Revised Cath Shielding 2024.pdf

PDF 513 KB Posted

Attached to
Z2DA--621-22-121 Renovate Bldg. 204 for Cath Lab II - Engineering
Solicitation number
36C24926R0057
Issued by

About this file

This is a Radiation Shielding Design document prepared for Mountain Home VA Medical Center's new Cardiac Catheterization Laboratory facility. The design specifies shielding requirements for two cardiac cath lab rooms (L222 and L220) located on the 2nd floor of the facility.

The physicist recommends using 1/32nd inch of leaded drywall for all barriers marked in green, including technologist viewing windows, scrub doors, and hallway entrance doors to protect adjacent low-occupancy areas (patient waiting areas, hallways, and storage rooms). Barriers marked in red at the technologist console area require no shielding due to the geometry of the proposed fluoroscopy unit layout. The design calculations are based on 100 patients per week and categorize all shielding as "Other wall" type construction using lead material. Specific barrier requirements vary by location, with lead thickness ranging from 1/8 inch to 1 inch depending on distance and occupancy type. The ceiling and floor require concrete shielding (2.07 inches and 3.62 inches respectively). Detailed specifications tables provide barrier identification, distance measurements in feet, dose calculations, and required shielding materials for each wall, door, and viewing window in both rooms. The design was completed by John Kevin Mullins, M.H.P., DABMP (Certified Medical Health Physicist) on January 3, 2025.

View the file

Other files

File Type Posted
07 42 13 - Insulated Metal Wall Panels.pdf PDF
00 01 10 - Table Of Contents 29072026.pdf PDF
Appendix B - HVAC CUTSHEETS.pdf PDF
07.112_AE112.2 - PHASE TWO ENLARGED PLAN.pdf PDF
36C24926R0057 0004.pdf PDF
07.314_AE301 - PENTHOUSE CONSTRUCTION.pdf PDF
07.734_AQ732.4 - EQUIPMENT PLANS - PHASE FOUR.pdf PDF
14.20_EE102.2.2 - PHASE 2 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
14.11_ED102.4.2 - PHASE 4 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
14.08_ED102.3.2 - PHASE 3 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
14.04_ED102.1.2 - PHASE 1 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
14.24_EE102.4.2 - PHASE 4 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
14.22_EE102.3.2 - PHASE 3 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
00 00 00 - Specification Cover.pdf PDF
14.27_EE102.5.3 - PHASE 5 ENLARGED LIGHTING TECH PLAN.pdf PDF
07 41 13 - Insulated Metal Roof Panels.pdf PDF
13.12_MH103 - MECHANICAL ROOF HVAC PLAN.pdf PDF
07.704_AF702.4 - PHASE FOUR FINISH PLANS.pdf PDF
14.13_ED102.5.2 - PHASE 5 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
23 82 00 - Convection Heating and Cooling Units.pdf PDF
28 23 00 - Video Surveillance.pdf PDF
01 45 35 - Special Inspections.pdf PDF
14.16_EE102.1.2 - PHASE 1 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
00 01 10 - Table Of Contents.pdf PDF
2026-0724 Addendum 02 Summary.docx DOCX document
14.26_EE102.5.2 - PHASE 5 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
14.38_E600 - PARTIAL SINGLE LINE DIAGRAM.pdf PDF
07.730_AQ732 - OVERALL EQUIPMENT PLAN.pdf PDF
FINAL COORDINATION STUDY -- 12-17-19.pdf PDF
01 45 35a - Schedule of SI.pdf PDF
28 05 00 - Common Work Results for Electronic Safety and Security.pdf PDF
11.10_PD102.5 - PLUMBING SECOND FLOOR DEMOLITION PLAN PHASE 5.pdf PDF
S-102824-291.pdf PDF
09 54 00 - Operating Room Modular Diffuser System.pdf PDF
13.10_MH102.4 - MECHANICAL SECOND FLOOR HVAC PLAN - PHASE 4.pdf PDF
36C24926R0057 0003.pdf PDF
14.02_E102 - SECOND FLOOR OVERALL PLAN.pdf PDF
14.00_E001 - ELECTRICAL LEGENDS AND ABBREVIATIONS.pdf PDF
11.22_PL601 - PLUMBING SCHEDULES and DIAGRAMS.pdf PDF
09 05 16 - Subsurface Preparation For Floor Finishes.pdf PDF
14.06_ED102.2.2 - PHASE 2 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
Project 621-22-121 RFI Log - Mt Home Cath Lab to VA 7-24-26.xlsx XLSX spreadsheet
10 51 26 - Plastic Lockers and Bench.pdf PDF
01 45 35b - Statement of SI.pdf PDF
07.705_AF702.5 - PHASE FIVE FINISH PLANS.pdf PDF
14.29_E501 - TECHNOLOGY DETAILS.pdf PDF
621-22-121 Site Visit Sign in sheet.pdf PDF
36C24926R0057 0002.pdf PDF
2026-0629 Cath Lab II - BID specs - Add 01.pdf PDF
36C24926R0057 0001.pdf PDF
Show 40 more

Latest 50 of 60 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MHVA Cardiac Cath Lab

RADIATION SHIELDING DESIGN

JOHN KEVIN MULLINS, M.H.P., DABMP

Mountain Home VA Medical Center

Radiation Shielding Design

New Cath Lab 1 & 2

2nd Floor Rooms L222 & L220

Physicist Shielding Results:

The planned Cardiac Cath Lab relocation includes two large area rooms L220 and L220. Presently, the proposed locations are surrounded by low occupancy areas; patient waiting area, hallways, and multiple storage rooms. The multiple storage areas are accessible, convenient, large, and easily converted to future offices with extended staff occupancy.

Circumventing excessive shielding costs for future storage room conversions, I recommend using 1/32th inch of leaded drywall for all barriers marked in green. This includes technologist’s viewing windows, scrub doors, and hallway entrance doors. Technologist’s console area barriers marked in red require no shielding due to the geometry of the proposed layout of the fluoroscopy unit.

Mountain Home VA Medical Center

Radiation Shielding Design

New Cath Lab 1 & 2

2nd Floor Rooms L222 & L220

Walls Viewing Window Door

Cath Lab Room L222

Barrier ID Distance (feet) Barrier ID Distance (feet)

Wall 2 - arrow 1 11.9 Wall 5 - arrow 8 11.9

Wall 3 - arrow 2 12.2 Door - arrow 9 13.6

Wall 3 - arrow 3 9.9 Wall 6 - arrow 10 14.4

Wall 4 - arrow 4 11.3 Wall 7 - arrow 11 17.2

Wall 4 - arrow 5 10.2 Door - arrow 12 20.4

Wall 4 - arrow 6 13.3 Ceiling 12

Wall 5 - arrow 7 13.6 Floor 5

Wall 1

Wall 2

Wall 3

Wall 4

Wall 5

Wall 6

Wall 7

5 6

12 Wall 1

Wall 2

Wall 4

Wall 5

Wall 6

Wall 7

Cath Lab Room L220

Barrier ID Distance (feet) Barrier ID Distance (feet)

Wall 2 - arrow 1 11.7 Wall 5 - arrow 8 11.7

Wall 3 - arrow 2 12.4 Door - arrow 9 13.8

Wall 3 - arrow 3 10.2 Wall 6 - arrow 10 14.5

Wall 4 - arrow 4 11.0 Wall 7 - arrow 11 17.0

Wall 4 - arrow 5 10.1 Door - arrow 12 20.2

Wall 4 - arrow 6 13.5 Ceiling 12

Wall 5 - arrow 7 13.4 Floor 5

Design prepared and completed by: John Kevin Mullins, M.H.P., DABMP

Certified Medical Health Physicist

Date: January 3, 2025