Attachment 1 - Spec Vol 1 - R1.pdf

PDF 32 MB Posted

Attached to
Z2DA--673-20-107 EHRM Infrastructure Upgrades Construction Tampa, FL
Solicitation number
36C77625R0092-RFP
Issued by

About this file

This is a specifications document for the EHRM Infrastructure Upgrades project at James A. Haley VA Medical Center in Tampa, Florida (VA Project #673-20-107), issued for construction on April 4, 2025. The document comprises the General Requirements and foundational specifications (Divisions 00-02) that establish the framework for a comprehensive infrastructure modernization including electrical system upgrades, bonding improvements, UPS installation, building management system interfaces, HVAC modifications, communications infrastructure, physical security upgrades, fiber optic backbone installation, data center updates, and hazardous material abatement across multiple buildings. The project requires the contractor to maintain medical center operations 24/7, coordinate work with ongoing patient care, implement strict infection control measures with Class II-IV contamination protocols depending on area criticality, complete a Critical Path Method schedule with detailed phasing, obtain approval for all submittals including shop drawings and product data within specified timeframes, and establish comprehensive quality control procedures with independent testing laboratory services and special inspections.

Key requirements include: contractor designation of a dedicated Commissioning Manager and Commissioning Representatives; submission of an Accident Prevention Plan addressing multiple hazard categories (fall protection, excavation, confined space, crane operations, electrical safety); pre-construction and construction phase commissioning activities with formal testing and training components; asbestos abatement procedures per EPA and OSHA standards with professional industrial hygienist oversight, respiratory protection programs, and decontamination facilities; construction waste management with minimum 50 percent diversion from landfills; environmental protection including dust control, water quality management, and noise limitations; sustainability requirements emphasizing low-VOC materials, recycled content, biobased products, and indoor air quality management; and photographic documentation using professional photography with interactive CAD-based indexing. The contractor must comply with all federal regulations including 29 CFR 1926 (OSHA construction standards), 40 CFR 61 Subpart M (EPA asbestos standards), and state/local requirements, with the most stringent standard prevailing; maintain performance and payment bonds throughout the warranty period; complete operations and maintenance training with factory-authorized representatives; and deliver comprehensive as-built drawings, warranty documentation, and final commissioning reports within specified timeframes.

View the file

Other files

File Type Posted
Amendment 9 - 36C77625R0092 0009.pdf PDF
673-107.Trailer.pdf PDF
4-15 RFI TRACKING SHEET - SOLICITATION 36C77625R0092 - Final.pdf PDF
Tampa EHRM Addendum 2 Narrative.pdf PDF
673-107.32.Tech.pdf PDF
673-107.53.Tech.pdf PDF
673-107.30.Tech.pdf PDF
673-107.38.Tech.pdf PDF
673-107.39.Tech.pdf PDF
673-107.52.Tech.pdf PDF
673-107.54.Tech.pdf PDF
Amendment 8 - 36C77625R0092 0008.pdf PDF
Amendment 7 - 36C77625R0092 0007.pdf PDF
Roof - As Built.pdf PDF
Calculations based on geo report_Sealed.pdf PDF
Amendment 6 - 36C77625R0092 0006.pdf PDF
4-7 RFI TRACKING SHEET - SOLICITATION 36C77625R0092 - Amend 6.pdf PDF
Question 161 - Lay down area.pdf PDF
3-31 RFI TRACKING SHEET No.14 - SOLICITATION 36C77625R0092 Amend 5.pdf PDF
Amendment 5 - 36C77625R0092 0005.pdf PDF
Revised 2.8 and 2.9 Tampa.pdf PDF
010000 TIL General Specification - Tampa Specific.pdf PDF
Tampa EHRM Addendum 1 Narrative.pdf PDF
01 32 16.15- Project Schedules-Small Projects.pdf PDF
3-30 RFI TRACKING SHEET - SOLICITATION 36C77625R0092 Amend 4.pdf PDF
PKI Readers.pdf PDF
Amendment 3 - 36C77625R0092 0003.pdf PDF
3-27 RFI TRACKING SHEET - SOLICITATION 36C77625R0092 Amend 3.pdf PDF
Amendment 2 - 36C77625R0092 0002.pdf PDF
Amendment 1 - 36C77625R0092 0001.pdf PDF
Attachment 3 - Drawings Vol 1 Part1.pdf PDF
Attachment 5 - Drawings Vol 1 Part3.pdf PDF
Attachment 7 - Drawings Vol 1 Part5.pdf PDF
Attachment 10 - Drawings Vol 2 Part3.pdf PDF
Attachment 14 - Construction Wage Rates - Hillsborough 1-2-2025.pdf PDF
Attachment 6 - Drawings Vol 1 Part4.pdf PDF
Attachment 9 - Drawings Vol 2 Part2.pdf PDF
Attachment 11 - Drawings Vol 2 Part4.pdf PDF
Attachment 12 - Drawings Vol 3.pdf PDF
Attachment 19 - Division Cost Breakdown.xlsx XLSX spreadsheet
Attachment 4 - Drawings Vol 1 Part2.pdf PDF
Attachment 8 - Drawings Vol 2 Part1.pdf PDF
Attachment 13 - Brand Name Justification - Tampa_Redacted.pdf PDF
Attachment 17 - PPQ.docx DOCX document
Attachment 18 - Project Information Sheet for Contractors.docx DOCX document
RFP - 36C77625R0092.pdf PDF
Attachment 2 - Spec Vol 2 - R1.pdf PDF
Attachment 15 - Limitations on Subcontracting Clause.docx DOCX document
Attachment 16 - Site Visit Instructions.pdf PDF
Attachment 20 - RFI TRACKING SHEET - SOLICITATION 36C77625R0092 - Project 673-20-107.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APRIL 04, 2025

