09 05 16 - Subsurface Preparation For Floor Finishes.pdf
PDF 143 KB Posted
- Solicitation number
- 36C24926R0057
About this file
This is a Performance Work Statement (Section 09 05 16) for subsurface preparation of floor finishes at Pittsburgh VAMC's Building 1, 9W and 10W renovation project (Contract 646-11-106, Addendum 02). The specification establishes requirements for removal of existing floor coverings, testing concrete for moisture and pH conditions, applying remedial floor coatings, and installing underlayment to achieve proper floor flatness and levelness tolerance.
The specification requires three primary product systems: (1) a high-solids epoxy moisture remediation coating with minimum 10 mils thickness and permeance rating less than 0.1 perm per ASTM E96/E96M for areas with excessive moisture (100% relative humidity testing per ASTM F2170); (2) a calcium aluminate cement-based, cementitious self-leveling underlayment with minimum compressive strength of 4,100 psi and flexural strength of 1,000 psi at 28 days, with thickness ranging from feathered edge to 1 inch as detailed, suitable for all flooring types; and (3) a cementitious trowel-applied underlayment (minimum 4,000 psi compressive strength, not suitable for resinous finishes) with rapid dry time of 15-20 minutes. Concrete substrates must meet ASTM F710 requirements and be prepared per ASTM D4259 using mechanical methods (dry abrasive blasting, wet abrasive blasting, vacuum-assisted, or centrifugal-shot blasting). Moisture testing per ASTM F1869 and in situ probe testing per ASTM F2170 are required before application, with written test reports documenting placement and results. For bidding purposes, contractors should assume 1/2 inch floor leveler across the Cath labs, Prep and Recovery areas, and any floor where tile is to be removed. Environmental conditions must maintain ambient temperature of 60°F minimum for 24 hours before testing and three days after, with substrate and material temperatures maintained between 60-85°F during installation. Surface tolerances shall not exceed 1/4 inch deviation in 10 feet unless otherwise specified on drawings or by flooring manufacturer recommendations.
View the file
Other files
Show 40 more
Latest 50 of 60 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PITTSBURGH VAMC
RENOVATE BUILDING 1, 9W AND 10W
646-11-106
02-01-26
SUBSURFACE PREPARATION FOR FLOOR FINISHES
09 05 16 - 1
SECTION 09 05 16
SUBSURFACE PREPARATION FOR FLOOR FINISHES
ADDENDUM 02 – IN RED
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies subsurface preparation requirements for areas to receive the installation of applied and resinous flooring. This section includes removal of existing floor coverings, testing concrete for moisture and pH, remedial floor coating for concrete floor slabs having unsatisfactory moisture or pH conditions, floor leveling and repair as required.
1.2 RELATED WORK
A. Section 07 92 00, JOINT SEALANTS.
B. Section 09 65 16, RESILIENT SHEET FLOORING.
C. Section 09 65 19, RESILIENT TILE FLOORING.
D. Section 09 67 23 60, RESINOUS (Urethane and Epoxy Mortar) FLOORING.
Section 09 68 00, CARPETING.
1.3 SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA and TEST DATA.
B. Written approval confirming product compatibility with subfloor material manufacturer and the flooring manufacturer
C. Product Data:
1. Moisture remediation system
2. Underlayment Primer
3. Cementitious Self-Leveling Underlayment
4. Cementitious Trowel-Applied Underlayment (Not suitable for resinous floor finishes)
D. Test Data:
1. Moisture test and pH results performed by a qualified independent testing agency.
1.4 DELIVERY AND STORAGE
A. Deliver materials in containers with legible and intact labels and grade-seals unbroken.
B. Store material to prevent damage or contamination.
646-11-106
02-01-26
SUBSURFACE PREPARATION FOR FLOOR FINISHES
09 05 16 - 2
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced in text by basic designation only.
B. ASTM International(ASTM):
D638-14(2014)...........Standard Test Method for Tensile Properties of
Plastics
D4259-18(2019)..........Standard Practice for Preparation of Concrete by Abrasion Prior to Coating Application.
C109/C109M-20b(2020)....Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2-in. or
[50-mm] Cube Specimens
7234-19(2020)...........Standard Test Method for Pull-Off Adhesion
Strength of Coatings on Concrete Using Portable
Pull-Off Adhesion Testers
E96/E96M-16(2016).......Standard Test Methods for Water Vapor
Transmission of Materials
F710-1e1(2020)..........Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring
F1869-16a...............Standard Test Method for Measuring Moisture
Vapor Emission Rate of Concrete Subfloor Using
Anhydrous Calcium Chloride
F2170-19a(2020).........Standard Test Method for Determining Relative
Humidity in Concrete Floor Slabs Using in situ
Probes
C348-20(2020)...........Standard Test Method for Flexural Strength of
Hydraulic-Cement Mortars
C191-19(2020)...........Standard Test Method for Time of Setting of
Hydraulic Cement by Vicat Needle
PART 2 - PRODUCTS
2.1 MOISTURE REMEDIATION COATING
A. System Descriptions:
1. High-solids, epoxy system designed to suppress excess moisture in concrete prior to an overlayment. For use under resinous products, VCT, tile and carpet where issues caused by moisture vapor are a concern.
