This is a mechanical engineering drawing showing steam tunnel piping sections, views and support details for a VA facility in Des Moines, IA. The drawing depicts specifications for a steam tunnel construction project, including 3D piping views of various sections (Northeast Section Vault No. 3, Building No. 11, and Southeast Expansion Loops).
The drawing includes detailed specifications for pipe supports using 3"x3"x¼" tube steel structures with 9"x9"x½" base plates and Simpson Titen HD anchors with 4" minimum embedment. The piping system includes multiple pipe sizes including 10" HPS (high pressure steam), 4" LPC (low pressure condensate), and 2" HPC (high pressure condensate) lines. Key components shown include steam pressure reducing stations, shut-off valves, expansion loops, flash tanks, and condensate receivers. The drawing also provides tunnel key plans showing the layout of buildings, vaults, and connecting links for both north and south sections of the facility.
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROLLER SUPPORT DETAIL SUPPORTS FOR ANCHOR LOCATIONS AND GUIDES DETAIL PIPE RACK KICKER DETAIL
10" HPS
4" LPC 2" HPC
10" HPS
ANCHOR OR
GUIDE
4" LPC
ANCHOR OR
GUIDE
2" HPC
3" x 3" x ¼"
TUBE STEEL
(TYP)
TUNNEL WALL
TUNNEL FLOOR
TUNNEL CEILING
TUNNEL WALL
TUNNEL WALL
TUNNEL FLOOR
TUNNEL CEILING
TUNNEL WALL
3" x 3" x ¼"
TUBE STEEL
(TYP)
3" x 3" x ¼"
TUBE STEEL
(TYP)
NOTE:
1. HEIGHT OF 3"x3"x¼" COLUMN
VARIES PER TUNNEL SECTION.
CONTRACTOR TO FIELD VERIFY.
2. HEIGHT OF 3"x3"x¼" BEAM
VARIES PER TUNNEL SECTION.
CONTRACTOR TO FIELD VARIFY.
9" x 9" x 1/2" BASE PLATE. USE
1/2" DIAMETER SIMPSON TITEN
HD ANCHORS. 4" MINIMUM
EMBEDMENT. (TYP)
NOTE:
1. HEIGHT OF 3"x3"x¼" COLUMN
VARIES PER TUNNEL SECTION.
CONTRACTOR TO FIELD VERIFY.
2. HEIGHT OF 3"x3"x¼" BEAM
VARIES PER TUNNEL SECTION.
CONTRACTOR TO FIELD VARIFY.
10" HPS
4" LPC
2" HPC
3" x 3" x ¼"
TUBE STEEL
(TYP)
9" x 9" x 1/2" BASE PLATE. USE
1/2" DIAMETER SIMPSON
TITEN HD ANCHORS. 4"
MINIMUM EMBEDMENT. (TYP)
9" x 9" x 1/2" BASE PLATE. USE
1/2" DIAMETER SIMPSON TITEN
HD ANCHORS. 4" MINIMUM
EMBEDMENT. (TYP)
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% FINAL BID
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
DESIGNER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
623 26TH AVENUE
ROCK ISLAND, IL 61201
9555 JAMES AVE S. SUITE 200
BLOOMINGTON, MN 55431
C U s e rs
\b b ra n d t\ D o c u m e n ts \1
-M -R b b ra n d tL
P A
S
.r v t
/6
/2
:5
:1
A
M
MP104
STEAM TUNNEL PIPING -
SECTIONS AND VIEWS
CONSTRUCT STEAM
TUNNEL
DES MOINES, IA
636A6-23-101
3 & 11
08/09/2024 RES RWB
17270
GENERAL NOTES:
1. COORDINATE INSTALLATION OF ALL PIPING
AND EQUIPMENT WITH ALL OTHER TRADES.
N
O R HT
NORTHEAST SECTION VAULT No. 3 - 3D PIPING VIEW
STEAM PRESSURE REDUCING STATION.
SEE DETAIL 4/MP302
SHUT-OFF VALVE
(TYP)
EXISTING 5" S-60
EXISTING 2"
CR-60
10" S-60
2" CR-60
EXISTING 5" MPS
NEW LOUVER
P.O.C. POINT OF
CONNECTION
(TYP)
5" S-30
5" S-30
EXISTING 4" CHS & CHR
PIPING
EXISTING 4" SANITARY SEWER
BUILDING No. 11 - 3D PIPING VIEW
EXISTING 4" S-60 PIPING
EXISTING 18" CWS
& CWR PIPING
EXISTING 4" RC-15
PIPING
EXISTING 12" S-60 PIPE MAIN
P.O.C. POINT OF
CONNECTION
(TYP)
NEW
10" S-60 PIPING
NEW 10" S-60
PIPING
NEW 10" S-60
PIPING
NEW 10" S-60
PIPING
REROUTE 4" CR-15 PIPING
TO CONDENSATE TANK
VAULT #2
FUTURE BUILDING
BUILDING 10
LINK B
LINK A
VAULT #1
BUILDING 9
BUILDING 11
SOUTH TUNNEL KEY PLAN
BUILDING 5
VAULT #6
BUILDING 3
FUTURE
BUILDING
BUILDING 25
VAULT #5
VAULT #4
VAULT #3
LINK E
LINK D
LINK C
NORTH TUNNEL KEY PLAN
SOUTHEAST EXPANSION LOOPS - LINK 'A' TO VAULT #1
NEW 10" S-60 PIPING
NEW 10" S-60
PIPING
P.O.C. POINT OF
CONNECTION
(TYP)
CONNECT NEW
10" HPS PIPING TO
EXISTING 8" S-60 PIPING
EXPANSION LOOP
1-ELI RELOCATED
FLASH TANK &
CONDENSATE
RECEIVER
EXISTING STEAM
RELIEF PIPING
EXISTING 4" S-60 TO
BUILDINGS 9, 10 & 13
2 1/2" DRIP RETURN
1 1/2" VAC. DETURN
3/4" DRIP LINE
EXPANSION LOOP
1A-ELI
NEW 10" S-60 & 4" CR-15
TO LINK 'B'
CONNECT NEW
4"CR-15 PIPING TO
EXISTING 4" CR-15
PIPING
VAULT #1
LINK 'A'
EXISTING 4" CR-15
PIPING
EXISTING 2" CR-60
PIPING
CONNECT
NEW 4" CR-15
TO EXISTING
4" CR-15
CONNECT NEW 10" S-60
TO EXISTING 12" S-60 AT
TRANSITION
STEAM TUNNEL SUPPORT DETAILS
NOT TO SCALE
NEW 4" CR-15 PIPING
CONNECT NEW 2" CR-15
TO EXISTING 4" CR-15
CONNECT NEW 2" CR-15
PIPING TO EXISTING 2" CR-15
PIPING
CONNECT NEW
2" CR-60 PIPING TO
EXISTING 2" CR-60
PIPING
CONNECT NEW
4" CR-15 PIPING TO
EXISTING 4" CR-15
PIPING
NOT TO SCALE
NOT TO SCALE NOT TO SCALE
TV-1 TRIP STOP
VALVE
N
O R HT
OUTSIDE AIR INTAKE GOOSENECK WITH
BACKDRAFT DAMPER & DRIP PAN. SEE DETAIL
7/MP301 FOR DETAILED INFORMATION
NEW 5" ISOLATION VALVE
Revisions: Date:
REVISION 1 02/07/2025
1 1 1
R E G
I S T E
R E
D P R O F E S S I O N A L E N G I N E E R
NORT H DA KOTA
RUSSELL
SCHULTZ
27753
DATE
08-09-2024
| Sheets |
| MP000 - PIPING COVERSHEET |
| MP101 - EXISTING STEAM TUNNEL SOUTH - LINK 'A' & 'B' PIPING PLANS |
| MP102 - STEAM TUNNEL NORTH - LINK 'C' PIPING PLANS |
| MP103 - STEAM TUNNEL NORTHEAST - LINK 'D' & 'E' PIPING PLAN |
| MP104 - STEAM TUNNEL PIPING - SECTIONS AND VIEWS |
| MP301 - MECHANICAL PIPING DETAILS |
| MP302 - MECHANICAL PIPING DETAILS |
| MP501 - MECHANICAL SCHEDULES |
| MPD101 - STEAM TUNNEL - PIPING DEMOLITION PLAN |
| MV402 - CONTROL DIAGRAMS |
File details come from the government source that posted it. Updated .