ISSUED FOR CONSTRUCTION

SPECIFICATIONS SUBMISSION

EHRM INFRASTRUCTURE UPGRADES

Volume 1– –(Divisions 00 through 14)

VA Project #673-20-107

PREPARED FOR:

DEPARTMENT OF VETERANS AFFAIRS NETWORK

James A. Haley VA Hospital 1300 Bruce B. Downs BLVD, Tampa, FL 33612

PREPARED BY:

CB DESIGN GROUP, INC.

421 King St., Suite 301

Alexandria, VA 22314

APRIL 04, 2025

THIS PAGE INTENTIONALLY LEFT BLANK

EHRM INFRASTRUCTURE UPGRADES Issued For Construction

James A. Haley VA Medical Center Project No. 673-20-107

April 04, 2025

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

VOLUME 1

DIVISION 00 - SPECIAL SECTIONS

00 01 00.10 Seal and Signature Sheet -

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21

01 32 16.15 Project Schedules (Small Projects – Design, Bid, Build) 03-20

01 33 23 Shop Drawings, Product Data, and Samples 02-23

01 35 26 Safety Requirements 05-24

VHA Pre-construction Risk Assessment (PCRA) 05-24

VHA Infection Control Risk Assessment for Construction, Renovation and Maintenance

12-24

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 02-21

01 45 29 Testing Laboratory Services 11-18

01 45 35 Special Inspections 06-21

01 57 19 Temporary Environmental Controls 01-21

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 04-22

01 81 13 Sustainable Construction Requirements 10-17

01 91 00 General Commissioning Requirements 04-22

DIVISION 02 – EXISTING CONDITIONS

02 21 13 Site survey 01-21

02 41 00 Demolition 08-17

02 82 11 Traditional Asbestos Abatement 01-21

ACM Report

02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21

02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY (NOT USED)

00 01 10-2

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18

05 36 00 Composite Metal Decking 01-21

05 40 00 Cold Formed Metal Framing 01-21

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES (NOT USED)

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 11 13 Bituminous Damproofing 01-21

07 21 13 Thermal Insulation 01-21

07 22 00 Roof and Deck Insulation 01-21

07 24 00 Exterior Insulation and Finish Systems 01-21

07 27 27 Fluid -Applied Membrane Air Barriers, Vapor Retarding 01-21

07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21

07 60 00 Flashing and Sheet Metal 01-21

07 71 00 Roof Specialties 01-21

07 72 00 Roof Accessories 01-21

07 81 00 Applied Fireproofing 10-17

07 84 00 Firestopping 01-21

07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 14 00 Interior Wood Doors 01-21