646-11-106
02-01-26
SUBSURFACE PREPARATION FOR FLOOR FINISHES
09 05 16 - 3
B. Products: Subject to compliance with applicable fire, health, environmental, and safety requirements for storage, handling, installation, and clean up.
C. System Components: Verify specific requirements as systems vary by manufacturer. Verify build up layers and installation method. Verify compatibility with substrate. Use manufacturer’s standard components, compatible with each other and as follows:
1. Liquid applied coating:
a. Resin: epoxy.
b. Formulation Description: Multiple component high solids.
c. Application: Per manufacturer’s written installation requirements.
d. Thickness: minimum 10 mils
D. Material Vapor Permeance: Application shall achieve a permeance rating of less than 0.1 perm in accordance with ASTM E96/E96M.
E. Maximum RH requirement: 100% testing in accordance with ASTM F2170.
2.2 CEMENTITIOUS SELF-LEVELING UNDERLAYMENT
A. System Descriptions:
1. High performance self-leveling underlayment resurfacer. Single component, self-leveling, cementitious material designed for easy
Property Test Value
Tensile Strength
ASTM D638 4,400 psi
Volatile Organic Compound
Limits (V.O.C.)
SCAMD Rule 1113
(Ammended
02/05/2016)
25 grams per liter
Permeance ASTM E96 0.1 perms
Tensile Modulus ASTM D638 1.9X105 psi
Percent Elongation ASTM D638 12%
Cure Rate Per manufacture’s
Data
4 hours Tack free with 24hr recoat window
Bond Strength ASTM D7234 100% bond to concrete failure
646-11-106
02-01-26
SUBSURFACE PREPARATION FOR FLOOR FINISHES
09 05 16 - 4 application as an underlayment for all types of flooring materials.
It is used for substrate repair and leveling.
B. Products: Subject to compliance with applicable fire, health, environmental, and safety requirements for storage, handling, installation, and clean up. Gypsum-based products are unacceptable.
C. System Characteristics:
1. Wearing Surface: smooth
2. Thickness: Per architectural drawings, ranging from feathered edge to 1”, per application. Applications greater than 1” require additional 3/8” aggregate to mix or as recommended by manufacturer.
D. Underlayment shall be calcium aluminate cement-based, containing
Portland cement. Gypsum-based products are unacceptable.
E. Compressive Strength: Minimum 4100 psi in 28 days in accordance with
ASTM C109/C109M.
F. Flexural Strength: Minimum 1000 psi in 28 days in accordance with ASTM
C348
G. Dry Time: Underlayment shall receive the application of moisture insensitive tile in 6 hours, floor coverings in 16 hours, and resinous flooring in 3-7 days.
H. Primer: compatible and as recommended by manufacturer for use over intended substrate
I. System Components: Manufacturer's standard components that are compatible with each other and as follows:
1. Primer:
a. Resin: copolymer
b. Formulation Description: single component ready to use.
c. Application Method: Squeegee and medium nap roller.
d. All puddles shall be removed, and material shall be allowed to dry, 1-2 hours at 70F/21C.
e. Number of Coats: (1) one.
2. Grout Resurfacing Base:
a. Formulation Description: Single component, cementitious self-leveling high-early and high-ultimate strength grout.
b. Application Method: colloidal mix pump, cam rake, spike roll.
1) Thickness of Coats: Per architectural scope, 1” lifts.
2) Number of Coats: More than one if needed.
646-11-106
02-01-26
SUBSURFACE PREPARATION FOR FLOOR FINISHES
09 05 16 - 5
c. Aggregates: for applications greater than 1inch, require additional 3/8” aggregate to mix.
J.
2.3 CEMENTITIOUS TROWEL-APPLIED UNDERLAYMENT(NOT SUITABLE FOR RESINOUS FLOOR
FINISHES)
A. Underlayment shall be calcium aluminate cement-based, containing
Portland cement. Gypsum-based products are unacceptable.
B. Compressive Strength: Minimum 4000 psi in 28 days
C. Trowel-applied underlayment shall not contain silica quartz (sand).
D. Dry Time: Underlayment shall receive the application of floor covering in 15-20 minutes.
PART 3 - EXECUTION
3.1 ENVIRONMENTAL REQUIREMENTS
A. Maintain ambient temperature of work areas at not less than 16 degree C
(60 degrees F), without interruption, for not less than 24 hours before testing and not less than three days after testing.
B. Maintain higher temperatures for a longer period of time where required by manufacturer's recommendation.
C. Do not install materials when the temperatures of the substrate or materials are not within 60-85 degrees F/ 16-30 degrees C.
3.2 SURFACE PREPARATION
A. Existing concrete slabs with existing floor coverings:
1. Conduct visual observation of existing floor covering for adhesion, water damage, alkaline deposits, and other defects.
2. Remove existing floor covering and adhesives. Comply with local, state and federal regulations and the RFCI Recommended Work
Practices for Removal of Resilient Floor Coverings, as applicable to the floor covering being removed.
B. Concrete shall meet the requirements of ASTM F710 and be sound, solid, clean, and free of all oil, grease, dirt, curing compounds, and any
Property Test Value
Compressive Strength
ASTM C109/C109M
2,200 psi @ 24 hrs
3,000 psi @ 7 days
Initial set time
Final Set time
ASTM C191
30-45 min.
1 to 1.5 hours
Bond Strength
ASTM D7234
100% bond to concrete failure
646-11-106
02-01-26
SUBSURFACE PREPARATION FOR FLOOR FINISHES
09 05 16 - 6 substance that might act as a bond-breaker before application. As required prepare slab by mechanical methods. No chemicals or solvents shall be used.
C. General: Prepare and clean substrates according to flooring manufacturer's written instructions for substrate indicated.
D. Prepare concrete substrates per ASTM D4259 as follows:
1. Dry abrasive blasting.
2. Wet abrasive blasting.
3. Vacuum-assisted abrasive blasting.
4. Centrifugal-shot abrasive blasting.
5. Comply with manufacturer's written instructions.
E. Repair damaged and deteriorated concrete according to flooring manufacturer's written recommendations.
F. Verify that concrete substrates are dry.
G. Perform anhydrous calcium chloride test, ASTM F 1869. Proceed with application only after substrates have maximum moisture-vapor-emission rate of per flooring manufactures formal and project specific written recommendation.
H. Perform in situ probe test, ASTM F2170. Proceed with application only after substrates do not exceed a maximum potential equilibrium relative humidity per flooring manufacture’s formal and project specific written recommendation.
I. Provide a written report showing test placement and results.
J. Prepare joints in accordance with Section 07 92 00, JOINT SEALANTS and material manufacturer’s instructions.
K. Alkalinity: Measure surface pH in accordance with procedures provided in ASTM F710 or as outlined by qualified testing agency or flooring manufacturer’s technical representative.
L. Tolerances: Subsurface shall meet the flatness and levelness tolerance specified on drawings or recommended by the floor finish manufacturer.
Tolerance shall also not to exceed 1/4” deviation in 10’. As required, install underlayment to achieve required tolerance. For bidding purposes assume 1/2" floor leveler across the Cath labs, Prep and
Recovery, and any floor where tile is to be removed. Contractors shall make reasonable assumptions of floor conditions at locations where existing floor finishes and is to be removed.
646-11-106
02-01-26
SUBSURFACE PREPARATION FOR FLOOR FINISHES
09 05 16 - 7
M. Other Subsurface: For all other subsurface conditions, such as wood or metal, contact the floor finish or underlayment manufacturer, as appropriate, for proper preparation practices.
3.3 MOISTURE REMEDIATION COATING
A. Where results of relative humidity testing (ASTM F2170) exceed the requirements of the specified flooring manufacturer, apply remedial coating as specified to correct excessive moisture condition.
B. Prior to remedial floor coating installation mechanically prepare the concrete surface to provide a concrete surface profile in accordance with ASTM D4259.
C. Mix and apply moisture remediation coating in accordance with manufacturer’s instructions.
3.4 CEMENTITOUS UNDERLAYMENT
A. Install cementitious self-leveling underlayment as required to correct surface defects, floor flatness or levelness corrections to meet the tolerance requirements as or detailed on drawings, address non-moving cracks or joints, provide a smooth surface for the installation of floor covering.
B. Mix and apply in accordance with manufacturer's instructions.
3.5 PROTECTION
A. Prior to the installation of the finish flooring, the surface of the underlayment shall be protected from abuse by other trades by the use of plywood, tempered hardwood, or other suitable protection course
3.6 FIELD QUALITY CONTROL
A. Where specified, field sampling of products shall be conducted by a qualified, independent testing facility.
- - - E N D - - -