This is Addendum Number 2 to the proposal drawing documents for the Tampa VAMC EHRM Infrastructure Upgrades project, issued by CB Design Group on April 14, 2026. The addendum modifies the original proposal documents and must be signed by offerors and submitted with their proposals. Offerors are required to make any necessary adjustments to their estimates based on the modifications specified in this addendum.
The addendum contains extensive drawing modifications across multiple buildings and structures at the Tampa VA Medical Center. Modifications include adding sheet notes (primarily sheet note #6, with some instances of notes #2, #3, and #7) to approximately 107 drawing sheets covering basement, ground, first, second, third, fourth, fifth, sixth, and seventh floor plans for Buildings 01, 30, 32, 36, 38, 39, 41, 42, 52, 53, 54, 68, and multiple trailers (33, 56, 61, 62, 73-78, 80, 81). Additionally, cable tray installations are being added to multiple overall floor plan sheets for Buildings 01, 32, 38, and the site overall plan. The specific content of the sheet notes and cable tray details is not detailed in this addendum document itself, suggesting they appear in the referenced drawing sheets. Offerors must acknowledge the addendum by signing and including the signed document with their proposal submission, providing company name, contact person, signature, and date.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NUMBER 2 TO THE PROPOSAL DRAWING DOCUMENTS
Project Name: Tampa VAMC EHRM Infrastructure Upgrades Date: April 14, 2026
A. This Addendum shall be considered part of the proposal documents for the above-mentioned project as though it had been issued at the same time and shall be incorporated integrally therewith. Where provisions of the following supplementary data differ from those of the original proposal documents, this Addendum shall govern and take precedence. OFFERORS MUST SIGN THE ADDENDUM AND SUBMIT IT
WITH THEIR PROPOSALS.
B. Offerors are hereby notified that they shall make any necessary adjustments in their estimates as a result of this Addendum. It will be construed that each offeror's proposal is submitted with full knowledge of all modifications and supplemental data specified herein.
Except as described below, the original proposal document remains unchanged. The proposal documents are modified and/or clarified, as follows:
DRAWINGS
1. Sheet 0-TN-002 OVERALL SITE PLAN – TECHNOLOGY
a. Add sheet note #2
2. Sheet 01-TN100A Building 01-Basement Plan Area A – Technology
a. Add sheet note #6
3. Sheet 01-TN100B Building 01-Basement Plan Area B – Technology
a. Add sheet note #6
4. Sheet 01-TN100C Building 01-Basement Plan Area C – Technology
a. Add sheet note #6
5. Sheet 01-TN100D Building 01-Basement Plan Area D – Technology
a. Add sheet note #6
6. Sheet 01-TN100E Building 01-Basement Plan Area E – Technology
a. Add sheet note #6
7. Sheet 01-TN100F Building 01-Basement Plan Area F – Technology
a. Add sheet note #6
8. Sheet 01-TN100G Building 01-Basement Plan Area G – Technology
a. Add sheet note #6
9. Sheet 01-TN100H Building 01-Basement Plan Area H – Technology
a. Add sheet note #6
10. Sheet 01-TN100J Building 01-Basement Plan Area J – Technology
a. Add sheet note #6
11. Sheet 01-TN101 Building 01 – OVERALL GROUND FLOOR PLAN - TECHNOLOGY
a. Add cable tray
12. Sheet 01-TN101A Building 01-Ground Floor Plan Area A – Technology
a. Add sheet note #6
13. Sheet 01-TN101B Building 01-Ground Floor Plan Area B – Technology
a. Add sheet note #6
14. Sheet 01-TN101C Building 01-Ground Floor Plan Area C – Technology
15. Sheet 01-TN101D Building 01-Ground Floor Plan Area D – Technology
a. Add sheet note #6
16. Sheet 01-TN101E Building 01-Ground Floor Plan Area E – Technology
a. Add sheet note #6
17. Sheet 01-TN101F Building 01-Ground Floor Plan Area F – Technology
a. Add sheet note #6
18. Sheet 01-TN101G Building 01-Ground Floor Plan Area G– Technology
a. Add sheet note #6
19. Sheet 01-TN101H Building 01-Ground Floor Plan Area H – Technology
a. Add sheet note #6
20. Sheet 01-TN101J Building 01-Ground Floor Plan Area J – Technology
a. Add sheet note #6
21. Sheet 01-TN102 Building 01 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add cable tray
22. Sheet 01-TN102A Building 01-First Floor Plan Area A – Technology
a. Add sheet note #6
23. Sheet 01-TN102B Building 01-First Floor Plan Area B – Technology
a. Add sheet note #6
24. Sheet 01-TN102C Building 01-First Floor Plan Area C – Technology
a. Add sheet note #6
25. Sheet 01-TN102D Building 01-First Floor Plan Area D – Technology
a. Add sheet note #6
26. Sheet 01-TN102E Building 01-First Floor Plan Area E – Technology
a. Add sheet note #6
27. Sheet 01-TN102F Building 01-First Floor Plan Area F – Technology
a. Add sheet note #6
28. Sheet 01-TN102G Building 01-First Floor Plan Area G – Technology
a. Add sheet note #6
29. Sheet 01-TN102H Building 01-First Floor Plan Area H – Technology
a. Add sheet note #6
30. Sheet 01-TN102J Building 01-First Floor Plan Area J – Technology
a. Add sheet note #6
31. Sheet 01-TN103 Building 01 – OVERALL SECOND FLOOR PLAN - TECHNOLOGY
a. Add cable tray
32. Sheet 01-TN103A Building 01-Second Floor Plan Area A – Technology
a. Add sheet note #6
33. Sheet 01-TN103B Building 01-Second Floor Plan Area B – Technology
a. Add sheet note #6
34. Sheet 01-TN103C Building 01-Second Floor Plan Area C – Technology
a. Add sheet note #6
35. Sheet 01-TN103D Building 01-Second Floor Plan Area D – Technology
a. Add sheet note #6
36. Sheet 01-TN103E Building 01-Second Floor Plan Area E – Technology
a. Add sheet note #6
37. Sheet 01-TN103F Building 01-Second Floor Plan Area F – Technology
a. Add sheet note #6
38. Sheet 01-TN103G Building 01-Second Floor Plan Area G – Technology
a. Add sheet note #6
39. Sheet 01-TN103H Building 01-Second Floor Plan Area H – Technology
40. Sheet 01-TN103J Building 01-Second Floor Plan Area J – Technology
a. Add sheet note #6
41. Sheet 01-TN104 Building 01 – OVERALL THIRD FLOOR PLAN - TECHNOLOGY
a. Add cable tray
42. Sheet 01-TN104A Building 01-Third Floor Plan Area A – Technology
a. Add sheet note #6
43. Sheet 01-TN104B Building 01-Third Floor Plan Area B – Technology
a. Add sheet note #6
44. Sheet 01-TN105 Building 01 – OVERALL FOURTH FLOOR PLAN - TECHNOLOGY
a. Add cable tray
45. Sheet 01-TN105A Building 01-Fourth Floor Plan Area A – Technology
a. Add sheet note #6
46. Sheet 01-TN105B Building 01-Fourth Floor Plan Area B – Technology
a. Add sheet note #6
47. Sheet 01-TN106 Building 01 – OVERALL FIFTH FLOOR PLAN - TECHNOLOGY
a. Add cable tray
48. Sheet 01-TN106A Building 01-Fifth Floor Plan Area A – Technology
a. Add sheet note #6
49. Sheet 01-TN106B Building 01-Fifth Floor Plan Area B – Technology
a. Add sheet note #6
50. Sheet 01-TN107 Building 01 – OVERALL SIXTH FLOOR PLAN - TECHNOLOGY
a. Add cable tray
51. Sheet 01-TN107A Building 01-Sixth Floor Plan Area A – Technology
a. Add sheet note #6
52. Sheet 01-TN107B Building 01-Sixth Floor Plan Area B – Technology
a. Add sheet note #6
53. Sheet 01-TN108 Building 01 – OVERALL SEVENTH FLOOR PLAN - TECHNOLOGY
a. Add cable tray
54. Sheet 01-TN108A Building 01-Seventh Floor Plan Area A – Technology
a. Add sheet note #6
55. Sheet 01-TN108B Building 01-Seventh Floor Plan Area B – Technology
a. Add sheet note #6
56. Sheet 30-TN100A Building 30 -Ground Floor Plan Area A – Technology
a. Add sheet note #6
57. Sheet 30-TN100B Building 30 -Ground Floor Plan Area B – Technology
a. Add sheet note #6
58. Sheet 30-TN101A Building 30 -First Floor Plan Area A – Technology
a. Add sheet note #6
59. Sheet 30-TN101B Building 30 -First Floor Plan Area B – Technology
a. Add sheet note #6
60. Sheet 30-TN102A Building 30 -Second Floor Plan Area A – Technology
a. Add sheet note #6
61. Sheet 30-TN102B Building 30 -Second Floor Plan Area B – Technology
a. Add sheet note #6
62. Sheet 30-TN103A Building 30 -Third Floor Plan Area A – Technology
a. Add sheet note #6
63. Sheet 30-TN103B Building 30 -Third Floor Plan Area B – Technology
a. Add sheet note #6
64. Sheet 32-TN102 Building 32 – OVERALL GROUND FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
65. Sheet 32-TN102 Building 32 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add cable tray
b. Add sheet note #7
66. Sheet 32-TN103 Building 32 – OVERALL SECOND FLOOR PLAN - TECHNOLOGY
a. Add cable tray
b. Add sheet note #7
67. Sheet 36-TN101 Building 36 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
68. Sheet 38-TN100A Building 38-Basement Plan Area A – Technology
a. Add sheet note #3
69. Sheet 38-TN100B Building 38-Basement Plan Area B – Technology
a. Add sheet note #3
70. Sheet 38-TN100C Building 38-Basement Plan Area C – Technology
a. Add sheet note #3
71. Sheet 38-TN100G Building 38-Basement Plan Area G – Technology
a. Add sheet note #3
72. Sheet 38-TN101 Building 38 – OVERALL GROUND FLOOR PLAN - TECHNOLOGY
a. Add cable tray
73. Sheet 38-TN101A Building 38-Ground Floor Plan Area A – Technology
a. Add sheet note #3
74. Sheet 38-TN101B Building 38-Ground Floor Plan Area B – Technology
a. Add sheet note #3
75. Sheet 38-TN101C Building 38-Ground Floor Plan Area C – Technology
a. Add sheet note #3
76. Sheet 38-TN101D Building 38-Ground Floor Plan Area D – Technology
a. Add sheet note #3
77. Sheet 38-TN101E Building 38-Ground Floor Plan Area E – Technology
a. Add sheet note #3
78. Sheet 38-TN101F Building 38-Ground Floor Plan Area F – Technology
a. Add sheet note #3
79. Sheet 38-TN101G Building 38-Ground Floor Plan Area G – Technology
a. Add sheet note #3
80. Sheet 38-TN103 Building 38 – OVERALL SECOND FLOOR PLAN - TECHNOLOGY
a. Add cable tray
81. Sheet 38-TN103A Building 38-Second Floor Plan Area A – Technology
a. Add sheet note #3
82. Sheet 38-TN103B Building 38-Second Floor Plan Area B – Technology
a. Add sheet note #3
83. Sheet 38-TN103C Building 38-Second Floor Plan Area C – Technology
a. Add sheet note #3
84. Sheet 38-TN103G Building 38-Second Floor Plan Area G – Technology
a. Add sheet note #3
85. Sheet 38-TN104 Building 38 – OVERALL THIRD FLOOR PLAN - TECHNOLOGY
a. Add cable tray
86. Sheet 38-TN104A Building 38-Third Floor Plan Area A – Technology
a. Add sheet note #3
87. Sheet 38-TN104B Building 38-Third Floor Plan Area B – Technology
a. Add sheet note #3
88. Sheet 38-TN104C Building 38-Third Floor Plan Area C – Technology
a. Add sheet note #3
89. Sheet 38-TN104G Building 38-Third Floor Plan Area G – Technology
a. Add sheet note #3
90. Sheet 39-TN101 Building 39 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
91. Sheet 39-TN102 Building 39 – OVERALL SECOND FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
92. Sheet 41-TN101 Building 41 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
93. Sheet 41-TN102 Building 41 – OVERALL SECOND FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
94. Sheet 42-TN101 Building 42 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
95. Sheet 42-TN102 Building 42 – OVERALL SECOND FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
96. Sheet 52-TN101 Building 52 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
97. Sheet 52-TN102 Building 52 – OVERALL SECOND FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
98. Sheet 53-TN101 Building 53 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
99. Sheet 53-TN102 Building 53 – OVERALL SECOND FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
100. Sheet 54-TN101 Building 54 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
101. Sheet 68-TN101 Building 68 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
102. Sheet 68-TN102 Building 68 – OVERALL SECOND FLOOR PLAN - TECHNOLOGY
a. Add sheet note #7
103. Sheet T30-TN101 TRAILER 33 & 56 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #6
104. Sheet T60-TN101 TRAILER 61 & 62 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #6
105. Sheet T73-TN101 TRAILER 73 TO78 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #6
106. Sheet T80-TN101 TRAILER 80 & 81 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
a. Add sheet note #6
107. Sheet T30-TN101 TRAILER 33 & 56 – OVERALL FIRST FLOOR PLAN - TECHNOLOGY
SPECIFICATIONS
OFFEROR MUST ACKNOWLEDGE THIS ADDENDUM BY SIGNING BELOW
AND ATTACHING THE SIGNED ADDENDUM TO THE PROPOSAL SUBMISSION:
Company Name ______________________________________
Contact Person _______________________________________
Signature ____________________________________________
Date _________________________________________________
File details come from the government source that posted it. Updated .