08 31 13 Access Doors and Frames 04-22

08 71 00 Door Hardware 05-22

08 90 00 Louvers and Vents 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21

09 06 00 Schedule for Finishes 01-21

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 51 00 Acoustical Ceilings 12-18

09 65 16 Resilient Sheet Flooring 06-22

09 65 16.13 Static Dissipative Resilient Sheet Flooring -

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21

10 44 13 Fire Extinguisher Cabinets 08-18

00 01 10-3

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS (NOT USED)

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components

11-16

DIVISION 14– CONVEYING EQUIPEMENT (NOT USED)

VOLUME 2

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 01-23

22 11 00 Facility Water Distribution 05-21

22 13 00 Facility Sanitary and Vent Piping 09-20

22 14 00 Facility Storm Drainage 09-15

22 62 00 Vacuum Systems for Laboratory 05-23

22 63 00 Gas Systems for Laboratory 05-23

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 03-23

23 05 12 General Motor Requirements For HVAC and Steam

Generation

03-23

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

03-23

23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 08 00 Commissioning of HVAC Systems 03-23

23 09 23 Direct-Digital Control System for HVAC 03-23

23 21 13 Hydronic Piping 03-23 23 23 00 Refrigerant Piping 03-23

23 31 00 HVAC Ducts and Casings 03-23

23 37 00 Air Outlets and Inlets 03-23

23 81 00 Decentralized Unitary HVAC Equipment 03-23

23 81 23 Computer-Room Air-Conditioners 03-24

23 82 16 Air Coils 03-23

00 01 10-4

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22

26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22

26 05 26 Grounding and Bonding for Electrical Systems 11-22

26 05 33 Raceway and Boxes for Electrical Systems 11-22

26 05 73 Overcurrent Protective Device Coordination Study 11-22

26 08 00 Commissioning of Electrical Systems 11-22

26 09 23 Lighting Controls 11-22

26 22 00 Low-Voltage Transformers 11-22

26 24 16 Panelboards 11-22

26 27 26 Wiring Devices 11-22

26 29 21 Enclosed Switches and Circuit Breakers 11-22

26 43 13 Surge Protective Devices 11-22

26 51 00 Interior Lighting 11-22

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 26 Grounding and Bonding for Communications Systems 07-23

27 05 33i Raceways and boxes for Communications Systems 12-22

27 05 36i Cable Trays for Communications Systems 12-22

27 05 53i Identification for Communications Systems 12-22

27 10 00i Structured Cabling 12-22

27 11 16i Communications, Cabinets, Racks, Frames and Enclosures 12-22

27 11 19i Communications Termination Blocks and Patch Panels 12-22

27 11 26 Communications Rack Mounted Power Protection and Power

Strips

06-23

27 13 23 Communications Optical Fiber Backbone Cabling 08-23

23 13 23.13i Communications Optical Fiber Splicing and Terminations 12-22

27 15 13i Communications Copper Horizontal Cabling 12-22

27 16 19i Communications Patch Cords, Station Cords, and Cross

Connect Wire

12-22

27 78 00 Closeout Submittals for Communications 03-23

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results For Electronic Safety and Security 04-18

28 05 13 Conductors and Cables for Electronic Safety and

Security

10-18

28 05 26 Grounding and Bonding for Electronic Safety and

Security

09-11

28 05 28.33 Conduits and Backbones for Electronics Safety and

Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

28 13 00 Physical Access Control System 10-11

28 23 00 Video Surveillance 09-11

00 01 10-5

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 07-16

31 31 16 Termite Treatment -

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16

32 12 16 Asphalt Paving 09-15

32 17 23 Pavement Markings 08-16

32 90 00 Planting 08-16

DIVISION 33 – UTILITIES (NOT USED)

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 48 – ELECTRICAL POWER GENERATION (NOT USED)

00 01 10-6

IMEG

RCDD

4/4/2025

EXP: 7/31/2026

ALONGEAU

Snapshot

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Refer to Drawings GI-001, GI-201, GI-301 for the complete List of Drawings.

00 01 15 - 2

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for as required by drawings and specifications for VA

Project #673-20-107.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.

Marco Lopez/COR

813-934-9680

Marco.Lopez2@va.gov

James A. Haley Medical Center

13000 Bruce B. Downs Blvd.

Tampa, FL 33612

C. Offices of CB Design Group, Inc., as Architect/Engineers, will render certain technical services during construction.

Such services shall be considered advisory to the

Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by the General Contractor, the General Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present

01 00 00 -2 at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. As an agency of the federal government, VA is not subject to local imposition of code enforcement procedures (drawing review, building permits, inspections, fees, etc.). VA must function as the Authority of Having Jurisdiction (AHJ) and thus has the responsibility to guard public health and safety through enforcing its adopted codes.

G. Contractor Work Hours:

1. Normal working hours for this contract will be from

07:00AM to 04:30PM (Local time) Monday through Friday except for weekends and established Federal Holidays.

2. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the

COR. Requests shall be submitted via e-mail at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes general construction, infrastructure upgrades, reconfiguring and renovating existing spaces impacted by or said improvements. Infrastructure upgrades include electrical, bonding, UPS, building management system interfaces, HVAC, communication, physical security

ALONGEAU

Snapshot

01 00 00 -3 upgrades, and fiber infrastructure backbone campus wide.

Within each and in between the buildings, which will include modification that may impact roads, walks, grading, drainage, and other existing utilities. Data Center WAN updates and hazardous material abatement. Project in

Buildings listed in the Construction Documents, and any associated work in other buildings as indicated and necessary for the removal of existing structures and construction and certain other items as shown.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

B. Unless otherwise directed by the COR, once construction documents are approved by the VA, the contractor shall provide one set to the project COR to be kept in the

Station Project Section space and keep one set on the project site for inspections for the complete duration of construction activities. Acceptable size and format of all construction documents must be approved by COR.

C. Any changes during construction that are not in accordance with the approved construction documents shall be resubmitted for approval as an amended set of construction documents.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

01 00 00 -4

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give three weeks’ notice to the Contracting Officer so that security escort and arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The

General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. At the start of the project, the VA will install a contractor key core on construction doors for site security and provide the contractor with keys. These keys are to be returned to the lockshop via the project COR at the end of the project.

2. The General Contractor shall provide duplicate keys and lock combinations for any other lock type to the

Contracting officers representative (COR), including

01 00 00 -5 toolboxes and parked machines, for the purpose of security inspections and emergency actions.

3. The VA lock shop will install all permanent cores at completion of the work. See Section 08 71 00, DOOR

HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General

Contractor/Subcontractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or

“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of

“sensitive information”.

01 00 00 -6

7. All electronic information shall be stored in specified location following VA standards and procedures using an

Engineering Document Management Software (EDMS).

Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.

Access shall be restricted to picking up and dropping off materials and supplies.

2. The General Contractor and its employees shall park in the Freedom Parking Lot unless otherwise arranged by the

COR on a case-by-case basis. Contractor to coordinate with VA Medical Center Facility Manager.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The

Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings

01 00 00 -7 and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the

Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the

Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly

01 00 00 -8 by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by

Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of

Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. Per facility requirements, no dead legs are allowed for plumbing work

(at this facility, a dead leg is defined as a length of pipe greater than 1.5 times the pipe diameter with one end open to the system and the other end terminating at a cap, blind flange or closed valve). All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be

01 00 00 -9 the responsibility of the Government and not the

Contractor.

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the General

Contractor's responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. Refer to Section 013216.15 PROJECT

SCHEDULE for additional information related to Project phasing.

2. To ensure such executions, the General Contractor shall furnish the COR with a schedule of approximate phasing and dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR three weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing and dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:

3. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

01 00 00 -10

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.

Coordinate alteration work in areas occupied by

Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

4. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

J. Contractor Work Hours: Normal working hours for this contract will be from 7:00AM to 4:30PM (local time) Monday through Friday except for weekends and established Federal

Holidays.

Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR.

Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.

K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area as indicated on the approved traffic modification drawings (if required). Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom

01 00 00 -11 of fences shall extend to 25mm (one inch) above grade.

Remove the fence when directed by COR.

L. When a building and/or construction site is turned over to

Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or

Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

M. Utilities Services: Maintain existing utility services for

Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems

(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on

01 00 00 -12 any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center

Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK

RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 21 days in advance of proposed interruption unless otherwise directed by COR.

Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical

Center may occur at other than Contractor's normal working hours.

4. Unless otherwise specified by the COR, major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be

01 00 00 -13 the responsibility of the Government and not the

Contractor.

N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions;

so that they are completely behind the finished surfaces.

All penetrations created must be sealed with appropriate firestopping material. Any existing penetrations found entering or within the site shall be immediately reported to the project COR.

O. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

01 00 00 -14

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of

VA Supply Service, of buildings and/or areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout the affected areas of buildings.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply

Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.

Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, 01 00 00 -15 under provisions of clause entitled "DIFFERING SITE

CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.

They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by

Contractor to such flooring and other surfaces, despite protection measures; and will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

01 00 00 -16

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the

Government are identified by attached tags and/or noted on drawings as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the

Contractor and be removed by Contractor from Medical

Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.

When rooms and spaces are vacated by the Department of

Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the

Government in advance of work to avoid interfering with

Contractor's operation.

4. PCB Transformers and Capacitors : The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl

(PCB) transformers and capacitors. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental

Protection Agency (EPA) and the Department of

Transportation (DOT) as outlined in Code of Federal

Regulation (CFR), Titled 40 and 49 respectively. The

01 00 00 -17

EPA's Toxic Substance Control Act (TSCA) Compliance

Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform Hazardous Waste

Manifest (EPA Form 8700-22), along with the Uniform

Hazardous Waste Manifest Continuation Sheet (EPA Form

8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the

Manifest to the Medical Center's Chief.

a) Copies of the following listed CFR titles may be obtained from the Government Printing Office:

40 CFR 261.....Identification and Listing of Hazardous

Waste

40 CFR 262.....Standards Applicable to Generators of

Hazardous Waste

40 CFR 263.....Standards Applicable to Transporters of

Hazardous Waste

40 CFR 761.....PCB Manufacturing, Processing, Distribution in Commerce, and use

Prohibitions

49 CFR 172.....Hazardous Material tables and Hazardous

Material Communications Regulations

49 CFR 173.....Shippers General Requirements for

Shipments and Packaging

49 CRR 173.....Subpart A General

49 CFR 173.....Subpart B Preparation of Hazardous

Material for Transportation

49 CFR 173.....Subpart J Other Regulated Material;

Definitions and Preparation

TSCA...........Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7

01 00 00 -18

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place.

If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting

Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The

Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL

CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, 01 00 00 -19

"Alterations", "Restoration", and "Operations and Storage

Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and

Responsibilities," which is included in General Conditions.

A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the

(appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the

Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair;

2. Providing waste receptacles at convenient locations and provide regular collection of wastes;

3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

5. Providing adequately maintained sanitary facilities.

01 00 00 -20

1.10 RESTORATION

. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

A. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

B. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by

Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

C. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in

01 00 00 -21 accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 PHYSICAL DATA – SOIL CONDITIONS

A. Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of, or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations provided by the VA station.

(FAR 52.236-4)

B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings.

C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering

Officer at the VA Medical Center, and shall be considered part of the contract documents.

D. Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of

Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the

01 00 00 -22

Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and benchmarks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting

Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, are in

01 00 00 -23 accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer.

Furnish such certification to the COR before any work

(such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings.

Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each building and/or addition.

01 00 00 -24

2. Elevations of bottoms of footings and tops of floors of each building and/or addition.

3. Lines and elevations of sewers and of all outside distribution systems.

4. Lines of elevations of all swales and interment areas.

5. Lines and elevations of roads, streets and parking lots.

E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.

F. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty-foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.

G. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying

Services".

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full-size sets of as-built drawings, at least one of which must be available on the construction site at all times, which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. Any changes during construction that are not in accordance with the approved construction documents shall be

01 00 00 -25 resubmitted for approval as an amended set of construction documents.

C. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

D. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (DWG and PDF) and two as hard copies to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

E. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21

Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one electronic set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance

01 00 00 -26 of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4-month and 9-month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting

Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the

Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of

Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

01 00 00 -27

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and

Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4- and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment

Bonds must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the

01 00 00 -28 work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the

Government at the contractor’s expenses, the Contracting

Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the

Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the

Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting.