This is an electrical plan drawing showing the layout of the North Tunnel Links C & D for a VA facility construction project in Rock Island, IL. The drawing, dated February 6, 2025, is prepared at a scale of 1/8" = 1'-0" and shows electrical components and routing for tunnel sections connecting Building 3.
The plan details electrical installations including panel locations, vault specifications (including Vault #4), and various electrical fixtures labeled with codes such as EF-2, ELI-5, ELI-6, and multiple "+48"GFIWP" notations throughout the tunnel layout. The drawing includes an existing electrical manhole location and contains general electrical notes and keyed notes in the upper right corner. The project appears to be part of a larger steam tunnel construction project (636A6-23-101) for the Department of Veterans Affairs, with IMEG and Anderson listed as the consultant and designer of record respectively.
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SS
S S
J
J
J
J
J
ELECTRICAL GENERAL NOTES
1. ALL DEVICES, EQUIPMENT, FIXTURES, AND THE LIKE MUST BE GROUNDED BY USE
OF A PROPERLY SIZED GROUNDING CONDUCTOR. MECHANICAL AND
ELECTRICAL BONDS OF THE METALLIC RACEWAY SYSTEM SHALL BE MAINTAINED.
GROUND AND BOND PER NEC ARTICLE 250.
2. ELECTRICAL CONTRACTOR SHALL PROVIDE TAMPER RESISTANCE RECEPTACLES
PER NEC 406.12.
3. ALL DISCONNECTS ON MECHANICAL EQUIPMENT SHALL BE MOUNTED ON
STRUCTURE TO ALLOW REMOVAL OF THE EQUIPMENT FOR MAINTENANCE WITH A
MINIMUM OF WIRING WORK. VERIFY NEC CLEARANCE REQUIREMENTS ARE MET
PRIOR TO ROUGH-IN.
4. MAINTAIN SERVICE CLEARANCE AROUND MECHANICAL & ELECTRICAL
EQUIPMENT. DO NOT ROUTE PIPING OR CONDUIT IN CLEARANCE SPACE.
5. ALL RECEPTACLE CIRCUITS SHALL HAVE DEDICATED NEUTRAL.
6. INSTALL DEVICES SUCH THAT NO TWO DEVICES ON OPPOSITE SIDES OF THE
SAME WALL ARE WITHIN 24" OF EACH OTHER.
7. PRIOR TO ROUGH-IN, COORDINATE ALL WALL DEVICES WITH FINAL CASEWORK
ELEVATIONS AND OTHER TRADES. CONFLICTS SHALL BE BROUGHT IMMEDIATELY
TO THE ATTENTION OF THE DESIGN TEAM.
8. ALL FLOOR BOXES SHALL HAVE THEIR EXACT ROUGH-IN LOCATIONS
DETERMINED BY THE DESIGN TEAM THROUGH DIMENSIONED DRAWINGS
APPROVED BY THE OWNER PRIOR TO ROUGH-IN. LOCATIONS SHOWN ARE FOR
BIDDING PURPOSES ONLY.
9. REFER TO TECH SHEETS FOR ADDITIONAL ROUGH-IN INFORMATION OF LOW
VOLTAGE DEVICES.
10. REFER TO ARCHITECTURAL ELEVATIONS AND REFLECTED CEILING PLANS FOR
THE SPECIFIC DEVICE ROUGH-IN AND PLACEMENT. ANY DEVIATIONS FROM THE
ARCHITECTURAL ELEVATIONS AND REFLECTED CEILING PLANS SHALL BE
REVIEWED AND APPROVED BY THE DESIGN TEAM PRIOR TO ROUGH-IN.
11. CONTRACTOR SHALL PROVIDE A UL924 RATED TRANSFER DEVICES SERVING ALL
TUNNEL LIGHTING. LIGHTING CONTROLS MANUFACTURER SHALL DETERMINED
EXACT QUANTITIES WITH LIGHTING CONTROL ZONES AND LAYOUTS. ELECTRICAL
CONTRACTOR SHALL EXTEND SWITCHED CONDUCTOR FROM 120V CIRCUIT TO
UL924 DEVICE TO BE USED FOR SENSING AND LIGHTING CONTROL OVERRIDE.
F1
F1
F1
F1
F1
F1
F1
F1
E1
F1
F1
F1
F1
F1
3-B-6E-37
E1
F1
F1
F1
F1
F1
F1
+48"
GFI
WP
+48"
GFI
WP
3-B-6E-36
+48"
GFI
WP
+48"
GFI
WP
+48"
GFI
WP
+48"
GFI
WP
F1
3-B-6E
BUILDING 3
SEE SHEET E104 FOR
CONTINUATION
VAULT #3
VAULT #4
EF-2 VAULT #4
3-B-6E-32
ELI-6
E2
E3
LINK D
ELI-5
LINK C
Panel 3-1-3
E8
E4
+48"
+48"
E11
+48"
+48"
E11
E5
E12+48"
+48"
+48"
GFI
WP
EXR
PANEL 3
APPROXIMATE LOCATION OF
EXISTING ELECTRICAL MANHOLE
E
E14
ELECTRICAL PLAN KEYED NOTES
E1
LOCATION OF UL924 SENSING CIRCUIT SWITCH. SWITCH SHALL BE WIRED
TO OPEN CIRCUIT USED FOR UL924 SENSING PURPOSES. WHEN SWITCH IS
OPENED, UL924 DEVICE SHALL OVERRIDE OCCUPANCY SENSORS
INTEGRAL TO LIGHT FIXTURES AND LINE VOLTAGE SWITCH(ES) SERVING
TUNNEL LIGHT FIXTURES. LIGHTS SHALL REMAIN ON AND UNCONTROLLED
WHEN SWITCH IS OPENED. SWITCH SHALL BE CLEARLY LABELED
"OCCUPANCY OVERRIDE". REFER TO SHEET E501 FOR UL924 TRANSFER
DEVICE DETAIL.
E2
PROVIDE HAND-OFF-AUTO COMBINATION MOTOR STARTER WITH 1 HP
RATED, 1P TOGGLE SWITCH WITH NEMA 1 HOUSING.
NOTE: NOT ALL KEYED NOTES MAY BE USED ON EACH PLAN
E3
DISCONNECT POWER FROM EXISTING LOUVER TO BE REMOVED. REMOVE
RACEWAY AND CONDUCTORS BACK TO NEAREST JUNCTION BOX. EXTEND
CIRCUIT TO NEW LOUVER CONTROLLER LOCATION. COORDINATE WITH
MECHANICAL CONTRACTOR.
E4
CIRCUIT SHALL BE (2)#10, #10G, 3/4"C TO LIMIT VOLTAGE DROP TO 3%.
VERIFY CIRCUIT LENGTH AND VOLTAGE DROP PRIOR TO ROUGH-IN.
E5
CIRCUIT SHALL BE (2)#8, #10G, 3/4"C TO LIMIT VOLTAGE DROP TO 3%.
VERIFY CIRCUIT LENGTH AND VOLTAGE DROP PRIOR TO ROUGH-IN.
E6
CIRCUIT SHALL BE (2)#4, #10G, 1-1/4"C TO LIMIT VOLTAGE DROP TO 3%.
VERIFY CIRCUIT LENGTH AND VOLTAGE DROP PRIOR TO ROUGH-IN.
E7
CIRCUIT SHALL BE (2)#3, #8G, 1-1/4"C TO LIMIT VOLTAGE DROP TO 3%.
VERIFY CIRCUIT LENGTH AND VOLTAGE DROP PRIOR TO ROUGH-IN.
E8
REFER TO CIVIL PLANS FOR RELOCATION OF EXISTING SITE LIGHTING
CONDUITS. DOWNTIME AND OUTAGES SHALL BE STRATEGICALLY
MINIMIZED AND COORDINATED CLOSELY WITH OWNER. COOORDINATE
DISCONNECTION OF CIRCUITS WITH CIVIL CONTRACTOR DURING
CONSTRUCTION.
E9
PROVIDE 120V POWER AND ANALOG TELEPHONE CONNECTION TO WALL
MOUNTED BLUE LIGHT CALL STATION EQUAL TO TALKAPHONE TWP-WMSE
WITH ETP-520E CALL STATION. WALL PHONE SHALL BE 316 MARINE GRADE
STAINLESS STEEL AND IP66 RATED. COORDINATE ROUGH-IN LOCATION
WITH ALL TRADES TO AVOID OBSTRUCTIONS. TELEPHONE LINE SHALL BE
TERMINATED TO CALL CONSOLIDATOR LOCATED IN BUILDING 11 TELECOM
ROOM.
E10
APPROXIMATE LOCATION OF BUILDING 11 TELECOM ROOM ON FIRST
FLOOR. PROVIDE 1 ANALOG TELEPHONE LINE TO CALL CONSOLIDATOR
EQUAL TO TALKAPHONE EC-6. PROVIDE 120V POWER TO UPS EQUAL TO
TALKAPHONE ETP-UPS TO POWER EC-6. COORDINATE EXACT MOUNTING
LOCATIONS IN TELECOM ROOM PRIOR TO ROUGH-IN.
E11
PROVIDE 120V POWER AND ANALOG TELEPHONE CONNECTION TO WALL
MOUNTED BLUE LIGHT CALL STATION EQUAL TO TALKAPHONE TWP-WMSE
WITH ETP-520E CALL STATION. WALL PHONE SHALL BE 316 MARINE GRADE
STAINLESS STEEL AND IP66 RATED. COORDINATE ROUGH-IN LOCATION
WITH ALL TRADES TO AVOID OBSTRUCTIONS. TELEPHONE LINE SHALL BE
TERMINATED TO CALL CONSOLIDATOR LOCATED IN BUILDING 3 TELECOM
ROOM.
E12
APPROXIMATE LOCATION OF BUILDING 3 TELECOM ROOM ON FIRST FLOOR.
PROVIDE 1 ANALOG TELEPHONE LINE TO CALL CONSOLIDATOR EQUAL TO
TALKAPHONE EC-6. PROVIDE 120V POWER TO UPS EQUAL TO TALKAPHONE
ETP-UPS TO PWER EC-6. COORDINATE EXACT MOUNTING LOCATIONS IN
TELECOM ROOM PRIOR TO ROUGH-IN.
E13
LOCATION OF 2'x2'x1' JUNCTION BOX FOR CHILLER FLOW SENSOR WIRING.
JUNCTION BOX SHALL BE RELOCATED APPROXIMATELY 3' SOUTH ALONG
WALL. REMOVE CONDUIT AND CONDUCTORS AS REQUIRED. SPLICE
CABLING AT NEW JUNCTION BOX LOCATION MATCHING EXISTING
CONDUCTORS. EXTEND WIRING TO NEW JUNCTION BOX LOCATED ABOVE
DOOR AND SPLICE CIRCUIT TO RESTORE CONTINUITY. COORDINATE WORK
AND CHILLER SHUTDOWN OWNER.
E14
REINSTALL EXISTING LIGHT POLE. RECIRCUIT FROM PANEL 3-1-3 IN
BUILDING 3. PROVIDE DIRECT BURIAL CONDUIT FROM EXISTING
ELECTRICAL MANHOLE MATCHING EXISTING CIRCUIT PROPERTIES. REFER
TO SITE PLAN FOR ADDITIONAL DETAILS AND EXACT LOCATION.
E15
REINSTALL EXISTING SALVAGED LIGHT POLE. CIRCUIT CONTINUITY SHALL
BE MAINTAINED FOR DURATION OF CONSTRUCTION. RECONNECT EXISTING
CIRCUIT AT NEW LOCATION. SPLICES IF REQUIRED SHALL REMAIN
ACCESSIBLE. REFER TO SITE PLAN FOR ADDITIONAL DETAILS AND EXACT
LOCATION.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% FINAL BID
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
DESIGNER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
623 26TH AVENUE
ROCK ISLAND, IL 61201
9555 JAMES AVE S. SUITE 200
BLOOMINGTON, MN 55431
C U s e rs \A
W e b e r\ D o c u m e n ts \1
-M
-R a w e b e r9
S
.r v t
/6
/2
:3
:0
A
M
E103
NORTH TUNNEL LINKS C & D CONSTRUCT STEAM
TUNNEL
DES MOINES, IA
636A6-23-101
3 & 11
08/09/2024 ATW Author 17270
1/8" = 1'-0"1
NORTH TUNNEL - LINKS C & D ELECTRICAL PLAN
BUILDING 5
VAULT #6
BUILDING 3
FUTURE
BUILDING
BUILDING 25
VAULT #5
VAULT #4
VAULT #3
LINK E
LINK D
LINK C
NORTH TUNNEL KEY PLAN
Revisions: Date:
REVISION 1 02/07/2025
| Sheets |
| E103 - NORTH TUNNEL LINKS C & D |
File details come from the government source that posted it. Updated .