271323-13i Communications Optical Fiber Splicing and Terminations - 1 pages.pdf
PDF 72 KB Posted
- Solicitation number
- 36C26325R0017
About this file
This is a technical specification section (27 13 23.13) for Communications Optical Fiber Splicing and Terminations related to a steam tunnel construction project at the Des Moines VA Medical Center. The document outlines requirements for fiber optic cable terminations as part of VA Project 636A6-23-101.
The specification requires fiber optic cabling to be terminated with duplex Lucent connector (LC) adapters, 12-fiber multi-fiber push on (MPO) connectors, or 24-fiber multi-fiber push on (MPO) connectors based on application needs. Pre-terminated connections are specified as preferred for computer room structured cabling applications, while field termination through fusion splicing is acceptable for non-computer room applications where cable lengths cannot be predetermined. The work must comply with VA Infrastructure Standards for Telecommunications Spaces and relates to other sections covering communications termination blocks, patch panels, and optical fiber backbone cabling requirements.
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Des Moines VAMC, Des Moines IA VA Project 636A6-23-101
Construct Steam Tunnel 02/07/2025
3600 30th Street Revision 1
Des Moines, IA 50310
27 13 23.13 - 1
SECTION 27 13 23.13
COMMUNICATIONS OPTICAL FIBER SPLICING AND TERMINATIONS
PART 1 - GENERAL
1.1 DESCRIPTION:
This section specifies requirements for terminations of fiber optic cabling.
1.2 SUMMARY
Section Includes:
A. Termination Requirements.
1.3 REFERENCES
A. VA Infrastructure Standard for Telecommunications Spaces.
1.4 RELATED WORK:
A. Termination equipment: Section 27 11 19, COMMUNICATIONS TERMINATION
BLOCKS AND PATCH PANELS.
B. Fiber optic cabling requirements: Section 27 13 23, COMMUNICATIONS
OPTICAL FIBER BACKBONE CABLING.
1.5 SUBMITTALS:
A. Submit in accordance with Section 27 05 00, COMMON WORK RESULTS FOR
COMMUNICATIONS SYSTEMS.
PART 2 - PRODUCTS
Not used.
PART 3 - EXECUTION
3.1 TERMINATION REQUIREMENTS.
A. Terminate fiber optic cabling with duplex Lucent connector (LC) adapters, 12-fiber multi-fiber push on (MPO) connectors, or 24-fiber multi-fiber push on (MPO) connectors as required for the application.
B. Pre-terminated connections are preferred for computer room structured cabling applications. Field termination (fusion splicing) for non-computer room applications where cable lengths cannot be determined in advance is acceptable.
- - - E N D - - -