BARRIER

1 HOUR FIRE BARRIER

SMOKE BARRIER

SMOKE PARTITION

EXISTING WALL RATING- GENERAL NOTES

1. ALL EXISTING FIRE RATINGS SHOWN HAVE BEEN PROVIDED BY THE VA. CONTRACTOR

SHALL FIELD VERIFY ALL EXISTING PARTITIONS WHERE WORK IS BEING PERFORMED AND

SEAL ALL PENETRATIONS THROUGH ALL FLOOR AND FIRE RATED BARRIERS WITH UL

LISTED ASSEMBLIES TO MAINTAIN FIRE RATED BARRIERS IN PLACE

2. SEE LIFE SAFETY SHEETS FOR DETAILED LIFE SAFETY PLANS.

EXISTING TELECOM

ROOM LOCATION

PLAN LEGEND

NEW TELECOM ROOM/TE

CABINET LOCATION

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

421 KING ST

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

LTCAL

EHRM INFRASTRUCTURE UPGRADES

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 75 - EXISTING CONDITION -

OVERALL FIRST FLOOR PLAN

75-GC101

-2

-1

-G

C

/2

/2

.p d f

1/4" = 1'-0"A11

TRAILER 75 - EXISTING CONDITION - 1ST FLOOR N

TRUE NORTH

SITE KEY PLAN

SCALE: NOT TO SCALE

N

PLAN

NORTH

N

RESTROOM

OFFICE

OFFICE

OFFICE

OFFICE

101-T75

105-T75

104-T75

103-T75

102-T75 107-T75

106-T75

R1

CSS

75-AE401

A14

75-AE401

D14 D2

D1 D4

E X

IS

TI

N G

V .I.

F.

4'

1"

EXISTING V.I.F.

4' - 0" ±

6'

5"

NEW TE

75-105

6 7

75-105

ALIGN

5' - 3"

FLOOR PLAN LEGEND

A3WALL AND DOOR TO REMAIN /

EXISTING CONDITION

WALL AND DOOR TO BE

DEMOLISHED

NEW WORK PARTITION /

NEW WORK DOOR

NEW PARTITION TAG

DEMO PARTITION

NEW PARTITION

NEW PARTITION INFILL

TO MATCH EXISTING

ADJACENT

CONSTRUCTION

PLYWD-01 3/4" AC GRADE FRT

PLYWOOD- SEE

KEYNOTE 8 & FINISH

SCHEDULE

FEC SEMI-RECESSED FIRE

EXTINGUISHER

CABINET- SEE AE-502

FOR DETAILS

ICRA PARTITION- SEE

GC SHEETS FOR ICRA

DETAILS

NOTE: NOT ALL DEMOLITION AND PLAN KEYNOTES APPLY

TO THE FLOOR PLANS ON THIS SHEET

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

COMPASS

8734 GALLOWAY TRAIL

NOVELTY, OH. 44072

619-925-1647

ARCHITECT:

CB DESIGN GROUP

421 KING ST

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd.

Tampa, FL. 33612

2345678910111213141516

B

C

D

E

F

G

H

I

J

12345678910111213141516

CONSULTANT:

SCOTT PRZYBYSZ

15 SUNNEN DR. SUITE 104

ST. LOUIS, MO 63143

314-951-2535

CONSULTANT:

MARK DYCK

148 S. QUEEN ST. SUITE 201

MARTINSBURG, WV. 25401

304-266-3115

CONSULTANT:

CLARE KRAMER

2815 DIRECTORS ROW

SUITE 500

ORLANDO, FL. 32809

407-917-2430

04/04/2025

673-20-107

LTCAL

EHRM INFRASTRUCTURE UPGRADES

TAMPA, FL.

ISSUED FOR CONSTRUCTION

TRAILER 75- 1ST FLOOR- ENLARGED

PLANS- DEMO AND NEW WORK

75-AE401

-2

-1

-A

E

/2

/2

.p d f

N

TRUE NORTH

SITE KEY PLAN

SCALE: NOT TO SCALE

N

PLAN

NORTH

N

TRUE

NORTH

1/4" = 1'-0"A11

TRAILER 75 - OVERALL 1ST FLOOR

1/2" = 1'-0"A14

75 TRAILER - 1ST FLOOR- DEMO WORK PLAN

1/2" = 1'-0"D14

75 TRAILER - 1ST FLOOR- NEW WORK PLAN

KEYNOTES - DEMOLITION

D1 REMOVE EXISTING DOOR, FRAME, AND HARDWARE IN THEIR ENTIRETY.

D2 REMOVE EXISTING FLOOR FINISH AND BASE WHERE REQUIRED. PREP SUBSURFACE, AS

REQUIRED, TO RECEIVE NEW FLOOR FINISH- SEE FINISH SCHEDULE

D3 REMOVE PORTION OF EXISTING WALL, AS REQUIRED, AND PREP…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .